CN105717365B - 双避雷线铁管塔工频接地电阻的测量方法 - Google Patents
双避雷线铁管塔工频接地电阻的测量方法 Download PDFInfo
- Publication number
- CN105717365B CN105717365B CN201410713665.7A CN201410713665A CN105717365B CN 105717365 B CN105717365 B CN 105717365B CN 201410713665 A CN201410713665 A CN 201410713665A CN 105717365 B CN105717365 B CN 105717365B
- Authority
- CN
- China
- Prior art keywords
- iron pipe
- tower
- pipe tower
- resistance
- lightning
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 title claims abstract description 110
- 229910052742 iron Inorganic materials 0.000 title claims abstract description 55
- 230000009977 dual effect Effects 0.000 title claims abstract description 12
- 238000009434 installation Methods 0.000 title claims abstract description 12
- 238000000691 measurement method Methods 0.000 title claims abstract description 9
- 238000000034 method Methods 0.000 claims abstract description 18
- 238000012360 testing method Methods 0.000 claims abstract description 15
- 238000005259 measurement Methods 0.000 claims abstract description 13
- 230000002159 abnormal effect Effects 0.000 claims abstract description 4
- 210000000080 chela (arthropods) Anatomy 0.000 claims abstract description 4
- 230000007717 exclusion Effects 0.000 claims abstract description 4
- 238000007689 inspection Methods 0.000 claims abstract description 4
- 239000002184 metal Substances 0.000 claims abstract description 4
- 229910052751 metal Inorganic materials 0.000 claims abstract description 4
- 238000009413 insulation Methods 0.000 claims description 11
- 229910052573 porcelain Inorganic materials 0.000 claims description 6
- 239000002689 soil Substances 0.000 claims description 3
- 230000006378 damage Effects 0.000 abstract description 2
- 238000010586 diagram Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000004020 conductor Substances 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000010998 test method Methods 0.000 description 1
Landscapes
- Measurement Of Resistance Or Impedance (AREA)
Abstract
一种可大大提高测试效率及测试的准确度,及时发现接地不良,提高设备耐雷水平的双避雷线铁管塔工频接地电阻的测量方法。其步骤如下:(a)铁管塔接地极检查,如发现有接地线破坏或螺栓被盗等异常情况应作好记录并及时处理;(b)在拆开一根避雷线连接情况下使用钳表法测量铁管塔的接地电阻,如果发现铁管塔接地电阻与周围其他塔及本塔以往数值比较有明显增大或者超过了相应的标准或规程中对接地电阻值的规定,则检查金具连接螺栓是否松动或接触不良,排除后重新测量如果仍然增大或超标,则执行步骤(c);(c)拆开两根避雷线与塔身金属连接情况下使用三极法测量铁管塔的接地电阻。
Description
技术领域
本发明涉及一种双避雷线铁管塔工频接地电阻的测量方法。
背景技术
目前,铁管塔接地测试普遍采用三极法,工作量大、效率低,测试结果受到现场影响因素较多,实际运行维护中很难保证测试的准确性和及时性。钳形表虽然测试方法简单,但由于铁管塔本身没有单独的接地引下线,不适于铁管塔的接地电阻的测量。
发明内容
本发明要解决的技术问题是提供一种可大大提高测试效率及测试的准确度,及时发现接地不良,提高设备耐雷水平的双避雷线铁管塔工频接地电阻的测量方法。
本发明的技术解决方案是:
双避雷线铁管塔工频接地电阻的测量方法,其步骤如下:
(a)铁管塔接地极检查
首先检查被测线路铁管塔是否符合测量导则 DL/T 475-2006的规定,记录避雷线型号、杆塔高度、接地极型式、杆塔编号、接地极编号、土壤状况和当地气温,检查被测杆塔接地线的电气连接状况,如发现有接地线破坏或螺栓被盗等异常情况作好记录并及时处理;
(b)在拆开一根避雷线连接情况下使用钳表法测量铁管塔的接地电阻
保持铁管塔其中一根避雷线和塔身连接不动,在做好安全措施的情况下将另一根避雷线与铁管塔的金具解开,使用瓷瓶或绝缘管、绝缘绳等将解开的避雷线与铁管塔绝缘隔开5mm以上,不能用手直接接触解开的避雷线,上塔使用钳形接地电阻测试仪测量铁管塔的接地电阻;
测量中如果发现铁管塔接地电阻与周围其他塔及本塔以往数值比较有明显增大,或者超过了相应的标准或规程中对接地电阻值的规定,则检查金具连接螺栓是否松动或接触不良,排除后重新测量如果仍然增大或超标,则执行步骤(c);
(c)拆开两根避雷线与塔身金属连接情况下使用三极法测量铁管塔的接地电阻
在做好安全措施的情况下将两根避雷线与铁管塔的金具都解开,使用瓷瓶或绝缘管、绝缘绳等将两根避雷线与铁管塔绝缘隔开5mm以上,不能用手直接接触避雷线,然后使用三极法接地电阻测试仪测试量铁管塔的接地电阻,检查是否存在接地极不合格或塔上方避雷线接触不良。
步骤(b)和步骤(c)中,在做好安全措施的情况下用绝缘棒临时支撑避雷线。
本发明的有益效果是:将钳表法引入无接地线的双避雷线铁管塔的接地电阻的测量,将钳表法和三极法有效结合,可大大提高测试效率及测试的准确度,及时发现接地不良,提高设备耐雷水平。
附图说明
图1是不拆动避雷线时钳表法测量双避雷线铁管塔的工频接地电阻的示意图;
图2是拆除避雷线时三极法测量双避雷线铁管塔的工频接地电阻的示意图;
图中:P-电压极,C-电流极。
具体实施方式
双避雷线铁管塔工频接地电阻的测量方法,其步骤如下:
(a)铁管塔接地极检查
首先检查被测线路铁管塔是否符合测量导则 DL/T 475-2006的规定,记录避雷线型号、杆塔高度、接地极型式、杆塔编号、接地极编号、土壤状况和当地气温,检查被测杆塔接地线的电气连接状况,如发现有接地线破坏或螺栓被盗等异常情况则作好记录并及时处理;
(b)在拆开一根避雷线连接情况下使用钳表法测量铁管塔的接地电阻
如图1所示 ,保持铁管塔其中一根避雷线和塔身连接不动,在做好安全措施的情况下将另一根避雷线与铁管塔的金具解开,使用瓷瓶或绝缘管、绝缘绳等将解开的避雷线与铁管塔绝缘隔开5mm以上,不能用手直接接触解开的避雷线,在做好安全措施的情况下可以用绝缘棒临时支撑避雷线,上塔使用钳形接地电阻测试仪测量铁管塔的接地电阻;
测量中如果发现铁管塔接地电阻与周围其他塔及本塔以往数值比较有明显增大,或者超过了相应的标准或规程中对接地电阻值的规定,则检查金具连接螺栓是否松动或接触不良,排除后重新测量如果仍然增大或超标,则执行步骤(c);
(c)拆开两根避雷线与塔身金属连接情况下使用三极法测量铁管塔的接地电阻
如图2所示,在做好安全措施的情况下将两根避雷线与铁管塔的金具都解开,使用瓷瓶或绝缘管、绝缘绳等将两根避雷线与铁管塔绝缘隔开5mm以上,不能用手直接接触避雷线,在做好安全措施的情况下可以用绝缘棒临时支撑避雷线,然后使用三极法通过接地电阻测试仪测试量铁管塔的接地电阻,检查是否存在接地极不合格或塔上方避雷线接触不良。
Claims (2)
1.双避雷线铁管塔工频接地电阻的测量方法,其特征是步骤如下:
(a)铁管塔接地极检查
首先检查被测线路铁管塔是否符合测量导则DL/T475-2006的规定,记录避雷线型号、杆塔高度、接地极型式、杆塔编号、接地极编号、土壤状况和当地气温,检查被测杆塔接地线的电气连接状况,如发现有接地线破坏或螺栓被盗异常情况作好记录并及时处理;
(b)在拆开一根避雷线连接情况下使用钳表法测量铁管塔的接地电阻
保持铁管塔其中一根避雷线和塔身连接不动,在做好安全措施的情况下将另一根避雷线与铁管塔的金具解开,使用瓷瓶、绝缘管或绝缘绳将解开的避雷线与铁管塔绝缘隔开5mm以上,不能用手直接接触解开的避雷线,上塔使用钳形接地电阻测试仪测量铁管塔的接地电阻;
测量中如果发现铁管塔接地电阻与周围其他塔及本塔以往数值比较有增大现象,或者超过了相应的标准或规程中对接地电阻值的规定,则检查金具连接螺栓是否松动或接触不良,排除后重新测量如果仍然增大或超标,则执行步骤(c);
(c)拆开两根避雷线与塔身金属连接情况下使用三极法测量铁管塔的接地电阻
在做好安全措施的情况下将两根避雷线与铁管塔的金具都解开,使用瓷瓶、绝缘管或绝缘绳将两根避雷线与铁管塔绝缘隔开5mm以上,不能用手直接接触避雷线,然后使用三极法接地电阻测试仪测试量铁管塔的接地电阻,检查是否存在接地极不合格或塔上方避雷线接触不良。
2.根据权利要求1所述的双避雷线铁管塔工频接地电阻的测量方法,其特征是:步骤(b)和步骤(c)中,在做好安全措施的情况下用绝缘棒临时支撑避雷线。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410713665.7A CN105717365B (zh) | 2014-12-01 | 2014-12-01 | 双避雷线铁管塔工频接地电阻的测量方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410713665.7A CN105717365B (zh) | 2014-12-01 | 2014-12-01 | 双避雷线铁管塔工频接地电阻的测量方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105717365A CN105717365A (zh) | 2016-06-29 |
CN105717365B true CN105717365B (zh) | 2019-08-13 |
Family
ID=56145370
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410713665.7A Active CN105717365B (zh) | 2014-12-01 | 2014-12-01 | 双避雷线铁管塔工频接地电阻的测量方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105717365B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106684586A (zh) * | 2017-03-13 | 2017-05-17 | 国网冀北电力有限公司迁西县供电分公司 | 一种降低接地电阻的结构及其安装方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1828313A (zh) * | 2006-02-21 | 2006-09-06 | 武汉高压研究所 | 免解线杆塔接地电阻快速测量方法及装置 |
CN101216215A (zh) * | 2008-01-15 | 2008-07-09 | 何立昌 | 墙体镶嵌式太阳能热水器 |
CN203224571U (zh) * | 2013-03-14 | 2013-10-02 | 辽宁省电力有限公司抚顺供电公司 | 柔性接地电阻测试仪 |
CN102353843B (zh) * | 2011-09-19 | 2013-11-13 | 清华大学 | 接地装置工频接地电阻测量的扫频测试方法及其测试仪 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000028661A (ja) * | 1998-07-07 | 2000-01-28 | Nippon Telegr & Teleph Corp <Ntt> | 接地抵抗測定方法及びその装置 |
-
2014
- 2014-12-01 CN CN201410713665.7A patent/CN105717365B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1828313A (zh) * | 2006-02-21 | 2006-09-06 | 武汉高压研究所 | 免解线杆塔接地电阻快速测量方法及装置 |
CN101216215A (zh) * | 2008-01-15 | 2008-07-09 | 何立昌 | 墙体镶嵌式太阳能热水器 |
CN102353843B (zh) * | 2011-09-19 | 2013-11-13 | 清华大学 | 接地装置工频接地电阻测量的扫频测试方法及其测试仪 |
CN203224571U (zh) * | 2013-03-14 | 2013-10-02 | 辽宁省电力有限公司抚顺供电公司 | 柔性接地电阻测试仪 |
Non-Patent Citations (2)
Title |
---|
500KV线路工频接地电阻测量方法的分析探讨;楚广虹等;《科技情报开发与经济》;20071231;第17卷(第31期);第134页左栏第2段至第135页右栏倒数第1段 |
两种杆塔接地电阻测量方法的比较;李德超等;《电瓷避雷器》;20080430(第2期);第42左栏第1段至第46页倒数第1段 |
Also Published As
Publication number | Publication date |
---|---|
CN105717365A (zh) | 2016-06-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104678246B (zh) | 一种变电站接地网腐蚀状态评估方法及其系统 | |
CN102707191A (zh) | 一种大型变电站地网腐蚀诊断装置及其诊断方法 | |
CN105891604A (zh) | 一种测量输电杆塔接地阻抗的回路阻抗法及测试系统 | |
CN205539205U (zh) | 一种测量输电杆塔接地阻抗的回路阻抗测试系统 | |
CN105717365B (zh) | 双避雷线铁管塔工频接地电阻的测量方法 | |
CN102937661A (zh) | 一种绝缘子检测用探杆 | |
CN203858320U (zh) | 一种基于阀值比较的接地网腐蚀断点检测系统 | |
CN103698656B (zh) | 一种非接触式接地漏电故障检测方法 | |
CN203759182U (zh) | 用于电力线路的避雷装置 | |
CN108051693A (zh) | 一种基于tas装置的提高接地故障判断准确性的方法 | |
CN105717364B (zh) | 单避雷线铁管塔工频接地电阻的测量方法 | |
Liu et al. | Optimized corrosion diagnosis of large-scale grounding grid | |
CN103472352B (zh) | 一种接地线检测方法 | |
CN203396835U (zh) | 单芯电缆接地电流监测及报警系统 | |
CN207396660U (zh) | 一种防雷接地电阻智能监测装置 | |
CN204789889U (zh) | 一种多功能高压试验装置 | |
CN111025091B (zh) | 一种城市配电网电缆不均匀受潮状态的智能测评方法 | |
CN204241608U (zh) | 一种漏电流测试盒 | |
CN202563012U (zh) | 大型电站接地网阻抗参数测量装置 | |
CN102879649A (zh) | 一种接地电阻测量方法 | |
CN203826913U (zh) | 一种用于电缆分接箱的电缆接头 | |
CN209542707U (zh) | 高压外线瓷瓶绝缘电阻测量杆 | |
CN104502726B (zh) | 铁塔和水泥杆工频接地电阻的测量方法 | |
CN205786989U (zh) | 一种绝缘子零值高精度检测装置 | |
CN209400577U (zh) | 一种电缆支撑检测固定架 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information |
Inventor after: Wang Qiang Inventor after: Yang Xinyu Inventor after: Chen Zhizhou Inventor after: Zhang Shenghong Inventor after: Li Hui Inventor before: Yang Xinyu Inventor before: Chen Zhizhou Inventor before: Zhang Shenghong Inventor before: Wang Qiang Inventor before: Li Hui |
|
CB03 | Change of inventor or designer information | ||
GR01 | Patent grant | ||
GR01 | Patent grant |