Prior art keywords
strand
unit
time
slab
speed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610087984.0A
Other languages
Chinese (zh)
Other versions
CN105710323A (en
Inventor
蔡森
田斌
李凤巧
李玲美
闫仲科
秦昌国
李玉平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Software Limited by Share Ltd
Original Assignee
Software Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Software Ltd By Share Ltd filed Critical Software Ltd By Share Ltd
Priority to CN201610087984.0A priority Critical patent/CN105710323B/en
Publication of CN105710323A publication Critical patent/CN105710323A/en
Application granted granted Critical
Publication of CN105710323B publication Critical patent/CN105710323B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D11/00Continuous casting of metals, i.e. casting in indefinite lengths
    • B22D11/12Accessories for subsequent treating or working cast stock in situ
    • B22D11/126Accessories for subsequent treating or working cast stock in situ for cutting
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D11/00Continuous casting of metals, i.e. casting in indefinite lengths
    • B22D11/16Controlling or regulating processes or operations
    • B22D11/163Controlling or regulating processes or operations for cutting cast stock

Abstract

The present invention relates to automatic control technology field, discloses a kind of slab scale and surveys long method and system, including:The default unit strand time, obtain strand and terminate required unit strand time number, obtain instantaneous strand speed of each unit strand time when starting, instantaneous strand speed when being started according to each unit strand time calculates the strand length of each unit strand time, adds and obtain slab length by the strand length of each unit strand time.The present invention is by dividing multiple unit strand times, the strand length of each unit strand time is obtained respectively, finally obtains total strand length, and the scale for completing the slab to casting out surveys length, the stability of slab scalling-off detecting is improved, improves slab lumber recovery comprehensively.

Description

A kind of slab scale surveys long method and system
Technical field
The present invention relates to automatic control technology field, and long method and system are surveyed more particularly to a kind of slab scale.
Background technology
Sheet billet continuous casting be by the smelting technique of slab caster continuous casting plate blank, will be through supercooling after the completion of slab casting But anneal, often slab can produce bad template after annealing, can be entered to reach following process requirement by withdrawal straightening machine Row stretches, and is then fed into slab cutting area.As STEELMAKING PRODUCTION rhythm is constantly accelerated, requirement of the client to slab quality is also more next It is higher.Therefore it is required for carrying out slab scale survey length before slab cutting, length is then surveyed according to scale and cut, is obtained The sub- base that client needs.
Present most domestic slab scale surveys length and generally uses traditional measurement roller scale system, as shown in figure 1, measurement Roller scale system includes measurement roller 1, pneumatic cylinder 2 and encoder 3, and pneumatic cylinder 2, which promotes, measures the side that roller 1 is pressed against slab, plate Base drives measurement roller to rotate in withdrawal straightening machine horizontal segment running, and the encoder 3 being connected with measurement roller calculates measurement roller rotation The number of turns turned obtains the length of slab.
Following Railway Projects be present using measurement roller scale system:1st, the speed reducing ratio for measuring roller is small;2nd, measurement roller is rotating During occur abrasion, skid situation;3rd, measure roller to lean against roll-in is measured on slab by cylinder pressure, gas pressure ripple It is dynamic big, it sometimes appear that measurement roller such as does not rotate at the failure, cause encoder can not normally count the length of tracking scale.More than Problem can all cause to influence the stability that slab scale surveys length, have a strong impact on the precision of slab cutting.
The content of the invention
A kind of slab scale is provided in the embodiment of the present invention and surveys long method and system, to solve scale of the prior art Survey the problem of long unstable.
In order to solve the above-mentioned technical problem, the embodiment of the invention discloses following technical scheme:
A kind of slab scale surveys long method, and methods described includes:
The default unit strand time;
Obtain strand and terminate required unit strand time number;
Obtain instantaneous strand speed of each unit strand time when starting;
Instantaneous strand speed when being started according to each unit strand time calculates the casting of each unit strand time Base length, the strand length of each unit strand time is added and obtained slab length.
Preferably, the acquisition strand terminates required unit strand time number, including:
When each unit strand time starts, the unit strand time number needed for strand is added up;
When terminating current one strand time strand, judge whether strand terminates;
If strand does not terminate, continue the strand of next unit strand time, and unit strand time number is carried out It is cumulative;Or
If strand terminates, stop strand, preserve unit strand time number.
Preferably, it is described to judge whether strand terminates, including:
The afterbody base head position of detection slab in real time;
If at the end of the current one strand time, detect that the afterbody base head position is differed with current end position Cause, then strand does not terminate, continues strand operation;Or
If at the end of the current one strand time, detecting that the afterbody base head position is consistent with current end position, Then strand terminates.
Preferably, instantaneous strand speed when acquisition each unit strand time starts includes:
Obtain each unit strand time motor for withdrawal & straightening machine instant rotation speed and motor for withdrawal & straightening machine running frequency when starting;
Instantaneous strand speed is obtained according to the instant rotation speed and the running frequency.
Preferably, the acquisition motor for withdrawal & straightening machine instant rotation speed includes:
Obtain the rated speed of motor for withdrawal & straightening machine and the speed reducing ratio of motor;
Obtain withdrawal straightening machine straightening roller diameter;
The motor for withdrawal & straightening machine instant rotation is obtained according to the rated speed, the speed reducing ratio and the straightening roller diameter Speed.
A kind of slab scale length measurement system, the system include:
Presetting module, for presetting the unit strand time;
First acquisition module, terminate required unit strand time number for obtaining strand;
Second acquisition module, for obtain each unit strand time start when instantaneous strand speed;
Processing module, instantaneous strand speed when each unit strand time for being obtained according to the acquisition module starts Degree calculates the strand length of each unit strand time, adds and obtain slab to grow the strand length of each unit strand time Degree.
Preferably, first acquisition module includes:
Counting unit, for when each unit strand time starts, entering to the unit strand time number needed for strand Row is cumulative;
Judging unit, for judging whether strand terminates when terminating current one strand time strand.
Preferably, the judging unit includes:
Detection sub-unit, for detecting the afterbody base head position of slab in real time;
Judgment sub-unit, for judge terminate the current one strand time, current end position whether with the detection The afterbody base head position consistency that subelement detects.
Preferably, second acquisition module includes:
Acquiring unit, for obtaining motor for withdrawal & straightening machine instant rotation speed and motor for withdrawal & straightening machine running frequency;
Processing unit, for handling the instant rotation speed and the running frequency that the acquiring unit obtains, obtain Obtain instantaneous strand speed.
Preferably, the acquiring unit includes:
Subelement is obtained, it is straight for obtaining the rated speed of motor for withdrawal & straightening machine, the speed reducing ratio of motor and withdrawal straightening machine pulling-straightening roller Footpath;
Subelement is handled, the rated speed, the speed reducing ratio and described obtained for handling the acquisition subelement Straightening roller diameter obtains the motor for withdrawal & straightening machine instant rotation speed.
From above technical scheme, a kind of slab scale provided in an embodiment of the present invention surveys long method and system, including: The default unit strand time, obtain strand and terminate required unit strand time number, obtaining each unit strand time starts When instantaneous strand speed, instantaneous strand speed when being started according to each unit strand time calculates each unit strand The strand length of time, the strand length of each unit strand time is added and obtained slab length.It is multiple by dividing The unit strand time, the strand length of each unit strand time is obtained respectively, finally obtain total strand length, complete to casting The scale for the slab produced surveys length, improves the stability of slab scalling-off detecting, improves slab lumber recovery comprehensively.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is the required accompanying drawing used in technology description to be briefly described, it should be apparent that, for those of ordinary skill in the art Speech, on the premise of not paying creative work, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is the structural representation that traditional measurement roller measures scale system;
Fig. 2 is the schematic flow sheet that a kind of slab scale provided in an embodiment of the present invention surveys long method;
Fig. 3 is a kind of method flow signal for obtaining strand and terminating unit strand time number provided in an embodiment of the present invention Figure;
Fig. 4 is a kind of schematic flow sheet of method for judging strand state provided in an embodiment of the present invention;
Fig. 5 is a kind of structural representation of slab scale length measurement system provided in an embodiment of the present invention.
Embodiment
In order that those skilled in the art more fully understand the technical scheme in the present invention, below in conjunction with of the invention real The accompanying drawing in example is applied, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described implementation Example only part of the embodiment of the present invention, rather than whole embodiments.It is common based on the embodiment in the present invention, this area The every other embodiment that technical staff is obtained under the premise of creative work is not made, should all belong to protection of the present invention Scope.
Referring to Fig. 2, for a kind of schematic flow sheet of the long method of slab scale survey provided in an embodiment of the present invention, methods described Including:
S101, the unit strand time is preset, because in slab casting, a bit of slab, the drawing of strand may be cast Speed in the default unit strand time, takes smaller value nor uniform as far as possible, so in each unit strand In strand speed level off to instantaneous strand speed of unit strand time when starting.Preferably, unit strand Time can be set as 100ms.
S102, obtain strand and terminate required unit strand time number;
During strand, a counter is set, when each unit strand time starts, to the unit needed for strand Strand time number is added up;For example, starting strand hour counter in first unit strand time is counted as 1, terminate the After N-1 unit strand time strand operation, rolling counters forward N-1;If now strand does not terminate, enter n-th list again The strand operation of position strand time, counter can when the n-th unit strand time starts, to the number of unit strand time from It is dynamic plus 1, because it is N-1 to be counted in previous moment, then when the n-th unit strand time starts, rolling counters forward N.
The method shown in Figure 3 for terminating unit strand time number for a kind of acquisition strand provided in an embodiment of the present invention Schematic flow sheet;
S201, the operation of current one strand time strand terminate;If with the unit strand time with the hypothesis in S101 Exemplified by 100ms, it is since operating current one strand time strand to judge that the operation of current one strand time strand terminates 100ms is crossed, judges that the operation of current one strand time strand terminates.
S202, judges whether strand terminates;
Referring to the schematic flow sheet that Fig. 4 is a kind of method for judging strand state provided in an embodiment of the present invention;
Judge whether strand terminates to be specially:
S301, the afterbody base head position of slab is detected in real time;Specifically during strand, multiple video cameras can be set IMAQ is carried out, the image collected is analyzed, obtains slab afterbody base head, and real-time tracking detects afterbody base head Position.
S302, judge whether the afterbody base head position is consistent with current end position;Current one strand time strand After operation terminates, video camera obtains whether the position currently terminated overlap with the image of the afterbody base head, to judge Whether consistent with current end position state afterbody base head position.
S303, if the afterbody base head position is consistent with current end position, strand terminates;What if video camera obtained Afterbody base head with current end position in the picture when overlap, then judge the afterbody base head position and current end position one Cause, send control instruction, terminate current strand operation, strand terminates.
S304, if the afterbody base head position and current end position are inconsistent, strand does not terminate;If video camera obtains The afterbody base head taken is misaligned in the picture with current end position, then judges the afterbody base head position and current end position It is inconsistent, continue current strand operation, strand does not terminate.
S203, if strand terminates, stop strand operation, preserve unit strand time number;For example, if complete N-1 After the strand operation of individual unit strand time, strand terminates, then need not continue strand, therefore records strand and terminate required unit The strand time is N-1, and is preserved, and is used for the follow-up slab length that calculates.
S204, if strand is not terminate, continue the strand of next unit strand time, and the unit strand time is individual Number is added up;After if the same strand in the N-1 unit strand time of completion operates, strand does not terminate, then can The strand operation of n-th unit strand time is gone successively to, at the same time the number of unit strand time can be in previous unit Added up on the basis of strand time counting, number is changed into N from N-1.
S103, obtain instantaneous strand speed of each unit strand time when starting;
Motor for withdrawal & straightening machine instant rotation speed and motor for withdrawal & straightening machine operation when starting of each unit strand time are obtained first Frequency;Instantaneous strand speed is obtained according to the instant rotation speed and the running frequency.
If the motor for withdrawal & straightening machine instant rotation speed obtained is vx, the motor operation frequency of withdrawal straightening machine is F, then institute It is Vn=vx/50*F to state instant rotation speed, it is assumed that strand terminates to need by N number of unit strand time, therefore to count respectively Calculate the instant rotation speed of each unit strand time, the motor operation frequency F of wherein withdrawal straightening machine is fixed, but withdrawal straightening machine Motor transient speed may change, therefore gather the withdrawal straightening machine instant rotation speed that each unit interval starts respectively.
The instant rotation speed of first unit strand time:V1=v1/50*F;
The instant rotation speed of second unit strand time:V2=v2/50*F;
The instant rotation speed of 3rd unit strand time:V3=v3/50*F;
…………………………………………
The instant rotation speed of the N-1 unit strand time:Vn-1=vn-1/50*F;
The instant rotation speed of n-th unit strand time:Vn=vn/50*F.
Preferably, the acquisition motor for withdrawal & straightening machine instant rotation speed includes:Obtain motor for withdrawal & straightening machine rated speed and The speed reducing ratio of motor, withdrawal straightening machine straightening roller diameter is obtained, according to the rated speed, the speed reducing ratio and the straightening roller diameter Obtain the motor for withdrawal & straightening machine instant rotation speed;
If the rated speed of motor is M, the speed reducing ratio of motor is S, a diameter of D of withdrawal straightening machine pulling-straightening roller, then withdrawal straightening machine Motor instant rotation speed vx=1/S*M* π * D/1000.When wherein each unit strand time starts, the deceleration of the motor The motor for withdrawal & straightening machine instant rotation speed vx can be influenceed than S, so as to cause withdrawal straightening machine when commensurate's strand time does not start Instant rotation speed has certain error.
S104, instantaneous strand speed when being started according to each unit strand time calculate each unit strand time Strand length, the strand length of each unit strand time is added and obtained slab length.
Also assume that strand terminated to need by N number of unit strand time, then:
The strand length of first unit strand time:S1=100/60000*V1;
The strand length of second unit strand time:S2=100/60000*V2;
The strand length of 3rd unit strand time:S3=100/60000*V2;
…………………………………………
The strand length of the N-1 unit strand time:Sn-1=100/60000*Vn-1;
The strand length of n-th unit strand time:Sn=100/60000*Vn,
Strand terminates N number of unit strand time strand length (cut lengths) L=S1+S2+S3+ ...+Sn-1+Sn.
As seen from the above-described embodiment, a kind of slab scale that the present embodiment provides, which surveys long method, to be included:Default unit strand Time, obtain strand and terminate required unit strand time number, obtain instantaneous strand of each unit strand time when starting Speed, instantaneous strand speed when being started according to each unit strand time calculate the strand of each unit strand time and grown Degree, the strand length of each unit strand time is added and obtained slab length.By dividing multiple unit strand times, The strand length of each unit strand time is obtained respectively, finally obtains total strand length, is completed to the slab that casts out Scale surveys length, improves the stability of slab scalling-off detecting, improves slab lumber recovery comprehensively.
Corresponding with a kind of long embodiment of the method for slab scale survey provided by the invention, present invention also offers a kind of slab Scale length measurement system.
It is a kind of structural representation of slab scale length measurement system provided in an embodiment of the present invention referring to Fig. 5, the system Including:
Presetting module 401, for presetting the unit strand time;
First acquisition module 402, terminate required unit strand time number for obtaining strand;
First acquisition module 402 includes counting unit and judging unit.The counting unit, in each unit When the strand time starts, the unit strand time number needed for strand is added up;The judging unit, for judging tying During beam current one strand time strand, whether strand terminates.
The judging unit includes detection sub-unit and judgment sub-unit again:The detection sub-unit, for detecting in real time The afterbody base head position of slab;The judgment sub-unit, for judging terminating the current one strand time, current end position Whether the afterbody base head position consistency detected with the detection sub-unit.
Second acquisition module 403, for obtain each unit strand time start when instantaneous strand speed;
Second acquisition module 403 includes:Acquiring unit and processing unit.The acquiring unit, for obtaining straightening Electromechanical machine instant rotation speed and motor for withdrawal & straightening machine running frequency;The processing unit, obtained for handling the acquiring unit The instant rotation speed and the running frequency, obtain instantaneous strand speed.
The acquiring unit includes obtaining subelement and processing subelement again:The acquisition subelement, for obtaining straightening The rated speed of electromechanical machine, the speed reducing ratio of motor and withdrawal straightening machine straightening roller diameter;The processing subelement, for handling described obtain The rated speed, the speed reducing ratio and the straightening roller diameter for taking subelement to obtain obtain the motor for withdrawal & straightening machine and instantaneously turned Dynamic speed.
Processing module 404, instantaneous casting when each unit strand time for being obtained according to the acquisition module starts Base speed calculates the strand length of each unit strand time, adds and obtain slab by the strand length of each unit strand time Length.
As seen from the above-described embodiment, a kind of slab scale that the present embodiment provides surveys long method system, including presetting module 401st, the first acquisition module 402, the second acquisition module 403 and processing module 404, the presetting module 401 preset unit strand Time, first acquisition module 402 obtain strand and terminate required unit strand time number, second acquisition module Instantaneous strand speed when 403 acquisition each unit strand times started, the processing module 404 are cast according to each unit Instantaneous strand speed when the base time starts calculates the strand length of each unit strand time, will each unit strand when Between strand length add and obtain slab length.The system improves the stability of slab scalling-off detecting, improve slab into Material rate.
Each embodiment in this specification is described by the way of progressive, identical similar portion between each embodiment Divide mutually referring to what each embodiment stressed is the difference with other embodiment.Especially for system or For system embodiment, because it is substantially similar to embodiment of the method, so describing fairly simple, related part is referring to method The part explanation of embodiment.System and system embodiment described above is only schematical, wherein the conduct The unit that separating component illustrates can be or may not be it is physically separate, can be as the part that unit is shown or Person may not be physical location, you can with positioned at a place, or can also be distributed on multiple NEs.Can root Factually border needs to select some or all of module therein realize the purpose of this embodiment scheme.Ordinary skill Personnel are without creative efforts, you can to understand and implement.
It should be noted that herein, the relational terms of such as " first " and " second " or the like are used merely to one Individual entity or operation make a distinction with another entity or operation, and not necessarily require or imply these entities or operate it Between any this actual relation or order be present.Moreover, term " comprising ", "comprising" or its any other variant are intended to Cover including for nonexcludability, so that process, method, article or equipment including a series of elements not only include those Key element, but also the other element including being not expressly set out, or also include for this process, method, article or set Standby intrinsic key element.In the absence of more restrictions, the key element limited by sentence "including a ...", it is not excluded that Other identical element in the process including the key element, method, article or equipment also be present.
Described above is only the embodiment of the present invention, is made skilled artisans appreciate that or realizing this hair It is bright.A variety of modifications to these embodiments will be apparent to one skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, it is of the invention The embodiments shown herein is not intended to be limited to, and is to fit to and principles disclosed herein and features of novelty phase one The most wide scope caused.

Claims (10)

1. a kind of slab scale surveys long method, it is characterised in that methods described includes:
The default unit strand time;
Obtain strand and terminate required unit strand time number;
Obtain instantaneous strand speed of each unit strand time when starting;
Instantaneous strand speed when being started according to each unit strand time calculates the strand of each unit strand time and grown Degree, the strand length of each unit strand time is added and obtained slab length.
2. slab scale according to claim 1 surveys long method, it is characterised in that the acquisition strand terminates required list Position strand time number, including:
When each unit strand time starts, the unit strand time number needed for strand is added up;
When terminating current one strand time strand, judge whether strand terminates;
If strand does not terminate, continue the strand of next unit strand time, and unit strand time number is added up; Or
If strand terminates, stop strand, preserve unit strand time number.
3. slab scale according to claim 2 surveys long method, it is characterised in that described to judge whether strand terminates, bag Include:
The afterbody base head position of detection slab in real time;
If at the end of the current one strand time, detect that the afterbody base head position and current end position are inconsistent, then Strand does not terminate, continues strand operation;Or
If at the end of the current one strand time, detect that the afterbody base head position is consistent with current end position, then cast Base terminates.
4. slab scale according to claim 1 surveys long method, it is characterised in that described to obtain each unit strand time Instantaneous strand speed during beginning includes:
Obtain each unit strand time motor for withdrawal & straightening machine instant rotation speed and motor for withdrawal & straightening machine running frequency when starting;
Instantaneous strand speed is obtained according to the instant rotation speed and the running frequency.
5. slab scale according to claim 4 surveys long method, it is characterised in that the acquisition motor for withdrawal & straightening machine instantaneously turns Dynamic speed includes:
Obtain the rated speed of motor for withdrawal & straightening machine and the speed reducing ratio of motor;
Obtain withdrawal straightening machine straightening roller diameter;
The motor for withdrawal & straightening machine instant rotation speed is obtained according to the rated speed, the speed reducing ratio and the straightening roller diameter Degree.
6. a kind of slab scale length measurement system, it is characterised in that the system includes:
Presetting module, for presetting the unit strand time;
First acquisition module, terminate required unit strand time number for obtaining strand;
Second acquisition module, for obtain each unit strand time start when instantaneous strand speed;
Processing module, instantaneous strand speedometer when each unit strand time for being obtained according to the acquisition module starts The strand length of each unit strand time is calculated, the strand length of each unit strand time is added and obtained slab length.
7. slab scale length measurement system according to claim 6, it is characterised in that first acquisition module includes:
Counting unit, for when each unit strand time starts, tiring out to the unit strand time number needed for strand Add;
Judging unit, for judging whether strand terminates when terminating current one strand time strand.
8. slab scale length measurement system according to claim 7, it is characterised in that the judging unit includes:
Detection sub-unit, for detecting the afterbody base head position of slab in real time;
Judgment sub-unit, for judging terminating the current one strand time, whether current end position is single with detection The afterbody base head position consistency that member detects.
9. slab scale length measurement system according to claim 6, it is characterised in that second acquisition module includes:
Acquiring unit, for obtaining motor for withdrawal & straightening machine instant rotation speed and motor for withdrawal & straightening machine running frequency;
Processing unit, for handling the instant rotation speed and the running frequency that the acquiring unit obtains, obtain wink When strand speed.
10. slab scale length measurement system according to claim 9, it is characterised in that the acquiring unit includes:
Subelement is obtained, for obtaining the rated speed of motor for withdrawal & straightening machine, the speed reducing ratio of motor and withdrawal straightening machine straightening roller diameter;
Subelement is handled, the rated speed, the speed reducing ratio and the straightening obtained for handling the acquisition subelement Roller diameter obtains the motor for withdrawal & straightening machine instant rotation speed.
CN201610087984.0A 2016-02-16 2016-02-16 A kind of slab scale surveys long method and system Active CN105710323B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610087984.0A CN105710323B (en) 2016-02-16 2016-02-16 A kind of slab scale surveys long method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610087984.0A CN105710323B (en) 2016-02-16 2016-02-16 A kind of slab scale surveys long method and system

Publications (2)

Publication Number Publication Date
CN105710323A CN105710323A (en) 2016-06-29
CN105710323B true CN105710323B (en) 2018-01-02

Family

ID=56156798

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610087984.0A Active CN105710323B (en) 2016-02-16 2016-02-16 A kind of slab scale surveys long method and system

Country Status (1)

Country Link
CN (1) CN105710323B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107378188A (en) * 2017-06-02 2017-11-24 内蒙古包钢钢联股份有限公司 A kind of strand method for scaling
CN107971347A (en) * 2017-10-20 2018-05-01 唐山中厚板材有限公司 The thick online hot long method of survey of hot rolled plate in one kind
CN107931554B (en) * 2017-11-30 2020-07-10 山信软件股份有限公司 Continuous casting billet positioning calculation method
CN107941186A (en) * 2017-12-13 2018-04-20 山信软件股份有限公司 A kind of displacement sensing system

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0732110A (en) * 1993-07-21 1995-02-03 Nippon Steel Corp Method for cutting off cast slab
JPH0919749A (en) * 1995-07-06 1997-01-21 Nippon Steel Corp Method for controlling cut-off of cast slab in continuous casting
CN101811182B (en) * 2009-02-25 2012-05-30 宝山钢铁股份有限公司 Process for online cut-to-length cutting production of continuous casting slabs for heavy plate mill
CN203862977U (en) * 2013-12-30 2014-10-08 南阳汉冶特钢有限公司 Slab continuous casting and cut length measuring device
CN104772443B (en) * 2015-04-09 2017-07-14 田志恒 A kind of continuous casting fixed-length length measurement system and method

Also Published As

Publication number Publication date
CN105710323A (en) 2016-06-29

Similar Documents

Publication Publication Date Title
CN105710323B (en) A kind of slab scale surveys long method and system
CN105718989B (en) A kind of bar counting method based on machine vision
CN104772443B (en) A kind of continuous casting fixed-length length measurement system and method
CN103913140A (en) Casting blank length precision measuring device and method
CN104190963A (en) Device and method of tool setting of digital controlled lathe based on machine vision
CN106424156A (en) Cold tandem mill thickness control system and thickness control method of cold tandem mill process
KR101430316B1 (en) Data analysys apparatus
EP2505965B1 (en) Method and monitoring unit for testing position values
CN110497248B (en) System and method for detecting fixed-length shearing precision of flying shears in real time
CN105629921A (en) Post-continuous casting slab cutting quality defect judgment and secondary processing method
EP3981719A1 (en) Deceleration cutting control method and control apparatus
CN105170483B (en) Based on the synchronous industry mechanical arm processing defective work statistical method of construction and device
CN103341508A (en) Automatic strip steel tension setting system and method
CN110976526A (en) Method, system and computer readable medium for detecting deviation degree of rolling mill thickness gauge
CN106077158B (en) A kind of cold-rolled steel sheet collecting machine, shear system and rewinding method
JP6729211B2 (en) Crane information presentation system
CN108856307A (en) A kind of mechanical equipment position detecting device and detection method
CN101634840B (en) Material tracking and controlling method for rotary hearth furnace
JP2547850B2 (en) Plate thickness controller for cold tandem rolling mill
JP2781860B2 (en) How to cut steel bars
CN104843266A (en) Control method used for labeling detection machine and apparatus thereof
CN104084448A (en) Synchronous control system used for rewinding subdivision set double coiling machine
CN115446126B (en) Steel biting and throwing method for hot rolling fixed-width press
DE3333091A1 (en) METHOD FOR CONTINUOUSLY DETECTING THE PART ROLLING LENGTH IN A CONTINUE. ROLLING MILL AND DEVICE FOR CARRYING OUT THE METHOD
CN113083911B (en) Rolling process control method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20161221

Address after: 250101 Shandong city of Ji'nan province high tech Zone Shun Road No. 2000 Shun Tai Plaza No. 4

Applicant after: Software Limited by Share Ltd

Address before: 271104 Shandong Province, Laiwu City Gangcheng District Front Street No. 99

Applicant before: Shandong Iron & Steel Group Co., Ltd.

GR01 Patent grant