- Prior art keywords
- screw
- insulator
- fixture
- clamping device
- left end
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
Landscapes
- Electric Cable Installation (AREA)
Abstract
The invention discloses a special tool for exchanging a first insulator of a tension insulator string, characterized by comprising a steel cap clamping device (2). The middle part of the steel cap clamping device (2) is provided with a groove (17), and left and right ends of the steel cap clamping device (2) are connected to left and right ends of a rocking handle (1). The left end of the rocking handle (1) is connected to a left lead screw, and the right end of the rocking handle (1) is connected to a right lead screw. The left lead screw is connected to an upper end of a left pulling plate through a left screw, and the right lead screw is connected to an upper end of a right pulling plate through a right screw. A lower end of the left puling plate is connected to a left end of an L-shaped clamping device (11) through a screw, and a lower end of the right pulling plate is connected to a right end of the L-shaped clamping device (11) through a screw. The L-shaped clamping device (11) is a clamping device with an opening in the left end. The left end of the L-shaped clamping device (11) is provided with a built-in L-shaped link plate clamping groove (18). The left end of the L-shaped clamping device (11) is provided with a left lower screw hole (7). The special tool for exchanging the first insulator of the tension insulator string has simple structure, small weight, simple operation, and easy operation, and is convenient to install and disassemble. A single person can carry the special tool for exchanging the first insulator of the tension insulator string to go on a tower and finishes the operation without removing the whole insulator string. The time and labor are saved, the high altitude operation labor intensity is reduced, and the special tool for exchanging the first insulator of the tension insulator string is safe and reliable.
Description
Technical field:
The present invention relates to a kind of replacing strain insulator string first insulator specific purpose tool, belong to power system transmission of electricity fortune inspection field。
Background technology:
In transmission line of electricity, strain insulator string determine that side of wire first insulator voltage's distribiuting is high because of voltage's distribiuting feature, deterioration rate is high, null value very easily occurs, need to be replaced, as changed not in time, it is easy to causes line insulation intensity to reduce, affect circuit safe operation。At present, the fixture of existing replacing strain insulator double insulator string monolithic insulator, can only start to change from the second of insulator chain, owing to fixture self restriction cannot change first insulator, therefore the method processing this type of defect can only be integral replacing insulator chain, and operation is loaded down with trivial details, longevity of service, not only increase work high above the ground labor intensity, and add potential safety hazard。
Summary of the invention:
It is an object of the invention to overcome the deficiency of above-mentioned prior art to provide a kind of simple in construction, weight is little, simple to operate, be easily installed dismounting, it is easy to operation, it is possible to single carry tower and complete operation, whole insulator chain need not be removed, time saving and energy saving, reduce work high above the ground labor intensity, the safe and reliable specific purpose tool changing strain insulator string first insulator。
The purpose of the present invention can be reached by following measure: a kind of specific purpose tool changing strain insulator string first insulator, it is characterized in that it includes steel cap fixture, the middle part of steel cap fixture is provided with groove, the left end of steel cap fixture connects the left end of rocking handle; the left end of rocking handle connects left leading screw; left leading screw connects the upper end of Zola's plate by left screw; the lower end of Zola's plate connects the left end of L-type fixture by upper left screw; L-type fixture is the fixture of left end opening; L-type fixture left end is provided with built-in L-type yoke plate draw-in groove, and L-type fixture left end is provided with lower-left screw hole;The right-hand member of steel cap fixture connects the right-hand member of rocking handle, and the right-hand member of rocking handle connects right leading screw, and right leading screw connects the upper end of right pulling plate by right screw, and the lower end of right pulling plate connects the right-hand member of fixture by bottom right screw。
The present invention can produce following good effect compared with the prior art: the present invention is a kind of safe and reliable, facilitation, practical replacing insulator instrument, it is provided with fixture, arm-tie, steel cap fixture, rocking handle four part, fixture is left end opening fixture, built-in draw-in groove, it is possible to L-type yoke plate is firmly stuck in draw-in groove;Left and right two panels arm-tie, by leading screw working tension, shortens the distance between fixture and steel cap fixture, allows insulator chain relax;Steel cap fixture is stuck on insulator chain gold utensil by groove;After equipment installs, pull rocking handle。It has:
1. simple in construction, weight is little, simple to operate, it is simple to installing/dismounting, it is easy to operation, it is possible to single carry tower and complete operation;
2. when need not remove whole insulator chain, realize changing yoke plate place first insulator, time saving and energy saving, reduce work high above the ground labor intensity, safe and reliable。
Accompanying drawing illustrates:
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the structural representation of the steel cap fixture of the present invention;
Fig. 3 is the structural representation of the L-type fixture of the present invention;
Fig. 4 is the use state diagram of the present invention。
Detailed description of the invention: the flow process that is embodied as of invention is elaborated below in conjunction with accompanying drawing。
Embodiment: a kind of specific purpose tool (referring to Fig. 1-Fig. 4) changing strain insulator string first insulator, it includes steel cap fixture 2, the middle part of steel cap fixture 2 is provided with groove 17, the left end of steel cap fixture 2 connects the left end of rocking handle 1; left end of rocking handle 1 connects left leading screw 3; left leading screw 3 connects the upper end of Zola's plate 5 by left screw 4; lower end of Zola's plate 5 connects the left end of L-type fixture 11 by upper left screw 6; L-type fixture 11 is the fixture of left end opening; L-type fixture 11 left end is provided with built-in L-type yoke plate draw-in groove 18, and L-type fixture 11 left end is provided with lower-left screw hole 7;The right-hand member of steel cap fixture 2 connects the right-hand member of rocking handle 1, and the right-hand member of rocking handle 1 connects right leading screw 16, and right leading screw 16 connects the upper end of right pulling plate 14 by right screw 15, and the lower end of right pulling plate 14 connects the right-hand member of fixture 11 by bottom right screw 12。
Operating insulator chain 13 is connected on L-type yoke plate 8, L-type yoke plate has screw hole 9 install U-shaped draw ring 10, is connected on steel tower by U-shaped draw ring 10。During work, steel cap fixture 2 is stuck on the gold utensil between two panels insulator is fixed by groove 17, two, left and right arm-tie 5,14 is connected on leading screw 3,16 is placed on insulator chain both sides by screw 4,15, fixture 11 is fixed on the arm-tie 14 of the right by bottom right screw 12, fixture 11 is the left end fixture with draw-in groove, fixture 11 is fixed by screw by lower-left screw hole 7 after being stuck on the L-type yoke plate 8 of steel tower, is connected with left side arm-tie 5 finally by fixture upper left screw 6 and fixes。
After inspection installs instrument, drive left and right leading screw to rotate tension the right and left arm-tie by shaking rocking handle 1, until insulator chain 13 loosens, reach to change the purpose of first insulator。
Claims (1)
1. the specific purpose tool changing strain insulator string first insulator, it is characterized in that it includes steel cap fixture (2), the middle part of steel cap fixture (2) is provided with groove (17), the left end of steel cap fixture (2) connects the left end of rocking handle (1), the left end of rocking handle (1) connects left leading screw (3), left leading screw (3) connects the upper end of Zola's plate (5) by left screw (4), the lower end of Zola's plate (5) connects the left end of L-type fixture (11) by upper left screw (6), the fixture that L-type fixture (11) is left end opening, L-type fixture (11) left end is provided with built-in L-type yoke plate draw-in groove (18), L-type fixture (11) left end is provided with lower-left screw hole (7);The right-hand member of steel cap fixture (2) connects the right-hand member of rocking handle (1); the right-hand member of rocking handle (1) connects right leading screw (16); right leading screw (16) connects the upper end of right pulling plate (14) by right screw (15), and the lower end of right pulling plate (14) connects the right-hand member of fixture (11) by bottom right screw (12)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610120157.7A CN105703266A (en) | 2016-03-03 | 2016-03-03 | Special tool for exchanging a first insulator of tension insulator string |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610120157.7A CN105703266A (en) | 2016-03-03 | 2016-03-03 | Special tool for exchanging a first insulator of tension insulator string |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105703266A true CN105703266A (en) | 2016-06-22 |
Family
ID=56222792
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610120157.7A Pending CN105703266A (en) | 2016-03-03 | 2016-03-03 | Special tool for exchanging a first insulator of tension insulator string |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105703266A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108418139A (en) * | 2018-05-31 | 2018-08-17 | 国家电网公司 | Live-line replacing strain string side of wire first insulator L-type fixture |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201178266Y (en) * | 2008-04-02 | 2009-01-07 | 云南电网公司大理供电局 | Clamp apparatus live replacing dual insulator of 500kV terminal |
CN201263063Y (en) * | 2008-07-21 | 2009-06-24 | 云南电网公司曲靖供电局 | Tool for replacing straight-line simply connected double-string overhang insulator |
CN101931181A (en) * | 2010-03-26 | 2010-12-29 | 福建省电力有限公司厦门电业局 | Strain tower double-hanging-point single-link-plate insulator chain ground potential live exchange device |
CN202308914U (en) * | 2011-11-08 | 2012-07-04 | 杭州市电力局 | Link plate clamping tool used to replace four-split lead duplex strain insulator string |
CN203456795U (en) * | 2013-08-15 | 2014-02-26 | 国网浙江省电力公司杭州供电公司 | Conductor-side link plate clamping tool for replacing four-split conductor duplex strain insulator string |
CN205565510U (en) * | 2016-03-03 | 2016-09-07 | 国网山东省电力公司烟台供电公司 | Change specialized tool of first piece insulator of strain insulator string |
-
2016
- 2016-03-03 CN CN201610120157.7A patent/CN105703266A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201178266Y (en) * | 2008-04-02 | 2009-01-07 | 云南电网公司大理供电局 | Clamp apparatus live replacing dual insulator of 500kV terminal |
CN201263063Y (en) * | 2008-07-21 | 2009-06-24 | 云南电网公司曲靖供电局 | Tool for replacing straight-line simply connected double-string overhang insulator |
CN101931181A (en) * | 2010-03-26 | 2010-12-29 | 福建省电力有限公司厦门电业局 | Strain tower double-hanging-point single-link-plate insulator chain ground potential live exchange device |
CN202308914U (en) * | 2011-11-08 | 2012-07-04 | 杭州市电力局 | Link plate clamping tool used to replace four-split lead duplex strain insulator string |
CN203456795U (en) * | 2013-08-15 | 2014-02-26 | 国网浙江省电力公司杭州供电公司 | Conductor-side link plate clamping tool for replacing four-split conductor duplex strain insulator string |
CN205565510U (en) * | 2016-03-03 | 2016-09-07 | 国网山东省电力公司烟台供电公司 | Change specialized tool of first piece insulator of strain insulator string |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108418139A (en) * | 2018-05-31 | 2018-08-17 | 国家电网公司 | Live-line replacing strain string side of wire first insulator L-type fixture |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103558421B (en) | For the junction pole of isolating switch electrical test | |
CN102185265B (en) | Construction method for replacing cross arm of 35kV line linear rod | |
CN203981720U (en) | A kind of setting up and lightning arrester live-line test wire clamp easy to use | |
CN105703266A (en) | Special tool for exchanging a first insulator of tension insulator string | |
CN204424804U (en) | Equipotential changes the instrument of the two soft bus strain insulator of simply connected | |
CN201514457U (en) | Voltage withstand testing device for insulating rod-like tools | |
CN103996469B (en) | A kind of composite insulator one-shot forming compression bonding apparatus | |
CN205565510U (en) | Change specialized tool of first piece insulator of strain insulator string | |
CN104375059A (en) | Test device and test method for electric transmission lines of power system | |
CN104014490A (en) | Automatic meter setting and sorting device used for detecting streamline by electric energy meter in automation mode | |
CN204241620U (en) | A kind of power system transmission line proving installation | |
CN204252623U (en) | A kind of easy-to-mount bracing wire sheath | |
CN203871639U (en) | Dismounting installation device of quick plug 2M head | |
CN105945855A (en) | Seal part mounting tool for deep-hole equipment | |
KR20170000575U (en) | A jig for maintenance 0f axial flow gas pressure regulator | |
CN203423430U (en) | Insulator maintenance device | |
CN204517272U (en) | The instrument of live installation of bird repeller | |
CN203747295U (en) | Special tool used for changing tension insulator of a 10kV power supply circuit in live-line state | |
CN103187695B (en) | Tool specially for assembling and disassembling power circuit spacer and assembling and disassembling method thereof | |
CN204030022U (en) | One exempts to step on rod earth wire | |
CN105048343A (en) | Double-end tackle for hot-line work of power transmission line | |
CN203039294U (en) | Working tool for live-line replacement of three-hole single connection plate linear insulator string | |
CN203760924U (en) | Auxiliary tool for mounting cross arm on telegraph pole | |
CN204885952U (en) | Assembly and disassembly tools of energy -stored spring | |
CN204154742U (en) | Super High Voltage Live-line Operation insulating safety tools test suspender |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20160622 |