CN105696625B - The dredging method of immersed tube tunnel rubble bedding desilting system - Google Patents

The dredging method of immersed tube tunnel rubble bedding desilting system Download PDF

Info

Publication number
CN105696625B
CN105696625B CN201610059035.1A CN201610059035A CN105696625B CN 105696625 B CN105696625 B CN 105696625B CN 201610059035 A CN201610059035 A CN 201610059035A CN 105696625 B CN105696625 B CN 105696625B
Authority
CN
China
Prior art keywords
bedding
dredging
immersed tube
slush pump
dredging pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610059035.1A
Other languages
Chinese (zh)
Other versions
CN105696625A (en
Inventor
刘德进
冯海暴
苏长玺
李增军
曲俐俐
张学俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Engineering Co Ltd
No 2 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
No 2 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd, No 2 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN201610059035.1A priority Critical patent/CN105696625B/en
Publication of CN105696625A publication Critical patent/CN105696625A/en
Application granted granted Critical
Publication of CN105696625B publication Critical patent/CN105696625B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/063Tunnels submerged into, or built in, open water
    • E02D29/07Tunnels or shuttering therefor preconstructed as a whole or continuously made, and moved into place on the water-bed, e.g. into a preformed trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/02Stream regulation, e.g. breaking up subaqueous rock, cleaning the beds of waterways, directing the water flow
    • E02B3/023Removing sediments

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

A kind of immersed tube tunnel rubble bedding desilting system, including foundation trench, bedding is equipped in the foundation trench, the bedding includes the block stone layer and metalling that set from bottom to top, dredging pipe, the dredging tube wall perforate are provided in the metalling, the dredging pipe is connected with slush pump.Immersed tube tunnel rubble bedding desilting system has just buried dredging pipe when bedding is laid in metalling, when bedding has mud, open slush pump, mud can be then entered by the gap of metalling in dredging pipe, and by silt displacement, system structure is simple, operation is easy, the influence of the environmental factors such as current, weather is not easily susceptible to, dredging effect is good, does not interfere with the foundation bed structure for being laid with completion, it can ensure the precision of later stage immersed tube installation, improve the service life in tunnel.

Description

The dredging method of immersed tube tunnel rubble bedding desilting system
Technical field
The present invention relates to immersed tube tunnel technical field of construction, are a kind of immersed tube tunnel rubble bedding dredging systems specifically The dredging method of system.
Background technology
Subaqueous tunnel is passed through frequently with immersed tunnelling method, and entire tunnel immersed tube is made of more piece tube coupling, and tube coupling is put into the bottom one by one Rubble bedding on, rubble bedding needs to consume a few days from starting to be routed to tube coupling installation, due in some waters silt content compared with Height, along with there is certain thickness mud in foundation trench top of the slope original mud face, by the ship travelled on the variation of flood season silt content, neighbouring navigation channel The influence of disturbance and atmospheric and climatic factors to water can cause to back-silt increasing or even causing poly- silt, in foundation trench on rubble bedding Mud will carry out many problems to Immersed tunnel and pipeline section forced belt itself.Mud adversely affects master caused by immersed tube tunnel Including:Change rubble bedding mechanical characteristic, influence the power transmission effect of foundation bed structure;Bedding face deposit, cause sinking tube coupling without Method implantation;Disturbance to deposit changes seawater unit weight, influences the anti-floating safety of immersed tube section;If on blotter basis In accompany mud, after tunnel operation, immersed tube settlement after construction can be caused excessive and differential settlement because of the consolidation deformation of mud It is exceeded, larger moment of flexure is generated in pipeline section, when serious pipeline section is caused to crack.
In order to avoid mud influences immersed tube tunnel, two ways is mainly used at present:One kind is cladding process, utilizes geotextiles Bedding is covered, prevents mud from falling on bedding;Another kind is dredging method, the mud that will be fallen on using rake suction ship on bedding Absorption is fallen.Both modes all there are it is more the problem of, the former operates more troublesome, is easily influenced, prevents be subject to current What is become silted up is ineffective;The latter needs that rake is made to inhale ship work department close to bedding, and under water currents, rake is inhaled ship and easily rocked, and makes it Work department touches bedding, destroys the bedding laid, influences the installation accuracy of immersed tube, if rake is inhaled after ship is fixed again Operation, and need repeatedly to carry out movement and fixation that rake inhales ship, add operation difficulty.
The content of the invention
The present invention for above-mentioned existing sludge treatment mode there are the problem of, it is proposed that a kind of new immersed tube tunnel rubble base The dredging method of bed desilting system.
The immersed tube tunnel rubble bedding desilting system of the present invention, including foundation trench, is equipped with bedding, the base in the foundation trench Bed includes the block stone layer and metalling that set from bottom to top, is provided with dredging pipe in the metalling, the dredging tube wall is opened Hole, the dredging pipe are connected with slush pump.
Preferably, the dredging pipe is horizontally set on the bottom of metalling, and the perforate of the dredging pipe is all located at upside.
A kind of dredging method of immersed tube tunnel rubble bedding desilting system, step are as follows:
1) foundation trench is excavated, then carries out underlayment processing, block stone is thrown into foundation trench, and block stone is rammed into Heisei block stone layer;
2) dredging pipe handling sinking is installed on block stone layer;
3) metalling is laid with above the block stone layer for having laid dredging pipe, bedding is completed and is laid with;
4) slush pump with dredging pipe is connected, opens slush pump, removed mud by rubble gap using waterway circulating.
Preferably, foundation trench excavation is carried out by dredger, by jackstone ram flat ship carry out block stone be thrown into and ram it is flat, it is logical It crosses lifting equipment and carries out dredging pipe installation, metalling is laid with by leveling ship.
Preferably, before dredging pipe being installed, the fast interface of connection slush pump is reserved on dredging pipe.
Preferably, bedding is laid with segmentation and carries out, and is first laid with one section of block stone layer, then installs dredging on this section of block stone layer Pipe is finally laid with metalling again on this section of block stone layer, complete the laying of one section of bedding, then carry out the laying of next section of bedding.
Preferably, often it is laid with and completes one section of bedding, you can monitoring of back-silting is carried out to this section of bedding, when the mud detected When thickness is more than that regulation requires, i.e., slush pump with the dredging pipe of this section of bedding is connected, carries out silt displacement.
Preferably, first using multi-beam and the box detection silt depth that back-silts, when the silt depth detected is more than regulation It is required that when, then slush pump is connected with dredging pipe, carry out silt displacement.
Preferably, slush pump is mounted on ship, dredger is positioned above the bedding for needing dredging, is used diver Dredging pipe is connected by lower water with slush pump.
Preferably, the water quality of discharge mud is monitored during the mud discharge of slush pump extraction in real time, when monitoring is arranged When the water quality for going out mud is clear water, slush pump is out of service.
The beneficial effects of the invention are as follows:Immersed tube tunnel rubble bedding desilting system is when bedding is laid with, just in metalling Dredging pipe has been buried, when bedding has mud, has opened slush pump, mud then can enter dredging pipe by the gap of metalling In, by silt displacement, system structure is simple, and operation is easy, is not easily susceptible to the influence of the environmental factors such as current, weather, dredging effect Fruit is good, does not interfere with the foundation bed structure for being laid with completion, can ensure the precision of later stage immersed tube installation, improves the use in tunnel Service life.Dredging pipe is located at metalling bottom, and seat alleviates influence of the dredging pipe to former base bed structure on block stone layer, ensures base The stability of bed structure, is also their ability to the fully erased mud fallen into rubble layer gap, the perforate of dredging pipe upward, energy Suction is enough enable more directly to be transferred to bedding surface, mud is enable to be absorbed completely, ensures the effect of mud cleaning.
The exploitation of foundation trench and the rammer that is thrown into of block stone are put down all using traditional work mode, and system building difficulty is low, Neng Goubao The higher construction quality of card.Bedding broken-up laying, dredging segmentation carry out, and circulate operation not to bedding row into disturbance, and can lead to Simple ship is crossed to realize, not under the influence of an accommodation basis leveling and other processes.Dredging pipe reserves fast interface, convenient for quick It is connected with slush pump, dredging is carried out beneficial to segmentation.Dredging operation is carried out again after detection silt depth, reduces dredging to the greatest extent The number of operation reduces the cost of operation.Slush pump flexibly can use and install connection, operating flexibility on dredger Property is strong.Dredging process to slush pump extraction monitored in real time, be just stopped after up to standard, avoid unnecessary energy consumption with Manpower consumption.
Description of the drawings
Attached drawing 1 is the horizontal schematic diagram of this immersed tube tunnel rubble bedding desilting system.
Attached drawing 2 is the top cross-sectional view of this immersed tube tunnel rubble bedding desilting system.
Attached drawing 3 is longitudinal schematic diagram of this immersed tube tunnel rubble bedding desilting system.
Specific embodiment
It is detailed in conjunction with appended preferred embodiment in order to further appreciate that structure, feature and the other purposes of the present invention It is described as follows, illustrated preferred embodiment is merely to illustrate technical scheme, and the non-limiting present invention.
The specific embodiment of the present invention is as follows:
As shown in Figures 1 to 3, which includes foundation trench 1, and bedding, base are equipped in foundation trench 1 Bed includes the block stone layer 2 set from bottom to top and metalling 3.It is provided with dredging pipe 4 in metalling 3, the 4 tube wall perforate of dredging pipe, Dredging pipe 4 is connected with slush pump 5.
During construction, foundation trench 1 is first excavated, then carries out underlayment processing, then block stone is thrown into foundation trench, and block stone is rammed and is put down Into block stone layer 2.Then 4 handling sinking of dredging pipe is installed on block stone layer 3.Then the block stone layer 2 of dredging pipe 4 is being laid Top is laid with metalling 3, and dredging pipe 4 is buried in metalling 3, and bedding, which is laid with, to be completed.Finally by slush pump 5 and dredging pipe 4 Connection is opened slush pump 5, is removed mud by rubble gap using waterway circulating, and the suction that slush pump 5 generates makes on bedding Mud pass sequentially through the perforate in the gap of metalling 3, dredging pipe 4 and enter in dredging pipe 4, finally by slush pump 5 from dredging It is taken away in pipe 4.
Before dredging pipe 4 is installed, the fast interface 6 of connection slush pump is reserved on dredging pipe 4.Dredging pipe 4 is horizontal positioned to be arrived On block stone layer 2, metalling 3 makes it be arranged on the bottom of metalling 3 after being laid with, and metalling 3 can be completely covered, make to fall into rubble Mud in 3 gap of layer can also be removed.The perforate of dredging pipe 4 all upward, positioned at the upside of dredging pipe 4, makes perforate directly right Quasi- mud improves cleaning efficiency.As shown in Fig. 2, dredging pipe 4 can be arranged at intervals in the plane on 2 surface of block stone layer it is multiple, comprehensively Cover entire metalling.
The excavation of foundation trench 1 uses dredger, block stone be thrown into and ram it is flat flat ship progress is then rammed by jackstone, dredging pipe 4 The installation of handling sinking is carried out by lifting equipment, is laid with metalling and is carried out by platform-type or floatation type leveling ship.
It is carried out as shown in figure 3, bedding is laid with segmentation, is first laid with one section of block stone layer 2, is then installed on this section of block stone layer 2 Dredging pipe 4 is finally laid with metalling 3 again on this section of block stone layer 2, complete the laying of one section of bedding, then carry out next section of bedding Laying.
It is often laid with and completes one section of bedding, you can monitoring of back-silting is carried out using multi-beam and the box that back-silts to this section of bedding, works as inspection When the silt depth measured is more than regulation requirement, i.e., slush pump with the dredging pipe of this section of bedding is connected, carries out silt displacement, clearly After the completion of silt, the installation of immersed tube 8 is just carried out on this section of bedding, the workload of dredging operation entirety can be mitigated.
Slush pump 5 is mounted on ship 7, and when carrying out dredging operation, ship 7 first is positioned at needs using modes such as ropes Above the bedding of dredging, then dredging pipe 4 with slush pump 5 is connected with water under diver, slush pump 5 is then turned on and carries out clearly It becomes silted up.The mud that slush pump 5 is extracted out is sent in the cabin of ship 7 or is directly pipelined to land, and slush pump 5 is taken out The water quality of the mud of monitoring discharge in real time during the mud discharge gone out when the water quality of monitoring discharge mud is clear water, takes out mud It pumps 5 out of service, removes connection, ship 7 is removed into Project Areas.

Claims (8)

1. a kind of dredging method of immersed tube tunnel rubble bedding desilting system, immersed tube tunnel rubble bedding desilting system includes base Slot, is equipped with bedding in the foundation trench, and the bedding includes the block stone layer and metalling that set from bottom to top, in the metalling Dredging pipe, the dredging tube wall perforate are provided with, the dredging pipe is connected with slush pump;The dredging pipe is horizontally set on broken The bottom of rock layers, the perforate of the dredging pipe are all located at upside;
It is characterized in that, the step of method, is as follows:
1) foundation trench is excavated, then carries out underlayment processing, block stone is thrown into foundation trench, and block stone is rammed into Heisei block stone layer;
2) dredging pipe handling sinking is installed on block stone layer;
3) metalling is laid with above the block stone layer for having laid dredging pipe, bedding is completed and is laid with;
4) slush pump with dredging pipe is connected, opens slush pump, removed mud by rubble gap using waterway circulating.
2. the dredging method of immersed tube tunnel rubble bedding desilting system according to claim 1, which is characterized in that pass through digging Mud ship carries out foundation trench excavation, is thrown into and rams flat by what jackstone rammed that flat ship carries out block stone, pass through lifting equipment progress dredging Guan An Dress, metalling is laid with by leveling ship.
3. the dredging method of immersed tube tunnel rubble bedding desilting system according to claim 1, which is characterized in that installation is clear Before silt pipe, the fast interface of connection slush pump is reserved on dredging pipe.
4. the dredging method of immersed tube tunnel rubble bedding desilting system according to claim 1, which is characterized in that bedding is spread If segmentation carries out, one section of block stone layer is first laid with, then dredging pipe is installed on this section of block stone layer, finally this section of block stone layer upper berth again If metalling, the laying of one section of bedding is completed, then carries out the laying of next section of bedding.
5. the dredging method of immersed tube tunnel rubble bedding desilting system according to claim 4, which is characterized in that be often laid with Complete one section of bedding, you can monitoring of back-silting is carried out to this section of bedding, it, will when the silt depth detected is more than regulation requirement Slush pump is connected with the dredging pipe of this section of bedding, carries out silt displacement.
6. the dredging method of immersed tube tunnel rubble bedding desilting system according to claim 1, which is characterized in that first use Multi-beam and the box detection silt depth that back-silts, when the silt depth detected is more than regulation requirement, then by slush pump and dredging Pipe connects, and carries out silt displacement.
7. the dredging method of immersed tube tunnel rubble bedding desilting system according to claim 1, which is characterized in that slush pump On ship, dredger is positioned above the bedding for needing dredging, is connected dredging pipe and slush pump with water under diver It connects.
8. the dredging method of immersed tube tunnel rubble bedding desilting system according to claim 1 or 5, which is characterized in that take out The water quality of the mud of monitoring discharge in real time during the mud discharge of dredge pump extraction, when the water quality of monitoring discharge mud is clear water When, slush pump is out of service.
CN201610059035.1A 2016-01-28 2016-01-28 The dredging method of immersed tube tunnel rubble bedding desilting system Active CN105696625B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610059035.1A CN105696625B (en) 2016-01-28 2016-01-28 The dredging method of immersed tube tunnel rubble bedding desilting system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610059035.1A CN105696625B (en) 2016-01-28 2016-01-28 The dredging method of immersed tube tunnel rubble bedding desilting system

Publications (2)

Publication Number Publication Date
CN105696625A CN105696625A (en) 2016-06-22
CN105696625B true CN105696625B (en) 2018-05-22

Family

ID=56229648

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610059035.1A Active CN105696625B (en) 2016-01-28 2016-01-28 The dredging method of immersed tube tunnel rubble bedding desilting system

Country Status (1)

Country Link
CN (1) CN105696625B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116927167B (en) * 2023-07-27 2024-01-30 广东省华建工程建设有限公司 Construction method for replacing and filling graded broken stone on pipeline foundation

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1281924A (en) * 1999-07-22 2001-01-31 陈启星 Method for preventing and controlling reservoir sediment accumulation by using siphon principle
DE10156950A1 (en) * 2001-11-20 2004-04-08 Heinze, Peter, Dr.-Ing. Construction method for underwater tunnels with steel tunnel sections fabricated on land, acting as lost shuttering and water-protection for internal concrete lining, and completely fitted-out before lowering into water
CN202577349U (en) * 2012-04-07 2012-12-05 中铁十八局集团有限公司 Large immersed tube tunnel dry dock floor structure
CN202577341U (en) * 2012-04-07 2012-12-05 中铁十八局集团有限公司 Pipe section foundation of large-scale immersed pipe tunnel
CN104947708A (en) * 2015-04-24 2015-09-30 中国交通建设股份有限公司 Combined foundation bed for immersed tube tunnels and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1281924A (en) * 1999-07-22 2001-01-31 陈启星 Method for preventing and controlling reservoir sediment accumulation by using siphon principle
DE10156950A1 (en) * 2001-11-20 2004-04-08 Heinze, Peter, Dr.-Ing. Construction method for underwater tunnels with steel tunnel sections fabricated on land, acting as lost shuttering and water-protection for internal concrete lining, and completely fitted-out before lowering into water
CN202577349U (en) * 2012-04-07 2012-12-05 中铁十八局集团有限公司 Large immersed tube tunnel dry dock floor structure
CN202577341U (en) * 2012-04-07 2012-12-05 中铁十八局集团有限公司 Pipe section foundation of large-scale immersed pipe tunnel
CN104947708A (en) * 2015-04-24 2015-09-30 中国交通建设股份有限公司 Combined foundation bed for immersed tube tunnels and construction method thereof

Also Published As

Publication number Publication date
CN105696625A (en) 2016-06-22

Similar Documents

Publication Publication Date Title
CN104846787B (en) Construction method for carrying out sand-blowing sea-filling land-making in shallow sea area by using cutter suction dredger
RU2730276C1 (en) Method of water protection/purification by repeated filling of formation destructed by coal mining, iron-containing waste water
CN109469082B (en) Open caisson construction equipment and construction method
CN109736338A (en) A kind of hydraulic engineering foundation pit pipe well combination light well point Yield rainfall relation method
CN105970900A (en) Offshore wind turbine gravity type foundation installation seabed treatment process
Garnett Marine placer gold, with particular reference to Nome, Alaska
CN108223910A (en) A kind of ductile iron pipe passes through the construction method of aqueous soil layer
CN107761670A (en) Stockyard dischargeable capacity method for optimally controlling based on the control of dredged mud original state
CN110424430A (en) Deep basal pit powder land floor Deep Pumped Wells construction method and its application
CN110055972A (en) Dry dock foundation ditch construction method and dry dock foundation pit structure
CN109339084A (en) Underwater big depth open caisson passes through the construction method of the hard soil layer for being difficult to abolish
CN106245652A (en) A kind of construction method of deep foundation pit earthwork digging near a river
CN103603666B (en) Tailing pond sand excavation method
CN105696625B (en) The dredging method of immersed tube tunnel rubble bedding desilting system
CN109577337A (en) The construction method of deep foundation ditch of flowing line
Van Impe et al. Underwater vacuum consolidation of dredged silt–a case history
CN110374124A (en) Subway work drainage system
CN205348226U (en) Immersed tube tunnel rubble foundation bed desilting system
Cooper et al. The role of bedding planes in Guadalquivir Blue Marls on the slope stability in Cobre Las Cruces open pit
CN109707445B (en) Dredgeable tunnel drainage system and method
CN104088664B (en) A kind of mine wastewater treatment method and system of upwards filling mining
CN104060636B (en) Pressure release anti-float method during high water level regional architecture foundation construction and device
KR101523367B1 (en) Method of dewatering for Landfill by directional drilling
CN105604605B (en) The complicated anti-broke-out diseases device of flood mine underground mine
CN108547320A (en) A kind of deep piping lane foundation pit method for digging of Collapsible Loess District

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20160622

Address after: 300461, Tianjin Port Free Trade Zone, Yuejin Road, shipping service center, building 8

Applicant after: CCCC First Harbor Engineering Co., Ltd.

Applicant after: The Second Engineering Co. of CCCC First Harbor Engineering Co., Ltd.

Address before: 266000 Shandong city of Qingdao province Fuzhou City Road No. 16 building in Hong Kong

Applicant before: The Second Engineering Co. of CCCC First Harbor Engineering Co., Ltd.

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Liu Dejin

Inventor after: Feng Haibao

Inventor after: Su Changxi

Inventor after: Li Zengjun

Inventor after: Qu Lili

Inventor after: Zhang Xuejun

Inventor before: Liu Dejin

Inventor before: Feng Haibao

Inventor before: Su Changxi

Inventor before: Qu Lili

Inventor before: Zhang Xuejun

GR01 Patent grant
GR01 Patent grant