CN105696467B - 一种基于p‐bim技术的支模架施工方法 - Google Patents
一种基于p‐bim技术的支模架施工方法 Download PDFInfo
- Publication number
- CN105696467B CN105696467B CN201610080120.6A CN201610080120A CN105696467B CN 105696467 B CN105696467 B CN 105696467B CN 201610080120 A CN201610080120 A CN 201610080120A CN 105696467 B CN105696467 B CN 105696467B
- Authority
- CN
- China
- Prior art keywords
- support
- shuttering
- bim
- method based
- model
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
本发明公开了一种基于BIM技术的支模架施工方法,与传统的支模架搭设方法相比较,本发明利用P‑BIM技术对建筑工程进行三维建模,根据建筑模型进行布设支模架、智能算量并形成实施方案,并利用模型进行技术交底、搭设、检查和验收,具有直观、快捷的特点,可大大提高工作的效率,增强支模架施工过程的可控性,确保施工的质量和安全。
Description
技术领域
本发明涉及一种基于P-BIM技术的模板及支架施工方法,尤其适用于房屋、桥梁等工程支模体系的施工,属于建筑工程模板与支架搭设技术领域。
背景技术
我国基础产业和基础设施建设投资一直保持快速增长,而混凝土模板支撑结构坍塌是当前造成建筑施工人员伤亡的最主要因素,在建筑业较大事故中,因支模架坍塌造成的人员伤亡数量占伤亡总数的40%以上,可以说模板及支架工程在基建领域措施项目中占据极其重要的地位。
建筑信息模型(Building Information Modeling,简称BIM)在我国已开展初步应用和本土化,鲁班、广联达和PKPM建研院等单位已展开软件的开发和营销团队的建立,但其目前的产品多针对建筑工程本身,很少有应用在建筑工程措施项目中。
一般承重模板支撑架均属于危险性较大的分部分项工程,需编制专项施工方案;且国家规定对超过一定规模的危险性较大的分部分项工程不仅要编制专项施工方案,而且要组织专家论证,施工材料计划、技术要求、安全计算和附图绘制为方案编制的关键内容。
技术交底是支模架搭设过程管理中的重要一环,有效直观的技术交底和过程中严密的跟踪检查可切实提高实际施工与方案的符合性。在搭设过程中,材料尺寸及质量、地基支座、立杆和剪刀撑布设、水平杆步距、梁柱节点为过程控制的重点。
当前,支模架专项方案编制根据现行国家标准规范、图纸和企业相关规定等要求编制,并附有计算书、二维剖面图和节点详图等,其中支模架安全计算已实现电算化,但随着建筑结构越来越复杂,支模架工程施工客观还存在以下众多问题:高支模区域识别困难、绘图和工程量计算繁琐、技术交底不直观和质量验收不易掌控等,特别是绘制立杆平面图时,由于梁板尺寸和空间位置变化较大,往往对立杆离梁的距离难以掌控,需多次重复工作以达到最佳效果,导致立杆平面图绘制工作量巨大。因此,需要一种新型施工方法解决这些难题,并减少这些因素带来的安全和质量风险。
发明内容
为了克服支模架施工中存在的高支模区域识别困难、绘图和工程量计算繁琐、技术交底不直观和实施过程不易掌控等问题,本发明提供一种基于BIM技术的支模架施工方法,利用该方法施工不仅可以快速识别高支模区域、智能计算和布架、自动算量、按需形成二维或三维图形,而且能够提升支模架材料计划、技术交底和施工验收等具体施工管理中的工作效率和效果。
本发明的目的可采用以下技术方案来实现:一种基于P-BIM技术的支模架施工方法,包括以下步骤:
(1)搜集相关信息,整理出必要的图纸和参数;所述相关信息包括合同文件、经审核的工程图纸及设计变更、支模架相关的标准规范和施工组织总设计。
(2)选择适用的规范和条件录入参数,建立建筑物BIM模型,BIM模型建立可以有直接建模和图纸转换再调整建模两种方式,所述建筑物BIM模型应如实反映混凝土工程实体,包括基础、梁、板、柱和剪力墙。
(3)根据建筑物BIM模型智能布设三维支模架,建筑结构构件(墙、梁、板、柱)的形状、尺寸、位置和高度共同影响着模板及支架在模型中的布置方式,根据支模架规范的要求定义模板和架体的布设规则,以适应建筑物不同的结构形式、部位和构件,在搭设尺寸合理区间值内确定唯一值。形成架体配置图,架体配置的计算依据为现行国家、行业和地方标准规范,利用计算机技术识别高支模区域,并输出材料清单和计算书。
(4)根据架体配置图、材料清单和计算书生成施工方案。施工方案中应有进度计划,根据进度计划对人工、材料和机具的配置,施工方案应按规定经过审批。
(5)根据方案的进度要求和具体工程量,购买材料机具并安排劳动力。
(6)按支模架模型进行技术交底、搭设、检查验收、监测、使用和拆除,由于支模架P-BIM模型具有3D可视化的特点,这一过程将更为直观,减轻沟通负担,提高工作效率。
进一步地,所述步骤1中,若条件发生变化,如产生设计变更或其它工程现场相关条件改变,应动态修正模型和参数,通过修正进一步提高支模架搭设精度。
进一步地,所述步骤2中的三维模型是根据工程图纸在软件平台中建立,各参数、规范和实施条件应根据信息和技术准备的内容进行设置和执行。本发明中所述的软件平台是一套辅助设计装置,是一种通用建模软件或者是通过对基础绘图软件二次开发而形成的软件平台,用于建筑物的建模。
进一步地,所述步骤3中建筑物建模完成后,在计算机中布设支模架。设置钢管、方木等材质与规格,设置立杆、横杆和剪刀撑尺寸要求等配置参数,自动识别高支模区域、布设三维架体、导出材料清单,并形成含有上述内容的专项施工方案,形成方案后再对其进行优化排版,适当调整内容,进一步提升方案编制质量。
进一步地,所述步骤5中材料进场后,应对钢管、模板、木方等材料进行抽样测试,测试结果若符合步骤3中的布设要求,则进入下一步工作,若不符合则在软件中修正模型参数,重新生成支模架模型,确保支模架的安全性。
进一步地,所述步骤6中技术交底基于三维模型进行,技术交底更加直观和更易于理解,交底应按规定履行签字手续。
进一步地,所述步骤6的搭设过程中按BIM支模架施工方案所提供的立杆、横杆和剪刀撑等配置要求进行搭设,应有专人跟踪检查,动态监控搭设过程,提高支模架搭设质量。
进一步地,所述步骤6中根据软件平台提供的BIM支模架模型对照验收,并按规定履行验收手续,若验收不合格则予以返工整改,整改后重新组织验收。
本发明的有益效果是:与传统的支模架搭设方法相比较,本发明利用P-BIM技术对建筑工程进行三维建模,根据建筑模型进行智能算量、布设支模架并形成实施方案,并利用模型进行技术交底、搭设、检查和验收,具有直观、快捷的特点,可大大提高工作的效率,增强支模架施工过程的可控性,确保施工的质量和安全。
附图说明
图1是P-BIM支模架施工流程图。
具体实施方式
下面结合附图和具体实施例对本发明作进一步详细说明。
如图1所示,本发明提供的一种基于P-BIM技术的支模架施工方法,包括以下步骤:
(1)搜集相关信息,整理出必要的图纸和参数;所述相关信息包括合同文件、经审核的工程图纸及设计变更、支模架相关的标准规范和施工组织总设计。若条件发生变化,如产生设计变更或其它工程现场相关条件改变,应动态修正模型和参数,通过修正进一步提高支模架搭设精度。
(2)选择适用的规范和条件录入参数,建立建筑物BIM模型,BIM模型建立可以有直接建模和图纸转换再调整建模两种方式,所述建筑物BIM模型应如实反映混凝土工程实体,包括基础、梁、板、柱和剪力墙。BIM模型是根据工程图纸在软件平台中建立,各参数、规范和实施条件应根据信息和技术准备的内容进行设置和执行。本发明中所述的软件平台是一套辅助设计装置,是一种通用建模软件或者是通过对基础绘图软件二次开发而形成的软件平台,用于建筑物的建模。
(3)根据建筑物BIM模型智能布设三维支模架,建筑结构构件(墙、梁、板、柱)的形状、尺寸、位置和高度共同影响着模板及支架在模型中的布置方式,根据支模架规范的要求定义模板和架体的布设规则,以适应建筑物不同的结构形式、部位和构件,在搭设尺寸合理区间值内确定唯一值。形成架体配置图,架体配置的计算依据为现行国家、行业和地方标准规范,利用计算机技术识别高支模区域,并输出材料清单和计算书。
(4)根据架体配置图、材料清单和计算书生成施工方案。施工方案中应有进度计划,根据进度计划对人工、材料和机具的配置,施工方案应按规定经过审批。
(5)根据方案的进度要求和具体工程量,购买材料机具并安排劳动力。
(6)按支模架模型进行技术交底、搭设、检查验收、监测、使用和拆除,由于支模架P-BIM模型具有3D可视化的特点,这一过程将更为直观,减轻沟通负担,提高工作效率。
Claims (8)
1.一种基于P-BIM技术的支模架施工方法,其特征在于,包括以下步骤:
(1)搜集相关信息,整理出必要的图纸和参数;所述相关信息包括合同文件、经审核的工程图纸及设计变更、支模架相关的标准规范和施工组织总设计;
(2)选择适用的规范和条件录入参数,建立建筑物BIM模型,BIM模型建立有直接建模和图纸转换再调整建模两种方式,所述建筑物BIM模型应如实反映混凝土工程实体,包括基础、梁、板、柱和剪力墙;
(3)根据建筑物BIM模型智能布设三维支模架,建筑结构构件的形状、尺寸、位置和高度共同影响着模板及支架在模型中的布置方式,根据支模架规范的要求定义模板和架体的布设规则,以适应建筑物不同的结构形式、部位和构件,在搭设尺寸合理区间值内确定唯一值;形成架体配置图,架体配置的计算依据为现行国家、行业和地方标准规范,利用计算机技术识别高支模区域,并输出材料清单和计算书;
(4)根据架体配置图、材料清单和计算书生成施工方案;施工方案中应有进度计划,根据进度计划对人工、材料和机具的配置,施工方案应按规定经过审批;
(5)根据方案的进度要求和具体工程量,购买材料机具并安排劳动力;
(6)按支模架模型进行技术交底、搭设、检查验收、监测、使用和拆除,由于支模架P-BIM模型具有3D可视化的特点,这一过程将更为直观,减轻沟通负担,提高工作效率。
2.根据权利要求1所述一种基于P-BIM技术的支模架施工方法,其特征在于,所述步骤(1)中,若条件发生变化,如产生设计变更或其它工程现场相关条件改变,则动态修正模型和参数,通过修正进一步提高支模架搭设精度。
3.根据权利要求1所述一种基于P-BIM技术的支模架施工方法,其特征在于,所述步骤(2)中的三维模型是根据工程图纸在软件平台中建立,各参数、规范和实施条件根据信息和技术准备的内容进行设置和执行。
4.根据权利要求1所述一种基于P-BIM技术的支模架施工方法,其特征在于,所述步骤(3)中建筑物建模完成后,在计算机中布设支模架;设置钢管、方木材质与规格,设置立杆、横杆和剪刀撑尺寸要求配置参数,自动识别高支模区域、布设三维架体、导出材料清单,并形成含有上述内容的专项施工方案,形成方案后再对其进行优化排版,适当调整内容,进一步提升方案编制质量。
5.根据权利要求1所述一种基于P-BIM技术的支模架施工方法,其特征在于,所述步骤(5)中材料进场后,对钢管、模板、木方材料进行抽样测试,测试结果若符合步骤(3)中的布设要求,则进入下一步工作,若不符合则在软件中修正模型参数,重新生成支模架模型,确保支模架的安全性。
6.根据权利要求1所述一种基于P-BIM技术的支模架施工方法,其特征在于,所述步骤(6)中技术交底基于三维模型进行,技术交底更加直观和更易于理解,交底应按规定履行签字手续。
7.根据权利要求1所述一种基于P-BIM技术的支模架施工方法,其特征在于,所述步骤(6)的搭设过程中按BIM支模架施工方案所提供的立杆、横杆和剪刀撑配置要求进行搭设,应有专人跟踪检查,动态监控搭设过程,提高支模架搭设质量。
8.根据权利要求1所述一种基于P-BIM技术的支模架施工方法,其特征在于,所述步骤(6)中根据软件平台提供的BIM支模架模型对照验收,并按规定履行验收手续,若验收不合格则予以返工整改,整改后重新组织验收。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610080120.6A CN105696467B (zh) | 2016-02-04 | 2016-02-04 | 一种基于p‐bim技术的支模架施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610080120.6A CN105696467B (zh) | 2016-02-04 | 2016-02-04 | 一种基于p‐bim技术的支模架施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105696467A CN105696467A (zh) | 2016-06-22 |
CN105696467B true CN105696467B (zh) | 2018-01-12 |
Family
ID=56222031
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610080120.6A Active CN105696467B (zh) | 2016-02-04 | 2016-02-04 | 一种基于p‐bim技术的支模架施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105696467B (zh) |
Families Citing this family (24)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107784137A (zh) * | 2016-08-26 | 2018-03-09 | 上海宝冶集团有限公司 | 基于bim技术的机电综合支吊架设计方法 |
CN107784409A (zh) * | 2016-08-27 | 2018-03-09 | 上海宝冶集团有限公司 | 基于建筑信息模型的项目模板工程管理系统 |
CN106354937B (zh) * | 2016-08-30 | 2019-08-20 | 江苏国泰新点软件有限公司 | 基于Revit平台的结构件构造方法和装置 |
CN106845039A (zh) * | 2017-03-21 | 2017-06-13 | 中建三局第建设工程有限责任公司 | 基于bim的内支撑拆除施工方法 |
CN107391793B (zh) * | 2017-06-15 | 2020-11-20 | 中国建筑一局(集团)有限公司 | 基于3d扫描技术与mr混合现实技术的建筑结构拆除方法 |
CN107169747A (zh) * | 2017-06-19 | 2017-09-15 | 郑州航空工业管理学院 | 一种土木建筑各项工程的管理系统 |
CN107489186A (zh) * | 2017-08-25 | 2017-12-19 | 广东省水利水电第三工程局有限公司 | 一种异形流道模板的制造及安装方法 |
CN107542064B (zh) * | 2017-08-25 | 2020-02-14 | 广东省水利水电第三工程局有限公司 | 一种基于bim平台的异形流道模板制造安装管理的方法 |
CN107563662A (zh) * | 2017-09-15 | 2018-01-09 | 中建海峡建设发展有限公司 | 一种pc构件生产任务管理的方法和计算设备 |
CN107748828A (zh) * | 2017-11-10 | 2018-03-02 | 重庆建工住宅建设有限公司 | 施工设备模板与脚手架工程bim应用方法 |
CN108252519A (zh) * | 2018-03-14 | 2018-07-06 | 中铁八局集团第四工程有限公司 | 一种基于bim的房建工程模板施工工艺样板的施工方法 |
CN108416162A (zh) * | 2018-03-23 | 2018-08-17 | 中国十七冶集团有限公司 | 一种基于bim的螺旋上升式钢筋混凝土结构的施工方法 |
CN109829214A (zh) * | 2019-01-21 | 2019-05-31 | 广东星层建筑科技股份有限公司 | 一种基于bim的附着升降脚手架智能设计方法 |
CN111027114A (zh) * | 2019-03-18 | 2020-04-17 | 杭州百慕建筑工程有限公司 | 利用bim技术确保高支模方案安全实施的方法 |
CN110206293A (zh) * | 2019-06-04 | 2019-09-06 | 中国十七冶集团有限公司 | 一种基于bim技术的模板支撑体系的施工方法 |
CN110761190B (zh) * | 2019-10-18 | 2021-10-01 | 中铁八局集团昆明铁路建设有限公司 | 一种贝雷梁满堂架组合支架的施工方法 |
CN111853347A (zh) * | 2020-07-10 | 2020-10-30 | 青岛新华友建工集团股份有限公司 | 一种基于bim的超前定位直埋锚栓预制管线支架施工工艺 |
CN112150627B (zh) * | 2020-08-25 | 2023-08-18 | 金华送变电工程有限公司 | 一种支模架使用量的计算方法 |
CN112163255B (zh) * | 2020-09-04 | 2022-07-12 | 中建二局第三建筑工程有限公司 | 基于无梁楼板柱帽架搭设数据的处理方法、装置及存储介质 |
CN112926114B (zh) * | 2021-02-23 | 2023-04-18 | 中建三局安装工程有限公司 | 机电与钢结构一体化施工方法 |
CN113158295A (zh) * | 2021-03-12 | 2021-07-23 | 贵州建工集团第四建筑工程有限责任公司 | 基于bim模板整装技术运用在模板支撑架体的施工工法 |
CN114065336B (zh) * | 2021-09-28 | 2022-07-22 | 广州优比建筑咨询有限公司 | 一种基于Revit的高支模区域的检查方法、装置、介质及设备 |
CN114991440A (zh) * | 2021-10-26 | 2022-09-02 | 五冶集团上海有限公司 | 一种基于bim的组合式支撑脚手架的施工方法 |
CN114722446B (zh) * | 2022-06-09 | 2022-08-16 | 山东高速德建集团有限公司 | 一种基于dynamo的模板系统竖向支撑建模方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9019269B1 (en) * | 2011-11-28 | 2015-04-28 | Robert Alan Pogue | Interactive rendering of building information model data |
CN104715113A (zh) * | 2015-03-19 | 2015-06-17 | 中铁二局第五工程有限公司 | 利用bim实现钢桁拱桥施工仿真的方法和装置 |
CN104715114A (zh) * | 2015-03-19 | 2015-06-17 | 中铁二局第五工程有限公司 | 利用bim实现钢桁拱桥梁的碰撞检测方法及装置 |
CN104715115A (zh) * | 2015-03-19 | 2015-06-17 | 中铁二局第五工程有限公司 | 利用bim实现钢桁拱桥施工辅助设施的设计方法及装置 |
CN105279311A (zh) * | 2015-09-23 | 2016-01-27 | 中建三局第三建设工程有限责任公司 | 钢箱梁顶推施工管理方法 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20130339078A1 (en) * | 2012-06-18 | 2013-12-19 | Coaxis, Inc. | System and method linking building information modeling and enterprise resource planning |
-
2016
- 2016-02-04 CN CN201610080120.6A patent/CN105696467B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9019269B1 (en) * | 2011-11-28 | 2015-04-28 | Robert Alan Pogue | Interactive rendering of building information model data |
CN104715113A (zh) * | 2015-03-19 | 2015-06-17 | 中铁二局第五工程有限公司 | 利用bim实现钢桁拱桥施工仿真的方法和装置 |
CN104715114A (zh) * | 2015-03-19 | 2015-06-17 | 中铁二局第五工程有限公司 | 利用bim实现钢桁拱桥梁的碰撞检测方法及装置 |
CN104715115A (zh) * | 2015-03-19 | 2015-06-17 | 中铁二局第五工程有限公司 | 利用bim实现钢桁拱桥施工辅助设施的设计方法及装置 |
CN105279311A (zh) * | 2015-09-23 | 2016-01-27 | 中建三局第三建设工程有限责任公司 | 钢箱梁顶推施工管理方法 |
Also Published As
Publication number | Publication date |
---|---|
CN105696467A (zh) | 2016-06-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105696467B (zh) | 一种基于p‐bim技术的支模架施工方法 | |
WO2021128675A1 (zh) | 一种基于bim技术的地下连续墙施工方法 | |
CN111627099B (zh) | 基于三维扫描技术的钢结构非接触式实测实量方法和系统 | |
CN104156544B (zh) | 基于bim技术的梁柱钢筋节点自动布置与施工模拟方法 | |
CN109885966B (zh) | 基于bim技术的滑槽管片冲突及优化布置的方法 | |
CN105731262B (zh) | 基于bim技术的塔吊平面布置系统及方法 | |
CN106886659A (zh) | 基于三维激光扫描和云平台的钢结构桥梁虚拟预拼和检测方法 | |
CN113158295A (zh) | 基于bim模板整装技术运用在模板支撑架体的施工工法 | |
WO2023159810A1 (zh) | 一种基于数字孪生的钢管混凝土拱桥施工监控方法及系统 | |
CN110080114A (zh) | 一种基于bim技术的可视化预制立柱承台施工方法 | |
CN112989532A (zh) | 基于bim的地铁车站市政管线改迁施工方法 | |
CN110414136B (zh) | 一种基于bim的桥梁快速建模方法及系统 | |
CN110162856A (zh) | 一种基于dynamo的梁箍筋智能化生成方法 | |
CN112163256A (zh) | 基于有限元分析与bim的模板支架模型的建立与分析方法 | |
CN103914589A (zh) | 一种电力铁塔单线模型快速生成方法 | |
CN116561871A (zh) | 一种桥梁承台预埋件安装深化施工方法 | |
CN114419227A (zh) | 一种基于数字孪生技术的基建运行数据贯通方法 | |
CN107491619A (zh) | 一种基于bim技术的旧改项目钢结构定位吊装施工方法 | |
CN116090981A (zh) | 基于ar的施工辅助系统、方法、计算机设备及存储介质 | |
CN113515654B (zh) | 基于建筑信息建模的桩基施工参数可视化处理方法及装置 | |
CN111126691B (zh) | 项目管理方法及相关产品 | |
CN110565856B (zh) | 一种双曲面金属板幕墙快速安装方法 | |
CN112699452A (zh) | 一种提高大面积地坪平整度的施工方法 | |
CN107644119A (zh) | 一种基于三维扫描点云的半孔率自动计算方法 | |
CN116446293A (zh) | 一种斜拉桥混凝土梁索导管施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |