CN105673993B - Fluid line press and open holes block pressure equaliser to high pressure gas pipeline boring method - Google Patents

Fluid line press and open holes block pressure equaliser to high pressure gas pipeline boring method Download PDF

Info

Publication number
CN105673993B
CN105673993B CN201610066851.5A CN201610066851A CN105673993B CN 105673993 B CN105673993 B CN 105673993B CN 201610066851 A CN201610066851 A CN 201610066851A CN 105673993 B CN105673993 B CN 105673993B
Authority
CN
China
Prior art keywords
auxiliary
aperture
valve
case
pipe fitting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610066851.5A
Other languages
Chinese (zh)
Other versions
CN105673993A (en
Inventor
邢琳琳
李夏喜
张海涛
贾应辉
陈文利
张海军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Gas Group Co Ltd
Original Assignee
Beijing Gas Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Gas Group Co Ltd filed Critical Beijing Gas Group Co Ltd
Priority to CN201610066851.5A priority Critical patent/CN105673993B/en
Publication of CN105673993A publication Critical patent/CN105673993A/en
Application granted granted Critical
Publication of CN105673993B publication Critical patent/CN105673993B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L55/00Devices or appurtenances for use in, or in connection with, pipes or pipe systems
    • F16L55/18Appliances for use in repairing pipes

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Branch Pipes, Bends, And The Like (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

The present invention relates to fluid line press and open holes to block pressure equaliser to high pressure gas pipeline boring method, balancing device includes: wiring pipe fitting and tapping machine, the inner cavity of wiring pipe fitting is that aperture connects case, connect case in aperture and is provided with tapping machine and sandwich valve, when sandwich valve is closed, aperture is connected case and is divided into two parts by sandwich valve, when sandwich valve is opened, aperture connects case connection and is integral, it further include: auxiliary connection pipe fitting, assist tapping machine and air accumulator, the inner cavity of auxiliary connection pipe fitting is that auxiliary aperture connects case, connect case in auxiliary aperture and is provided with auxiliary tapping machine and auxiliary sandwich valve, when assisting sandwich valve closure, auxiliary aperture is connected case and is divided into two parts by auxiliary sandwich valve, when sandwich valve being assisted to open, auxiliary aperture connects case connection and is integral, aperture connects case and auxiliary aperture connects case and passes through pipeline respectively and is connected with air accumulator, this method avoid High pressure in high-pressure gas pipeline protects production safety and the safety of operator to intense impact caused by puncher.

Description

Fluid line press and open holes block pressure equaliser to high pressure gas pipeline boring method
Technical field
The present invention relates to a kind of balancing device, in particulard relate to fluid line press and open holes block pressure equaliser and The method that aperture is carried out to high-pressure gas pipe with the device.
Background technique
In recent years, as the step of urbanization is getting faster, combustion gas enters ten million family, gas pipeline in old city or It is laid with extensively in emerging city, the high-pressure gas pipeline of delivery of fuel gas is also widely laid on the underground in city, when this When kind of high-pressure gas pipeline breaks down, operator is in order to ensure the conveying of combustion gas, it is necessary to pressure in high-pressure gas pipeline In the case of, high-pressure gas pipeline is punched, is then changed the pipeline that one section breaks down as early as possible, due to delivery of fuel gas Pipeline is high-pressure gas pipeline, the moment of high-pressure gas pipeline is opened in puncher, due to the high pressure meeting in high-pressure gas pipeline Strong impact is generated to puncher, is even caused the accident.
Summary of the invention
Pressure equaliser is blocked the object of the present invention is to provide a set of fluid line press and open holes and to high pressure gas pipeline The method for carrying out aperture, avoids the high pressure in high-pressure gas pipeline to intense impact caused by puncher.
To achieve the goals above, technical solution of the invention are as follows:
A kind of fluid line press and open holes of the invention block pressure equaliser, it includes: wiring pipe fitting and tapping machine, The inner cavity of wiring pipe fitting is that aperture connects case, connects case in aperture and is provided with tapping machine and sandwich valve, and when sandwich valve is closed, sandwich valve will Aperture connects case and is divided into two parts, and when sandwich valve is opened, aperture connects case connection and is integral, in which: it further include: auxiliary connection pipe Part, auxiliary tapping machine and air accumulator, the inner cavity of auxiliary connection pipe fitting are that auxiliary aperture connects case, auxiliary aperture connect case be provided with it is auxiliary Tapping machine and auxiliary sandwich valve are helped, when auxiliary sandwich valve is closed, assists sandwich valve that aperture will be assisted to connect case and is divided into two parts, assist When sandwich valve is opened, auxiliary aperture connects case connection and is integral, and aperture connects case and auxiliary aperture connects case and passes through pipeline and storage respectively Gas tank is connected;
A kind of fluid line press and open holes of the invention block pressure equaliser, in which: connect case and storage in auxiliary aperture First connection valve is housed between gas tank;
A kind of fluid line press and open holes of the invention block pressure equaliser, in which: connect case and air accumulator in aperture Between be equipped with the second connection valve;
A kind of fluid line press and open holes of the invention block pressure equaliser, in which: are also equipped on the air accumulator Pressure gauge and exhaust valve;
A kind of fluid line press and open holes of the invention block pressure equaliser, in which: the aperture connects also to be filled on case There is exhaust-valve;
The method that a kind of pair of high pressure gas pipeline of the invention carries out aperture, in which:
(a) wiring pipe fitting and auxiliary connection pipe fitting are respectively welded to separated by a distance two for being fixed on high pressure gas pipeline On point, tapping machine, aperture are connected into case and sandwich valve is mounted on wiring pipe fitting, auxiliary tapping machine, auxiliary aperture are connected into case and auxiliary It helps sandwich valve to be mounted on auxiliary connection pipe fitting, then the second connection valve, wiring pipe fitting and air accumulator links together, pass through First connection valve, auxiliary connection pipe fitting and air accumulator are linked together;
(b) auxiliary sandwich valve and the first connection valve are opened, the second connection valve and exhaust valve are closed, makes auxiliary tapping machine downward Moving and starting auxiliary tapping machine makes its rotation, carries out aperture to high pressure gas pipeline, makes the high-pressure gas in high pressure gas pipeline Into in air accumulator, the pressure gauge on air accumulator is observed, keeps the pressure of pressure gauge identical as the pressure of high pressure gas pipeline;
(c) sandwich valve, the second connection valve and exhaust-valve are opened, using in air accumulator high-pressure gas butted line pipe fitting, open The air that hole connects in case and clamping plate valve chamber is replaced, and after above-mentioned cavity is full of combustion gas, is closed exhaust-valve, is made wire barrel Part, aperture connect case and the chamber pressure of sandwich valve and the pressure of high pressure gas pipeline is identical, then allow tapping machine move down and Starting tapping machine makes its rotation, to high pressure gas pipeline aperture.
The method that a kind of pair of high pressure gas pipeline of the invention carries out aperture, in which: after step (c), close first Then connection valve and the second connection valve open exhaust valve and exhaust-valve.
Compared with prior art, since fluid line press and open holes of the present invention block pressure equaliser and to high pressure gas transmission The method that pipe carries out aperture, avoids the high pressure in high-pressure gas pipeline to intense impact caused by puncher, protects life Produce the safety of safety and operator.
Detailed description of the invention
Fig. 1 is the structural schematic diagram that fluid line press and open holes of the present invention block pressure equaliser.
In Fig. 1, label 1 is high pressure gas pipeline;Label 2 is wiring pipe fitting;Label 3 is sandwich valve;Label 4 is aperture company Case;Label 5 is tapping machine;Label 6 is exhaust-valve;Label 7 is pressure gauge;Label 8 is air accumulator;Label 9 is the first connection valve; Label 10 is auxiliary tapping machine;Label 11 is that auxiliary aperture connects case;Label 12 is auxiliary sandwich valve;Label 13 is the second connection Valve;Label 14 is exhaust valve;Adjuvant grafting spool part supplemented by label 15.
Specific embodiment
As shown in Figure 1, it includes: wiring pipe fitting 2, aperture that fluid line press and open holes of the invention, which block pressure equaliser, Machine 5, adjuvant grafting spool part 15, auxiliary tapping machine 10 and air accumulator 8, the inner cavity of wiring pipe fitting 2 are that aperture connects case 4, connect case 4 in aperture It is provided with tapping machine 5 and sandwich valve 3, when sandwich valve 3 is closed, aperture is connected case 4 and is divided into two parts by sandwich valve 3, and sandwich valve 3 is opened When, aperture connects the connection of case 4 and is integral, and the inner cavity of auxiliary connection pipe fitting 15 is that auxiliary aperture connects case 11, connects case in auxiliary aperture 11 are provided with auxiliary tapping machine 10 and auxiliary sandwich valve 12, and when auxiliary sandwich valve 12 is closed, auxiliary sandwich valve 12 will assist aperture Even case 11 is divided into two parts, and when auxiliary sandwich valve 12 is opened, auxiliary aperture connects the connection of case 11 and is integral, and aperture connects case 4 and auxiliary It helps aperture to connect case 11 to be connected by pipeline with air accumulator 8 respectively, pressure gauge 7 and exhaust valve 14 is also equipped on air accumulator 8.It is assisting Aperture connects between case 11 and air accumulator 8 equipped with the first connection valve 9.Connect between case 4 and air accumulator 8 in aperture equipped with the second connection valve 13, hole, which connects, is also equipped with exhaust-valve 6 on case 4.
A kind of fluid line press and open holes as shown in Figure 1 block pressure equaliser and carry out aperture to high pressure gas pipeline Method, it the following steps are included:
(a) wiring pipe fitting 2 and auxiliary connection pipe fitting 15 are respectively welded and are fixed on the separated by a distance of high pressure gas pipeline 1 Two o'clock on, tapping machine 5, aperture are connected into case 4 and sandwich valve 3 is mounted on the upper of wiring pipe fitting 2, will auxiliary tapping machine 10, auxiliary Aperture connects case 11 and auxiliary sandwich valve 12 is mounted on auxiliary connection pipe fitting 15, then by the second connection valve 13,2 and of wiring pipe fitting Air accumulator 8 links together, by the way that the first connection valve 9, auxiliary connection pipe fitting 15 and air accumulator 8 link together;
(b) auxiliary sandwich valve 12 and the first connection valve 9 are opened, the second connection valve 13 and exhaust valve 14 is closed, auxiliary is allowed to open Hole machine 10, which moves down and starts auxiliary tapping machine 10, makes its rotation, carries out aperture to high pressure gas pipeline 1, makes high pressure gas pipeline High-pressure gas in 1 enters in air accumulator 8, observes the pressure gauge 7 on air accumulator 8, makes the pressure and high pressure gas pipeline of pressure gauge 7 1 pressure is identical;
(c) sandwich valve 3, the second connection valve 13 and exhaust-valve 6 are opened, docks spool using the high-pressure gas in air accumulator 8 Part 2, aperture connect case 4 and the intracorporal air of 3 chamber of sandwich valve is replaced, and after above-mentioned cavity is full of combustion gas, close exhaust-valve 6, Make that wiring pipe fitting 2, aperture connect case 4 and the chamber pressure of sandwich valve (3) is identical as the pressure of high pressure gas pipeline 1, then allows aperture Machine 5, which moves down and starts tapping machine 5, makes its rotation, to 1 aperture of high pressure gas pipeline;
(d) after step (c), the first connection valve 9 and the second connection valve 13 are closed, then opens exhaust valve 14 and row Empty valve 6.
Embodiment described above is only that preferred embodiments of the present invention will be described, not to the scope of the present invention It is defined, without departing from the spirit of the design of the present invention, this field ordinary engineering and technical personnel is to technology of the invention The various changes and improvements that scheme is made, should fall within the scope of protection determined by the claims of the present invention.

Claims (2)

1. a kind of fluid line press and open holes block pressure equaliser to high pressure gas pipeline boring method, the fluid line is with pressure Plugging holes pressure equaliser includes: wiring pipe fitting (2), tapping machine (5), auxiliary connection pipe fitting (15), auxiliary tapping machine (10) and air accumulator (8), the inner cavity of wiring pipe fitting (2) is that aperture connects case (4), aperture connect case (4) be provided with tapping machine (5) and Sandwich valve (3), when sandwich valve (3) is closed, aperture is connected case (4) and is divided into two parts by sandwich valve (3), when sandwich valve (3) is opened, is opened Hole connects case (4) connection and is integral, and the inner cavity of auxiliary connection pipe fitting (15) is that auxiliary aperture connects case (11), connects case in auxiliary aperture (11) it is provided with auxiliary tapping machine (10) and auxiliary sandwich valve (12), when auxiliary sandwich valve (12) is closed, is assisted sandwich valve (12) Auxiliary aperture is connected into case (11) and is divided into two parts, when auxiliary sandwich valve (12) is opened, it is whole for one that auxiliary aperture connects case (11) connection Body, aperture connects case (4) and auxiliary aperture connects case (11) and is connected respectively by pipeline with air accumulator (8), connects case in auxiliary aperture (11) the first connection valve (9) are housed between air accumulator (8), connect between case (4) and air accumulator (8) in aperture equipped with the second connection Valve (13) is also equipped with pressure gauge (7) and exhaust valve (14) on air accumulator (8), and aperture, which connects, is also equipped with exhaust-valve (6) on case (4), should Fluid line press and open holes block pressure equaliser to high pressure gas pipeline boring method the following steps are included:
(a) wiring pipe fitting (2) and auxiliary connection pipe fitting (15) are respectively welded be fixed on high pressure gas pipeline (1) be separated by a spacing From two o'clock on, tapping machine (5), aperture are connected into case (4) and sandwich valve (3) is mounted on the upper of wiring pipe fitting (2), aperture will be assisted Machine (10), auxiliary aperture connect case (11) and auxiliary sandwich valve (12) is mounted on auxiliary connection pipe fitting (15), then connects second It connects valve (13), wiring pipe fitting (2) and air accumulator (8) to link together, by by the first connection valve (9), auxiliary connection pipe fitting (15) it links together with air accumulator (8);
(b) auxiliary sandwich valve (12) and the first connection valve (9) are opened, the second connection valve (13) and exhaust valve (14) is closed, allows auxiliary Helping tapping machine (10) to move down and starting auxiliary tapping machine (10) makes its rotation, carries out aperture to high pressure gas pipeline (1), makes High-pressure gas in high pressure gas pipeline (1) enters in air accumulator (8), and the pressure gauge (7) in observation air accumulator (8) makes pressure gauge (7) pressure is identical as the pressure of high pressure gas pipeline (1);
(c) sandwich valve (3), the second connection valve (13) and exhaust-valve (6) are opened, is docked using the high-pressure gas in air accumulator (8) Spool part (2), aperture connect case (4) and the intracorporal air of sandwich valve (3) chamber is replaced, and after above-mentioned cavity is full of combustion gas, close Exhaust-valve (6) are closed, wiring pipe fitting (2), aperture is made to connect the chamber pressure of case (4) and sandwich valve (3) and the pressure of high pressure gas pipeline (1) Power is identical, and then allowing tapping machine (5) to move down and starting tapping machine (5) makes its rotation, to high pressure gas pipeline (1) aperture.
2. method as described in claim 1, it is characterised in that: after step (c), close the first connection valve (9) and second Connection valve (13) then opens exhaust valve (14).
CN201610066851.5A 2016-01-29 2016-01-29 Fluid line press and open holes block pressure equaliser to high pressure gas pipeline boring method Active CN105673993B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610066851.5A CN105673993B (en) 2016-01-29 2016-01-29 Fluid line press and open holes block pressure equaliser to high pressure gas pipeline boring method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610066851.5A CN105673993B (en) 2016-01-29 2016-01-29 Fluid line press and open holes block pressure equaliser to high pressure gas pipeline boring method

Publications (2)

Publication Number Publication Date
CN105673993A CN105673993A (en) 2016-06-15
CN105673993B true CN105673993B (en) 2018-12-18

Family

ID=56303341

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610066851.5A Active CN105673993B (en) 2016-01-29 2016-01-29 Fluid line press and open holes block pressure equaliser to high pressure gas pipeline boring method

Country Status (1)

Country Link
CN (1) CN105673993B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107262762B (en) * 2017-07-07 2019-05-07 上海煤气第二管线工程有限公司 A kind of construction method of the gas pipeline with angled aperture
CN107588280B (en) * 2017-10-24 2019-02-15 上海煤气第一管线工程有限公司 Natural gas line expansive cylinder stopping transportation pressure method for blocking
CN107990074B (en) * 2017-11-22 2020-01-07 连云港新奥燃气有限公司 Gas-carrying perforating device for natural gas pipeline
CN114427631A (en) * 2020-09-30 2022-05-03 中国石油化工股份有限公司 Method for opening hole, leaking stoppage and replacing leakage valve of amine liquid medium pipeline under pressure
CN112628509A (en) * 2020-12-16 2021-04-09 上海能源建设集团有限公司 Method for preventing iron filings from backflushing in process of drilling and connecting new pipe with pressure in gas high-pressure pipeline

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2777865B2 (en) * 1994-01-25 1998-07-23 コスモ工機株式会社 Fluid pipe perforator
US5439331A (en) * 1994-03-31 1995-08-08 Tdw Delaware, Inc. High pressure tapping apparatus
US6012878A (en) * 1997-12-02 2000-01-11 Tdw Delaware, Inc. Pressure balanced subsea tapping machine
US6648562B1 (en) * 2001-06-08 2003-11-18 Charles D. Calkins Apparatus for tapping a hole in a pipeline
GB2482671A (en) * 2010-08-09 2012-02-15 Mark Edward Klinck A hot-tapping unit having pressure equalising means to balance the drill rod
CN103016893B (en) * 2011-09-21 2014-08-13 中国建筑第七工程局有限公司 Hot tapping plugging construction method of long natural gas delivery pipeline
CN102661469A (en) * 2012-05-29 2012-09-12 天津市江达扬升工程技术有限公司 High-pressure tapping machine with pressure balancing mechanism
CN203093088U (en) * 2013-01-05 2013-07-31 中国石油天然气集团公司 Pressure balancing device of heavy-caliber high-pressure tapping machine
CN203356656U (en) * 2013-07-10 2013-12-25 陕西延长石油(集团)有限责任公司研究院 Hydraulic high-pressure on-line puncher
CN203628140U (en) * 2013-11-15 2014-06-04 重庆大唐国际彭水水电开发有限公司 Under-pressure plugging structure of bottom ring drain pipe of Francis type water turbine-generator unit
CN204603372U (en) * 2015-04-21 2015-09-02 中船重工(沈阳)辽海输油设备有限公司 With the hydraulic drilling machine of equilibrium function
CN205350710U (en) * 2016-01-29 2016-06-29 北京市燃气集团有限责任公司 Gas pipeline tapping shutoff pressure equaliser

Also Published As

Publication number Publication date
CN105673993A (en) 2016-06-15

Similar Documents

Publication Publication Date Title
CN105673993B (en) Fluid line press and open holes block pressure equaliser to high pressure gas pipeline boring method
CN207080207U (en) A kind of oil field is every excavating technology tubing string
CN103671364B (en) Electrohydraulic control system is turned to for remote control loader
CN205350710U (en) Gas pipeline tapping shutoff pressure equaliser
CN203836598U (en) Safety hydrogen supply device
CN113932081A (en) Plugging method for gas pipeline partition operation
CN103174399B (en) A kind of down-hole of multi pressure series of strata oil and gas development controls sliding bush apparatus automatically
CN103711452A (en) Gel plug packing well control method
CN102808591A (en) Subsea wellhead assembly
CN104213848B (en) A kind of arc sealing device and using method for pipeline with pressure or drilling rod perforate
CN103758505B (en) Drilling tool well head method for security protection
CN210105821U (en) Wellhead device for intermittent gas lift liquid drainage and gas production assisted by plunger
CN202349599U (en) Pipeline adjusting device and skid-mounted producing test device
CN108252678A (en) A kind of down-hole plugging device of uncoupling plunger tubing pump snubbing serving
CN105465100A (en) Pressure testing device and pressure testing method for cabin opening oil cylinder
CN203730859U (en) Safety cut-off valve
CN106285559B (en) Pressure-controlled normally open valve is combined the unit with pressure-controlled normally close valve and its operating method
CN202810729U (en) Multi-configuration instruction down-transmission device
CN204267428U (en) Steel tube expansion unloads pressure control system
CN203939494U (en) Drilling tool well head security protection and control device
CN105526491B (en) Hydraulic natural gas filling for automobile substation oil return system and oil return method
RU111578U1 (en) TUBING OF GAS WELLS WITH INTER-COLUMNED GAS DEVELOPMENTS
CN107990034B (en) From inhaling slowly formula air valve of arranging that overhauls soon
CN105757065B (en) A kind of conical degree of crystallizer keeps hydraulic control system online
CN205225088U (en) Two horizontal wells of SAGD and well head discharging equipment of producing well thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant