concrete
pile
convex tendon
pile body
slot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610203893.9A
Other languages
Chinese (zh)
Other versions
CN105672253A (en
Inventor
俞向阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610203893.9A priority Critical patent/CN105672253B/en
Publication of CN105672253A publication Critical patent/CN105672253A/en
Application granted granted Critical
Publication of CN105672253B publication Critical patent/CN105672253B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/066Quays
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/10Prefabricated parts, e.g. composite sheet piles made of concrete or reinforced concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Revetment (AREA)

Abstract

The present invention relates to a kind of hollow concrete-pile, including concrete pile body, there is inner chamber that is annular in shape and running through along concrete pile body length direction inside concrete pile body, it is characterized in that in the opposite two of which side of concrete pile body, each side is provided with convex tendon or slot alternative one, and convex tendon and slot meet aftermentioned condition:Adjacent two concrete pile bodies can be stitched together by the convex tendon and slot inserting;Multiple extraneous permeable holes with inner chamber of connection are provided with two other opposite side of concrete pile body.Adjacent two concrete pile bodies can be stitched together this concrete-pile beneficial to manufacture bunding protecting wall by convex tendon and slot inserting;The bunding protecting wall such as built using this concrete-pile, river can are penetrated into bunding soil via permeable hole and inner chamber, can also penetrated into via permeable hole and inner chamber in river, more conducively the ecological balance.The invention further relates to the bunding protecting wall using foregoing concrete-pile.

Description

Hollow concrete-pile and the ecological environment-friendly type bunding protecting wall using this
Technical field
The invention belongs to the technical field of the pile foundation engineering of all kinds of architectural structure systems, more particularly to it is a kind of very suitable Share in the hollow concrete-pile of manufacture embankment protection wall;The invention further relates to using raw made of the hollow concrete-pile State environment-friendly type bunding protecting wall, this protecting wall are mainly used in the bunding protection of rivers,lakes and seas.
Background technology
Regulation of large-scale hypogee, port and pier quaywall and channel revetment etc., these buildings need pair in construction Itself or the basic of surrounding building implement to go along with sb. to guard him.The requirement of opposite bank dyke revetment is:High rigidity wall, ecological, environmental protective are easily applied Work, certainly on the premise of aforementioned condition is met, cost is more low better.
At present frequently with bunding protecting wall have three kinds of forms, the first be using multiple reinforced concrete circular stakes combine Zinc fractions enclosure wall is inserted after cement mixing pile, is also had using multiple T-shaped stakes or using cement mixing made of SMW engineering methods Stake insertion Zinc fractions enclosure wall.Because the cement mixing pile of RC Circular stake, T-shaped stake and SMW engineering methods production inserts soil The maintenance wall formed after earth can not be permeable, it is impossible to meets the ecological, environmental protective requirement of bunding protecting wall.In addition, SMW engineering methods and drilling Bored concrete pile needs cofferdam to banket when manufacturing enclosure wall, and cost is surprising, and T-shaped stake etc. is limited by its shape, steady when doing bunding protection It is qualitative unsatisfactory.
Second is its structure such as Application No. CN200680009749.6 by the way of steel sheet pile and its combining wall The Chinese invention patent of (notification number CN101146960A)《Combined bulkhead》And Application No. CN200480018307.9 is (public It number is CN1813108A to accuse) Chinese invention patent《The I-shaped sheet pile wall section bar of steel》Disclose similar Guardwall structures. Load-carrying unit is hot rail manufacture used by patent application disclosed in this two parts, for the connection endpiece of this pestle capitiform is made, Need to be through processes such as roughing, finish rolling, it is surprising that expensive roll stacks, which are spent,.
The third is the bunding protecting wall for using the H types support pile being sequentially connected each other by muscle groove inserting structure to form, Such as the Chinese utility model patent of a Patent No. ZL201320461012.5 (notification number CN203559411U)《H type supportings Stake attachment structure》Such a bunding protecting wall form is just disclosed, the protecting wall form there are more H type support piles to pass through splicing Structure is gapless successively to be stitched together.Because being tightly combined between stake and stake so that water can hardly penetrate this protection Wall construction, bunding is blocked completely with river, destroys the ecological balance of river levee.
Therefore it is existing to manufacture the concrete-pile of bunding protecting wall and bunding Guardwall structures can be further improved it is excellent Change.
The content of the invention
First technical problem to be solved by this invention is provided a kind of very suitable for above-mentioned state of the art Share in the hollow concrete-pile of manufacture embankment protection wall, the concrete-pile is not only easy to be connected with each other, and also permeable work( Can, using bunding protecting wall made of the stake river can be made to carry out exchange of moisture with soil on bunding.
Technical scheme is used by the present invention solves above-mentioned technical problem:A kind of hollow concrete-pile, including coagulation Native pile body, concrete pile body inside have the inner chamber extended along concrete pile body length direction, it is characterised in that the concrete In the opposite two of which side of pile body, each side is provided with convex tendon or slot alternative one;The concrete pile body is opposite The permeable hole of multiple extraneous and described inner chambers of connection is provided with two other side.Described inner chamber can be concrete pile body An internal complete hollow structure, is once manufactured;Described inner chamber can also be a side by concrete pile body Or the hollow structure that the concave part being molded on pile body and plate, buckle etc. are put together, now, to the plate or button of split Plate then forms a part for single concrete pile body, then it is extraneous and described interior to offer multiple connections on plate or buckle accordingly The permeable hole of chamber.Convex tendon and slot meet aftermentioned condition:Adjacent two concrete pile bodies can pass through the convex tendon and slot Inserting is stitched together.
In the opposite two of which side of above-mentioned concrete pile body, one of side is provided with the convex tendon, another Side is provided with the slot.It is the optimal set-up mode of convex tendon and slot, and the program only needs a kind of the hollow of structure type Concrete pile structure achieves that the construction of the bunding protecting wall using this, and construction is more convenient, and save a kind of mould into This.
The opposite two of which side of above-mentioned concrete pile body is equipped with the convex tendon or the slot.It is convex tendon and The secondary of slot selects scheme, and the program needs the hollow concrete pile structure of two kinds of structure types to realize the bank using this The construction of dyke revetment.
The cross section of above-mentioned concrete pile body is rectangle or circle.The most common hollow concrete of above concrete-pile The cross-sectional profile of stake, not merely limits to profile or other abnormity concrete stakes of foregoing concrete-pile certainly.
As an improvement, the cross section of above-mentioned convex tendon, in outer small interior big trapezoidal, the cross section of the slot is small in outer imperial palace It is trapezoidal.This opening for allowing for slot has to be gradually reduced from outside to inside, is inserted beneficial to convex tendon in slot, while also causes convex tendon Closer, trapezoidal convex tendon is combined with slot and slot profile is additionally favorable for the demoulding of the prefabricated pile in shaping manufacture process.
Alternatively, above-mentioned convex tendon is the continuous long rib strip shaped set along concrete pile body length direction.It is continuous long Rib strip shaped convex tendon can make the mutual inserting of muscle groove inserting structure more firm, and can simplify mould structure.
Alternatively, above-mentioned convex tendon has more and is arranged at intervals up and down along the length direction of concrete pile body, neighbouring Spacing is formed between two convex tendons.Bunding protecting wall made of the stake is so used, its spacing also may make up the one of penetrating passage Part, improve permeability rate.
Second technical problem to be solved by this invention, which is to provide one kind, can make river carry out moisture with soil on bunding The ecological environment-friendly type bunding protecting wall of exchange, this bunding protecting wall is not only firm, has good mechanical property, is additionally favorable for bunding The ecological balance.
A kind of ecological environment-friendly type bunding protecting wall using foregoing concrete-pile, it is characterised in that:Including more insertion soil The concrete pile body in earth, it is stitched together by the convex tendon and slot inserting between adjacent two concrete pile bodies, The permeable hole and inner chamber form the penetrating passage to supply water by concrete pile body.
As an improvement, above-mentioned interior intracavitary is filled with rubble or particulate matter, rubble or particulate matter play medium effect, Yi Mianhe Water directly washes away bunding soil, prevents soil erosion.
Compared with prior art, the advantage of the invention is that:In the opposite two of which side of concrete pile body, each side Face is provided with convex tendon or slot alternative one, and adjacent two concrete pile bodies can be stitched together by convex tendon and slot inserting This concrete-pile is beneficial to manufacture bunding protecting wall;It is extraneous that multiple connections are provided with two other opposite side of concrete pile body With the permeable hole of inner chamber, the bunding protecting wall such as built using this concrete-pile, river can is oozed via permeable hole and inner chamber Thoroughly into bunding soil, make the enough moisture of the soil conservation near bunding, in addition, the soil moisture such as near bunding is excessive, Also it can be penetrated into via permeable hole and inner chamber in river, realize river and the exchange of moisture in bunding soil, furthermore, on protecting wall Permeable hole and inner chamber can provide boarding and breeding place for the biology such as fishes and shrimps shellfish, finally make the bunding built using this concrete-pile Protecting wall is more conducive to the ecological balance while anti-bank protection dam effect is played.
Brief description of the drawings
Fig. 1 is the dimensional structure diagram one (square pile) of one embodiment of concrete-pile of the present invention;
Fig. 2 is the dimensional structure diagram two (square pile) of one embodiment of concrete-pile of the present invention;
Fig. 3 is the sectional view (square pile) of one embodiment of concrete-pile of the present invention;
Fig. 4 is the sectional view (rectangle stake) of one embodiment of concrete-pile of the present invention;
Fig. 5 is the dimensional structure diagram one (circle stake) of second embodiment of concrete-pile of the present invention;
Fig. 6 is the dimensional structure diagram two (circle stake) of second embodiment of concrete-pile of the present invention;
Fig. 7 is the sectional view (circle stake) of second embodiment of concrete-pile of the present invention;
Fig. 8 is the dimensional structure diagram (square pile) of one embodiment of bunding protecting wall of the present invention;
Fig. 9 is the structural representation (square pile) of one embodiment of bunding protecting wall of the present invention;
Figure 10 is the structural representation (circle stake) of second embodiment of bunding protecting wall of the present invention.
Embodiment
The present invention is described in further detail below in conjunction with accompanying drawing embodiment.
As shown in figures 1-4, it is one embodiment of concrete-pile of the present invention.
A kind of hollow concrete-pile, including concrete pile body 1, the inside of concrete pile body 1 have annular in shape and along coagulation The inner chamber 11 that the native length direction of pile body 1 runs through, (square pile is special to be square for the cross section of concrete pile body 1 in the present embodiment Rectangular pile), as shown in Figures 1 to 3.Or rectangle, as shown in figure 4, the cross section length of short sides of pile body is 30cm, long side side A length of 60cm, it is such as square, then the length of side is 60cm, and factorial praluction, for pile body length between 3 meters to 20 meters, inner chamber 11 can Formed by the way of centrifugation.
In the opposite side of left and right two of concrete pile body 1, one of side is provided with convex tendon 2, and another side is set There is the slot 3 for the inserting of convex tendon 2.Certain opposite side of left and right two of concrete pile body 1 can also be equipped with convex tendon 2 or be all provided with There is slot 3.The cross section of convex tendon 2 is in outer small interior big trapezoidal, and the cross section of slot 3 is in small trapezoidal of outer imperial palace.The present embodiment Middle convex tendon 2 has more and is arranged at intervals up and down along the length direction (Y-direction as shown in the figure) of concrete pile body 1, neighbouring two Spacing d is formed between convex tendon 2.Certainly, convex tendon 2 is the continuous long rib strip shaped set along concrete pile body (1) length direction.It is convex Muscle 2 and slot 3 meet aftermentioned condition:Adjacent two concrete pile bodies 1 can be by convex tendon 2 and the inserting of slot 3 splicing one Rise;The permeable hole 4 of multiple extraneous and described inner chambers 11 of connection is provided with former and later two opposite sides of concrete pile body 1.
In the opposite side of left and right two of concrete pile body 1, each side is provided with convex tendon 2 or the alternative one of slot 3, adjacent Two concrete pile bodies 1 can be stitched together this concrete-pile beneficial to manufacture bunding protection by convex tendon 2 and the inserting of slot 3 Wall;Multiple extraneous permeable holes 4 with inner chamber 11 of connection are provided with former and later two opposite sides of concrete pile body 1, are such as used The bunding protecting wall that this concrete-pile is built, river can are penetrated into bunding soil via permeable hole 4 and inner chamber 11, make bank The enough moisture of soil conservation near dike, in addition, as the soil moisture near bunding is excessive, also can be via permeable hole and inner chamber Penetrate into river, realize river and the exchange of moisture in bunding soil, furthermore, permeable hole and inner chamber can be fishes and shrimps on protecting wall The biology such as shellfish provides boarding and breeding place, finally makes playing anti-bank protection dam using the bunding protecting wall that this concrete-pile is built The ecological balance is more conducive to while effect.
It is second embodiment of concrete-pile of the present invention as shown in Fig. 5~7.
The difference of the present embodiment and one embodiment is:The cross section of concrete pile body 1 is circle.Concrete-pile The cross-sectional diameter of body 1 is 60 ㎝.
As shown in Figure 8,9, for using the embodiment of the ecological environment-friendly type bunding protecting wall of one embodiment concrete-pile.
Concrete pile bodies 1 in a kind of ecological environment-friendly type bunding protecting wall, including more insertion soil, in the present embodiment Concrete pile body 1 is square pile, naturally it is also possible to rectangle stake, passes through convex tendon 2 and slot 3 between adjacent two concrete pile bodies 1 Inserting is stitched together, and permeable hole 4 and inner chamber 11 form the penetrating passage 5 to supply water by concrete pile body 1.Certain two convex tendons The part that spacing d also forms penetrating passage 5 is formed between 2.Rubble or particulate matter are filled with inner chamber 11.Rubble or particulate matter Do not shown in drawing.
The infiltration lane 5 that this protecting wall can be such that river is formed via permeable hole 4 and inner chamber 11 is penetrated into bunding soil, is made The enough moisture of soil conservation near bunding, also can be via permeable hole 4, interior in addition, as the soil moisture near bunding is excessive Chamber 11 and spacing d are penetrated into river, realize the exchange of moisture in river and bunding soil, furthermore, on protecting wall permeable hole and Inner chamber can provide boarding and breeding place for the biology such as fishes and shrimps shellfish, finally make to exist using the bunding protecting wall that this concrete-pile is built The ecological balance is more conducive to while playing anti-bank protection dam effect.
As shown in Figure 10, the reality for the present invention using the ecological environment-friendly type bunding protecting wall of second embodiment concrete-pile Apply example.The difference of the present embodiment and one embodiment is:The cross section of concrete pile body 1 is circle.As round stake
Although the preferred embodiments of the present invention described in detail above, it is to be clearly understood that for this area Technical staff for, the present invention can have various modifications and variations.That is made within the spirit and principles of the invention appoints What modification, equivalent substitution, improvement etc., should be included in the scope of the protection.

Claims (9)

1. a kind of hollow concrete-pile, including concrete pile body (1), have inside concrete pile body (1) and along concrete-pile The inner chamber (11) of body (1) length direction extension, inner chamber (11) are formed using centrifugation, it is characterised in that:The concrete-pile In the opposite two of which side of body (1), each side is provided with convex tendon (2) or slot (3) alternative one;The concrete pile body (1) permeable hole (4) of multiple extraneous and described inner chambers (11) of connection is provided with two other opposite side.
2. hollow concrete-pile according to claim 1, it is characterised in that:Opposite its of the concrete pile body (1) In in two sides, one of side is provided with the convex tendon (2), and another side is provided with the slot (3).
3. hollow concrete-pile according to claim 1, it is characterised in that:Opposite its of the concrete pile body (1) In two sides be equipped with the convex tendon (2) or the slot (3).
4. hollow concrete-pile according to claim 1, it is characterised in that:The cross section of the concrete pile body (1) For rectangle or circle.
5. hollow concrete-pile according to claim 1, it is characterised in that:The cross section of the convex tendon (2) is in outer small Interior big trapezoidal, the cross section of the slot (3) is in small trapezoidal of outer imperial palace.
6. hollow concrete-pile according to claim 1, it is characterised in that:The convex tendon (2) is along concrete pile body (1) the continuous long rib strip shaped that length direction is set.
7. hollow concrete-pile according to claim 1, it is characterised in that:The convex tendon (2) has more and along coagulation The length direction of native pile body (1) is arranged at intervals up and down, and spacing (d) is formed between neighbouring two convex tendons (2).
A kind of 8. ecological environment-friendly type bunding protecting wall using concrete-pile as claimed in claim 1, it is characterised in that:Including more The concrete pile body (1) in root insertion soil, by the convex tendon (2) and slotting between adjacent two concrete pile bodies (1) Groove (3) inserting is stitched together, and the permeable hole (4) and inner chamber (11) form to supply water and led to by the infiltration of concrete pile body (1) Road (5).
9. ecological environment-friendly type bunding protecting wall according to claim 8, it is characterised in that:It is filled with the inner chamber (11) Particulate matter.
CN201610203893.9A 2016-04-01 2016-04-01 Hollow concrete-pile and the ecological environment-friendly type bunding protecting wall using this Active CN105672253B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610203893.9A CN105672253B (en) 2016-04-01 2016-04-01 Hollow concrete-pile and the ecological environment-friendly type bunding protecting wall using this

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610203893.9A CN105672253B (en) 2016-04-01 2016-04-01 Hollow concrete-pile and the ecological environment-friendly type bunding protecting wall using this

Publications (2)

Publication Number Publication Date
CN105672253A CN105672253A (en) 2016-06-15
CN105672253B true CN105672253B (en) 2018-02-23

Family

ID=56225831

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610203893.9A Active CN105672253B (en) 2016-04-01 2016-04-01 Hollow concrete-pile and the ecological environment-friendly type bunding protecting wall using this

Country Status (1)

Country Link
CN (1) CN105672253B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013137B (en) * 2016-07-01 2017-12-01 俞晓东 Prestressed-concrete pile and the combination using this
CN112942446B (en) * 2021-02-04 2022-04-19 浙江吉祥建设集团有限公司 Sheet pile foundation waterproof structure
CN113638359B (en) * 2021-08-13 2023-01-17 清华珠三角研究院 Protection device for preventing coast erosion and construction process thereof
CN115262480B (en) * 2022-08-24 2024-07-19 江苏麦廊新材料科技有限公司 Ecological imitation wood pile for river ecological management and paving method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100554761B1 (en) * 2005-11-22 2006-02-24 (주)부림종합건축사사무소 Watertproof structure of protection wall for building foundation work
CN203808010U (en) * 2014-03-18 2014-09-03 陆见华 Permeable T-shaped pile
CN204715294U (en) * 2015-06-16 2015-10-21 湖北工业大学 The permeable dry type stake of regeneration concrete
CN205604228U (en) * 2016-04-01 2016-09-28 俞向阳 Hollow concrete pile and adopt this ecological environment -friendly bank dyke revetment

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100554761B1 (en) * 2005-11-22 2006-02-24 (주)부림종합건축사사무소 Watertproof structure of protection wall for building foundation work
CN203808010U (en) * 2014-03-18 2014-09-03 陆见华 Permeable T-shaped pile
CN204715294U (en) * 2015-06-16 2015-10-21 湖北工业大学 The permeable dry type stake of regeneration concrete
CN205604228U (en) * 2016-04-01 2016-09-28 俞向阳 Hollow concrete pile and adopt this ecological environment -friendly bank dyke revetment

Also Published As

Publication number Publication date
CN105672253A (en) 2016-06-15

Similar Documents

Publication Publication Date Title
CN1837512B (en) Combined cofferdam of steel slab pile and steel pipe pile an method for manufacturing the same
CN105672253B (en) Hollow concrete-pile and the ecological environment-friendly type bunding protecting wall using this
CN202672093U (en) Anchoring type dock wall structure of sheet-pile wall
CN105544465B (en) A kind of bunding protecting wall
CN206591509U (en) Protecting wall and the precast concrete pile for building protecting wall
CN205604228U (en) Hollow concrete pile and adopt this ecological environment -friendly bank dyke revetment
CN205604225U (en) Stake of concrete trough shaped plate
CN105625300B (en) Ecological environment-friendly type bunding protecting wall and the concrete-pile for the protecting wall
CN109356186B (en) Bridge tower composite foundation applicable to deep water soft soil areas and construction method
CN106013137B (en) Prestressed-concrete pile and the combination using this
CN105780756B (en) Protecting wall and H-type prestressed-concrete pile for the protecting wall
CN203939032U (en) A kind of for upper lower the formula deep footing groove enclosing structure of wall of ground consisting of hard rock
CN105019472A (en) Composite fender pile for building basement
CN105040707A (en) Combined densely-arrayed pile deep foundation pit supporting and enclosure structure used as basement external wall
CN206971233U (en) A kind of supporting construction for deep basal pit
CN205348097U (en) Bank dyke revetment
CN203924037U (en) Cast-in-situs type external prestressing steel tube concrete pile and supporting piling wall
CN205688429U (en) H type prestressed-concrete pile and use this combination
CN204825964U (en) A compound retaining pile for building basement
CN210482182U (en) Double-river structure for constructing ecological circulating water system
CN105625257B (en) Ecological environment-friendly type bunding protecting wall and the H-type prestressed-concrete pile for the protecting wall
CN209907423U (en) Ultra-deep dam foundation grouting curtain structure
CN209873700U (en) Mixed type ecological beach building engineering
CN205742171U (en) Prestressed-concrete pile and use this combination
CN204875670U (en) Compound retaining pile structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant