CN105672239B - A kind of monitoring device deformed for karst region and goaf railway bed ground collapse - Google Patents

A kind of monitoring device deformed for karst region and goaf railway bed ground collapse Download PDF

Info

Publication number
CN105672239B
CN105672239B CN201610040151.9A CN201610040151A CN105672239B CN 105672239 B CN105672239 B CN 105672239B CN 201610040151 A CN201610040151 A CN 201610040151A CN 105672239 B CN105672239 B CN 105672239B
Authority
CN
China
Prior art keywords
railway bed
top plate
induction coil
inductance type
connecting rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610040151.9A
Other languages
Chinese (zh)
Other versions
CN105672239A (en
Inventor
郭建湖
李小和
赵新益
姚洪锡
李巍
王勇刚
杨辉建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201610040151.9A priority Critical patent/CN105672239B/en
Publication of CN105672239A publication Critical patent/CN105672239A/en
Application granted granted Critical
Publication of CN105672239B publication Critical patent/CN105672239B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D1/00Investigation of foundation soil in situ
    • E02D1/08Investigation of foundation soil in situ after finishing the foundation structure

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Soil Sciences (AREA)
  • Analytical Chemistry (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Force Measurement Appropriate To Specific Purposes (AREA)
  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)
  • Measurement Of Length, Angles, Or The Like Using Electric Or Magnetic Means (AREA)

Abstract

The invention discloses a kind of monitoring device deformed for karst region and goaf railway bed ground collapse, including inductance type strain gauge and inductance type transducer tester, inductance type strain gauge includes top test device, middle part connecting rod, lower fastening device and ring flange;Karst cave top plate or mined out hole top plate can drive induction coil synchronously sedimentation when settling;Railway bed can drive the magnet synchronously to settle when settling;When the sedimentation that railway bed is produced is different from the sedimentation that karst cave top plate or mined out hole top plate are produced, magnet mutually cuts generation electric current with induction coil, is the sedimentation difference that can obtain karst cave top plate or mined out hole top plate and railway bed by inductance type transducer tester.The device is located between railway bed bottom and ground, is interfered without that through railway bed, can avoid filling generation with railway bed in work progress, and does not influence the globality of railway bed and track, and the safe operation of train is not influenceed.

Description

A kind of monitoring device deformed for karst region and goaf railway bed ground collapse
Technical field
The invention belongs to foundation deformation monitoring technical field, more particularly, to karst region and goaf railway bed The monitoring of base collapse-deformation.
Background technology
China is vast in territory, and complex geologic conditions are various, unavoidable when railway bed is built to pass through givey rock Molten area and goaf.Although being handled using certain foundation stabilization measure, due to karsts developing area and small-sized mined out hole distribution Erratic behavior, still suffer from the possibility collapsed.When ground is collapsed, cause top railway bed to lose support generation and collapse, So as to cause railway bed to occur differential settlement, the ride comfort of railway is influenceed, the safe operation of train is influenceed when serious.Cause This, railway bed work point higher to classification of rail or important is necessary to carry out ground collapse observation, according to collapsing situation Take necessary measure to punish in time, prevent further harm.
The patent of invention CN103276755B announced provides a kind of railway raft foundation bottom soil body void that is used for and become The monitoring device of shape, including the steel plate arranged positioned at raft plate lower horizontal, steel plate bottom surface, which is provided with, is anchored in steel plate below raft plate Foundation soil in anchor pole, steel plate top surface, which is fixed with outside the inner side reinforcing bar being vertically arranged, inner side reinforcing bar, to be arranged with and raft plate is overall Pour and be arranged with the outside pillar being fixed in embankment outside the raft slab pipe being vertically arranged together, raft slab pipe.The monitoring Device is measured using slide measure, although precision is high, due to train continuous service during operation, is difficult to realize artificial survey Amount, and influenceed by measurement peopleware, weather etc., measurement quality is difficult to ensure.Furthermore, steel pipe and outside pillar need to run through railway Roadbed and upper track etc., fill to be also easy to produce and interfere in work progress with railway bed, and inevitably influence railway The globality of roadbed and track, is likely to form hidden danger when serious.
The content of the invention
For the disadvantages described above or Improvement requirement of prior art, the present invention proposes a kind of for karst region and goaf iron The monitoring device of road roadbed ground collapse deformation, the device should avoid the problem of manual measurement is difficult, ensure measurement essence again The safe operation of degree and train, while requiring not influenceing the globality of structure.
To achieve the above object, it is proposed, according to the invention, be used for karst region there is provided one kind and goaf railway bed ground collapses The monitoring device of notch distortion, it is characterised in that including inductance type strain gauge and inductance type transducer tester, the inductance type should Becoming meter includes top test device, middle part connecting rod, lower fastening device and ring flange, wherein,
The lower fastening device is fixedly connected on karst cave top plate or mined out hole top plate;
The middle part connecting rod is hollow structure and its upper and lower end is open, and it is vertically arranged and lower end is fixedly connected On the lower fastening device;
The ring flange is fixed on railway bed, and it is located at the top of the middle part connecting rod and is connected with the middle part There is spacing between bar, wherein, the railway bed is located at the top of the karst cave top plate or mined out hole top plate;
The top test device includes induction coil and magnet, and the induction coil is vertically arranged and is fixedly connected on On the inwall of the middle part connecting rod, the karst cave top plate or mined out hole top plate can drive the middle part when settling Connecting rod and the induction coil are synchronously settled;The upper end of the magnet is fixedly connected on the ring flange, and its lower end is stretched into In the induction coil, the railway bed can drive the magnet synchronously to settle when settling;
The inductance type transducer tester is connected by wire with the induction coil;
The sedimentation of the sedimentation of railway bed and/or karst cave top plate or mined out hole top plate can make magnet and induction coil phase Mutually cutting produces electric current, is that can obtain railway bed to push up with karst cave top plate or mined out hole by inductance type transducer tester The sedimentation difference of plate.
Preferably, the top test device also includes being used for protecting the bellows of induction coil, the bellows it is upper End is fixedly connected on the ring flange, and its lower end is stretched into the induction coil, and the ripple is stretched into the lower end of the magnet In pipe.
Preferably, the lower fastening device includes bolt and reinforcing bar group, and the bolt is vertically arranged and its upper end spiral shell Line connects the lower end of the middle part connecting rod, and the reinforcing bar group includes many reinforcing bars and every reinforcing bar is welded on the bolt Outside.
Preferably, every reinforcing bar carries out bending processing, and it includes the first bending end and the second bending end, first folding Bent-up end is fixedly connected on the outside of the bolt, and the second bending end is upturned.
In general, by the contemplated above technical scheme of the present invention compared with prior art, it can obtain down and show Beneficial effect:
(1) inductance type transducer tester of the invention can be arranged on beyond railway bed closed-loop, not by circuit Closing, train operation amount be big and influence of space limitation, can be observed at any time.
(2) present invention carries out reading using inductance type transducer tester to ground collapse-deformation data value, is not measured Peopleware, atmospheric and climatic factors etc. influence, and measurement quality is readily obtained guarantee.
(3) present invention is located between railway bed bottom and karst cave or mined out hole, without that through railway bed, can keep away Exempt to fill generation with railway bed in work progress and interfere, and do not influence the globality of railway bed and track, do not influence The safe operation of train.
Brief description of the drawings
Fig. 1 is structural representation of the present invention in rail support structures;
The structural representation that Fig. 2 is stretched into the connecting rod of middle part for the top test device in the present invention;
Fig. 3 is the structural representation of the lower fastening device in the present invention.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, it is right below in conjunction with drawings and Examples The present invention is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, and It is not used in the restriction present invention.As long as in addition, technical characteristic involved in each embodiment of invention described below Not constituting conflict each other can just be mutually combined.
1~Fig. 3 of reference picture, a kind of monitoring device deformed for karst region and goaf railway bed ground collapse, bag Inductance type strain gauge 1 and inductance type transducer tester are included, the inductance type strain gauge 1 includes top test device 1.1, middle part Connecting rod 1.2, lower fastening device 1.3 and ring flange 1.4, wherein,
The lower fastening device 1.3 is fixedly connected on karst cave top plate or mined out hole top plate 7;
The middle part connecting rod 1.2 is hollow structure and its upper and lower end is open, and it is vertically arranged and lower end is fixed and connected It is connected on the lower fastening device 1.3;
The ring flange 1.4 is fixed on railway bed 5, its be located at the middle part connecting rod 1.2 top and with it is described There is spacing between middle part connecting rod 1.2;
It is vertical that the top test device 1.1 includes magnet 1.1.1 and induction coil 1.1.2, the induction coil 1.1.2 Set and be fixedly connected on the inwall of the middle part connecting rod 1.2, the karst cave or mined out hole 8 are when collapsing Top plate 7 can be made to produce sedimentation, so as to can also drive the middle part connecting rod 1.2 and the induction coil 1.1.2 synchronously to settle;Institute State that magnet 1.1.1 is vertically arranged and its upper end is fixedly connected on the ring flange 1.4 and itself and the middle part connecting rod There is spacing between 1.2, its lower end is stretched into the induction coil 1.1.2, the railway bed 5 can drive when settling The magnet 1.1.1 is synchronously settled;
The inductance type transducer tester is connected by wire 1.5 with the induction coil 1.1.2;
The sedimentation of railway bed 5 and/or karst cave or collapsing for mined out hole 8 can make magnet 1.1.1 and induction coil 1.1.2 mutually cutting produces electric current, by inductance type transducer tester be can obtain the top plate in karst cave or mined out hole 8 with The sedimentation difference of railway bed 5.
Further, the inductance type strain gauge 1 also includes the bellows 1.1.3 for being used to protect induction coil 1.1.2, described Bellows 1.1.3 upper end is fixedly connected on the ring flange 1.4, and its lower end is stretched into the induction coil 1.1.2, described Magnet 1.1.1 lower end is stretched into the bellows 1.1.3.
Further, the lower fastening device 1.3 includes bolt 1.3.1 and reinforcing bar group, and the bolt 1.3.1 is vertically arranged And its upper end is threaded in the lower end of the middle part connecting rod 1.2, the reinforcing bar group includes many reinforcing bar 1.3.2 and every Root reinforcing bar 1.3.2 is welded on the outside of the bolt 1.3.1.
In addition, every reinforcing bar 1.3.2 carries out bending processing, it includes the first bending end and the second bending end, described One bending end is fixedly connected on the outside of the bolt 1.3.1, and the second bending end is upturned.
When mounted, Specific construction process is as follows by the present invention:
(1) smooth location, carries out necessary basement process according to foundation condition, according to design attitude, size etc., can press Drilling 2 is formed on contracting stratum 6.
(2) middle part connecting rod 1.2 is threadedly coupled by bolt 1.3.1, welded reinforcement will be carried on request in drilling 2 1.3.2 karst cave top plate or the mined out top of hole top plate 7 are fixed on bolt 1.3.1 steel pipe, from foot of hole from the bottom up Cement injection mortar 4 and medium coarse sand 3 are backfilled successively.
(3) magnet 1.1.1 and induction coil 1.1.2 is installed successively and draws wire 1.5 from top, vertically to electricity The formation top test device 1.1 of sense formula strain gauge top mounting flange 1.4.
(4) placement in layers railway bed 5, it is by inductance type transducer tester that the test of inductance type strain gauge 1 is initial Value is set to zero, after debugging is finished.
The middle part connecting rod 1.2 of the present invention is made using stainless steel tube, filling medium coarse sand in space between its outer wall and drilling 2 3, the space filling concrete mortar 4 between the bolt 1.3.1 outer walls of lower fastening device 1.3 and drilling 2.Bellows 1.1.3 is set Be placed in induction coil 1.1.2 outside, act to protect induction coil 1.1.2, middle part connecting rod 1.2 and ring flange 1.4 it Between there is spacing, so that the bellows 1.1.3 for having certain length therebetween exposes the middle part connecting rod 1.2 so that Allow magnet 1.1.1 to occur certain sedimentation in the presence of the load of railway bed 5, prevent karst cave or mined out hole 8 from not sending out During raw collapse-deformation, inductance type strain gauge 1 is because of the excessive generation flexural deformation of stress.
The lower fastening device 1.3 of inductance type strain gauge 1 is made up of bolt 1.3.1 and reinforcing bar 1.3.2, reinforcing bar 1.3.2's Second bending end is placed up the crotch-shaped tilted, and its first bending end is welded in the stainless steel steel of bolt 1.3.1 bottoms On the outside of pipe, karst cave top plate or mined out hole top plate 7 are anchored in jointly with the cement mortar 4 of foot of hole, for preventing karst Solution cavity or mined out hole 8 occur monitoring device during collapse-deformation and depart from bottom plate, and lower fastening device 1.3 is by bolt 1.3.1 with Portion's connecting rod 1.2 is connected, when collapse-deformation occurs for karst cave or mined out hole 8, drives lower fastening device 1.3, middle part connection Synchronous deformation occurs for bar 1.2 and test lead induction coil 1.1.2, and induction coil 1.1.2 mutually cuts production with magnet 1.1.1 magnetic fields Raw electric current, displacement signal is converted to by demarcating conversion.Lower fastening device 1.3 can factorial praluction, top set screw thread with Portion's connecting rod 1.2 is connected, and is easy to site operation and installation.
Drilling 2 is that this monitoring device provides installing space, in drilling 2 from bottom to top back-filling in layers cement mortar 4 with slightly Sand 3, plays fixed magnet 1.1.1 and induction coil 1.1.2, prevents inductance type strain gauge 1 from producing flexural deformation.
Magnet 1.1.1 and induction coil 1.1.2 are mutually cut generation current signal and are transferred to convenient test by wire 1.5 At cable port guard box, deformation data value is read by inductance type transducer tester.
The collapse-deformation monitoring device can both realize the monitoring of the sedimentation and deformation of railway bed 5, can realize again karst cave or The monitoring of the mined out collapse-deformation of hole 8, each situation is as follows:
1) when sedimentation and deformation occurs for railway bed 5, lower fastening device 1.3 is fixed, and test lead 1.1 is settled downwards Generation compression, the testable maximum railroad bed settlement deflection of the collapse-deformation monitoring device is middle part connecting rod The bellows 1.1.3 reserved between 1.2 and ring flange 1.4 total length.
2) when collapse-deformation occurs for karst cave or mined out hole 8, the bottom that ring flange 1.4 is fixed on railway bed 5 makes Inductance type strain gauge top is fixed, and inductance type strain gauge bottom occurs collapse-deformation with karst cave or mined out hole 8 and produced Raw stretcher strain.
3) when railway bed 5 and karst cave or mined out hole 8 deform and the deflection of the two is inconsistent, magnetic Occurs relative motion between both iron 1.1.1 and induction coil 1.1.2.
Above-mentioned three kinds of situations can make magnet 1.1.1 and induction coil 1.1.2 mutually cut generation electric current, and pass through wire 1.5 are transferred to current signal at the cable port guard box of convenient test, by inductance type transducer tester by sedimentation and deformation Or collapse-deformation data value is read.By the change curve and rule of analyzing deformation data, it can be determined that karst cave is adopted Specific deflection when the state in cavity 8 is collapsed, and then take necessary measure to punish in time according to the situation that collapses, prevent Produce further harm.
Inductance type strain gauge is fixed on the top plate 7 in karst cave or mined out hole 8 by the present invention, when karst cave or mined out When collapse-deformation occurs for hole 8, magnet 1.1.1 and induction coil 1.1.2 mutually cut generation electric current, and by wire 1.5 by electricity Stream signal is transferred at the cable port guard box of convenient test, is read sedimentation and deformation data value by inductance type transducer tester Go out.The device to test digital independent is arranged on beyond railway bed closed-loop, not big and empty by closure of track, train operation amount Between the influence that limits, can be observed at any time;The device is carried out using inductance type transducer tester to sedimentation and deformation data value Reading, is not influenceed, quality is readily obtained guarantee by measurement peopleware, atmospheric and climatic factors etc., while the device is located at railway Between roadbed bottom and ground, without through railway bed, it is to avoid fill generation with railway bed in work progress and interfere And the globality of railway bed and track is not influenceed, the safe operation of train is not influenceed.
As it will be easily appreciated by one skilled in the art that the foregoing is merely illustrative of the preferred embodiments of the present invention, it is not used to The limitation present invention, any modifications, equivalent substitutions and improvements made within the spirit and principles of the invention etc., it all should include Within protection scope of the present invention.

Claims (4)

1. a kind of monitoring device deformed for karst region and goaf railway bed ground collapse, it is characterised in that including electricity Sense formula strain gauge and inductance type transducer tester, the inductance type strain gauge include top test device, middle part connecting rod, under Portion's fixing device and ring flange, wherein,
The lower fastening device is fixedly connected on karst cave top plate or mined out hole top plate;
The middle part connecting rod is hollow structure and its upper and lower end is open, and it is vertically arranged and lower end is fixedly connected on institute State on lower fastening device;
The ring flange is fixed on railway bed, its be located at the middle part connecting rod top and with the middle part connecting rod it Between there is spacing, wherein, the railway bed is located at the top of the karst cave top plate or mined out hole top plate;
The top test device includes induction coil and magnet, and the induction coil is vertically arranged and is fixedly connected on described On the inwall of middle part connecting rod, the karst cave top plate or mined out hole top plate can drive the middle part to connect when settling Bar and the induction coil are synchronously settled;The upper end of the magnet is fixedly connected on the ring flange, and its lower end is stretched into described In induction coil, the railway bed can drive the magnet synchronously to settle when settling;
The inductance type transducer tester is connected by wire with the induction coil;
The sedimentation of the sedimentation of railway bed and/or karst cave top plate or mined out hole top plate can be such that magnet is mutually cut with induction coil Generation electric current is cut, is that can obtain railway bed and karst cave top plate or mined out hole top plate by inductance type transducer tester Settle difference.
2. a kind of monitoring dress deformed for karst region and goaf railway bed ground collapse according to claim 1 Put, it is characterised in that the top test device also includes the bellows for being used to protect induction coil, the upper end of the bellows It is fixedly connected on the ring flange, its lower end is stretched into the induction coil, the bellows is stretched into the lower end of the magnet It is interior.
3. a kind of monitoring dress deformed for karst region and goaf railway bed ground collapse according to claim 1 Put, it is characterised in that the lower fastening device includes bolt and reinforcing bar group, the bolt is vertically arranged and its threaded upper ends The lower end of the middle part connecting rod is connected, the reinforcing bar group includes many reinforcing bars and every reinforcing bar is welded on the bolt Outside.
4. a kind of monitoring dress deformed for karst region and goaf railway bed ground collapse according to claim 3 Put, it is characterised in that every reinforcing bar carries out bending processing, it includes the first bending end and the second bending end, first folding Bent-up end is fixedly connected on the outside of the bolt, and the second bending end is upturned.
CN201610040151.9A 2016-01-21 2016-01-21 A kind of monitoring device deformed for karst region and goaf railway bed ground collapse Active CN105672239B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610040151.9A CN105672239B (en) 2016-01-21 2016-01-21 A kind of monitoring device deformed for karst region and goaf railway bed ground collapse

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610040151.9A CN105672239B (en) 2016-01-21 2016-01-21 A kind of monitoring device deformed for karst region and goaf railway bed ground collapse

Publications (2)

Publication Number Publication Date
CN105672239A CN105672239A (en) 2016-06-15
CN105672239B true CN105672239B (en) 2017-09-12

Family

ID=56301868

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610040151.9A Active CN105672239B (en) 2016-01-21 2016-01-21 A kind of monitoring device deformed for karst region and goaf railway bed ground collapse

Country Status (1)

Country Link
CN (1) CN105672239B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107313305B (en) * 2017-07-06 2018-12-14 中铁第一勘察设计院集团有限公司 The processing method of type sinkhole is lain concealed under the railway bed of karst area
CN107767625A (en) * 2017-10-23 2018-03-06 山西省交通科学研究院 A kind of highway goaf subgrade stability monitoring and pre-warning system and method
CN108049328B (en) * 2017-12-26 2023-12-26 山西路桥第一工程有限责任公司 Highway collapse early warning device and early warning method thereof
CN115682888B (en) * 2022-10-30 2023-05-23 山东省地质矿产勘查开发局第七地质大队(山东省第七地质矿产勘查院) Karst monitoring devices that sinks

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE69010627D1 (en) * 1989-11-10 1994-08-18 Kidoh Construction Co Method and device for measuring ground fluctuations.
JP3324582B2 (en) * 1999-09-27 2002-09-17 株式会社興和 Measuring method of ground and rock displacement
CN101592487A (en) * 2009-06-22 2009-12-02 铁道第三勘察设计院集团有限公司 Magnet ring type settlement layered horizontal test system
DE102010045465A1 (en) * 2010-09-14 2011-09-22 Siemens Aktiengesellschaft Method for monitoring structural integrity of e.g. dam-like structure, involves transmitting monitoring signal to evaluation device, and monitoring structural integrity of structure or site based on monitoring signal
CN103276755A (en) * 2013-06-07 2013-09-04 中铁第四勘察设计院集团有限公司 Raft foundation bottom soil body void deformation monitoring device
CN204098005U (en) * 2014-10-27 2015-01-14 铁道第三勘察设计院集团有限公司 A kind of roadbed horizontal movement and vertical displacement integrated test system
CN204329887U (en) * 2015-01-07 2015-05-13 西南大学 Railway bed Collapse monitor system
CN105137031A (en) * 2015-07-24 2015-12-09 华北水利水电大学 Test apparatus and test method of simulating goaf sedimentation mechanism
CN105203626A (en) * 2015-10-27 2015-12-30 西南大学 Railway roadbed collapse full-process evolution dynamic monitoring system and monitoring method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE69010627D1 (en) * 1989-11-10 1994-08-18 Kidoh Construction Co Method and device for measuring ground fluctuations.
JP3324582B2 (en) * 1999-09-27 2002-09-17 株式会社興和 Measuring method of ground and rock displacement
CN101592487A (en) * 2009-06-22 2009-12-02 铁道第三勘察设计院集团有限公司 Magnet ring type settlement layered horizontal test system
DE102010045465A1 (en) * 2010-09-14 2011-09-22 Siemens Aktiengesellschaft Method for monitoring structural integrity of e.g. dam-like structure, involves transmitting monitoring signal to evaluation device, and monitoring structural integrity of structure or site based on monitoring signal
CN103276755A (en) * 2013-06-07 2013-09-04 中铁第四勘察设计院集团有限公司 Raft foundation bottom soil body void deformation monitoring device
CN204098005U (en) * 2014-10-27 2015-01-14 铁道第三勘察设计院集团有限公司 A kind of roadbed horizontal movement and vertical displacement integrated test system
CN204329887U (en) * 2015-01-07 2015-05-13 西南大学 Railway bed Collapse monitor system
CN105137031A (en) * 2015-07-24 2015-12-09 华北水利水电大学 Test apparatus and test method of simulating goaf sedimentation mechanism
CN105203626A (en) * 2015-10-27 2015-12-30 西南大学 Railway roadbed collapse full-process evolution dynamic monitoring system and monitoring method

Also Published As

Publication number Publication date
CN105672239A (en) 2016-06-15

Similar Documents

Publication Publication Date Title
CN105672239B (en) A kind of monitoring device deformed for karst region and goaf railway bed ground collapse
CN105350509B (en) Filing layered sedimentation monitoring device and method
CN207079558U (en) High-speed railway subgrade settlement monitoring element protection
CN204479060U (en) A kind of subgrade stability recording geometry
CN103485549B (en) Based on the localization method to large-scale built-in fitting
CN105926672B (en) A kind of Underground Subway Station steel pipe column construction method
CN205617351U (en) A monitoring devices that is used for deformation of sining of karst region and collecting space area railway roadbed ground
CN102966096A (en) Construction method for double pile casings of large-diameter cast-in-situ bored pile
WO2017125018A1 (en) Device for monitoring void value of settlement of rail support beam and roadbed of medium-low-speed magnetic suspension low line
CN106372292A (en) Calculation method for building settlement caused by shield tunnel construction
CN206941325U (en) The newly-built peg board formula roadbed of girder construction system in length and breadth
CN206670617U (en) Settlement monitoring device is used in a kind of Underground Engineering Excavation construction
CN106988339B (en) Sandy gravel stratum piping lane construction technology
CN202814388U (en) Device for tunnel pipe shed support deformation testing
CN104316029B (en) A kind of geology settlement monitoring device and monitoring method
CN103276755B (en) Raft foundation bottom soil body void deformation monitoring device
CN209459633U (en) A kind of subgrade settlement monitoring device
CN205475313U (en) Add muscle balance weight formula retaining wall structure
CN105525749A (en) Large-formwork casting construction method for transformer station accident oil pool
CN113006163A (en) Test device and test method for karst cave-containing foundation pit excavation model
CN107447771A (en) A kind of land bearing platform construction system and construction method
CN215252128U (en) Paving and leveling device for road cement stabilized base layer
CN207073046U (en) A kind of newly-built peg board formula roadbed of the chainless drives formula structural system with bent cap
CN214583185U (en) Highway is reformed transform and is expanded fill road bed section and subsides monitoring devices
CN109162259B (en) Method for mounting array type displacement meter on high rock-fill dam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant