CN105672145A - Structure for broadening bridge by additionally arranging steel cap beam on top of pier - Google Patents

Structure for broadening bridge by additionally arranging steel cap beam on top of pier Download PDF

Info

Publication number
CN105672145A
CN105672145A CN201610165224.7A CN201610165224A CN105672145A CN 105672145 A CN105672145 A CN 105672145A CN 201610165224 A CN201610165224 A CN 201610165224A CN 105672145 A CN105672145 A CN 105672145A
Authority
CN
China
Prior art keywords
bridge
steel
pier
box
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610165224.7A
Other languages
Chinese (zh)
Other versions
CN105672145B (en
Inventor
李文武
祁伟超
王骞
张哲�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian University of Technology
Original Assignee
Dalian University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dalian University of Technology filed Critical Dalian University of Technology
Priority to CN201610165224.7A priority Critical patent/CN105672145B/en
Publication of CN105672145A publication Critical patent/CN105672145A/en
Application granted granted Critical
Publication of CN105672145B publication Critical patent/CN105672145B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明提供了一种墩顶增设钢盖梁拓宽桥梁,属于桥梁工程技术领域。一种墩顶增设钢盖梁拓宽桥梁的结构,在原混凝土桥墩的两侧浇筑后浇混凝土,根据桥梁上部受力确定后浇混凝土的具体宽度;在浇筑后浇混凝土桥墩的顶部增设钢盖梁,钢盖梁为箱型截面,由钢板焊接而成;根据桥梁上部受力,在钢盖梁内布置预应力钢束和预应力锚筋,预应力钢束和预应力锚筋在钢盖梁内垂直布置;在原混凝土箱梁两侧增设钢箱梁,钢箱梁坐落在钢盖梁上。本发明的效果和益处是不拆除原有桥梁主体结构确保加宽改造的经济性;新增钢箱梁结构的设计荷载不受限,拓宽后的桥梁运营可靠性高;施工过程不需要中断桥上交通,同时现场施工工期短,对地面交通影响小。

The invention provides a bridge widened by adding a steel cover beam on the top of a pier and belongs to the technical field of bridge engineering. A structure in which a steel cover beam is added to the top of the pier to widen the bridge. Post-cast concrete is poured on both sides of the original concrete pier, and the specific width of the post-cast concrete is determined according to the force on the upper part of the bridge; a steel cover beam is added on the top of the post-cast concrete pier, The steel cover beam is a box-shaped section welded by steel plates; according to the force on the upper part of the bridge, prestressed steel beams and prestressed anchor bars are arranged in the steel cover beam, and the prestressed steel beams and prestressed anchor bars are placed in the steel cover beam. Vertical arrangement; steel box girders are added on both sides of the original concrete box girders, and the steel box girders are located on the steel cover girders. The effects and benefits of the present invention are that the main structure of the original bridge is not removed to ensure the economy of widening and reconstruction; the design load of the newly added steel box girder structure is not limited, and the widened bridge has high operational reliability; the construction process does not need to interrupt the bridge At the same time, the on-site construction period is short, and the impact on ground traffic is small.

Description

A kind of Dun Ding sets up the structure that bridge widened by steel bent cap
Technical field
The invention belongs to technical field of bridge engineering, it relates to need the bridge of widening and improving in bridge construction, especially need the Urban Bridge that two side is widened, a kind of Dun Ding of concrete offer sets up the structure that bridge widened by steel bent cap.
Background technology
At present, in bridge widening field, common way has following several way:
Increase Steel Concrete cantilever outrigger: remove old bridge railings and walkway facility, strengthen or increase cantilever outrigger, it is achieved widen the object of bridge. Two sides that the method is applicable to general beam bridge and arcuately bridge are widened, but the restriction by self-bearing capacity, widen span limited, act on the load on cantilever also unsuitable excessive, be usually suitable only for People's Bank of China and the vehicle that should not pass through.
Set up side bar: bridge girder being adopted to cored slab, T beam and small box girder, remove railing and the walkway facility of Jiu Qiao one or both sides, the side bar of same beam bodily form formula is set up in original bridge both sides, splice with primary structure, set up bridge pier simultaneously and lengthen former bent cap to support newly-increased side bar, it is achieved widen the object of bridge. Mostly needing to set up bridge pier due to this method, original ground traffic impact is big, and therefore the construction land in city is by the use of restriction the method, and in addition, Urban Bridge is in the majority with overall case beam, and the method is not suitable for.
Newly building bridge: old bridge short of width, builds new bridge in old bridge list side or both sides, in widening, does not substantially change old bridge structure, build Fu Qiao and former bridge relatively independent, after widening, new bridge and Jiu Qiao are independent. But, need to set up bridge pier due to this method, seriously affect original ground traffic, therefore the construction land in city is by the use of restriction the method.
Summary of the invention
In order to solve existing old bridge widening technology exists to widen design load limited, newly-increased hydrodynamic conditions traffic above-ground, and construction process needs middle bridge cut-off submit the deficiencies such as logical, the present invention provides the structure of a kind of new old bridge widening, this structure does not need to set up new bridge pier, widening design load unrestricted, construction process is submitted logical without the need to middle bridge cut-off.
The technical scheme of the present invention is:
Dun Ding sets up the structure that bridge widened by steel bent cap, pouring concrete after the both sides of former concrete pier are built, and determines the concrete width of rear pouring concrete by power according to bridge top; After building, steel bent cap is set up at the top of pouring concrete bridge pier, and steel bent cap is box-type section, is welded by steel plate; According to bridge top by power, in steel bent cap, arrangement prestress steel bundle and prestress dowel, prestressed strand and prestress dowel are arranged vertically in steel bent cap; Setting up steel box-girder in former concrete box girder both sides, steel box-girder is seated on steel bent cap.
Effect and the benefit of the present invention be: does not remove the economy that original bridge main body structure guarantees widen and rebuild; The design load of newly-increased steel box girder is not limited; Do not set up new bridge pier, original ground traffic organization impact is little; It is logical that construction process does not need middle bridge cut-off to submit, and is operated in factory in a large number and completes, and the site operation duration is short, and construction process is little on traffic above-ground impact.
Accompanying drawing explanation
The Dun Ding that Fig. 1 is the present invention sets up the structural front view that bridge widened by steel bent cap.
The Dun Ding that Fig. 2 is the present invention sets up the structure right view that bridge widened by steel bent cap.
The Dun Ding that Fig. 3 is the present invention sets up the structure vertical view that bridge widened by steel bent cap.
In figure: 1 steel box-girder; 2 former concrete box girders; 3 steel bent caps; 4 prestressed strands; 5 prestress dowels; 6 former concrete piers; Pouring concrete after 7.
Embodiment
The specific embodiment of the present invention is described in detail below in conjunction with technical scheme and accompanying drawing.
Former bridge width is 18.5 meters, and girder is concrete box girder cross section, and widening rear bridge width is 26m, and Specific construction flow process is as follows:
(1) at steel beam column such as prefabrication steel bent cap and both sides steel box-girder.
(2) to former bridge pier dabbing, bar planting, building rear pouring concrete, by vertical for bridge pier bridge to each thickening 0.5 meter, add thick-layer top at concrete and install steel bent cap embedded section, steel bent cap is fixed by the prestress dowel of the fixing steel bent cap of stretch-draw, splicing residue steel bent cap.
(3) traffic on bridge is carried out control, remove the crashproof guardrail of former bridge and part concrete cantilever.
(4) support installing both sides steel box-girder is adopted.
(5) the external prestressed strand of stretch-draw steel bent cap.
(6) anticorrosion of steel structure process is carried out, construction bridge deck pavement and attached engineering.
Cross section: former bridge cross section remains unchanged, steel box-girder adopts box-type section.

Claims (1)

1. a Dun Ding sets up the structure that bridge widened by steel bent cap, it is characterised in that, pouring concrete after the both sides of former concrete pier are built, determines the concrete width of rear pouring concrete according to bridge top by power; After building, steel bent cap is set up at the top of pouring concrete bridge pier, and steel bent cap is box-type section, is welded by steel plate; According to bridge top by power, in steel bent cap, arrangement prestress steel bundle and prestress dowel, prestressed strand and prestress dowel are arranged vertically in steel bent cap; Setting up steel box-girder in former concrete box girder both sides, steel box-girder is seated on steel bent cap.
CN201610165224.7A 2016-03-18 2016-03-18 A kind of pier top sets up the structure that steel lid beam widens bridge Expired - Fee Related CN105672145B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610165224.7A CN105672145B (en) 2016-03-18 2016-03-18 A kind of pier top sets up the structure that steel lid beam widens bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610165224.7A CN105672145B (en) 2016-03-18 2016-03-18 A kind of pier top sets up the structure that steel lid beam widens bridge

Publications (2)

Publication Number Publication Date
CN105672145A true CN105672145A (en) 2016-06-15
CN105672145B CN105672145B (en) 2017-10-13

Family

ID=56311260

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610165224.7A Expired - Fee Related CN105672145B (en) 2016-03-18 2016-03-18 A kind of pier top sets up the structure that steel lid beam widens bridge

Country Status (1)

Country Link
CN (1) CN105672145B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110468743A (en) * 2019-07-31 2019-11-19 中铁大桥局集团有限公司 A kind of traveling cradle and construction method for the transformation of old pier coping
CN112323653A (en) * 2020-10-29 2021-02-05 德州市公路工程总公司 Construction method of active bridge channel widening structure and application thereof
CN114214969A (en) * 2021-12-01 2022-03-22 广州市市政工程设计研究总院有限公司 A kind of wide-splitting structure and method of split-width bridge

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL2003626C2 (en) * 2009-10-12 2011-04-13 Heijmans Beton En Waterbouw B V METHOD FOR IMPROVING A STEEL BRIDGE, AND ALSO IMPROVED STEEL BRIDGE.
US20110219554A1 (en) * 2010-03-15 2011-09-15 Aumuller Paul M Bridge construction and method of replacing bridges
MX2010007687A (en) * 2009-07-27 2011-10-28 Encon Solutions Llc Apparatus and method for replacing a bridge using pre-cast construction techniques.
CN203403373U (en) * 2013-08-20 2014-01-22 中铁第四勘察设计院集团有限公司 Antidumping reinforcing device of single-column pier bridge
CN203700977U (en) * 2013-11-12 2014-07-09 丁西焘 Spring supporting-jacking reinforcing structure used for improving shear resistance capacity of bridge
CN205557351U (en) * 2016-03-18 2016-09-07 大连理工大学 Dun ding sets up structure that bridge was widened to steel bent cap

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
MX2010007687A (en) * 2009-07-27 2011-10-28 Encon Solutions Llc Apparatus and method for replacing a bridge using pre-cast construction techniques.
NL2003626C2 (en) * 2009-10-12 2011-04-13 Heijmans Beton En Waterbouw B V METHOD FOR IMPROVING A STEEL BRIDGE, AND ALSO IMPROVED STEEL BRIDGE.
US20110219554A1 (en) * 2010-03-15 2011-09-15 Aumuller Paul M Bridge construction and method of replacing bridges
CN203403373U (en) * 2013-08-20 2014-01-22 中铁第四勘察设计院集团有限公司 Antidumping reinforcing device of single-column pier bridge
CN203700977U (en) * 2013-11-12 2014-07-09 丁西焘 Spring supporting-jacking reinforcing structure used for improving shear resistance capacity of bridge
CN205557351U (en) * 2016-03-18 2016-09-07 大连理工大学 Dun ding sets up structure that bridge was widened to steel bent cap

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
丁佳元,钟小军,芮浩飞: "上海市内环高架道路(宛平南路—瑞金南路)拓宽方案探讨", 《中国市政工程》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110468743A (en) * 2019-07-31 2019-11-19 中铁大桥局集团有限公司 A kind of traveling cradle and construction method for the transformation of old pier coping
CN110468743B (en) * 2019-07-31 2020-12-01 中铁大桥局集团有限公司 A mobile hanger and construction method for the renovation of old bridge pier caps
CN112323653A (en) * 2020-10-29 2021-02-05 德州市公路工程总公司 Construction method of active bridge channel widening structure and application thereof
CN114214969A (en) * 2021-12-01 2022-03-22 广州市市政工程设计研究总院有限公司 A kind of wide-splitting structure and method of split-width bridge

Also Published As

Publication number Publication date
CN105672145B (en) 2017-10-13

Similar Documents

Publication Publication Date Title
CN104988844B (en) Two times tensioning prestressing force assembled Wavelike steel webplate combination beam
CN205557351U (en) Dun ding sets up structure that bridge was widened to steel bent cap
CN204715224U (en) A kind of case beam reinforcing construction based on i iron diaphragm
EP3482000A1 (en) System for construction of composite u shaped reinforced girders bridge deck and methods thereof
CN103981803B (en) The combined gate pier of precast assembly and construction method thereof
CN105970800B (en) The abutment connecting structure and its construction method of monoblock type combination beam is seamless bridge
CN107217598A (en) A kind of construction method for improving concrete flexural beam bridge antidumping bearing capacity
CN101298756A (en) Technique for widening concrete box girder without increasing foot stall steel component
CN108374320A (en) A kind of construction and construction method of novel RC-masonry combination arch bridge
CN208151833U (en) A kind of construction of novel RC-masonry combination arch bridge
CN105672145A (en) Structure for broadening bridge by additionally arranging steel cap beam on top of pier
CN103882797B (en) A corrugated steel web composite box girder and its construction technology
CN206438380U (en) The long overhanging crossbeam bridge structure of one kind
CN203807928U (en) Corrugated-steel-web combined box girder
CN106087694A (en) Assembling steel plate beams of concrete combined bridge structure and construction method
CN202227268U (en) Concrete box beam structure capable of widening steel cantilever beam
CN103669193A (en) Laterally spliced combination T beam with wavy steel webs and construction method thereof
CN102392421B (en) Small-town arch bridge local widening and reinforcing method based on characteristic of tidal traffic flow
CN111501516A (en) Pedestrian overpass and frame pier
CN210482000U (en) Limiting device for jacking construction of large-span steel pipe concrete tied arch bridge
CN203878460U (en) Prefabricated assembly combined type portal pier
CN104805761A (en) Widened thin-film concrete box girder
CN103255714B (en) Assembly integral-type slab for reinforced concrete slab bridge
CN208235305U (en) A kind of through tied arch bridge structural unit and arch bridge structure
CN115058961B (en) Displaced middle pier structure of re-span continuous beam bridge and construction method of re-span continuous beam bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171013

Termination date: 20200318

CF01 Termination of patent right due to non-payment of annual fee