CN105649652B - The real-time monitoring grouting strengthening method that a kind of Support System in Soft Rock Tunnels is built - Google Patents

The real-time monitoring grouting strengthening method that a kind of Support System in Soft Rock Tunnels is built Download PDF

Info

Publication number
CN105649652B
CN105649652B CN201610105350.3A CN201610105350A CN105649652B CN 105649652 B CN105649652 B CN 105649652B CN 201610105350 A CN201610105350 A CN 201610105350A CN 105649652 B CN105649652 B CN 105649652B
Authority
CN
China
Prior art keywords
core
grouting
face
slip casting
support system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610105350.3A
Other languages
Chinese (zh)
Other versions
CN105649652A (en
Inventor
孔恒
王文正
黄明利
杨建华
李琳
刘学义
石国伶
韩雪刚
张艳秋
马虹霞
郑雪梅
潘政
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Jiaotong University
Beijing Municipal Construction Co Ltd
Original Assignee
Beijing Jiaotong University
Beijing Municipal Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Jiaotong University, Beijing Municipal Construction Co Ltd filed Critical Beijing Jiaotong University
Priority to CN201610105350.3A priority Critical patent/CN105649652B/en
Publication of CN105649652A publication Critical patent/CN105649652A/en
Application granted granted Critical
Publication of CN105649652B publication Critical patent/CN105649652B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The real-time monitoring grouting strengthening method that a kind of Support System in Soft Rock Tunnels is built, belongs to Tunnel Engineering technical field.Comprise the following steps:When a circulation driving task is completed in tunnel, stop driving.Closing face is sprayed with net, is drilled along face, throws advanced tubule into.Grouting and reinforcing is carried out to face using advanced tubule.Grouting amount is controlled using grouting pressure, stops slip casting when final grouting pressure reaches 2~3MPa.After mortar depositing construction terminates, the core-drilling in injecting cement paste, slip casting situation is checked.Observe slurries filling situation and by core censorship.Next work cycle is carried out if core intensity and slurries filling situation reach the standard of construction.The present invention can improve the degree of safety that Support System in Soft Rock Tunnels is built, and reduce unnecessary personal casualty loss, and measure is reasonable and safely controllable.

Description

The real-time monitoring grouting strengthening method that a kind of Support System in Soft Rock Tunnels is built
Technical field
The present invention relates to the real-time monitoring grouting strengthening method that a kind of Support System in Soft Rock Tunnels is built, belong to Tunnel Engineering technology Field.
Background technology
At present, as national basis facility investment builds the increasing of dynamics, metro project and mountain tunnel project gradually increase It is more, there is the constructing tunnel being greatly related in weak surrounding rock in these Tunnel Projects.Weak surrounding rock from support capacity It is weaker, even without from support capacity.Therefore, constructed in weak surrounding rock above all improve country rock from supporting Ability.And Grouting Consolidation has obtained extensively as a kind of method of practicable stable face in tunnel construction field Application.
But the quality of slip casting how is controlled during Grouting Consolidation, between how controlling slip casting and excavating Interval time do not form unified standard, slip casting effect can not obtain accurately evaluation and also become restriction weak surrounding rock Construction safety, the key issue of quality control.The real-time monitoring note that a kind of Support System in Soft Rock Tunnels is built is invented in this case Slurry reinforcement means is then particularly important.
The content of the invention
It is an object of the invention to overcome the shortcomings of Modelling of Tunnel Excavation in Soft Rock slip casting effect can not accurate evaluation, provide one The real-time monitoring grouting strengthening method that kind Support System in Soft Rock Tunnels is built, the effect of grouting strengthening method can be carried out soon in time Speed and accurately evaluate, so as to improve the degree of safety that Support System in Soft Rock Tunnels is built, reduce unnecessary personal casualty loss, measure is reasonable It is and safely controllable.
The purpose of the present invention is realized by following working measure.
The real-time monitoring grouting strengthening method that a kind of Support System in Soft Rock Tunnels is built, contains following steps:
Step 1, when tunnel complete one circulation driving task when, stop driving.
Step 2, closing face is sprayed with net, drilled along face, throw advanced tubule into.
Step 3, using advanced tubule to face carry out grouting and reinforcing.
Step 4, using grouting pressure control grouting amount, stop slip casting when final grouting pressure reaches 2~3MPa.
After step 5, mortar depositing construction terminate, the core-drilling in injecting cement paste, slip casting situation is checked.
Step 6, observation slurries filling situation and by core censorship.
Step 7, carry out next work cycle if core intensity and slurries filling situation reach the standard of construction;If Core intensity and slurries filling situation do not reach standard, then restart step 4 step.
Preferably, terminate in step 1 step, after a circulation excavation is completed in tunnel, to carry out the step 2 net spray closing palm immediately Sub- face step.
Preferably, arch and Core Soil position of the advanced tubule 3 along face 2 are squeezed into, spacing between advanced tubule 0.3~0.5m.
Preferably, when carrying out slip casting to face 2, slurries used are cement single slurry.
Preferably, after slip casting terminates, according to the presetting period of cement grout, start to drill again after 45min~1h Coring.
Preferably, during boring and coring, using special rig, core length control in 10~15cm, diameter control 5~ 8cm。
Preferably, when intuitively observation core slurries fill situation, if slurries filling porosity reaches more than 80%, then it is assumed that Slurries fill qualified carry out strength checking, otherwise, restart step 4 step.
Preferably, core intensity reaches the strength criterion of II level granite, then it is assumed that Surrounding Rock Strength is up to standard to be entered The operation of the next circulation of row, otherwise, restarts step 4 step.
The advantages of grouting strengthening method of monitoring in real time of the present invention is can to overcome Modelling of Tunnel Excavation in Soft Rock slip casting Effect can not accurate evaluation deficiency, monitor the effect of grouting and reinforcing in real time, and can be in time to the effect of grouting and reinforcing Evaluated, so as to make up the deficiency of slip casting effect bad assessment when Support System in Soft Rock Tunnels is built, so as to improve tunneling Degree of safety.
The present invention can improve the degree of safety that Support System in Soft Rock Tunnels is built, and reduce unnecessary personal casualty loss, and measure is reasonable It is and safely controllable.
Brief description of the drawings
When considered in conjunction with the accompanying drawings, by referring to following detailed description, can more completely more fully understand the present invention with And easily learn many of which with the advantages of, but accompanying drawing described herein be used for a further understanding of the present invention is provided, The part of the present invention is formed, schematic description and description of the invention is used to explain the present invention, do not formed to this hair Bright improper restriction, such as figure are wherein:
Fig. 1 is the flow chart of the present invention;
The front view of grouting program when Fig. 2 builds for Support System in Soft Rock Tunnels;
The side view of grouting program when Fig. 3 builds for Support System in Soft Rock Tunnels.
Icon explanation
2. face;3. advanced tubule;4. core.
The present invention is further described with reference to the accompanying drawings and examples.
Embodiment
The invention will be further described with reference to the accompanying drawings and detailed description, in order to which engineers and technicians manage Solution.
As shown in Figure 1, Figure 2, Figure 3 shows, the present invention provides the real-time monitoring grouting and reinforcing side that a kind of Support System in Soft Rock Tunnels is built Method, this method comprise the following steps:
Step 1, when tunnel complete one circulation about advance 50cm driving task when, stop operation task, gets out wet shot Machine.
Step 2, closing face is sprayed with net, is drilled with pneumatic pick or drill jumbo along face, throw advanced tubule into, Arch and Core Soil position of the advanced tubule along face are squeezed into, 0.3~0.5m of spacing between advanced tubule, advanced small Conduit squeezes into face about 1.5m~3m.
Step 3, when carrying out grouting and reinforcing to face using advanced tubule, slurries used are the cement that has configured in advance Single slurry.
Using grouting pressure control grouting amount during step 4, slip casting, stop note when final grouting pressure reaches 2~3MPa Slurry.
After step 5, mortar depositing construction terminate, after slip casting terminates, according to the presetting period of cement grout, in 45min~1h Start boring and coring again afterwards, during boring and coring, using special rig, the length of core 4 is controlled in 10~15cm, diameter control In 5~8cm.
Step 6, observation slurries filling situation, and by the censorship of core 4.
When step 7, observation core slurries filling situation directly perceived, if slurries filling porosity reaches more than 80%, then it is assumed that Slurries filling is qualified.If core slurries filling situation does not reach standard, restart step 4 step.
When checking core intensity, if core intensity reaches the strength criterion of II level granite, then it is assumed that Surrounding Rock Strength is The operation up to standard that next circulation can be carried out, otherwise, restarts step 4 step.
As described above, embodiments of the invention are explained, as long as but essentially without this hair of disengaging Bright inventive point and effect can have many deformations, and this will be readily apparent to persons skilled in the art.Therefore, this The variation of sample is also integrally incorporated within protection scope of the present invention.

Claims (1)

1. the real-time monitoring grouting strengthening method that a kind of Support System in Soft Rock Tunnels is built, it is characterised in that contain following steps:
Step 1, when tunnel complete one circulation driving task when, stop driving;
Step 2, closing face is sprayed with net, drilled along face, throw advanced tubule into;
Step 3, using advanced tubule to face carry out grouting and reinforcing;
Step 4, using grouting pressure control grouting amount, stop slip casting when final grouting pressure reaches 2~3MPa;
After step 5, mortar depositing construction terminate, the core-drilling in injecting cement paste, slip casting situation is checked;
Step 6, observation slurries filling situation and by core censorship;
Step 7, carry out next work cycle if core intensity and slurries filling situation reach the standard of construction;If core Intensity and slurries filling situation do not reach standard, then restart step 4 step;
Terminate in step 1 step, after a circulation excavation is completed in tunnel, to carry out step 2 net spray closing face step immediately;
Arch and Core Soil position of the advanced tubule along face are squeezed into, 0.3~0.5m of spacing between advanced tubule;
When carrying out slip casting to face, slurries used are cement single slurry;
After slip casting terminates, according to the presetting period of cement grout, start boring and coring again after 45min~1h;
During boring and coring, using special rig, core length is controlled in 10~15cm, and diameter control is in 5~8cm;
During observation core slurries filling situation directly perceived, if slurries filling porosity reaches more than 80%, then it is assumed that slurries filling is closed Lattice carry out strength checking, otherwise, restart step 4 step;
Core intensity reaches the strength criterion of II level granite, then it is assumed that Surrounding Rock Strength is up to standard can to carry out next circulation Operation, otherwise, restart step 4 step.
CN201610105350.3A 2016-02-25 2016-02-25 The real-time monitoring grouting strengthening method that a kind of Support System in Soft Rock Tunnels is built Active CN105649652B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610105350.3A CN105649652B (en) 2016-02-25 2016-02-25 The real-time monitoring grouting strengthening method that a kind of Support System in Soft Rock Tunnels is built

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610105350.3A CN105649652B (en) 2016-02-25 2016-02-25 The real-time monitoring grouting strengthening method that a kind of Support System in Soft Rock Tunnels is built

Publications (2)

Publication Number Publication Date
CN105649652A CN105649652A (en) 2016-06-08
CN105649652B true CN105649652B (en) 2018-03-30

Family

ID=56488672

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610105350.3A Active CN105649652B (en) 2016-02-25 2016-02-25 The real-time monitoring grouting strengthening method that a kind of Support System in Soft Rock Tunnels is built

Country Status (1)

Country Link
CN (1) CN105649652B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108590704A (en) * 2018-04-27 2018-09-28 中铁十二局集团有限公司 Light section per-fore pouring liquid with small pipe pays maintaining method in advance
CN109578021B (en) * 2018-11-29 2021-04-06 长安大学 Grouting reinforcement method for soft rock tunnel
CN109611131A (en) * 2018-12-10 2019-04-12 中交公局桥隧工程有限公司 Process for treating primary support water leakage at rear part of palm surface
CN114991819B (en) * 2022-05-20 2023-09-12 中国矿业大学(北京) Three-super control technology for water damage tunnel

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1074001A (en) * 1992-10-27 1993-07-07 中国建筑西南勘察院 Processing method of hole digging mud jacking pile
CN101975070A (en) * 2010-09-15 2011-02-16 中铁四局集团第五工程有限公司 Advance pre-reinforcement method for unfavorable geology in cavern
CN102182470A (en) * 2011-03-21 2011-09-14 同济大学 Full-section sealing extrusion grouting method
CN103256060B (en) * 2013-05-18 2015-01-14 中铁十六局集团有限公司 Moisture rich and weak mylonite large section tunnel surrounding rock consolidation and excavation method
CN105041325B (en) * 2015-07-13 2017-03-22 长沙理工大学 Construction method of high-tension water-rich extra-large-section weak breccia tunnel

Also Published As

Publication number Publication date
CN105649652A (en) 2016-06-08

Similar Documents

Publication Publication Date Title
CN105649652B (en) The real-time monitoring grouting strengthening method that a kind of Support System in Soft Rock Tunnels is built
CN207974823U (en) A kind of grouting pipeline structure of deep hole grouting
CN107701200A (en) A kind of section of jurisdiction crack restorative procedure
CN107725056A (en) One kind passes through silly stratum tunnel loopful quick grouting construction method in advance
CN112502720B (en) Method for passing open TBM through fault fracture zone
CN104632249A (en) Tunnel system supporting technology used in loose and soft broken surrounding rock
CN107059960A (en) A kind of indoor full automatic simulates the experimental rig of cement mixing method
CN104805831A (en) Pore-forming method of hard rock foundation pile with large diameter
CN104895583A (en) Tunnel surrounding rock control technology combining pressure relief and slip-casting reinforcement
CN109208592A (en) A kind of anchor rod construction method
CN111764818A (en) Eccentric casing following drilling construction structure and method for anchoring engineering
CN105040695A (en) Anchor rod structure capable of integrally working and construction method
CN104458506A (en) Method for measuring and controlling diffusion range of grouted slurry in rock-soil mass
CN108643193A (en) A kind of pattern foundation pit supporting structure prestress anchorage cable Drilling draw out method
CN103452115A (en) Casing pipe type bottom feeding post-pipe-plugging and post-grouting device and construction method
CN101358529A (en) Short tube and short tube sand consolidation agent strengthening construction process
CN104328781A (en) Unfavorable geologic body controlling infiltration chemical grouting method
CN208934712U (en) Wall multiple-arch tunnel transverse direction long duct positioning reinforcing device in a kind of nothing
CN106939619A (en) A kind of anti-vibration for underground engineering disturbs the leak stopping reinforcement means of voids and pits
CN103046869A (en) Construction method for controlling drilling positions to penetrate through guide rock strata
CN113236222B (en) Automatic drilling control method and system for rotary drilling rig based on self-learning
CN115199296A (en) Disassembly-free grouting and tapping method for shield segment
CN209761331U (en) Eccentric casing drilling construction structure for anchoring engineering
CN205154205U (en) A vertical pre -reinforcing handles structure for massif tunnel excavation
CN110453659B (en) Construction method for rock plug reservation construction key technology of diversion tunnel of weak surrounding rock

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant