CN105625686A - Process for laying prefabricated compound floor tiles - Google Patents

Process for laying prefabricated compound floor tiles Download PDF

Info

Publication number
CN105625686A
CN105625686A CN201510998389.8A CN201510998389A CN105625686A CN 105625686 A CN105625686 A CN 105625686A CN 201510998389 A CN201510998389 A CN 201510998389A CN 105625686 A CN105625686 A CN 105625686A
Authority
CN
China
Prior art keywords
combined floor
skeleton
ground
tubing
width
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510998389.8A
Other languages
Chinese (zh)
Inventor
石光乐
孙旭东
屠艳东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Alka Dicko (beijing) Building Materials Trading Co Ltd
Original Assignee
Alka Dicko (beijing) Building Materials Trading Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Alka Dicko (beijing) Building Materials Trading Co Ltd filed Critical Alka Dicko (beijing) Building Materials Trading Co Ltd
Priority to CN201510998389.8A priority Critical patent/CN105625686A/en
Publication of CN105625686A publication Critical patent/CN105625686A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/02Flooring or floor layers composed of a number of similar elements
    • E04F15/08Flooring or floor layers composed of a number of similar elements only of stone or stone-like material, e.g. ceramics, concrete; of glass or with a top layer of stone or stone-like material, e.g. ceramics, concrete or glass
    • E04F15/082Flooring or floor layers composed of a number of similar elements only of stone or stone-like material, e.g. ceramics, concrete; of glass or with a top layer of stone or stone-like material, e.g. ceramics, concrete or glass with a top layer of stone or stone-like material, e.g. ceramics, concrete or glass in combination with a lower layer of other material

Abstract

The invention discloses a process for laying prefabricated compound floor tiles. The method includes the following steps that 1, materials are prepared, wherein the prefabricated compound floor tiles, a framework and a height adjusting piece are provided; 2, the framework is laid on the ground obtained after waterproof treatment is conducted while the height adjusting piece is mounted at the bottom of a connection connector of the framework; 3, the height adjusting piece is adjusted so that the framework can be in a horizontal state or the framework can be inclined towards a floor drain opening; 4, the compound floor tiles are laid in grids of the framework so that a mounting step can be arranged on the framework in a supported mode; 5, the positions between the compound floor tiles and the ground are filled with cement. The laying process is simple, the laying work can be completed without professional bricklayers, consumed time is short, flatness of a floor obtained after the compound floor tiles are laid is high, and quality is controllable.

Description

The laying process of a kind of prefabricated combined floor
Technical field
The present invention relates to the laying process of a kind of indoor, refer to the laying process of a kind of prefabricated combined floor especially.
Background technology
The paving technics comparing of ground ceramic tile traditional at present is complicated, utilizes the bricklayer of specialty after the mix and blend cement of working-yard, then by cement on the ground, by one piece of block ceramic tile paving on cement. There is following shortcoming in this kind of traditional technology: 1. this laying process difficulty height, it is necessary to the bricklayer of specialty is laid, cost of labor height; 2. the effect that this laying process is laid is subject to the impact of bricklayer professional skill, and the floor flatness after laying is difficult to ensure; 3. according to after this kind of traditional paving mode laying floor, it is difficult to ensure that the downward mouth of a river, floor tilts, be inverted on ground phenomenon ponding easily occurring, returning water; 4. lay the time long, lay on-the-spot dirty, unrest, difference.
Summary of the invention
Technical problem to be solved by this invention is: the laying process providing a kind of prefabricated combined floor, and this laying process is simple, it is not necessary to specialty bricklayer can complete, consuming time short, and the planeness height on the floor after laying is quality controllable.
For solving the problems of the technologies described above, the technical scheme of the present invention is: the laying process of a kind of prefabricated combined floor, and it comprises the following steps:
A, material prepare: provide prefabricated combined floor, skeleton and height adjusting part, described prefabricated combined floor comprises decoration ceramic tile and function plate layer, described function plate layer is bonded in the back side of decoration ceramic tile, the size of function plate layer is less than the size of ceramic tile, the each outer edge of function plate layer is to the equal formation installation step of the outer Edge Distance that decoration ceramic tile is corresponding, described skeleton comprises some connection joints and some square tubing, by connecting, joint constitutes grid shape, the size of each grid and the size match of combined floor to tubing; Height adjusting part connects the bottom of joint for installing;
B, the ground of WATER REPELLENT is laid skeleton height adjusting part is installed on bottom the connection joint of skeleton simultaneously carrying out;
C, adjustment height adjusting part, make skeleton be in horizontality or skeleton is tilted to ground sewer;
D, combined floor is laid in the grid of skeleton, makes installation step be supported on skeleton;
E, to filling concrete between combined floor and ground.
Wherein preferred further, the stud that described height adjusting part comprises a blade and is fixed in a blade, is installed on the altitude mixture control that the bottom connecting joint realizes skeleton by stud screw thread.
In preferred scheme, in step C, skeleton tilt regulative mode be: according to the height at the lower mouth of a river, the stud on rotary support sheet make each rice of the upper surface of skeleton have one centimeter return the water gradient.
Preferred further, the horizontal clearance of described installation step is 1/2nd of tubing width, combined floor paving is buckled in the grid of skeleton.
Further preferred, in described step D, the laying direction of combined floor is: lay away from one jiao of indoor outlet from ground, on ground near the position ending of indoor outlet.
Preferred further, described connection joint comprises the four-way connection for connecting four orthogonal tubing, for connecting the Y-junction of three orthogonal tubing and two pass joints for connecting two vertical tubing, this four-way connection, the upper surface of Y-junction and two pass joints is provided with the caulking groove facilitating pipe end to embed, this four-way connection, the lower surface of Y-junction and two pass joints is provided with screw, in stepb, when skeleton is laid in assembling, first height adjusting part is installed on four-way connection, in the screw of Y-junction and two pass joint lower surfaces, then along face length limit, ground, each connection joint is placed on ground, being embedded into by tubing in the caulking groove of each connection joint, wherein, four-way connection is arranged at the middle part on ground again, and Y-junction is arranged at the edge on ground and pastes by wall limit, and two pass joints are arranged at the corner on ground.
Preferred further, described combined floor also comprises special in laminating edge, ground edge combined floor and special in laminating corner, ground corner combined floor, the width of three installation steps of edge combined floor is equal and equals the half of tubing width, and the width of another installation step is the twice of other installation step width; Orthogonal two installation step width of corner combined floor are equal and equal the half of tubing width, and the width of another two orthogonal installation steps is equal and equals the width of tubing; During paving, by edge combined floor paving on skeleton and edge paste by wall, by corner combined floor paving on skeleton and the both sides of corner combined floor press close to the wall in corner, ground.
Preferred further, described step e adopt self-leveling cement to fill.
After have employed technique scheme, the effect of the present invention is: have the following advantages after have employed this laying process: 1. prefabricated combined floor paving is buckled on skeleton by this laying process, planeness height, and paving is firm; 2. skeleton carries out according to the needs of reality adjusting in advance, for parlor, horizontal grade is without the ground at the lower mouth of a river, directly by skeleton leveling, toilet, kitchen etc. are had to the ground at the lower mouth of a river, then directly skeleton is adjusted into the state of downward mouth of a river inclination by body, and the floor after laying like this there will not be ponding or returns the phenomenon of water, and quality is more controlled; 3. the laying of this combined floor is consuming time short, laying effect and quality not handicraft by workmen affect, therefore bricklayer without the need to specialty is constructed, and cost of labor reduces.
Again owing to described connection joint comprises the four-way connection for connecting four orthogonal tubing, for connecting the Y-junction of three orthogonal tubing and two pass joints for connecting two vertical tubing, this four-way connection, the upper surface of Y-junction and two pass joints is provided with the caulking groove facilitating pipe end to embed, this four-way connection, the lower surface of Y-junction and two pass joints is provided with screw, in stepb, when skeleton is laid in assembling, first height adjusting part is installed on four-way connection, in the screw of Y-junction and two pass joint lower surfaces, then along face length limit, ground, each connection joint is placed on ground, again tubing is embedded in the caulking groove of each connection joint, wherein, four-way connection is arranged at the middle part on ground, Y-junction is arranged at the edge on ground and pastes by wall limit, two pass joints are arranged at the corner on ground, this kind of structure can make skeleton and connect joint effectively to support combined floor, makes the laying on floor more firm.
Again due to described combined floor also comprises special in laminating edge, ground edge combined floor and special in laminating corner, ground corner combined floor, the width of three installation steps of edge combined floor is equal and equals the half of tubing width, and the width of another installation step is the twice of other installation step width; Orthogonal two installation step width of corner combined floor are equal and equal the half of tubing width, and the width of another two orthogonal installation steps is equal and equals the width of tubing; During paving, by edge combined floor paving on skeleton and edge paste by wall, by corner combined floor paving on skeleton and the both sides of corner combined floor press close to the wall in corner, ground, utilizing edge combined floor and corner combined floor that the laying effect on ground can be made better, entirety is more attractive in appearance.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the present invention is further described.
Fig. 1 is the structural representation for laying middle prefabricated combined floor of the embodiment of the present invention;
Fig. 2 is the structural representation of the corner combined floor of the embodiment of the present invention;
Fig. 3 is the structural representation of the edge combined floor of the embodiment of the present invention;
Fig. 4 is the laying schematic diagram of a grid in the middle of embodiment of the present invention skeleton;
Fig. 5 is the laying schematic diagram of the grid in edge of embodiment of the present invention skeleton;
Fig. 6 is the structure iron of two pass joints;
Fig. 7 is the structure iron of Y-junction;
Fig. 8 is the structure iron of four-way connection;
Fig. 9 is the structure iron of height adjusting part;
In accompanying drawing: 1. decoration ceramic tile; 2. function plate layer; 3. installation step; 4. edge installation step; 5. four-way connection; 6. two pass joint; 7. Y-junction; 8. tubing; 9. caulking groove; 10. height adjusting part; 101. blade; 102. stud.
Embodiment
Below by specific embodiment, the present invention is described in further detail.
The downside mentioned in the present embodiment refers to the side near ground, and corresponding upside is the side away from ground.
A laying process for prefabricated combined floor, it comprises the following steps:
A, material prepares: provide prefabricated combined floor, skeleton and height adjusting part 10, such as Fig. 1, 2, shown in 3, described prefabricated combined floor comprises decoration ceramic tile 1 and function plate layer 2, described function plate layer 2 is bonded in the back side of decoration ceramic tile 1, function plate layer 2 is foamed ceramic layer, there is certain fire prevention, sound insulation, the function of insulation, the size of function plate layer 2 is less than the size of ceramic tile, the each outer edge of function plate layer 2 is to the equal formation installation step 3 of outer Edge Distance of decoration ceramic tile 1 correspondence, wherein preferred further, prefabricated combined floor has three kinds of specifications: the first specification is the middle combined floor not contacted with metope for laying ground Middle face, the horizontal clearance of each installation step 3 of this middle combined floor is 1/2nd of tubing 8 width, so the installation step 3 of two pieces of combined floors just covers the width of a tubing 8, make the easier for installation of combined floor, accuracy is installed higher. 2nd kind of specification is near the edge combined floor contacted with a metope, special in laminating edge, ground, this edge combined floor has an edge installation step 43 abutted mutually with metope, this edge installation step 43 is 2 times of the width of other three installation steps 3 and equals the width of tubing 8, like this, when laying edge, ground, edge installation step 43 entirety covers a tubing 8, make one of them edge of edge combined floor as much as possible near metope, make the effect of laying better. the third specification is corner combined floor, special in the corner being laid on ground, this kind of corner combined floor has two common installation steps 3 and two edge installation steps 43, the width of same edge installation step 43 is the width of tubing 8, common installation step 3 is the half of tubing 8 width, during paving, the tubing 8 of two whole pavings of edge installation step 43 of corner combined floor on skeleton is covered.
Certainly, in the construction process of reality, also need to be decorated by metope due to upholstery, so backward is considered, even if all combined floors all only the first specification equally can complete construction, even if combined floor and metope exist certain gap, but carry out metope again can effectively covering this gap when laying wallboard, good laying effect can be played equally.
As shown in Figures 2 and 3. described skeleton comprises some connection joints and some square tubing 8, and by connecting, joint constitutes grid shape, the size of each grid and the size match of combined floor to tubing 8, tubing 8 generally adopts square galvanized pipe, such as Fig. 6, 7, shown in 8, described connection joint comprises the four-way connection 5 for connecting four orthogonal tubing 8, for connecting the Y-junction 7 of three orthogonal tubing 8 and two pass joints 6 for connecting two vertical tubing 8, this four-way connection 5, the upper surface of Y-junction 7 and two pass joints 6 is provided with the caulking groove 9 facilitating tubing 8 end to embed, this four-way connection 5, the lower surface of Y-junction 7 and two pass joints 6 is provided with screw, in stepb, when skeleton is laid in assembling, first height adjusting part 10 is installed on four-way connection 5, in the screw of Y-junction 7 and two pass joint 6 lower surfaces, then along face length limit, ground, each connection joint is placed on ground, being embedded into by tubing 8 in the caulking groove 9 of each connection joint, wherein, four-way connection 5 is arranged at the middle part on ground again, and Y-junction 7 is arranged at the edge on ground and pastes by wall limit, and two pass joints 6 are arranged at the corner on ground.
As shown in Figure 9, the bottom that height adjusting part 10 connects joint for installing; The stud 102 that described height adjusting part 10 comprises a blade 101 and is fixed in a blade 101, is installed on the altitude mixture control that the bottom connecting joint realizes skeleton by stud 102 screw thread.
B, above-mentioned materials is ready to, the ground of WATER REPELLENT is laid skeleton height adjusting part 10 is installed on bottom the connection joint of skeleton simultaneously carrying out; Owing to this skeleton assembles, therefore, when laying skeleton, first stud 102 is connected to the bottom of various connection joint, then each connection joint is placed on ground, tubing 8 is embedded in caulking groove 9, thus realize the laying of skeleton.
C, adjustment height adjusting part 10, make skeleton be in horizontality or skeleton is tilted to ground sewer; For different indoor, there is different construction requirements, such as, in parlor, bedroom, owing to there not being the lower mouth of a river, therefore, skeleton is in horizontality, and the ground for kitchen, toilet then needs to make the downward mouth of a river of the height of skeleton to tilt, concrete regulative mode is: according to the height at the lower mouth of a river, the stud 102 on rotary support sheet 101 make each rice of the upper surface of skeleton have one centimeter return the water gradient.
D, combined floor is laid in the grid of skeleton, makes installation step 3 be supported on skeleton; In described step D, the laying direction of combined floor is: lay away from one jiao of indoor outlet from ground, on ground near the position ending of indoor outlet. Combined floor all spreads in the grid being buckled in skeleton. The laying of combined floor is more convenient, and installation step 3 embeds in grid, lays accurately, and the level requirement of workmen reduces, and laying effect is good.
E, to filling concrete between combined floor and ground. Described step e adopts self-leveling cement to fill, it is not necessary in indoor mixing, the environment of working-yard is improved.
This laying process can control skeleton accurately and tilt or level, makes the laying effect of combined floor better, and water or seeping phenomenon no longer occurs returning in the ground after laying.
The above embodiment is only the description to the preferred embodiment of the present invention; not as limiting the scope of the invention; on the basis not departing from inventive design spirit; various distortion technical solution of the present invention made and transformation, in the protection domain that the claim book that all should fall into the present invention is determined.

Claims (8)

1. a laying process for prefabricated combined floor, it comprises the following steps:
A, material prepare: provide prefabricated combined floor, skeleton and height adjusting part, described prefabricated combined floor comprises decoration ceramic tile and function plate layer, described function plate layer is bonded in the back side of decoration ceramic tile, the size of function plate layer is less than the size of ceramic tile, the each outer edge of function plate layer is to the equal formation installation step of the outer Edge Distance that decoration ceramic tile is corresponding, described skeleton comprises some connection joints and some square tubing, by connecting, joint constitutes grid shape, the size of each grid and the size match of combined floor to tubing; Height adjusting part connects the bottom of joint for installing;
B, the ground of WATER REPELLENT is laid skeleton height adjusting part is installed on bottom the connection joint of skeleton simultaneously carrying out;
C, adjustment height adjusting part, make skeleton be in horizontality or skeleton is tilted to ground sewer;
D, combined floor is laid in the grid of skeleton, makes installation step be supported on skeleton;
E, to filling concrete between combined floor and ground.
2. the laying process of a kind of prefabricated combined floor as claimed in claim 1, it is characterised in that: the stud that described height adjusting part comprises a blade and is fixed in a blade, is installed on the altitude mixture control that the bottom connecting joint realizes skeleton by stud screw thread.
3. the laying process of a kind of prefabricated combined floor as claimed in claim 2, it is characterized in that: in step C, skeleton tilt regulative mode be: according to the height at the lower mouth of a river, the stud on rotary support sheet make each rice of the upper surface of skeleton have one centimeter return the water gradient.
4. the laying process of a kind of prefabricated combined floor as claimed in claim 3, it is characterised in that: the horizontal clearance of described installation step is 1/2nd of tubing width, combined floor paving is buckled in the grid of skeleton.
5. the laying process of a kind of prefabricated combined floor as claimed in claim 4, it is characterised in that: in described step D, the laying direction of combined floor is: lay away from one jiao of indoor outlet from ground, on ground near the position ending of indoor outlet.
6. the laying process of a kind of prefabricated combined floor as claimed in claim 5, it is characterized in that: described connection joint comprises the four-way connection for connecting four orthogonal tubing, for connecting the Y-junction of three orthogonal tubing and two pass joints for connecting two vertical tubing, this four-way connection, the upper surface of Y-junction and two pass joints is provided with the caulking groove facilitating pipe end to embed, this four-way connection, the lower surface of Y-junction and two pass joints is provided with screw, in stepb, when skeleton is laid in assembling, first height adjusting part is installed on four-way connection, in the screw of Y-junction and two pass joint lower surfaces, then along face length limit, ground, each connection joint is placed on ground, being embedded into by tubing in the caulking groove of each connection joint, wherein, four-way connection is arranged at the middle part on ground again, and Y-junction is arranged at the edge on ground and pastes by wall limit, and two pass joints are arranged at the corner on ground.
7. the laying process of a kind of prefabricated combined floor as claimed in claim 6, it is characterized in that: described combined floor also comprises special in laminating edge, ground edge combined floor and special in laminating corner, ground corner combined floor, the width of three installation steps of edge combined floor is equal and equals the half of tubing width, and the width of another installation step is the twice of other installation step width; Orthogonal two installation step width of corner combined floor are equal and equal the half of tubing width, and the width of another two orthogonal installation steps is equal and equals the width of tubing; During paving, by edge combined floor paving on skeleton and edge paste by wall, by corner combined floor paving on skeleton and the both sides of corner combined floor press close to the wall in corner, ground.
8. the laying process of a kind of prefabricated combined floor as claimed in claim 7, it is characterised in that: described step e adopt self-leveling cement to fill.
CN201510998389.8A 2015-12-26 2015-12-26 Process for laying prefabricated compound floor tiles Pending CN105625686A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510998389.8A CN105625686A (en) 2015-12-26 2015-12-26 Process for laying prefabricated compound floor tiles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510998389.8A CN105625686A (en) 2015-12-26 2015-12-26 Process for laying prefabricated compound floor tiles

Publications (1)

Publication Number Publication Date
CN105625686A true CN105625686A (en) 2016-06-01

Family

ID=56040992

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510998389.8A Pending CN105625686A (en) 2015-12-26 2015-12-26 Process for laying prefabricated compound floor tiles

Country Status (1)

Country Link
CN (1) CN105625686A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111535541A (en) * 2020-05-09 2020-08-14 灿高机电装备高邑有限公司 Construction method for laying framework leveling ceramic tiles

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2050197A3 (en) * 1969-06-13 1971-04-02 Farvalube Francaise
WO2003066995A1 (en) * 2002-02-05 2003-08-14 E-Floor Systems Limited Flooring system
CN1519445A (en) * 2003-09-02 2004-08-11 程崇钧 Floor decorated by floor tiles and assembling method
CN103790334A (en) * 2014-01-21 2014-05-14 万科企业股份有限公司 Combined splicing floor tile and laying technology of combined splicing floor tile
CN204126226U (en) * 2014-08-15 2015-01-28 天津贝利泰陶瓷有限公司 Tile laying lattice plate

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2050197A3 (en) * 1969-06-13 1971-04-02 Farvalube Francaise
WO2003066995A1 (en) * 2002-02-05 2003-08-14 E-Floor Systems Limited Flooring system
CN1519445A (en) * 2003-09-02 2004-08-11 程崇钧 Floor decorated by floor tiles and assembling method
CN103790334A (en) * 2014-01-21 2014-05-14 万科企业股份有限公司 Combined splicing floor tile and laying technology of combined splicing floor tile
CN204126226U (en) * 2014-08-15 2015-01-28 天津贝利泰陶瓷有限公司 Tile laying lattice plate

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111535541A (en) * 2020-05-09 2020-08-14 灿高机电装备高邑有限公司 Construction method for laying framework leveling ceramic tiles

Similar Documents

Publication Publication Date Title
CN203669291U (en) Movable raised floor installing structure
CN104120855A (en) Construction method for paving ground tile floor
CN108385872A (en) A kind of assembling type partition wall and its construction method
CN106381980A (en) Floor tile paving process
CN104831926B (en) A kind of tenon joint type bulk surface layer flooring method for paving
CN105625686A (en) Process for laying prefabricated compound floor tiles
CN113431292A (en) Dry-method overall paving structure of fabricated ground
CN107304625A (en) Foam concrete is combined terrace and its construction method with concrete
CN205224503U (en) Prefabricated composite wall panel
CN203394108U (en) Fabricated bathroom
CN104264953A (en) Support, paving method for ground stone and cement mortar stirring and conveying all-in-one machine
CN208815955U (en) A kind of swimming pool bottom plate structure and its expansion joint node waterproof structure
CN110185230B (en) Assembly type ceramic tile installation structure and construction process thereof
CN105421707A (en) Prefabricated composite wall panel
KR20130114041A (en) Indoor molding to be installed to finish as finishing materials the indoor of architecture and installation method of indoor molding
GB2437370A (en) Floor for wet area
CN107090923B (en) Filled wall building construction technique at cold bridge
CN110259036A (en) A kind of floor leveling method
CN213897227U (en) Bottom plate segmentation joint filling structure for building construction
CN210134616U (en) Dry-method overall paving structure of fabricated ground
CN210134614U (en) Horizontal assembled structure of mating formation of ground finish material
CN206448501U (en) A kind of floor covering layers locating rack
CN204754084U (en) Prefabricated board that warms up that can splice integratedly and floor heating structure who constitutes thereof
CN105926799A (en) Building exterior wall structure and construction method thereof
CN110206313A (en) A kind of construction method of the mixed paving of flooring plate dry method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
AD01 Patent right deemed abandoned

Effective date of abandoning: 20180622

AD01 Patent right deemed abandoned