CN105604580A - Tunnel inverted arch construction movable formwork - Google Patents

Tunnel inverted arch construction movable formwork Download PDF

Info

Publication number
CN105604580A
CN105604580A CN201610162825.2A CN201610162825A CN105604580A CN 105604580 A CN105604580 A CN 105604580A CN 201610162825 A CN201610162825 A CN 201610162825A CN 105604580 A CN105604580 A CN 105604580A
Authority
CN
China
Prior art keywords
longeron
side template
formwork
crossbeams
beams
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610162825.2A
Other languages
Chinese (zh)
Inventor
张晓玮
雷星辉
魏孔斌
熊荣华
赵祥允
席兵印
刘博峰
王丽锋
高晓磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Fourth Highway Engineering Co Ltd
Original Assignee
CCCC Fourth Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Fourth Highway Engineering Co Ltd filed Critical CCCC Fourth Highway Engineering Co Ltd
Priority to CN201610162825.2A priority Critical patent/CN105604580A/en
Publication of CN105604580A publication Critical patent/CN105604580A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention provides a tunnel inverted arch construction movable formwork. The tunnel inverted arch construction movable formwork comprises an arc-shaped side formwork, a central ditch formwork and two beams which are parallel to each other, the two ends of the side formwork are rotatably connected with the ends of the beams respectively, and the two ends of the central ditch formwork are fixedly connected with the middles of the beams respectively; a middle longitudinal beam perpendicular to the beams is arranged above the middles of the beams, and side longitudinal beams perpendicular to the beams are arranged above the two ends of the beams respectively; formwork lifting hydraulic jacks are arranged at the two ends of the middle longitudinal beam, lateral hydraulic jacks for pushing the side formwork are arranged on the outer sides of the side longitudinal beams, side formwork lifting supports are arranged above the middles of the side longitudinal beams, side formwork traction motors are arranged on the side formwork lifting supports, and the side formwork traction motors are connected with the side formwork through chain blocks.

Description

A kind of tunnel invert construction mobile formwork
Technical field
The present invention relates to tunnel invert construction equipment field, be specifically related to a kind of mould bases of tunnel invert pouring construction.
Background technology
Constructing tunnel process, it is a critical process that inverted arch and inverted arch are filled construction, how to ensure efficiency of construction and the construction of inverted archQuality becomes key element. The small-sized combined steel formwork of many employings in work progress at present, globality is poor, and the fixing difficulty of template is large,Construction Linear Control is bad, and efficiency of construction is low.
In prior art, Chinese Patent Application No. 201420824474.3, name are called " a kind of self-propelled tunnel invert construction platformCar " patent of invention, its using the arc formwork of each side as an integral installation on a chassis, pallet bottom install roller,Can automatic moving, but separately construction of width about when its construction, globality is poor; At Chinese periodical " Sichuan building " the 32nd volume 1In the document of phase a section " application in tunnel of inverted arch mobile formwork quick construction technology " by name, disclose a kind of entirety and movedDynamic formula mould bases, has also adopted integral curved side template, and it connects left and right width side template by termination beam (crossbeam), and establish centreHave Central drain template, it adopts the trestle matching track crane of establishing guide rail to realize mould bases integrated moving, and structure is comparatively complicated, andIts inverted arch and inverted arch are filled and will be constructed respectively, have reduced efficiency of construction.
Summary of the invention
The object of the invention is to the defect existing for inverted arch construction in prior art, a kind of tunnel invert mobile mould of constructing is providedFrame, improves the construction quality of inverted arch, shortens inverted arch and constructs activity duration of every circulation, improves efficiency of construction.
Technical scheme of the present invention is as follows:
A kind of tunnel invert construction mobile formwork, comprises and it is characterized in that side template, the Central drain template of arc: be provided with twoThe crossbeam that root is parallel to each other, the two ends of described side template is rotationally connected with the end of described two crossbeams respectively, described Central drainThe two ends of template are fixedly connected with the middle part of two crossbeams respectively; The middle part top of described two crossbeams, be provided with two beam vertical inLongeron, the top, two ends of described two crossbeams, is respectively equipped with the limit longeron with two beam vertical; The two ends of described middle longeron, are provided withMould bases lifting hydraulic jack, the outside of described limit longeron is provided with the side hydraulic jack for pushing tow side template, and described limit is verticalThe top, middle part of beam is provided with side template lifting bracket, and described side template lifting bracket is provided with side template traction electric machine, described side formBetween plate traction electric machine and side template, be connected by cucurbit jack.
Further, described crossbeam below is also provided with arc support, and the bottom of described arc support is provided with support bar, described support barBe connected by latch with described arc support.
Further, the both sides of middle longeron are also provided with guide rail, described crossbeam top and middle longeron junction be provided with can along on longeronThe roller that guide rail moves; One end of described middle longeron is provided with the displacement motor that traction crossbeam moves forward and backward along described guide rail.
Further, the bottom of described limit longeron is also provided with the slide rail extending longitudinally along limit longeron, is provided with traction mould bases edge on guide railThe mould bases traction electric machine that slide rail slides.
Inverted arch mould bases provided by the invention is compared with the prior art has following beneficial effect:
Mould bases is integrated moving voluntarily, and formwork erection is quick, overall perfusion, and parallel operations, synchronous coordination, does not interfere with each other; Curved sideTemplate reels by jack, and can disposablely complete inverted arch and fill construction in layer, and Central drain construction, save constructionOperation, has accelerated the construction speed that inverted arch and inverted arch are filled greatly; Build linear quality good, ensured construction quality.
Brief description of the drawings
Fig. 1 is top view of the present invention;
Fig. 2 is transverse side view of the present invention.
Detailed description of the invention
As shown in Figure 1 and Figure 2, tunnel invert provided by the invention construction mobile formwork, comprises side template 1, the center of arcDitch template 2, is also provided with two crossbeams that are parallel to each other 3, and the two ends of described side template 1 is respectively with described two crossbeams 3End is rotationally connected, and the two ends of described Central drain template 2 are fixedly connected with the middle part of two crossbeams 3 respectively; Described two crossbeamsTop, middle part, is provided with the middle longeron 4 vertical with two crossbeams 3, and the top, two ends of described two crossbeams 3, is respectively equipped with and two crossbeamsVertical limit longeron 5; The two ends of described middle longeron 4, are provided with mould bases lifting hydraulic jack 6, the outside of described limit longeron 5Be provided with the side hydraulic jack 7 for pushing tow side template, the top, middle part of described limit longeron is provided with side template lifting bracket 8,Described side template lifting bracket 8 is provided with side template traction electric machine 9, between described side template traction electric machine 9 and side template, passes through calabashReed jack 10 connects.
When the present invention specifically implements, also can arc support 11 be set below described crossbeam, establish the bottom of described arc support 11Have support bar 12, described support bar 12 is connected by latch with described arc support 11. When formwork erection, by support bar to mould basesSupport and fix.
Occupation mode of the present invention is as follows:
After tunnel invert has excavated, before inverted arch pouring construction, mould bases is moved to assigned address and start formwork erection, start mould bases literHydraulic jack 6 is fallen, by mobile formwork vertical adjustment to design altitude; Under arc support below crossbeam, support is set simultaneouslyBar 12 is also fixed by latch, to mould bases integrated support and fixing; Determine plan-position and the elevation of the above side template of inverted arch face,Start the side hydraulic jack 7 on the longeron of limit, pushing tow side template is laterally received by starting side template traction electric machine 9 simultaneouslyPutting cucurbit jack 10 coordinates side hydraulic jack location inverted arch to fill the position of the following curved side template of face.
After completing, formwork erection can carry out concreting. First build inverted arch, after inverted arch concrete initial set, start side template and leadDraw motor and promote cucurbit jack 10, more than the curved side template inverted arch face of filling is partly upwards promoted to inverted arch filling face below, systemOne builds inverted arch fill concrete, realizes that inverted arch, inverted arch are filled and Central drain is built once and completed.
When inverted arch fill concrete is solidified to designing requirement, start the demoulding. Starting mould bases lifting hydraulic jack upwards indulges in pushing towBeam upwards raises mould bases entirety, makes concrete demoulding.
When the present invention specifically implements, accurately locate for realizing mould bases, also can guide rail 13 be set in the both sides of middle longeron 4, in instituteState crossbeam top and middle longeron junction arrange can along in the roller 14 that moves of guide rail on longeron; One end of described middle longeron is provided withThe displacement motor 15 that traction crossbeam moves forward and backward along described guide rail. Displacement motor 15 drives cross beam movement by chain and sprocket wheel.When formwork erection, draw crossbeam and template by displacement motor and move forward and backward and better realize Template Location.
Further, the present invention in the specific implementation, also can arrange the cunning extending longitudinally along limit longeron in the bottom of described limit longeron 5Rail 16 arranges the mould bases traction electric machine 17 that traction mould bases slides along slide rail on guide rail, realizes mould bases is carried out to integrated moving.After having constructed in a position, longeron in rising by mould bases lifting hydraulic jack, arranges slide rail along longeron end, limit, logicalCross mould bases traction electric machine traction mould bases and be forwarded to next construction location along slide rail.

Claims (4)

1. a tunnel invert construction mobile formwork, comprises and it is characterized in that side template, the Central drain template of arc: establishHave two crossbeams that are parallel to each other, the two ends of described side template is rotationally connected with the end of described two crossbeams respectively, described centerThe two ends of ditch template are fixedly connected with the middle part of two crossbeams respectively; The top, middle part of described two crossbeams, is provided with and two beam verticalMiddle longeron, the two ends top of described two crossbeams, is respectively equipped with the limit longeron with two beam vertical; The two ends of described middle longeron,Be provided with mould bases lifting hydraulic jack, the outside of described limit longeron is provided with the side hydraulic jack for pushing tow side template, described inThe top, middle part of limit longeron is provided with side template lifting bracket, and described side template lifting bracket is provided with side template traction electric machine, described inBetween side template traction electric machine and side template, be connected by cucurbit jack.
2. tunnel invert construction mobile formwork according to claim 1, is characterized in that: described crossbeam below is provided with arcShape support, the bottom of described arc support is provided with support bar, and described support bar is connected by latch with described arc support.
3. tunnel invert construction mobile formwork according to claim 1, is characterized in that: the both sides of middle longeron are provided with leadsRail, described crossbeam top and middle longeron junction be provided with can along in the roller that moves of guide rail on longeron; One end of described middle longeronBe provided with the displacement motor that traction crossbeam moves forward and backward along described guide rail.
4. tunnel invert construction mobile formwork according to claim 1, is characterized in that: establish the bottom of described limit longeronHave the slide rail extending longitudinally along limit longeron, described guide rail is provided with the mould bases traction electric machine that traction mould bases slides along slide rail.
CN201610162825.2A 2016-03-21 2016-03-21 Tunnel inverted arch construction movable formwork Pending CN105604580A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610162825.2A CN105604580A (en) 2016-03-21 2016-03-21 Tunnel inverted arch construction movable formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610162825.2A CN105604580A (en) 2016-03-21 2016-03-21 Tunnel inverted arch construction movable formwork

Publications (1)

Publication Number Publication Date
CN105604580A true CN105604580A (en) 2016-05-25

Family

ID=55984865

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610162825.2A Pending CN105604580A (en) 2016-03-21 2016-03-21 Tunnel inverted arch construction movable formwork

Country Status (1)

Country Link
CN (1) CN105604580A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106761825A (en) * 2016-12-23 2017-05-31 泰安东岳重工有限公司 For the inverted arch trestle device in tunnel
CN106939793A (en) * 2017-04-21 2017-07-11 四川省创力隧道机械设备有限公司 It is easy to the tunnel central trench chassis efficiently constructed
CN107059625A (en) * 2016-12-22 2017-08-18 中铁五局集团有限公司 A kind of access bridge hoisting mechanism of stepping type self movable trestle
CN113669082A (en) * 2021-09-09 2021-11-19 中铁隧道集团二处有限公司 Tunnel inverted arch filling construction method containing central ditch

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007291794A (en) * 2006-04-27 2007-11-08 Kumagai Gumi Co Ltd Form device
CN201666157U (en) * 2010-03-08 2010-12-08 中铁隧道集团四处有限公司 Inverted arch integral type moving die carrier
CN102146799A (en) * 2011-03-10 2011-08-10 中铁二局股份有限公司 Construction equipment for inverted arch of two-track tunnel of high-speed railway
CN102230383A (en) * 2011-06-14 2011-11-02 中交隧道工程局有限公司 All-hydraulic tunnel inverted arch trestle-type moving die frame
CN102444406A (en) * 2010-10-15 2012-05-09 中铁五局(集团)有限公司 Needle beam type inverted arch lining sliding framework and construction method thereof
CN103325710A (en) * 2013-06-25 2013-09-25 南通皋鑫电子股份有限公司 Method of testing three-inch diffusion silicon piece surface nickel plating thickness
CN204386615U (en) * 2014-12-24 2015-06-10 中铁四局集团第五工程有限公司 A kind of self-propelled tunnel invert construction trolley
CN205605224U (en) * 2016-03-21 2016-09-28 中交第四公路工程局有限公司 Tunnel invert moving die carrier that is under construction

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007291794A (en) * 2006-04-27 2007-11-08 Kumagai Gumi Co Ltd Form device
CN201666157U (en) * 2010-03-08 2010-12-08 中铁隧道集团四处有限公司 Inverted arch integral type moving die carrier
CN102444406A (en) * 2010-10-15 2012-05-09 中铁五局(集团)有限公司 Needle beam type inverted arch lining sliding framework and construction method thereof
CN102146799A (en) * 2011-03-10 2011-08-10 中铁二局股份有限公司 Construction equipment for inverted arch of two-track tunnel of high-speed railway
CN102230383A (en) * 2011-06-14 2011-11-02 中交隧道工程局有限公司 All-hydraulic tunnel inverted arch trestle-type moving die frame
CN103325710A (en) * 2013-06-25 2013-09-25 南通皋鑫电子股份有限公司 Method of testing three-inch diffusion silicon piece surface nickel plating thickness
CN204386615U (en) * 2014-12-24 2015-06-10 中铁四局集团第五工程有限公司 A kind of self-propelled tunnel invert construction trolley
CN205605224U (en) * 2016-03-21 2016-09-28 中交第四公路工程局有限公司 Tunnel invert moving die carrier that is under construction

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107059625A (en) * 2016-12-22 2017-08-18 中铁五局集团有限公司 A kind of access bridge hoisting mechanism of stepping type self movable trestle
CN106761825A (en) * 2016-12-23 2017-05-31 泰安东岳重工有限公司 For the inverted arch trestle device in tunnel
CN106761825B (en) * 2016-12-23 2018-08-31 泰安东岳重工有限公司 Inverted arch trestle device for tunnel
CN106939793A (en) * 2017-04-21 2017-07-11 四川省创力隧道机械设备有限公司 It is easy to the tunnel central trench chassis efficiently constructed
CN106939793B (en) * 2017-04-21 2023-07-18 四川省创力隧道机械设备有限公司 Tunnel center ditch trolley convenient for efficient construction
CN113669082A (en) * 2021-09-09 2021-11-19 中铁隧道集团二处有限公司 Tunnel inverted arch filling construction method containing central ditch

Similar Documents

Publication Publication Date Title
CN109681238B (en) Two linings of tunnel side wall are pour and prefabricated section of jurisdiction of vault is forwardded and is used template platform truck
CN105604580A (en) Tunnel inverted arch construction movable formwork
CN110513125B (en) Inner and outer mould trolley lining system for open cut underdrain
CN207212365U (en) A kind of wall arch is separable can Monolithic lining chassis
CN104790977A (en) Tunnel primary lining formwork trolley and construction method thereof
CN111022079A (en) Trestle type full-section inverted arch two-lining trolley equipment and construction method thereof
CN205778918U (en) Loess tunnel excavation and just formwork build concrete construction combined type chassis
CN204457807U (en) A kind of tunnel ditch cable channel hydraulic formwork trolley
JP4318042B2 (en) Tunnel construction method
CN109139050B (en) Self-propelled integrated tunnel inverted arch device
CN204492846U (en) Movable type with inverted arch lining device crosses car trestle
CN104453951A (en) Combined lining formwork trolley for subway station
CN107060831B (en) Be used for tunnel slot construction equipment
CN110894792A (en) Trestle type lower opening full-section synchronous construction equipment and construction method thereof
CN205605224U (en) Tunnel invert moving die carrier that is under construction
CN109371851B (en) Groove making machine with multiple bottom die head cover supporting frames
CN212744018U (en) Traveling system of mobile trolley
CN104500106A (en) Tunnel inverted arch construction die carrier and tunnel inverted arch construction process
CN205295849U (en) Mechanized ditch template
CN210637087U (en) Inner and outer mould trolley lining system for open-cut underground canal
CN211081965U (en) Self-walking hydraulic trestle
CN206785405U (en) One kind is used for tunnel groove constructing device
CN210105880U (en) Alternate hydraulic lifting template ditch cable trough trolley device
CN106593474A (en) Lining trolley for subway station construction and construction method thereof
CN103556835B (en) Floor slab trolley

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160525