CN105604555A CN201610141808.0A CN201610141808A CN105604555A CN 105604555 A CN105604555 A CN 105604555A CN 201610141808 A CN201610141808 A CN 201610141808A CN 105604555 A CN105604555 A CN 105604555A
Authority
CN
China
Prior art keywords
tunnel
push pipe
construction
pipe
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610141808.0A
Other languages
Chinese (zh)
Inventor
黎伟
苏伟
房营光
谷任国
欧振锋
陈沛民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou electric power design institute
South China University of Technology SCUT
Original Assignee
Guangzhou electric power design institute
South China University of Technology SCUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou electric power design institute, South China University of Technology SCUT filed Critical Guangzhou electric power design institute
Priority to CN201610141808.0A priority Critical patent/CN105604555A/en
Publication of CN105604555A publication Critical patent/CN105604555A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Soil Sciences (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a pipe-jacking tunnel and a construction method of the pipe-jacking tunnel. The construction method comprises the following steps that S1, an original well of the pipe-jacking tunnel is constructed and built; S2, a reinforcement layer is formed on the outer side of an arc-shaped turning section of the pipe-jacking tunnel; S3, construction device installation is performed, and jacking operation is conducted on the pipe-jacking tunnel; S4, a receiving well of the pipe-jacking tunnel is constructed and built. The strength of the ground at the construction position can be greatly improved through the reinforcement layer formed by casting slurry in an area to be reinforced of the outer side of the arc-shaped turning section, accordingly the arc-shaped turning section can bear a radial pushing force caused by an eccentric force, the phenomenon that a jacked pipe deviates towards the outer side of the arc-shaped turning section and the construction quality is affected is avoided, meanwhile construction safety accidents caused by buckling failure of a soil body can be also prevented, and smooth implementation of pipe joint jacking construction is ensured.

Description

The construction method in push pipe tunnel and push pipe tunnel
Technical field
The present invention relates to push pipe tunnel construction technology field, especially relate to a kind of push pipe tunnel and push pipe tunnelConstruction method.
Background technology
Push bench process is as a kind of non-excavating construction method in tunnel, because it is to urban transportation and Environmental security shadowThe outstanding advantages such as sound is little, advanced technology, effect is high, construction cost is lower, in urban electric power constructing tunnelObtain applying more and more widely.
Busy city proper electric power tunnel circuit selects to be subject to the densely covered municipal pipeline of Urban Underground, intensive building basePlinth, the busy many factors such as road traffic and urban planning restrict, and tunnel line has to wriggling sometimesUnder Yan road, extend, whole piece electric power tunnel is divided into some tunnel construction sections, between each tunnel construction sections, must be turned by littleSweep tunnel construction sections connects. Compare tight turn radius curve tunnel with general curve section tunnel with straightwayThe construction by pipeline jacking method difficulty in road (radius of turn is less than 150m) is large, technical requirement is high, axis direction is difficult to controlMake, especially in soft layer, carry out the construction by pipeline jacking method of tight turn radius curved tunnel, soft layer oftenBe difficult to bear the radial thrust that eccentric top power causes, very easily cause push pipe tunnel axis to extra curvature lateral deviation from,And cannot be along the tunnel axis jacking of design, the soil compaction effect that simultaneously axis runout produces will cause groundProtuberance and sedimentation, the safety that can threaten pipeline and ground buildings or structures, the serious soil that also may causeBody unstable failure, causes construction safety accident. In addition, tube coupling is in jack-in process, and its end face bears axiallyEffect when thrust and radial shear, the flat mouth end face docking of conventional steel mouthing tube coupling, easily produces pipeSave end face faulting of slab ends and cause leaking. At present, for tight turn radius curved tunnel, generally adopt at curve tunnelThe mode of inserting vertical shaft in the middle of road section replaces curved tunnel with broken line tunnel, to solve construction difficult problem. But,The construction of inserting vertical shaft in the middle of curved tunnel section will greatly increase construction costs and extend the duration, also simultaneouslyTo produce severe jamming to traffic and urban environment.
Summary of the invention
Based on this, the invention reside in the defect that overcomes prior art, a kind of push pipe tunnel and push pipe tunnel are providedConstruction method, improve soil strength by grouting and reinforcing, the radial thrust causing to bear eccentric top power,Avoid push pipe to extra curvature lateral deviation from, prevent simultaneously sediment failure destroy and cause construction safety accident, guaranteeCarrying out smoothly of tube coupling jacking construction.
The object of the present invention is achieved like this:
The construction method in push pipe tunnel, comprises the steps:
S1, construction push pipe tunnel starting well;
S2, at the formation back-up coat in the arc turnaround section outside in push pipe tunnel;
S3, construction equipment are installed, and push pipe tunnel carries out jacking operation;
S4, construction push pipe tunnel received well.
Below further technical scheme is described:
Further, reinforcing area is treated in the outside formation that was also included in described arc turnaround section before step S2And injected hole, described injected hole and described regional connectivity to be processed.
Further, in step S2, the diameter of described arc turnaround section is d, described arc turnaround section bagDraw together initiating terminal and clearing end, the length range of described back-up coat serve as reasons the initiating terminal of described arc turnaround section front 0~2d place is to 0~2d place after the clearing end of described arc turnaround section.
Further, in step S2, the thickness range of described back-up coat is 0.5d~3d.
The push pipe that the present invention also provides a kind of construction method of the push pipe tunnel as described in the claims to buildTunnel, comprises push pipe body, and described push pipe body comprises arc turnaround section, the outside of described arc turnaround sectionBe provided with and treat reinforcing area, described in treat that reinforcing area is covered with back-up coat.
Further, the two ends of described back-up coat are equipped with bottom incline section.
Further, the material of described back-up coat is cement mortar, mortar or concrete grout.
Further, described arc turnaround section comprises at least two sections of tube segment, and two sections of described tube segment compriseOne tube segment and the second tube segment, an end face of described the first tube segment is provided with blind mortise, described the second tube segmentOne end relative with described blind mortise is provided with tenon, and described blind mortise and described tenon coordinate clamping.
Further, also comprise connection steel loop, described connection steel ring cap be loaded on described the first tube segment with described inThe joint of the second tube segment.
Further, also comprise multiple strengthening mechanisms of arranging along the bearing of trend of described arc turnaround section, instituteState strengthening mechanism and comprise section setting anti-shearing of interconnection first and along described arc turnaround sectionTwo anti-shearing.
Beneficial effect of the present invention is:
The construction method in above-mentioned push pipe tunnel is treated reinforcing area described in the outside in described arc turnaround sectionBuild slurries and form described back-up coat, can greatly improve the intensity in construction place soil, thereby make described arcTurnaround section is born the radial thrust that eccentric force causes, avoids push pipe to depart to the outside of described arc turnaround section,Affect construction quality, can also prevent from causing construction safety accident because sediment failure destroys, guarantee pipe simultaneouslyCarrying out smoothly of joint jacking construction.
Slurries shape is built by treating reinforcing area described in the outside in described arc turnaround section in above-mentioned push pipe tunnelBecome described back-up coat, can greatly improve the intensity in construction place soil, thereby described arc turnaround section is bornThe radial thrust that eccentric force causes, avoids push pipe to depart to the outside of described arc turnaround section, impact construction matterAmount, can also prevent from causing construction safety accident because sediment failure destroys simultaneously, guarantees tube coupling jacking constructionCarry out smoothly.
Brief description of the drawings
Fig. 1 is the structural representation in the push pipe tunnel described in the embodiment of the present invention;
Fig. 2 is the profile in the push pipe tunnel described in the embodiment of the present invention;
Fig. 3 is the structural representation of the tube segment described in the embodiment of the present invention.
Description of reference numerals:
100, push pipe body, 120, arc turnaround section, 122, tube segment, 123, blind mortise, 124, firstTube segment, 125, tenon, 126, the second tube segment, 200, treat reinforcing area, 300, back-up coat, 320,Bottom incline section, 400, injected hole, 500, connect steel loop, 600, strengthening mechanism, 620, the first shearing resistanceCut part, 640, second anti-shearing, 700, push pipe tunnel starting well, 800, push pipe tunnel received well.
Detailed description of the invention
Below embodiments of the invention are elaborated:
As shown in Figure 1, the construction method in a kind of push pipe tunnel, comprises the steps:
S1, construction push pipe tunnel starting well 700;
S2, at the described back-up coat 300 of formation in described arc turnaround section 120 outsides in push pipe tunnel;
S3, construction equipment are installed, and push pipe tunnel carries out jacking operation;
S4, construction push pipe tunnel received well 800.
Please refer to Fig. 2 is that example describes, and push pipe tunnel is arranged in silt soil strata, and above-mentioned push pipe tunnel alsoComprise two straightways that are connected with described arc turnaround section 120 two ends, and two length of straigh line are respectively200m and 220m, the length of described arc turnaround section is 188.5m, radius of curvature R=120m, push pipe external diameter2940mm, internal diameter 2500mm, wall thickness 220mm, the anti-shearing screw thread of intersection of Φ 16 is buried at the two ends of tube segment undergroundReinforcing bar, constructs successively according to the following step: outside the push pipe tunnel curved section of 1. construction of working shaft → 2., slip casting addsGu → 3. datum mark establish and the jacking pipe joints of shaft centerline measurement → 4. installation of construction equipment → 5. in place → 6. tube couplingThe construction procedure of jacking → 7. slip casting drag reduction → 8. repeat 5.-7. until tube coupling jacking near received well → 9. connectReceive well construction → 10. head jacking received well → sling head do completion cleaning.
The construction method in above-mentioned push pipe tunnel is waited to reinforce by described in the outside in described arc turnaround section 120Region 200 is built slurries and is formed described back-up coat 300, can greatly improve the intensity in construction place soil, therebyMake described arc turnaround section 120 bear the radial thrust that eccentric force causes, avoid push pipe to turn to described arcDepart from the outside of section, affects construction quality, can also prevent from causing construction peace because sediment failure destroys simultaneouslyFull accident, guarantees carrying out smoothly of tube coupling jacking construction. It should be pointed out that above-mentioned " first, second ... .. "Only for the differentiation to same item with refer to, the not restriction of the protection domain to quantity etc.
The outside that was also included in described arc turnaround section 120 before step S2 forms treats reinforcing area 200 HesInjected hole 400, described injected hole 400 is communicated with described region 200 to be processed. Calculate by theory, canObtain the size of the construction area of sufficient intensity and volume, reach thus the object of reinforcing soil layer intensity, withTime can also reduce materials cost as far as possible, reduce spending. Afterwards by building toward the interior perfusion of described injected hole 400Build the construction that slurries can complete described back-up coat 300, build process is simple, reliable. PreferablyIn embodiment, can build multiple described injected holes 400 and carry out pouring construction simultaneously, can greatly carry thusHigh efficiency of construction, reduces construction period.
In step S2, the diameter of described arc turnaround section 120 is d, and described arc turnaround section comprises initialEnd and clearing end, the length range of described back-up coat 300 is served as reasons before the initiating terminal of described arc turnaround section 1200~2d place is to 0~2d place after the clearing end of described arc turnaround section 120. Wherein, described in, treat reinforcing area200 for being covered in the pouring region of the certain area in jacking pipeline top, by the length restriction of described back-up coat 300Front 0~the 2d of the initiating terminal place of the described arc turnaround section 120 of serving as reasons is to the clearing end of described arc turnaround section 120In the scope at rear 0~2d place, playing good soil mass consolidation intensity, preventing that push pipe is because being sent out by radial thrustWhen raw lateral deviation, can also reduce construction cost and time preferably, improve efficiency of construction.
In addition, the thickness range of described back-up coat 300 is the extremely described arc of outer wall of described arc turnaround section 1200.5d~3d place, outside of z bend section 120. The thickness of described back-up coat 300 is defined as to described arc to be turnedThe outer wall of curved segment 120, to 0.5d~3d place, outside of described arc turnaround section 120, ensures described reinforcing simultaneouslyLayer 300 and the center superposition in push pipe tunnel, and the thickness of the above-below direction of preferred described back-up coat be 0.5d~2d, can realize and prevent that push pipe from turning because the radial thrust of bearing eccentric top power and causing produces to described arcThe problem that depart from the outside of section 120, further can also play to the soil body of construction periphery the effect of reinforcing,Guarantee construction safety.
The push pipe that the present invention also provides a kind of construction method of the push pipe tunnel as described in the claims to buildTunnel, comprises push pipe body 100, and described push pipe body comprises arc turnaround section 120, described arc turnaround section120 outside is provided with treats reinforcing area 200, described in treat that reinforcing area 200 is covered with back-up coat 300.
Wherein, above-mentioned push pipe tunnel is mainly for the stressed offset problem to curved section constructing tunnel in Soft Soil LayerSolve, concrete is in the larger arc length of the described arc turnaround section 120 of described push pipe body 100Reinforcing area 200 is treated described in reserving in outside, thereby and builds construction slurry slurries to this region and add described in formingGu layer 300, reinforces thus the intensity that improves the soil body, thereby makes described arc turnaround section 120 bear eccentric forceThe radial thrust causing, avoids push pipe to depart to the outside of described arc turnaround section 120, affects construction quality,Can also prevent from causing construction safety accident because sediment failure destroys, guarantee the suitable of tube coupling jacking construction simultaneouslyProfit is carried out.
In addition, the material of described back-up coat 300 is cement mortar, mortar or concrete grout. Described back-up coat canWith according to flexible selection material types such as the needs of the character of construction ground soil layer and construction intensity, not only can fallLow difficulty of construction and cost, can also improve the functional reliability of described back-up coat 300. At other embodimentIn also can adopt the material of other types or character. The two ends of described back-up coat 300 are equipped with bottom inclineSection 320. Preferably the two ends of described back-up coat 300 are built into described bottom incline section 320, this has a down dipThe thickness of face section 320 trend that tapered off to two ends by centre, can save the materials'use amount of construction, reducesConstruction cost.
Above-mentioned push pipe tunnel also comprises multiple injected holes 400, multiple described injected holes 400 all with described in wait to reinforceRegion 200 is communicated with. By multiple described injected holes 400 are set, and ensure they all with described in treat reinforcing area200 connect and are communicated with, and can improve to a certain extent the speed of slip casting, thereby improve efficiency of construction, exist in additionWhen the problems such as obstruction occur certain injected hole 400, other injected hole also can ensure carrying out smoothly of construction.
As Fig. 2, shown in Fig. 3, described arc turnaround section 120 comprises 122, two sections of institutes of at least two sections of tube segmentState tube segment 122 and comprise the first tube segment 124 and the second tube segment 126, one of described the first tube segment 124End face is provided with blind mortise 123, and described the second tube segment 126 one end relative with described blind mortise 123 is provided with tenon125, described blind mortise 123 and described tenon 125 coordinate clamping.
For convenient construction, in preferred embodiment of the present invention, described arc turnaround section 120 is by leastTwo sections of tube segment 122 form, the concrete blind mortise that passes through described the first tube segment 124 and described the second tube couplingThe tenon of section 126 cooperatively interacts to splice and is assembled, and can form anti-shearing key by this assembly structure, canThe radial thrust that effectively the eccentric top of opposing power causes, thus described the first tube segment 124 and described second avoidedThere is end face faulting of slab ends in tube segment 126, affects construction quality.
Above-mentioned push pipe tunnel also comprises connection steel loop 500, and described connection steel loop 500 is set in described the first tube couplingThe joint of section 124 and described the second tube segment 126. At described the first tube segment 124 and described the second pipeThe outside of the mosaic of sections 126 is set with described connection and just encircles, and can further play reinforcement by connection, preventThere is the staggered problem separating in both.
Further, also comprise multiple strengthening mechanisms of arranging along the bearing of trend of described arc turnaround section 120600, multiple described strengthening mechanisms 600 include along the section setting of described arc turnaround section 120, also intersectConnect first anti-shearing 620 and second anti-shearing 640. Wherein, described first anti-shearing 620 and instituteState the second shear reinforcement 640 for intersecting the X-type ruggedized construction being spliced into, four ends of this X-type ruggedized constructionPortion all pushes against and contacts with the sidewall of push pipe, and this X-type ruggedized construction is along the section of described arc turnaround section 120Direction is arranged, can play a protective role to described blind mortise 123 and described tenon 125 thus, prevents bothBecause of the stressed excessive problem that produces fatigue fracture, the functional reliability and the security that improve this push pipe tunnel.Preferably, described first anti-shearing 620 and described second anti-shearing 640 for diameter be 12~20mm ruleThe spiral of lattice, when installation all with described the first tube segment 124 and described the second tube segment 126 axiallyReinforcing bar is welded to connect, and spacing 200mm is uniformly distributed vertically, has ensured enough shearing strengths and stableProperty.
Each technical characterictic of the above embodiment can combine arbitrarily, for making to describe succinctly, not rightThe all possible combination of each technical characterictic in above-described embodiment is all described, but, as long as these skillsThere is not contradiction in the combination of art feature, is all considered to be the scope that this description is recorded.
The above embodiment has only expressed several embodiment of the present invention, and it describes comparatively concrete and detailed,But can not therefore be construed as limiting the scope of the patent. It should be pointed out that for this areaThose of ordinary skill, without departing from the inventive concept of the premise, can also make some distortion and changeEnter, these all belong to protection scope of the present invention. Therefore, the protection domain of patent of the present invention should be with appended powerProfit requires to be as the criterion.

Claims (10)

1. the construction method in push pipe tunnel, is characterized in that, comprises the steps:
S1, construction push pipe tunnel starting well;
S2, at the formation back-up coat in the arc turnaround section outside in push pipe tunnel;
S3, construction equipment are installed, and push pipe tunnel carries out jacking operation;
S4, construction push pipe tunnel received well.
2. the construction method in push pipe according to claim 1 tunnel, is characterized in that, at step S2The outside that is before also included in described arc turnaround section forms treats reinforcing area and injected hole, described injected hole withTreat that in described reinforcing area is communicated with.
3. the construction method in push pipe according to claim 1 tunnel, is characterized in that, at step S2In, the diameter of described arc turnaround section is d, described arc turnaround section comprises initiating terminal and clearing end, described in addThe extremely described arc turnaround section of front the 0~2d of the initiating terminal place of described arc turnaround section Gu the length range of layer is served as reasons0~2d place after clearing end.
4. the construction method in push pipe according to claim 1 tunnel, is characterized in that, at step S2In, the thickness range of described back-up coat is 0.5d~3d.
5. the push pipe that the construction method in the push pipe tunnel described in application rights requirement 1 to 4 any one is builtTunnel, is characterized in that, comprises push pipe body, and described push pipe body comprises arc turnaround section, described arcThe outside of turnaround section is provided with treats reinforcing area, described in treat that reinforcing area is covered with back-up coat.
6. push pipe according to claim 5 tunnel, is characterized in that, all establish at the two ends of described back-up coatThere is bottom incline section.
7. push pipe according to claim 5 tunnel, is characterized in that, the material of described back-up coat is waterMud, mortar or concrete grout.
8. push pipe according to claim 5 tunnel, is characterized in that, described arc turnaround section comprise toFew two sections of tube segment, two sections of described tube segment comprise the first tube segment and the second tube segment, described the first tube couplingOne end face of section is provided with blind mortise, and described the second tube segment one end relative with described blind mortise is provided with tenon, described inBlind mortise and described tenon coordinate clamping.
9. push pipe according to claim 8 tunnel, is characterized in that, also comprises connection steel loop, described inConnect the joint that steel ring cap is loaded on described the first tube segment and described the second tube segment.
10. push pipe according to claim 5 tunnel, is characterized in that, also comprises along described arc and turningMultiple strengthening mechanisms that the bearing of trend of curved segment is arranged, described strengthening mechanism comprises along described arc turnaround sectionAnti-shearing and second anti-shearing of section setting interconnection first.
CN201610141808.0A 2016-03-11 2016-03-11 Pipe-jacking tunnel and construction method of pipe-jacking tunnel Pending CN105604555A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610141808.0A CN105604555A (en) 2016-03-11 2016-03-11 Pipe-jacking tunnel and construction method of pipe-jacking tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610141808.0A CN105604555A (en) 2016-03-11 2016-03-11 Pipe-jacking tunnel and construction method of pipe-jacking tunnel

Publications (1)

Publication Number Publication Date
CN105604555A true CN105604555A (en) 2016-05-25

Family

ID=55984840

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610141808.0A Pending CN105604555A (en) 2016-03-11 2016-03-11 Pipe-jacking tunnel and construction method of pipe-jacking tunnel

Country Status (1)

Country Link
CN (1) CN105604555A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106246189A (en) * 2016-08-04 2016-12-21 广州电力设计院 The installation method of pipe jacking tunnel tube coupling
CN106837344A (en) * 2017-01-02 2017-06-13 陈建强 A kind of constructing metro tunnel method
CN109119943A (en) * 2018-09-10 2019-01-01 国网天津市电力公司 System of laying optimization method of the cable at push pipe both ends
CN110130910A (en) * 2019-05-22 2019-08-16 重庆大学 Earth pressure balanced shield, EPBS small curve radius tunneling shield driving method
CN110159291A (en) * 2019-05-06 2019-08-23 广州电力设计院有限公司 Method for tunnel construction and tunnel structure
CN111379573A (en) * 2020-05-06 2020-07-07 中国石油天然气集团有限公司 Connecting system for connecting shield tunnel in middle of oil and gas pipeline
CN111379574A (en) * 2020-05-06 2020-07-07 中国石油天然气集团有限公司 Method for connecting oil-gas pipeline into shield tunnel from middle

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1327134A (en) * 2001-07-27 2001-12-19 卢清国 Resistance increasing automatic drive conduit jacking method between pipe and soil and its jacking device
CN102032393A (en) * 2010-11-10 2011-04-27 博大建设有限公司 Small-bore long distance curved pipe jacking method
CN102072359A (en) * 2009-11-24 2011-05-25 上海市政工程设计研究总院 Curved-jacked steel pipe section and jacking method
CN102338244A (en) * 2011-08-25 2012-02-01 上海市第二市政工程有限公司 Steel pipe joint structure for pipe jacking
CN203161238U (en) * 2013-03-27 2013-08-28 国家电网公司 Grouting device for long-distance curved top pipe in cable tunnel
WO2014006204A2 (en) * 2012-07-05 2014-01-09 Astrium Sas Drilling device and method
CN104389615A (en) * 2014-09-30 2015-03-04 中铁四局集团第二工程有限公司 Small-radius curve large-slope shield construction method in coastal soft soil stratum
CN204852606U (en) * 2015-07-26 2015-12-09 中铁十八局集团有限公司 Curve push pipe tube coupling bell and spigot connection form
CN105240019A (en) * 2015-09-24 2016-01-13 中国石油天然气集团公司 Pipe jacking construction method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1327134A (en) * 2001-07-27 2001-12-19 卢清国 Resistance increasing automatic drive conduit jacking method between pipe and soil and its jacking device
CN102072359A (en) * 2009-11-24 2011-05-25 上海市政工程设计研究总院 Curved-jacked steel pipe section and jacking method
CN102032393A (en) * 2010-11-10 2011-04-27 博大建设有限公司 Small-bore long distance curved pipe jacking method
CN102338244A (en) * 2011-08-25 2012-02-01 上海市第二市政工程有限公司 Steel pipe joint structure for pipe jacking
WO2014006204A2 (en) * 2012-07-05 2014-01-09 Astrium Sas Drilling device and method
CN203161238U (en) * 2013-03-27 2013-08-28 国家电网公司 Grouting device for long-distance curved top pipe in cable tunnel
CN104389615A (en) * 2014-09-30 2015-03-04 中铁四局集团第二工程有限公司 Small-radius curve large-slope shield construction method in coastal soft soil stratum
CN204852606U (en) * 2015-07-26 2015-12-09 中铁十八局集团有限公司 Curve push pipe tube coupling bell and spigot connection form
CN105240019A (en) * 2015-09-24 2016-01-13 中国石油天然气集团公司 Pipe jacking construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴荣荣: "泥水平衡式曲线顶管施工技术在电力改造工程中的应用", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106246189A (en) * 2016-08-04 2016-12-21 广州电力设计院 The installation method of pipe jacking tunnel tube coupling
CN106246189B (en) * 2016-08-04 2018-07-31 广州电力设计院 The installation method of pipe jacking tunnel tube coupling
CN106837344A (en) * 2017-01-02 2017-06-13 陈建强 A kind of constructing metro tunnel method
CN109119943A (en) * 2018-09-10 2019-01-01 国网天津市电力公司 System of laying optimization method of the cable at push pipe both ends
CN110159291A (en) * 2019-05-06 2019-08-23 广州电力设计院有限公司 Method for tunnel construction and tunnel structure
CN110130910A (en) * 2019-05-22 2019-08-16 重庆大学 Earth pressure balanced shield, EPBS small curve radius tunneling shield driving method
CN111379573A (en) * 2020-05-06 2020-07-07 中国石油天然气集团有限公司 Connecting system for connecting shield tunnel in middle of oil and gas pipeline
CN111379574A (en) * 2020-05-06 2020-07-07 中国石油天然气集团有限公司 Method for connecting oil-gas pipeline into shield tunnel from middle

Similar Documents

Publication Publication Date Title
CN105604555A (en) Pipe-jacking tunnel and construction method of pipe-jacking tunnel
RU2451134C2 (en) Method and equipment to develop micropiles in soil, in particular, to fix active anchors
CN104018518B (en) The method of prefabricated diaphragm wall and construction outer wall of basement and floor
CN103074890A (en) Plastic sleeve and steel pipe combined cast-in-place concrete hollow pipe pile and construction method thereof
CN103485334B (en) Bi-layer plastic-bushing inverted-arch cambered hollow special-shaped pile and construction method
CN109667985B (en) Method for butting pipe pushing jack and receiving well steel sleeve in pipe pushing construction
CN101545270B (en) Double sleeve for pile foundation test and construction technique thereof
JPWO2004035942A1 (en) Pile digging method, foundation pile structure
CN106121658B (en) Freezing method sinking shaft well wall supporting structure and construction method thereof
CN108930544A (en) A kind of broken ground underground large space method of construction
CN205503133U (en) Push pipe tunnel
KR101029311B1 (en) Non-excavation laying method for pipeline and tunnel using temporary composite pipe
CN109695453B (en) Auxiliary excavation construction method for vertical shaft main tunnel three-dimensional intersection
CN206090547U (en) Strength nature composite pile of dysmorphism
CN102409702A (en) Method for performing seam waterproof construction in underground continuous wall by using embedded rubber water stop tapes
CN206467661U (en) The resistance to compression attachment structure of secondary splitting grouting
CN208669327U (en) A kind of broken ground underground volumed space building structure
CN108343065A (en) The resistance to compression connection structure and construction method of secondary splitting grouting
CN212983845U (en) Engineering pile and pile foundation
CN103556630A (en) Multistage grouting concrete filling pile and construction process thereof
CN214944357U (en) Grouting anchor rod structure supported by broken belt
CN112681336B (en) Construction method of plastic sleeve secant pile
CN219011195U (en) PHC composite filling pile
CN203730070U (en) Gob-side entry retaining filled wall structure with rectangular concrete filled steel tubes
CN211692481U (en) Supporting base for assembled lining

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160525