CN105603969A - Regeneration connection method of truncated remainder precast concrete pipe pile - Google Patents

Regeneration connection method of truncated remainder precast concrete pipe pile Download PDF

Info

Publication number
CN105603969A
CN105603969A CN201610052756.XA CN201610052756A CN105603969A CN 105603969 A CN105603969 A CN 105603969A CN 201610052756 A CN201610052756 A CN 201610052756A CN 105603969 A CN105603969 A CN 105603969A
Authority
CN
China
Prior art keywords
pile
strip
coil
section
cutoff
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610052756.XA
Other languages
Chinese (zh)
Other versions
CN105603969B (en
Inventor
王怀忠
田青超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baoshan Iron and Steel Co Ltd
Original Assignee
Baoshan Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baoshan Iron and Steel Co Ltd filed Critical Baoshan Iron and Steel Co Ltd
Priority to CN201610052756.XA priority Critical patent/CN105603969B/en
Publication of CN105603969A publication Critical patent/CN105603969A/en
Application granted granted Critical
Publication of CN105603969B publication Critical patent/CN105603969B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete

Abstract

The invention relates to a regeneration connection method of a truncated remainder precast concrete pipe pile. The method comprises the following steps: (1) taking a section of truncated remainder concrete pipe pile as a first pile section, and enabling the first pile section to lie flat on the processing site; (2) taking a section of straight seam steel pipe which is not formed by welding yet as a connection steel coil, and enabling the connection steel coil to be sleeved at the outer side of the truncated end surface of the first pile section; (3) arranging a ring-shaped filling along the ring direction on the truncated end surface to be connected of the first pile section, wherein the longitudinal length of the filling is less than the radial thickness of the first pile section, and the ring-shaped external diameter of the filling is not larger than the external diameter of the first pile section; (4) taking another section of truncated remainder concrete pipe pile as a second pile section, and enabling the second pile section to lie flat on the processing site; enabling one end of the truncated surface to be connected of the second pile section to be sleeved in the connection steel coil to prop against the filling; (5) enabling the connection steel coil to be tightened and wrap the first pile section and the second pile section, then welding a straight welded joint on the steel coil, and enabling the steel coil to be processed into a steel pipe; finally, connecting the first pile section with the second pile section by the steel pipe and the filling to form a section of recycled concrete pipe pile.

Description

Block remaining prefabricated concrete pipe pile regeneration method of attachment
Technical field
The present invention relates to pile foundation engineering technique, relate in particular to and block remaining prefabricated concrete pipe pile regenerationMethod of attachment.
Background technology
Existingly block remaining prefabricated concrete pipe pile major part as waste disposal, so both wasted materialMaterial, also can cause environmental pollution.
Summary of the invention
The object of the present invention is to provide one to block remaining prefabricated concrete pipe pile regeneration connection sideMethod, solve block remaining prefabricated concrete pipe pile waste disposal problem, and open up high strength steel orThe application market of steel pipe.
For achieving the above object, technical scheme of the present invention is:
Block remaining prefabricated concrete pipe pile regeneration method of attachment, comprise the steps:
1) getting one section blocks remaining concrete tubular pile and lies in processing space on the ground as the first pile cutoff;
2) get one section not yet the steel pipes with straight of welding fabrication conduct connect coil of strip be enclosed within described firstThe outside of blocking end face of section, the longitudinal length of this connection coil of strip is greater than described the first pile cutoffOverall diameter, its longitudinal length that is enclosed within described the first pile cutoff outside is greater than outer half of the first pile cutoffFootpath, the hoop length that it does not close up is not less than the hoop girth of described the first pile cutoff, connects steelVolume thickness is greater than 3mm;
3) described the first pile cutoff to be connected block end face pressed on ring have to the initial stage of setting plasticity and afterThe charges that phase can harden, form annular charges; The longitudinal length of charges is less thanThe radial thickness of one pile cutoff, its annular overall diameter is not more than the overall diameter of described the first pile cutoff;
4) get another section and block remaining concrete tubular pile and lie in processing space on the ground as the second pile cutoff,The end face one end of blocking to be connected the second pile cutoff is enclosed within described connection coil of strip, holds out against fillingThing, the longitudinal length that connection coil of strip is enclosed within the second pile cutoff outside is greater than outer half of the second pile cutoffFootpath;
5) connection coil of strip is tightened up and is coated the first pile cutoff and the second pile cutoff, be then welded to connect coil of strip straightWeld seam, is processed into steel pipe by this connection coil of strip; Finally utilize the filling of steel pipe and after-hardeningThing, is connected to become a joint regeneration concrete pile tube by the first pile cutoff and the second pile cutoff.
Further, step 5) tighten up and connect coil of strip and utilize arc shaped pincers that connection coil of strip is tightened up and be coated theOne pile cutoff and the second pile cutoff.
Again, step 5) tighten up connect coil of strip adopt on two link lateral surfaces of described connection coil of stripRespectively welded nut, connect coil of strip be enclosed within the first pile cutoff with on the second pile cutoff after be connected with bolt, will connectConnect coil of strip and tighten up and be coated the first pile cutoff and the second pile cutoff, then weld straight weld, connection coil of strip is addedWork becomes steel pipe; Then remove and be welded on the nut connecting on coil of strip.
Preferably, described charges are pea gravel concreten, resin concrete or sulphide mastic.
Beneficial effect of the present invention:
1) the invention solves the remaining prefabricated concrete pipe pile waste disposal problem of blocking.
2) the present invention opens up the application market of high strength steel or steel pipe.
3) the present invention can provide reliable pipe of concrete pile material.
Brief description of the drawings
Fig. 1~Fig. 5 is that concrete tubular pile pile cutoff regeneration of the present invention connects process schematic diagram.
Fig. 6 is that the present invention utilizes instrument (arc shaped pincers) coil of strip to be tightened up and is coated pile cutoff then to weld and showIntention.
Fig. 7 is that the present invention utilizes instrument (nuts/bolts) coil of strip to be tightened up and is coated pile cutoff then to weldSchematic diagram.
Detailed description of the invention
Below in conjunction with embodiment and accompanying drawing, the present invention will be further described.
Embodiment 1
Referring to Fig. 1~Fig. 6, the present invention blocks remaining prefabricated concrete pipe pile regeneration method of attachment, bagDraw together following steps:
1) get one section and block remaining concrete tubular pile--the first pile cutoff 1 lies in processing space on the ground, shouldPile cutoff 1 length 6.2m, overall diameter 600mm, interior diameter 380mm, thickness 110mm;
2) get one section not yet the connection coil of strip 2 of the steel pipes with straight of welding fabrication be enclosed within the first pile cutoff 1 cutThe outside of broken ends of fractured bone face one end, the longitudinal length that connects coil of strip 2 is 700mm, it is enclosed within the first pile cutoff 1The longitudinal length in outside is 330mm, and the hoop length that it does not close up is 2000mm, and its thickness is10mm;
3) there is plasticity and later stage energy in the to be connected end face pressed on ring of blocking of the first pile cutoff 1 to the initial stage of settingThe charges 3 (pea gravel concreten) of enough sclerosis, form annular charges; Longitudinal length of charges 3Degree 40mm, its annular overall diameter 580mm, interior diameter 390mm;
4) get another section and block remaining concrete tubular pile--the second pile cutoff 4 lies in processing space on the ground,This pile cutoff 4 length 5.6m, overall diameter 600mm, interior diameter 380mm, thickness 110mm. By stakeSection 4 is to be connected blocks end face one end and is enclosed within and connects in coil of strip 2, holds out against charges 3 (microlith coagulationSoil), the longitudinal length that connection coil of strip 2 is enclosed within the second pile cutoff 4 outsides is 330mm;
5) utilize arc shaped pincers 6 that connection coil of strip 2 is tightened up and be coated the first pile cutoff 1 and the second pile cutoff 4,Then weld straight weld, connection coil of strip 2 is processed into steel pipe;
6) remove arc shaped pincers 6, utilize the charges 3 of steel pipe and after-hardening, by the first pile cutoff 1 HeThe second pile cutoff 4 is connected to become the regeneration concrete pile tube of a joint length 12.2m.
Embodiment 2
Referring to Fig. 1~Fig. 5, Fig. 7, the present invention blocks remaining prefabricated concrete pipe pile regeneration connection sideMethod, comprises the steps:
1) get one section and block remaining concrete tubular pile--the first pile cutoff 1 lies in processing space on the ground, shouldPile cutoff 1 length 6.2m, overall diameter 600mm, interior diameter 380mm, thickness 110mm;
2) get one section not yet the connection coil of strip 2 of the steel pipes with straight of welding fabrication be enclosed within the first pile cutoff 1 cutThe outside of broken ends of fractured bone face one end, the longitudinal length that connects coil of strip 2 is 700mm, it is enclosed within pile cutoff 1 outsideLongitudinal length be 330mm, the hoop length that it does not close up is 1884mm, its thickness is 8mm;
3) on end face, arrange in to be connected the blocking of the first pile cutoff 1 that the initial stage has plasticity and the later stage can be hardThe annular charges 3 (sulphide mastic) of changing, the longitudinal length 40mm of charges 3, outside its annularDiameter 580mm, interior diameter 390mm;
4) get another section and block remaining concrete tubular pile--the second pile cutoff 4 lies in processing space on the ground,This pile cutoff 4 length 5.6m, overall diameter 600mm, interior diameter 380mm, thickness 110mm; ByWhat two pile cutofves 4 were to be connected block, and end face one end is enclosed within connects in coil of strip 2, holds out against charges 3 (sulphurClay), the longitudinal length that connection coil of strip 2 is enclosed within the second pile cutoff 4 outsides is 330mm;
5) utilize bolt 8 and be welded on the nut 7,7 ' connecting on coil of strip 2 temporarily and will connect coil of strip2 tighten up and are coated the first pile cutoff 1 and the second pile cutoff 4, then weld straight weld, will connect coil of strip 2Be processed into steel pipe;
6) remove and be welded on the nut 7,7 ' connecting on coil of strip 2, utilize filling of steel pipe and after-hardeningFill out thing 3, the first pile cutoff 1 and the second pile cutoff 4 are connected to become to the regeneration coagulation of a joint length 12.2mSoil pile tube.
The present invention can solve and block remaining prefabricated concrete pipe pile waste disposal problem, is conducive to environmentProtection. The present invention can be soft clay area pile foundation engineering reliable pipe of concrete pile material is provided.

Claims (4)

1. block remaining prefabricated concrete pipe pile regeneration method of attachment, it is characterized in that, comprise the steps:
1) getting one section blocks remaining concrete tubular pile and lies in processing space on the ground as the first pile cutoff;
2) get one section not yet the steel pipes with straight of welding fabrication conduct connect coil of strip be enclosed within described firstThe outside of blocking end face of section, the longitudinal length of this connection coil of strip is greater than described the first pile cutoffOverall diameter, its longitudinal length that is enclosed within described the first pile cutoff outside is greater than outer half of the first pile cutoffFootpath, the hoop length that it does not close up is not less than the hoop girth of described the first pile cutoff, connects steelVolume thickness is greater than 3mm;
3) described the first pile cutoff to be connected block end face pressed on ring have to the initial stage of setting plasticity and afterThe charges that phase can harden, the longitudinal length of charges is less than the radially thick of the first pile cutoffDegree, its annular overall diameter is not more than the overall diameter of described the first pile cutoff;
4) get another section and block remaining concrete tubular pile and lie in processing space on the ground as the second pile cutoff,The end face one end of blocking to be connected the second pile cutoff is enclosed within described connection coil of strip, holds out against fillingThing, the longitudinal length that connection coil of strip is enclosed within the second pile cutoff outside is greater than outer half of the second pile cutoffFootpath;
5) connection coil of strip is tightened up and is coated the first pile cutoff and the second pile cutoff, be then welded to connect coil of strip straightWeld seam, is processed into steel pipe by this connection coil of strip; Finally utilize the filling of steel pipe and after-hardeningThing, is connected to become a joint regeneration concrete pile tube by the first pile cutoff and the second pile cutoff.
2. as claimed in claim 1ly block remaining prefabricated concrete pipe pile regeneration method of attachment, its spyLevy and be, step 5) tighten up and connect coil of strip and utilize arc shaped pincers that connection coil of strip is tightened up and be coated firstSection and the second pile cutoff.
3. as claimed in claim 1ly block remaining prefabricated concrete pipe pile regeneration method of attachment, its spyLevy and be, step 5) tighten up and connect coil of strip and adopt on two link lateral surfaces of described connection coil of stripRespectively welded nut, connect coil of strip be enclosed within the first pile cutoff with on the second pile cutoff after be connected with bolt,Connection coil of strip is tightened up and be coated the first pile cutoff and the second pile cutoff, then weld straight weld, will connectConnect coil of strip and be processed into steel pipe; Then remove and be welded on the nut connecting on coil of strip.
4. as claimed in claim 1ly block remaining prefabricated concrete pipe pile regeneration method of attachment, its spyLevy is that described charges are pea gravel concreten, resin concrete or sulphide mastic.
CN201610052756.XA 2016-01-26 2016-01-26 Block remaining prefabricated concrete pipe pile regeneration connection method Active CN105603969B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610052756.XA CN105603969B (en) 2016-01-26 2016-01-26 Block remaining prefabricated concrete pipe pile regeneration connection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610052756.XA CN105603969B (en) 2016-01-26 2016-01-26 Block remaining prefabricated concrete pipe pile regeneration connection method

Publications (2)

Publication Number Publication Date
CN105603969A true CN105603969A (en) 2016-05-25
CN105603969B CN105603969B (en) 2017-10-31

Family

ID=55984276

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610052756.XA Active CN105603969B (en) 2016-01-26 2016-01-26 Block remaining prefabricated concrete pipe pile regeneration connection method

Country Status (1)

Country Link
CN (1) CN105603969B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004250984A (en) * 2003-02-20 2004-09-09 Sumitomo Mitsui Construction Co Ltd Cast-in-place steel pipe reinforced concrete pile
CN201817810U (en) * 2010-09-21 2011-05-04 中国二十冶集团有限公司 Anti-corrosion device for tubular pile connecting joints in corrosive soil layers or underground water environments
CN202227334U (en) * 2011-10-09 2012-05-23 中建七局第三建筑有限公司 Socket type steel pipe pile joint
CN203270556U (en) * 2013-05-23 2013-11-06 福州第七建筑工程有限公司 Reinforced structure at tubular pile joint
CN104060606A (en) * 2014-07-01 2014-09-24 国鼎(南通)管桩有限公司 Combined splicing tubular pile and pile splicing method
CN104343117A (en) * 2013-07-31 2015-02-11 天津永生鑫和管桩有限公司 Concrete pipe pile connector

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004250984A (en) * 2003-02-20 2004-09-09 Sumitomo Mitsui Construction Co Ltd Cast-in-place steel pipe reinforced concrete pile
CN201817810U (en) * 2010-09-21 2011-05-04 中国二十冶集团有限公司 Anti-corrosion device for tubular pile connecting joints in corrosive soil layers or underground water environments
CN202227334U (en) * 2011-10-09 2012-05-23 中建七局第三建筑有限公司 Socket type steel pipe pile joint
CN203270556U (en) * 2013-05-23 2013-11-06 福州第七建筑工程有限公司 Reinforced structure at tubular pile joint
CN104343117A (en) * 2013-07-31 2015-02-11 天津永生鑫和管桩有限公司 Concrete pipe pile connector
CN104060606A (en) * 2014-07-01 2014-09-24 国鼎(南通)管桩有限公司 Combined splicing tubular pile and pile splicing method

Also Published As

Publication number Publication date
CN105603969B (en) 2017-10-31

Similar Documents

Publication Publication Date Title
CN103422674B (en) Prefabricated concrete structure Cast-in-Situ Segment concrete construction method
CN103114717A (en) Formwork system of shear walls at two sides of extensible seam
CN104805775B (en) The construction method of recovery technique after the shake of a kind of RC bridge pier
CN111828053A (en) Steel pipe concrete and sprayed concrete rigid combined structure tunnel supporting system and construction method
CN107355239A (en) Adapt to the compound section of jurisdiction of corrugated steel and its assembling method of shield tunnel Longitudinal Settlement
CN102966185B (en) Novel concrete-filled steel tube connection joint and construction method thereof
CN104196489A (en) Column beam type grouting device and hole sealing and grouting technology thereof
CN106121056A (en) Thin-wall steel tube regenerative mixed column and the bilayer narrow ring flat-plate FRP node of girder steel
CN106013153A (en) End protector for construction of steel pipe pile and working method thereof
CN107476572A (en) A kind of Split bolt sleeve device for building
CN100520140C (en) Fiberglass sand inclusion pipe with axial direction fibre and manufacturing method
CN105603969A (en) Regeneration connection method of truncated remainder precast concrete pipe pile
CN207159844U (en) A kind of reinforcement structure for Steel Corrugated Pipe Culvert
CN104196023B (en) A kind of using method of the concrete precast pipe pile pile top of band mechanical connecting device
CN205857182U (en) A kind of end-protecting device for steel-pipe pile construction
CN204212406U (en) A kind of one-sided strengthening construction big steelmoulds
JP4764580B2 (en) Temporary water pipe
CN104343117A (en) Concrete pipe pile connector
CN110666956A (en) Reinforced shield tunnel segment and preparation method thereof
CN109898752A (en) Half grout sleeve and preparation method thereof
CN210482760U (en) A steel bar sleeve grout connects overlap joint for assembled structure
CN211599935U (en) Pipeline installation tip protection device
CN206072630U (en) Plastics wall tube material with stress relief structure holds/inserting structure
CN110469124A (en) Steel hoop reinforcement in concrete construction method
CN213450492U (en) Reinforcement structure of tunnel transverse drain pipe

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant