CN105545321B - A kind of small area blasting mining in thin seam working face gob-side entry retaining support method - Google Patents

A kind of small area blasting mining in thin seam working face gob-side entry retaining support method Download PDF

Info

Publication number
CN105545321B
CN105545321B CN201511008424.3A CN201511008424A CN105545321B CN 105545321 B CN105545321 B CN 105545321B CN 201511008424 A CN201511008424 A CN 201511008424A CN 105545321 B CN105545321 B CN 105545321B
Authority
CN
China
Prior art keywords
shaped steel
face
canopy
support
entry retaining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201511008424.3A
Other languages
Chinese (zh)
Other versions
CN105545321A (en
Inventor
王昌祥
江宁
王玉成
李金平
王建行
孔贺
孔德志
张保良
张士川
赵金海
王学武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University of Science and Technology
Original Assignee
Shandong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University of Science and Technology filed Critical Shandong University of Science and Technology
Priority to CN201511008424.3A priority Critical patent/CN105545321B/en
Publication of CN105545321A publication Critical patent/CN105545321A/en
Application granted granted Critical
Publication of CN105545321B publication Critical patent/CN105545321B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/02Lining predominantly with wood
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Abstract

The invention discloses a kind of small area blasting mining in thin seam working face gob-side entry retaining support methods, small area blasting mining in thin seam works face gob-side entry retaining using H shaped steel shack and timber progress supporting, strengthening supporting is carried out using hydraulic prop, method for protecting support uses following steps: (1) advance support: the advanced blast mining face complement anchor pole in crossheading;Advanced blast mining face sets up H shaped steel shack;(2) Lagging support: I-shaped steel type frame, which is set, to be finished, and lag blast mining face segment frame sets hydraulic prop strengthening supporting;(3) goaf side caving: after blast mining face has returned material, as top plate voluntarily cannot carry out powder charge caving if inbreak.By H shaped steel shack, individual prop, powder charge caving carry out staying lane the present invention.The gob side entry retaining small investment, quick, high efficiency, safety coefficient are high, are to enhance extremely advantageous one of the approach of mine safety production.

Description

A kind of small area blasting mining in thin seam working face gob-side entry retaining support method
Technical field
The present invention relates to field of coal mining, more particularly, to a kind of small area blasting mining in thin seam work face gob-side entry retaining branch Maintaining method.
Background technique
As central and east coal resources are becoming tight, small area thin seam mining will be increasing.Gob side entry retaining tunnelling rate It substantially reduces, exploiting field recovery ratio significantly increases, and realizes fast extraction, shortens moving time, prevents island working face from generating, and prevents The only advantages such as ignition.Gob side entry retaining is compared with having coal column to protect lane, in Technological Economy, production safety, all has advantage.But mesh Before, the scientific method for protecting support of the blast mining face of small area girdle is not corresponded to, there are security risks for existing support pattern.
Summary of the invention
In order to solve the deficiencies in the prior art, the invention proposes a kind of apply to invest in low-angle dip small area girdle Less, the high gob-side entry retaining method of quick, high efficiency, safety coefficient.
The present invention adopts the following technical scheme:
A kind of small area blasting mining in thin seam working face gob-side entry retaining support method, small area blasting mining in thin seam working face is along empty It stays lane to carry out supporting using H shaped steel shack and timber, strengthening supporting is carried out using hydraulic prop, method for protecting support is using such as Lower step:
(1) advance support: (the advanced of blast mining face answers complement anchor pole at advanced blast mining face 20-25m in crossheading Power coverage is 20m or so);Advanced blast mining face sets up H shaped steel shack;
(2) Lagging support: I-shaped steel type frame, which is set, to be finished, and lag blast mining face segment frame sets hydraulic prop and reinforces branch Shield;
(3) it goaf side caving: after blast mining face has returned material, is put as top plate voluntarily cannot carry out powder charge if inbreak Top.
Anchor pole array pitch is 1.0-1.2m in the step (1), and four anchor poles of every row, anchor pole specification is 22 × 2000mm of Φ. The relatively large anchor pole of diameter length, array pitch is relatively large, can obtain preferable Surrounding Rock Control and economic comprehensive effect.
Reality is first looked for by the top in tunnel, side before setting up H shaped steel shack in the step (1).
Keep top beam concordant when setting up H shaped steel shack in the step (1), top is connect on capplce in fact, canopy leg connects on the spot, and front and back is flat Together;
With the wooden nail jail between two canopies, canopy leg lower part is packed tightly with waste metal net.
Preferably, the canopy of the H shaped steel shack meets Yan Jieshi with timber on capplce away from for 0.8m, and canopy leg is buried to real bottom In, angle folded by canopy leg capplce is chosen at 8-12 °, apart from angle according to field experience, to obtain optimum efficiency.
Preferably, capplce length, canopy leg height are determined by heading sizes, and the capplce length of the H shaped steel shack is 2.2m, And installing anti-skidding baffle additional at the 0.20m of both ends;
Canopy leg height is 2.3m, and bottom end adds pedestal;
The timber on top and waist side is connect on capplce, thickness is not less than 0.1m.
Set up twin columns close to goaf side in the step (2), the other side sets up single-column, column away from for 2m, array pitch 0.8m, Setting load is greater than 90kN.
Blasthole drilling, borehole have two rows, borehole depth 2m, borehole before blast mining face feed back in the step (3) Array pitch is also 0.8m;
Wherein tier eye distance is 0.1m from top beam, and inclined angle is 85 °;
Another row's hole spacing top beam is 0.2m, and inclined angle is 75 °.
Preferably, described 750 grams of every hole blashole charge, explosive payload can rule of thumb rule be chosen.
The distance of lag blast mining face section hydraulic prop is not less than 40m, hydraulic prop in the step (2) It does not withdraw temporarily, terminates to start to withdraw hydraulic prop again after mine pressure is stablized after working face extraction.40m, which is converted into, promotes the time It is 8 days, goaf is stablized at this time.
Using technical solution acquisition of technology effect as above are as follows:
The present invention beats jail with wood support between H shaped steel shack, canopy and canopy by setting up by lane, is connect on capplce with timber and is sternly connect Real, lower side is helped using waste metal net waist, is lagged section and is made a call to two hydraulic props by goaf side under capplce, the other side is Single-column carries out strengthening supporting.After having returned material, as top plate voluntarily cannot carry out powder charge caving if inbreak.It is single by H shaped steel shack Pillar body, powder charge caving carry out staying lane.The gob side entry retaining small investment, quick, high efficiency, safety coefficient are high, enhancing mine peace Extremely advantageous one of approach is produced entirely.
Specifically:
(1) present invention will make that worker's difficulty of construction is small, easy to operate, simple process, beat anchor pole and super using advanced coal wall The method of preceding coal wall frame canopy had not only strengthened roadway support but also had been next lane to be stayed to save working hour.
(2) present invention adds timber to combine with individual prop to assemble by H shaped steel shack, both met lane side top plate it is appropriate under It is heavy again can timely and effectively supporting roof.In lane, side overhead caving cuts off the direct top that goaf side is leaned in tunnel in time, effectively The pressure that road-in packing is born is reduced, keeps also achieving the closing in goaf, anti-leak-stopping while Drift stability The spontaneous fire and pernicious gas of wind and coal enter working face.
(3) side is helped using waste metal net waist under H shaped steel shack, realizes the secondary application of material.
(4) application of the invention can make entire exploiting field fully phase out section coal pillar, greatly reduce drivage ratio While entire working section recovery can be made to improve 15% or so, shorten the time in exploiting field, can generally make to adopt under this condition Ten thousand tons of drivage ratios in area tunnel reduce by 25% or so.
Detailed description of the invention
Fig. 1 is gob-side entry retaining method arrangement floor map of the present invention.
Fig. 2 is caving eye schematic diagram of the present invention.
Fig. 3 is gob-side entry retaining support method placement-face schematic diagram of the present invention.
In figure,
21: the first boreholes;22: the second boreholes;23: timber;24: capplce;
31: canopy leg;32: anti-skid base;33: hydraulic prop;34: grillage;35: anti-skidding baffle.
Specific embodiment
It is described further in conjunction with 1 to 3 pair of a specific embodiment of the invention of attached drawing:
Double face conceptual design is as shown in Figure 1.
Supporting scheme is as shown in Fig. 2 Fig. 3, process are as follows: first advance 20m complement anchor pole, array pitch 1.0m, every row four Anchor pole, anchor pole specification are 22 × 2000mm of Φ;Frame canopy, H shaped steel shack first advance coal wall are carried out using the method for advanced coal wall Distance must not exceed 4m.
Before advanced frame canopy, frame canopy region bottom plate spoil is cleared up using hand fit's pneumatic pick, and the spoil cleaned out is by manually turning It is transported to former belt feeder transportation system and is delivered to ground, it is necessary to reality be looked for by the top in tunnel, side, to ensure the safety during frame canopy.On Liang Qian measures head-room, must first be located when not meeting design requirement first, in accordance with middle ray examination drift section width Reason.
When frame canopy, canopy connects Yan Jieshi, canopy with timber on capplce 24 away from portion of side cash, crag living for 0.8m, is looked for before construction Leg 31 must bury real bottom, and canopy leg bottom bracket has anti-skid base 32.H shaped steel shack beam length is 2.2m, and apart from both ends Anti-skidding baffle 35 is processed at 0.20m;Canopy height is 2-2.3m, and bottom end must processing base;The wood on top and waist side is connect on capplce Material, thickness cannot be less than 0.1m.There should be special messenger to observe frame when frame canopy upper beam, it is oblique to prevent frame, beam is lived using hand rest when setting a roof beam in place Son, inaccurate handle are placed on beam.To accomplish that Liangping, leg are neat, push up side when frame canopy to connect tightly, the angle that leg, beam combine is controlled in 8- Between 12 °.
The trapezoidal canopy canopy of I-steel is away from determination: setting the Width of Plastic Zone at coal body edge as S0, then direct top edge roadway direction list The pressure of bit length are as follows:
Q=(LK+S0)hγ
L in formulaKFor span length, 3.4m;S0For the Width of Plastic Zone at coal body edge, 0.12m;H is direct top thickness, 2m;
γ is balkstone density, and 2.5t/m3 will obtain Q=176kN in each parameter substitution formula, the support force P of every frame canopy takes 300kN, the then spacing of the trapezoidal canopy of I-steel are as follows:
L=P/ (nQ)=0.85m
N is safety coefficient in formula, takes 2.If selecting the spacing of trapezoidal canopy for L=0.8m, actual safety coefficient: n' =P/QL'=2.1.
Jail is beaten with wood support between canopy and canopy, every frame canopy is no less than 4 support points, two, every side, and lower side uses waste metal Net waist side prevents the spoil of wall caving, folding side from pouring in main entry.After frame is good, lags section and play two lists by goaf side under capplce Body hydraulic prop 33, the outer supporting of hydraulic prop have grillage 34, and to carry out strengthening supporting to cylindricality formula, the other side is single list Body hydraulic prop, column are not less than 90kN away from the setting load for 2.0m, array pitch 0.8m, strengthening supporting.Setting load is generally 50- 70kN is stayed and is suitably increased under the conditions of lane.In addition, setting load is 90kN.That is the top plate of control pillar about 4m upwards.Relative to bog-head coal For layer, this is direct top range, can inhibit the development of caving zone.For column away from for 2m, this is heading sizes limitation, and array pitch is 0.8m, with canopy away from consistent.
Before working face feed back, old man side is leaned on, the place apart from capplce end 0.1m and 0.2m beats two rows and caunches eye, borehole depth 2.0m, borehole spacing 0.8m, wherein an array pitch is the second borehole 22 from top beam 0.1m, inclined angle is 85 °;Another row It is the first borehole 21 apart from top beam 0.2m, inclined angle is 75 °.Borehole depth depends on the range directly pushed up, relatively In girdle, 2m is zone of reasonableness.Field measurement also turns out that zone of reasonableness is 2m.
After having returned material, if top plate cannot voluntarily carry out powder charge caving if inbreak, every explosive payload is 750g, is manually put Top.
Especially suitable for the shallow coal seam under tight roof, gob side entry retaining produces is gob-side entry retaining method of the present invention The advantage of small area gently inclined thin seam, tunnelling rate substantially reduce, and exploiting field recovery ratio significantly increases, and realize and quickly return It adopts, enhances the purpose of mine safety.The present invention adds timber 23 to combine with individual prop to assemble, both met by lane by H shaped steel shack Top plate it is appropriate sink again can timely and effectively supporting roof.In lane, side overhead caving cuts off tunnel by goaf side in time It directly pushes up, effectively reduces the pressure that road-in packing is born, keep also achieving goaf while Drift stability Closing, preventing from leaking out enters working face with the spontaneous fire of coal and pernicious gas.Side uses waste metal net waist under H shaped steel shack Side, realizes the secondary application of material.
Certainly, described above is only that presently preferred embodiments of the present invention is answered the present invention is not limited to enumerate above-described embodiment When explanation, anyone skilled in the art is all equivalent substitutes for being made, bright under the guidance of this specification Aobvious variant, all falls within the essential scope of this specification, ought to be by protection of the invention.

Claims (1)

1. a kind of small area blasting mining in thin seam working face gob-side entry retaining support method, which is characterized in that small area blasting mining in thin seam Face gob-side entry retaining work using H shaped steel shack and timber progress supporting, strengthening supporting, supporting are carried out using hydraulic prop Method uses following steps:
(1) advance support: the complement anchor pole at advanced blast mining face 20-25m in crossheading;Advanced blast mining face sets up I-shaped Steel canopy;Keep top beam concordant when setting up H shaped steel shack, top is connect on capplce in fact, canopy leg connects on the spot, and front and back is concordant;With wood support between two canopies Stickfast, canopy leg lower part are packed tightly with waste metal net;
Anchor pole array pitch is 1.0-1.2m in the step (1), and four anchor poles of every row, anchor pole specification is 22 × 2000mm of Φ;
Reality is first looked for by the top in tunnel, side before setting up H shaped steel shack in the step (1);The canopy of the H shaped steel shack away from for 0.8m, Yan Jieshi is met with timber on capplce, canopy leg is buried into real bottom, and angle folded by canopy leg capplce is at 8-12 °;
The capplce length of the H shaped steel shack is 2.2m, and is installing anti-skidding baffle additional at the 0.20m of both ends;
Canopy leg height is 2.3m, and bottom end adds pedestal;
The timber on top and waist side is connect on capplce, thickness is not less than 0.1m;
(2) Lagging support: I-shaped steel type frame, which is set, to be finished, and lag blast mining face segment frame sets hydraulic prop strengthening supporting;
In the step (2) close to goaf side set up twin columns, the other side set up single-column, column away from be 2m, array pitch 0.8m, just support Power is greater than 90kN;The distance of lag blast mining face section hydraulic prop is not less than 40m, monomer hydraulic in the step (2) Pillar is not withdrawn temporarily, terminates to start to withdraw hydraulic prop again after mine pressure is stablized after working face extraction;
(3) goaf side caving: after blast mining face has returned material, as top plate voluntarily cannot carry out powder charge caving if inbreak;
Blasthole drilling, borehole have two rows, borehole depth 2m, row spacing before blast mining face feed back in the step (3) It is also 0.8m;Wherein tier eye distance is 0.1m from top beam, and inclined angle is 85 °;Another row's hole spacing top beam is 0.2m, inclined angle are 75 °;750 grams of every hole blashole charge.
CN201511008424.3A 2015-12-29 2015-12-29 A kind of small area blasting mining in thin seam working face gob-side entry retaining support method Active CN105545321B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201511008424.3A CN105545321B (en) 2015-12-29 2015-12-29 A kind of small area blasting mining in thin seam working face gob-side entry retaining support method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201511008424.3A CN105545321B (en) 2015-12-29 2015-12-29 A kind of small area blasting mining in thin seam working face gob-side entry retaining support method

Publications (2)

Publication Number Publication Date
CN105545321A CN105545321A (en) 2016-05-04
CN105545321B true CN105545321B (en) 2019-01-08

Family

ID=55824826

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201511008424.3A Active CN105545321B (en) 2015-12-29 2015-12-29 A kind of small area blasting mining in thin seam working face gob-side entry retaining support method

Country Status (1)

Country Link
CN (1) CN105545321B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105956929B (en) * 2016-05-11 2019-04-09 中国矿业大学 A kind of method of determining girdle alternate heading cross dimensions
CN106640187A (en) * 2016-12-23 2017-05-10 济宁矿业集团有限公司霄云煤矿 Down coal face goaf water dredging structure and dredging method thereof
CN106640148B (en) * 2016-12-27 2018-11-30 山西晋城无烟煤矿业集团有限责任公司 Underground coal mine superelevation tunnel permanent reinforcement technique
CN108049896B (en) * 2017-12-19 2019-04-02 河南力行科创矿山技术开发有限公司 A kind of fully mechanized coal face gob-side entry retaining method
CN109184771B (en) * 2018-11-20 2023-10-24 中煤新集能源股份有限公司 Method for manufacturing flexible shield type reserved return air channel for retracting working face
CN109812269A (en) * 2018-12-27 2019-05-28 天地科技股份有限公司 It is a kind of suitable for second mining working face without pillar mining method
CN113863956B (en) * 2021-09-24 2023-08-22 国家能源集团宁夏煤业有限责任公司 Coal mine underground working face gateway roadway passing method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101737047A (en) * 2008-11-19 2010-06-16 孙广义 Method for mining coal of steeply inclined thin seam
CN101942999A (en) * 2010-08-20 2011-01-12 天地科技股份有限公司 Coal mining method for high-dipping low seam
CN101967992A (en) * 2010-09-17 2011-02-09 山东新矿赵官能源有限责任公司 Different-strength bearing roadside filler for pillar-free mining of thin coal bed
CN103061806A (en) * 2012-12-28 2013-04-24 山东科技大学 Composite roof thin seam fully-mechanized coal mining face gob-side entry retaining method
CN103388488A (en) * 2013-08-21 2013-11-13 大同煤矿集团有限责任公司 Thin seam gob-side entry retaining filling method
CN104047629A (en) * 2014-06-25 2014-09-17 中国矿业大学 Method for extracting gas close to lower coal layer through directional drilling in thin coal seam fully-mechanized coal mining gob-side entry

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101737047A (en) * 2008-11-19 2010-06-16 孙广义 Method for mining coal of steeply inclined thin seam
CN101942999A (en) * 2010-08-20 2011-01-12 天地科技股份有限公司 Coal mining method for high-dipping low seam
CN101967992A (en) * 2010-09-17 2011-02-09 山东新矿赵官能源有限责任公司 Different-strength bearing roadside filler for pillar-free mining of thin coal bed
CN103061806A (en) * 2012-12-28 2013-04-24 山东科技大学 Composite roof thin seam fully-mechanized coal mining face gob-side entry retaining method
CN103388488A (en) * 2013-08-21 2013-11-13 大同煤矿集团有限责任公司 Thin seam gob-side entry retaining filling method
CN104047629A (en) * 2014-06-25 2014-09-17 中国矿业大学 Method for extracting gas close to lower coal layer through directional drilling in thin coal seam fully-mechanized coal mining gob-side entry

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
薄煤层坚硬顶板工作面沿空留巷技术实践;刘坤等;《煤炭科学技术》;20110425;第17-20页

Also Published As

Publication number Publication date
CN105545321A (en) 2016-05-04

Similar Documents

Publication Publication Date Title
CN105545321B (en) A kind of small area blasting mining in thin seam working face gob-side entry retaining support method
WO2020211784A1 (en) Non-pillar automatically formed roadway-based mining method applicable to fully mechanized top-coal caving of thick coal seam
CN107191208B (en) Rigid protection body Support Method in the lane flexible support Ti Yu by gob side entry retaining lane
CN108678769A (en) Deep Gateway anchor note cuts top master control and stays lane method
CN104061001B (en) Gob side entry retaining exploitation support process method
CN102261248B (en) Sill-pillar-free stage caving stopping method based on creasing-type structure
CN104358572B (en) Non-pillar mining technology by spontaneous caving filling roadway at large inclined angle steeply inclined seam
CN105804748B (en) A kind of method of block mining Wall ore under open air transport system
CN105003288B (en) A kind of method and support system of medium-thickness seam gob side entry retaining
CN102661169A (en) Gob-side entry retaining method for anchor bolt network gangue bag wall body for coal mining without pillars
CN102778182A (en) Beside-roadway escribing pressure relief method of roadway driving along gob of small coal pillar influenced by dynamic pressure
CN108286442A (en) Excavation method suitable for a Support System in Soft Rock Tunnels quick closure cyclization of two steps
CN102261249B (en) Creasing-type sill-pillar-free stage caving stopping method based on steel structured artificial top
CN104863591B (en) Goaf controls inbreak and earth's surface filling administering method
CN106194203A (en) A kind of coal-mine soft-rock method for protecting support
CN107035405A (en) One kind is used for the double filling wall constructions of gob side entry retaining and cuts top pressure relief method
CN108915764A (en) A kind of method of reserved tunnel consolidated fill recycling room formula coal column
CN102720498A (en) Gob-side entry retaining mining process for coal face
CN109779652A (en) A kind of expansion of coal-mine soft-rock tailentry is repaired and method for protecting support
CN103437766B (en) In-situ fragmentation mining method
CN107237638A (en) Both wired concealed tunneling structure and its construction method are worn under a kind of
CN110985083B (en) Stoping roadway stack type support supporting system and method
CN102678123A (en) Gob-side entry retaining method for thin coal layer under hard limestone top plate
CN102418528B (en) End ore-drawing caving mining technology with steel concrete composite man-made false roofs
CN106285692B (en) A kind of construction method of gob side entry retaining

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant