CN105544562A - 高陡边坡岩堆整治喷锚网防护施工工艺 - Google Patents
高陡边坡岩堆整治喷锚网防护施工工艺 Download PDFInfo
- Publication number
- CN105544562A CN105544562A CN201510852108.8A CN201510852108A CN105544562A CN 105544562 A CN105544562 A CN 105544562A CN 201510852108 A CN201510852108 A CN 201510852108A CN 105544562 A CN105544562 A CN 105544562A
- Authority
- CN
- China
- Prior art keywords
- construction
- anchor
- slope
- scaffold
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
本发明涉及一种高陡边坡岩堆整治喷锚网防护施工工艺,采用自下而上分台阶施工的方式,先在坡脚搭设脚手架,提供施工作业平台,然后测量放线,确定锚杆钻孔和排水孔位置,其后进行钻孔,制作并安装不同施工区域的大小锚杆以及PVC排水管,采用注浆机进行注浆,保证锚孔注浆密实、饱满。之后进行铺设镀锌机编网,保证机编网铺设紧贴岩面。最后使用喷浆机进行喷砼,务必使喷成面平整、顺直。本工艺采用搭设边坡脚手架来降低施工难度,加快施工进度,保证施工工期要求。在脚手架搭设的平台上进行边坡喷锚防护施工,有效的降低了高边坡喷锚施工的难度,降低了投资,确保了高陡边坡岩堆整治喷锚网施工的安全。
Description
技术领域
本发明属于喷锚网防护施工领域,尤其是一种用于公路、铁路路基高陡边坡喷锚网防护施工工艺。
背景技术
成兰铁路新民隧道出口危岩治理工程高边坡防护工程位于成兰铁路CLZQ-10标段新民隧道出口岩堆处,线位以隧道、桥梁通过该岩堆。隧道出口端DK186+710~+760段山势陡峭,陡崖高差近170m,山体自然坡度75°~85°,局部近直立或倒悬,发育大量危岩、落石。
岩堆体经过光面爆破清方后,露出的千枚岩组成成分复杂,岩性较软,更由于本地区多雨多风,极易二次风化,产生二次危岩、落石,威胁之后的进洞施工和铁路的安全运行。因新民隧道出口岩堆体山势陡峭,施工时人员、机械、材料运输困难。
发明内容
本发明的目的在于克服现有技术的不足之处,提供一种安全可靠,能够加快施工进度的高陡边坡岩堆整治喷锚网防护施工工艺。
本发明解决技术问题所采用的技术方案是:
一种高陡边坡岩堆整治喷锚网防护施工工艺,步骤如下:
⑴搭设脚手架:采用自下而上分台阶施工的方式,先在坡脚搭设脚手架,提供施工作业平台,然后测量放线,确定锚杆钻孔和排水孔位置;
⑵钻孔:钻孔符合设计要求后,用风管将孔内钻屑冲干净;
⑶注浆:钻孔完成后,将注浆管插入孔底,将配置好的水泥砂浆通过注浆泵注入锚杆孔,直到孔内溢出的水泥砂浆与注入的浆比重相同为止;
⑷锚杆和排水管安装:将符合设计要求的锚杆、排水管分别置于注浆孔内和排水孔内;
⑸清理坡面:安装好锚杆和排水管后,除去坡面杂物,为喷射砼作准备;
⑹坡面喷射砼:喷砼强度C25,厚度10cm;
1)初喷:启动喷浆机、空气压缩机向清理好的边坡喷射C25砼,厚度为5cm;
2)挂网:先将镀锌钢丝网挂在初喷砼面上,再将Ф6双向钢筋与锚杆焊接在一起;
3)复喷:镀锌钢丝网挂好后,在镀锌钢丝网上复喷砼。
而且,所述脚手架搭设采用双排双立杆的方式,使用尺寸为钢管,纵距1.4m,横距1.0m,步距1.5m,排架最大搭建单元高度36m,施工范围内铺设4层木脚手板,同时作业1层,每层布置2台钻机,连墙件采用钢管、扣件组成的刚性连墙件。
而且,采用Φ49钻孔。
而且,锚杆采用Φ25HRB400钢筋制作,长3.5m,间距2m。
而且,坡面每3m间距设一排水孔,排水孔上下错开布置,内设长1.0mΦ42PVC花管。
本发明的优点和积极效果是:
1、本工艺采用搭设脚手架进行喷锚施工,提供足够的施工平台,保证了喷锚防护施工的安全和质量,确保工程如期完工。
2、本工艺采用直径的钻孔,插入相应的锚杆后,立即进行注浆施工,能够有效的稳定危岩整治爆破清方区部分区域节理比较发育、岩面较破碎的千枚岩软岩坡面。
3、本工艺采用铺设机编网后喷射混凝土可以有效的提高机编网的使用性能和使用寿命,并且覆盖了爆破清方后产生的新岩面,防止新岩面二次风化产生碎石。
附图说明
图1为喷锚网施工作业布置图
具体实施方式
下面结合附图并通过具体实施例对本发明作进一步详述,以下实施例只是描述性的,不是限定性的,不能以此限定本发明的保护范围。
一种高陡边坡岩堆整治喷锚网防护施工工艺,步骤如下:
1、搭设脚手架:采用自下而上分台阶施工的方式,先在坡脚搭设脚手架,提供施工作业平台,然后测量放线,确定锚杆钻孔和排水孔位置;
2、钻孔:钻孔符合设计要求后,用风管将孔内钻屑冲干净,以防钻屑影响安装锚杆和注浆质量及排水管安装;
3、注浆:钻孔完成后,将注浆管插入孔底,将配置好的水泥砂浆通过注浆泵注入锚杆孔,直到孔内溢出的水泥砂浆与注入的浆比重相同为止;
4、锚杆和排水管安装:将符合设计要求的锚杆(钢筋)、排水管分别置于注浆孔内和排水孔内;
5、安装好锚杆和排水管后,清理坡面,除去坡面杂物,为喷射砼作准备;
6、坡面喷射砼喷砼强度C25,厚度10cm;
1)初喷:启动喷浆机、空气压缩机向清理好的边坡喷射C25砼,厚度为5cm。
2)挂网:先将镀锌钢丝网(2mm)挂在初喷砼面上,再将Ф6双向钢筋与锚杆焊接在一起。
3)复喷:镀锌钢丝网挂好后,在镀锌钢丝网上复喷砼。
脚手架搭设采用双排双立杆的方式,使用尺寸为钢管,纵距1.4m,横距1.0m,步距1.5m,排架最大搭建单元高度36m。施工范围内铺设4层木脚手板,同时作业1层,每层布置2台钻机1(连续5跨内布置1台钻机作业)。连墙件采用钢管、扣件组成的刚性连墙件。为了分解立杆传至基础的竖向力,增设插筋2,插筋入岩0.8m,外露0.4m,插筋与水平面成45度下倾角。排架搭建至6m以上时,增设水平插筋。
喷射C25混凝土厚10cm,分两次机械喷射,中间铺设一层镀锌机编钢丝网。锚孔采用Φ49钻孔,锚杆采用Φ25HRB400钢筋制作,长3.5m,间距2m。坡面每3m间距设一排水孔,排水孔上下错开布置,内设长1.0mΦ42PVC花管。如图1所示。
以上所述的仅是本发明的优选实施方式,应当指出,对于本领域的普通技术人员来说,在不脱离发明构思的前提下,还可以做出若干变形和改进,这些都属于本发明的保护范围。
Claims (5)
1.一种高陡边坡岩堆整治喷锚网防护施工工艺,其特征在于:步骤如下:
⑴搭设脚手架:采用自下而上分台阶施工的方式,先在坡脚搭设脚手架,提供施工作业平台,然后测量放线,确定锚杆钻孔和排水孔位置;
⑵钻孔:钻孔符合设计要求后,用风管将孔内钻屑冲干净;
⑶注浆:钻孔完成后,将注浆管插入孔底,将配置好的水泥砂浆通过注浆泵注入锚杆孔,直到孔内溢出的水泥砂浆与注入的浆比重相同为止;
⑷锚杆和排水管安装:将符合设计要求的锚杆、排水管分别置于注浆孔内和排水孔内;
⑸清理坡面:安装好锚杆和排水管后,除去坡面杂物,为喷射砼作准备;
⑹坡面喷射砼:喷砼强度C25,厚度10cm;
1)初喷:启动喷浆机、空气压缩机向清理好的边坡喷射C25砼,厚度为5cm;
2)挂网:先将镀锌钢丝网挂在初喷砼面上,再将Ф6双向钢筋与锚杆焊接在一起;
3)复喷:镀锌钢丝网挂好后,在镀锌钢丝网上复喷砼。
2.根据权利要求1所述的高陡边坡岩堆整治喷锚网防护施工工艺,其特征在于:
所述脚手架搭设采用双排双立杆的方式,使用尺寸为钢管,纵距1.4m,横距1.0m,步距1.5m,排架最大搭建单元高度36m,施工范围内铺设4层木脚手板,同时作业1层,每层布置2台钻机,连墙件采用钢管、扣件组成的刚性连墙件。
3.根据权利要求1所述的高陡边坡岩堆整治喷锚网防护施工工艺,其特征在于:采用Φ49钻孔。
4.根据权利要求1所述的高陡边坡岩堆整治喷锚网防护施工工艺,其特征在于:锚杆采用Φ25HRB400钢筋制作,长3.5m,间距2m。
5.根据权利要求1所述的高陡边坡岩堆整治喷锚网防护施工工艺,其特征在于:坡面每3m间距设一排水孔,排水孔上下错开布置,内设长1.0mΦ42PVC花管。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510852108.8A CN105544562A (zh) | 2015-11-27 | 2015-11-27 | 高陡边坡岩堆整治喷锚网防护施工工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510852108.8A CN105544562A (zh) | 2015-11-27 | 2015-11-27 | 高陡边坡岩堆整治喷锚网防护施工工艺 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105544562A true CN105544562A (zh) | 2016-05-04 |
Family
ID=55824083
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510852108.8A Pending CN105544562A (zh) | 2015-11-27 | 2015-11-27 | 高陡边坡岩堆整治喷锚网防护施工工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105544562A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106368231A (zh) * | 2016-10-08 | 2017-02-01 | 张献斌 | 一种山区陡坡地段公路桥梁桩基施工方法 |
CN110453766A (zh) * | 2019-08-23 | 2019-11-15 | 瑞派尔(宜昌)科技集团股份有限公司 | 一种弥补供水空档期用的导水系统 |
CN111691528A (zh) * | 2020-05-22 | 2020-09-22 | 中国路桥工程有限责任公司 | 自然灾害风险防范系统 |
CN114319296A (zh) * | 2021-12-13 | 2022-04-12 | 大唐陕西发电有限公司旬阳水力发电厂 | 一种高效处理千枚岩基岩面的施工方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050271478A1 (en) * | 2002-09-19 | 2005-12-08 | Francesco Ferraiolo | Element for forming ground covering, restraining and reinforcing structures |
CN104032758A (zh) * | 2014-05-26 | 2014-09-10 | 中国建筑第八工程局有限公司 | 废弃矿坑内超高边坡加固施工方法 |
CN204000902U (zh) * | 2014-08-11 | 2014-12-10 | 中国路桥工程有限责任公司 | 预应力组合法高速公路高边坡支护结构 |
-
2015
- 2015-11-27 CN CN201510852108.8A patent/CN105544562A/zh active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20050271478A1 (en) * | 2002-09-19 | 2005-12-08 | Francesco Ferraiolo | Element for forming ground covering, restraining and reinforcing structures |
CN104032758A (zh) * | 2014-05-26 | 2014-09-10 | 中国建筑第八工程局有限公司 | 废弃矿坑内超高边坡加固施工方法 |
CN204000902U (zh) * | 2014-08-11 | 2014-12-10 | 中国路桥工程有限责任公司 | 预应力组合法高速公路高边坡支护结构 |
Non-Patent Citations (2)
Title |
---|
吴晓宾: ""喷锚网技术在某高陡边坡防护中的应用"", 《西部探矿工程》 * |
张学利等: ""喷锚网技术在高陡边坡防护中的应用"", 《建筑安全》 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106368231A (zh) * | 2016-10-08 | 2017-02-01 | 张献斌 | 一种山区陡坡地段公路桥梁桩基施工方法 |
CN110453766A (zh) * | 2019-08-23 | 2019-11-15 | 瑞派尔(宜昌)科技集团股份有限公司 | 一种弥补供水空档期用的导水系统 |
CN111691528A (zh) * | 2020-05-22 | 2020-09-22 | 中国路桥工程有限责任公司 | 自然灾害风险防范系统 |
CN111691528B (zh) * | 2020-05-22 | 2021-04-20 | 中国路桥工程有限责任公司 | 自然灾害风险防范系统 |
CN114319296A (zh) * | 2021-12-13 | 2022-04-12 | 大唐陕西发电有限公司旬阳水力发电厂 | 一种高效处理千枚岩基岩面的施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101929340B (zh) | 煤矿井下平斜巷管棚预注浆超前支护施工工艺 | |
CN104963689A (zh) | 隧道三台阶七步开挖方法 | |
CN104032758B (zh) | 废弃矿坑内超高边坡加固施工方法 | |
CN104806272B (zh) | 隧道分流复合式防排水综合系统及其施工方法和使用方法 | |
CN102021911B (zh) | 边坡加固方法及加固结构 | |
CN204098049U (zh) | 一种破碎岩体边坡的防护加固结构 | |
WO2015196872A1 (zh) | 一种固体充填采煤液压支架撤架方法 | |
CN105201513A (zh) | 一种轨道交通的竖井施工方法 | |
CN208136927U (zh) | 一种土质路堑边坡支护结构 | |
CN101985882A (zh) | 高原冻土隧道模筑混凝土刚性初期支护的施工方法 | |
CN105155550B (zh) | 联合支护开挖大厚度强风化砂岩层深基坑的施工方法 | |
CN102562075A (zh) | 一种大断面软弱围岩隧道三台阶六部短距施工方法 | |
CN105544562A (zh) | 高陡边坡岩堆整治喷锚网防护施工工艺 | |
CN101748741A (zh) | 一种混凝土支护结构的施工方法 | |
CN109736334A (zh) | 一种湿陷性黄土边坡支护施工装置及方法 | |
CN108049417A (zh) | 一种高位滑坡体加固处置方法 | |
CN104912088A (zh) | 一种边坡防护结构及其施工方法 | |
CN104831733A (zh) | 拱桥拱座隧洞式大角度斜桩施工方法 | |
CN102400470B (zh) | 坡地高层建筑物多平台深基础施工方法 | |
CN104404979A (zh) | H型桩板墙施工方法 | |
CN205712143U (zh) | 一种矿山环境恢复治理的喷砼飘台结构 | |
CN103774673A (zh) | 一种基坑支护施工工艺 | |
CN113374295A (zh) | 一种老旧钢木结构屋架拆除复建施工方法 | |
CN112012747B (zh) | 一种ⅴ级围岩土质的隧道斜井施工方法 | |
CN108999196A (zh) | 一种桩间网喷混凝土支护施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160504 |
|
RJ01 | Rejection of invention patent application after publication |