CN105507153A - Steel bridge deck composite structure paving method - Google Patents

Steel bridge deck composite structure paving method Download PDF

Info

Publication number
CN105507153A
CN105507153A CN201510850756.XA CN201510850756A CN105507153A CN 105507153 A CN105507153 A CN 105507153A CN 201510850756 A CN201510850756 A CN 201510850756A CN 105507153 A CN105507153 A CN 105507153A
Authority
CN
China
Prior art keywords
steel bridge
bridge deck
asphalt concrete
paving method
paving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510850756.XA
Other languages
Chinese (zh)
Inventor
任自放
任伟
袁洪钊
张伟伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201510850756.XA priority Critical patent/CN105507153A/en
Publication of CN105507153A publication Critical patent/CN105507153A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention relates to a steel bridge deck composite structure paving method. The steel bridge deck composite structure paving method comprises that step 1, the steel bridge deck is derusted by sandblast, and rust-resisting paint is sprayed to the steel bridge deck; step 2, an epoxy asphalt bonding layer is painted on the surface of the steel bridge deck, then epoxy asphalt concrete is paved and serves as a paving bottom layer material, and the paving bottom layer is compacted; step 3, within 2-6 hours after the step 2 is finished and when the temperature of the paving bottom layer material is in a range from 20 DEG C to 50 DEG C, common modified asphalt concrete is laid and rolled on the surface layer. With respect to the steel bridge deck composite structure paving method, the problem that the paving construction period of an existing conventional steel bridge deck epoxy asphalt concrete composite structure is long is overcome, and the steel bridge deck composite structure paving method is simple, quick, good and economical.

Description

A kind of paving method of Steel Bridge composite construction
Technical field
The present invention relates to a kind of paving method of Steel Bridge composite construction.Belong to bridge technology field.
Background technology
The bridge industry develop rapidly of China in recent years, increasing big-span steel bridge builds up.Bridge deck pavement, as the important component part of bridge, has extremely important effect to the durability of bridge, safety.
The pavement material one that current China Steel Bridge generally adopts is epoxy asphalt concrete or SMA bituminous concrete (stone mastic asphalt), and another kind is epoxy asphalt concrete composite construction.
Epoxy asphalt concrete due to good with steel plate following, self-strength is high, thinning pave-load layer can reduce deadweight, it has the performances such as outstanding durable, resistance to chemical attack, Rut resistance simultaneously.But because epoxy asphalt mixture match ratio adopts close-graded type, void content control to cause within 3% bituminous epoxy concrete construct shallow, skid resistance is poor, and two-layer equation bituminous epoxy concrete structure is mated formation that cost is high, maintenance difficult, curing time are long generally needs maintenance about 30 days could open to traffic.
Epoxy asphalt concrete composite construction refers to epoxy asphalt concrete+modified asphalt concrete structure (abbreviation composite construction), the cost of asphalt concrete is then much cheap relative to epoxy asphalt concrete, easy to maintenance, construction technology is simple, but poor with steel plate following, intensity is low, should not as bottom paving structure, therefore China's Steel Bridge adopts pavement material to be composite construction.Conventional composite construction and paving method still follow traditional method: brush bonding oil need maintenance 2-3 days after having laid first floor epoxy asphalt concrete bottom after, then paved surface Rotating fields after maintenance 1-2 days.Above-mentioned way not only work consuming is time-consuming, increases construction period and operating expenses, and get half the result with twice the effort, effect runs counter to desire, its main cause is:
1, epoxy asphalt concrete performance is different from other bituminous concrete completely, needs the long period of about about 30 days to carry out the process of heat cure chemical reaction, could solidify gradually and reach design strength.
2, in its solidify reaction process, also need a metastable temperature environment, and temperature is higher, reaction is faster, intensity is higher, and maintenance and brushing bond in the 5-7 days times of oil after conventional primer epoxy asphalt concrete is laid, bottom temperature of mating formation declines, and slowly, intensity reduces, adds curing time in solidification.
3, after bottom is mated formation in several days, again carry out secondary when epoxy asphalt concrete does not also reach intensity and mat formation, the main equipment such as paver, road roller can cause larger damage to substructure.
Summary of the invention
The object of the invention is to overcome above-mentioned deficiency, provide a kind of paving method of Steel Bridge composite construction, the method overcomes the defect that existing traditional Steel Bridge epoxy asphalt concrete composite construction is mated formation, the effect reach simple, fast, good, economizing and object.
The object of the present invention is achieved like this:
A paving method for Steel Bridge composite construction, comprises the following steps:
Step 1, by steel bridge deck derusting by sandblasting, rust prevention by applying liquid material paint;
Step 2, at steel bridge deck external coating bituminous epoxy tack coat, epoxy asphalt concrete of then mating formation, as primer of mating formation, the bottom and compacting is mated formation;
Step 3, in 2-6 hour that terminates in step 2, mat formation primer temperature 20-50 DEG C time, carry out that surface layer modified asphalt is concrete to pave and roll.
The paving method of a kind of Steel Bridge composite construction of the present invention, is characterized in that: the epoxy asphalt concrete of described bottom, its bitumen aggregate ratio oil content is 7%-9%.
The paving method of a kind of Steel Bridge composite construction of the present invention, is characterized in that: after completing steps 2, and interim lane plate can be laid in the haul track of carrying out surface layer structure laying.
Compared with prior art, the invention has the beneficial effects as follows:
1, the paving method of a kind of Steel Bridge composite construction of the present invention, compared with existing bridge floor composite construction paving method, can reduce the bonding oil of nearly half, under the prerequisite of quality that fully ensures to mat formation, significantly reduce cost; Not only simplify working programme but also decrease time of middle extraordinary maintenance.
2, the paving method of a kind of Steel Bridge composite construction of the present invention, bottom epoxy asphalt concrete is when just complete (2-6 hour), temperature are in 20-50 degree left and right for final pressure, directly carry out that surface layer modified asphalt is concrete to pave and roll, the surface of bottom epoxy asphalt concrete still has epoxy resin and matrix pitch can for combining with surface material and carrying out synchronous curing reaction; And interval time of mating formation between bottom and surface layer is shorter, less on the curing reaction impact of substructure; Combination between two-layer is also better; By the timely covering of surface layer hard pitch, the reaction of bottom curable epoxide is accelerated, and be combined better with steel facing and surface layer structure, intensity is higher, and quality is more excellent, more remarkable effect.
3, the paving method of a kind of Steel Bridge composite construction of the present invention, after bottom epoxy asphalt concrete is mated formation, do not need middle extraordinary maintenance, therefore retardation of curing is caused to react after avoiding the cooling of bottom epoxy asphalt concrete, the epoxy asphalt concrete of bottom obtains the hard pitch covering of surface layer in time simultaneously, thus accelerate solidify reaction process, therefore make the normal pass time advance to about 3 days from about 30 days, improve economic benefit and social benefit.
Detailed description of the invention
The present invention relates to a kind of paving method of Steel Bridge composite construction, the described primer for deck paving is epoxy asphalt concrete, and the surface material of mating formation is modified asphalt concrete.
The paving method step of a kind of Steel Bridge of the present invention composite construction is as follows:
Step 1, by steel bridge deck derusting by sandblasting, rust prevention by applying liquid material paint;
Step 2, at steel bridge deck external coating bituminous epoxy tack coat, epoxy asphalt concrete of then mating formation, as primer of mating formation, the bottom and compacting is mated formation;
Step 3, in 2-6 hour that terminates in step 2, mat formation primer temperature 20-50 DEG C time, carry out that surface layer modified asphalt is concrete to pave and roll;
Preferably, the epoxy asphalt concrete of described bottom, its bitumen aggregate ratio oil content is 7%-9%.
Preferably, after completing bottom epoxy asphalt concrete of mating formation, also should can lay interim lane plate on the haul track of carrying out surface layer structure laying, prevent from polluting substructure and destroying.
Operating principle: after laying bottom epoxy asphalt concrete according to a conventional method, according to different material sources and performance indications, bottom mated formation and tool some strength (because bottom temperature at the end of final pressure just of mating formation is still higher, epoxy asphalt concrete intensity rises very fast) and temperature conditions, generally in 2-6 hour, namely carry out paving and rolling of surface layer asphalt concrete, do not need to carry out middle extraordinary maintenance and spread bonding oil on bottom epoxy asphalt concrete, main cause is: because bottom epoxy asphalt concrete is just complete in final pressure, temperature surface about 20 DEG C time still has epoxy resin and matrix pitch can supply combine with surface material and carry out synchronous curing reaction, and interval time of mating formation between bottom and surface layer is shorter, less on the curing reaction impact of substructure, combination between two-layer is also better, through long term test with detect discovery on the spot, by the timely covering of surface layer hard pitch, the reaction of bottom curable epoxide is accelerated, and be combined better with steel facing and surface layer structure, intensity is higher, and quality is more excellent, more remarkable effect.

Claims (3)

1. a paving method for Steel Bridge composite construction, comprises the following steps:
Step 1, by steel bridge deck derusting by sandblasting, rust prevention by applying liquid material paint;
Step 2, at steel bridge deck external coating bituminous epoxy tack coat, epoxy asphalt concrete of then mating formation, as primer of mating formation, the bottom and compacting is mated formation;
Step 3, in 2-6 hour that terminates in step 2, mat formation primer temperature 20-50 DEG C time, carry out that surface layer modified asphalt is concrete to pave and roll.
2. the paving method of a kind of Steel Bridge composite construction according to claim 1, is characterized in that: the epoxy asphalt concrete of described bottom, and its bitumen aggregate ratio oil content is 7%-9%.
3. the paving method of a kind of Steel Bridge composite construction according to claim 1, is characterized in that: after completing steps 2, and interim lane plate can be laid in the haul track of carrying out surface layer structure laying.
CN201510850756.XA 2015-11-30 2015-11-30 Steel bridge deck composite structure paving method Pending CN105507153A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510850756.XA CN105507153A (en) 2015-11-30 2015-11-30 Steel bridge deck composite structure paving method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510850756.XA CN105507153A (en) 2015-11-30 2015-11-30 Steel bridge deck composite structure paving method

Publications (1)

Publication Number Publication Date
CN105507153A true CN105507153A (en) 2016-04-20

Family

ID=55715431

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510850756.XA Pending CN105507153A (en) 2015-11-30 2015-11-30 Steel bridge deck composite structure paving method

Country Status (1)

Country Link
CN (1) CN105507153A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797397A (en) * 2018-09-11 2018-11-13 安徽建筑大学 A kind of reparation construction method suitable for large longitudinal slope bridge floor
CN112627046A (en) * 2020-12-30 2021-04-09 长城海工装备(江苏)有限公司 Assembling method of truss steel bridge

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2304004A1 (en) * 1973-01-27 1974-08-01 Ruettgerswerke Ag DEVICE FOR ROADWAYS, IN PARTICULAR ON BRIDGE BUILDINGS
CN103122608A (en) * 2012-10-12 2013-05-29 中交第三公路工程局有限公司 Steel bridge deck paving structure and construction technology
CN203755157U (en) * 2014-03-25 2014-08-06 宋金博 Highway bridge asphalt concrete bridge deck pavement
CN104452584A (en) * 2014-11-26 2015-03-25 安徽省交通投资集团有限责任公司 Steel bridge deck laying structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2304004A1 (en) * 1973-01-27 1974-08-01 Ruettgerswerke Ag DEVICE FOR ROADWAYS, IN PARTICULAR ON BRIDGE BUILDINGS
CN103122608A (en) * 2012-10-12 2013-05-29 中交第三公路工程局有限公司 Steel bridge deck paving structure and construction technology
CN203755157U (en) * 2014-03-25 2014-08-06 宋金博 Highway bridge asphalt concrete bridge deck pavement
CN104452584A (en) * 2014-11-26 2015-03-25 安徽省交通投资集团有限责任公司 Steel bridge deck laying structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
王勤福等: "京杭运河特大桥钢桥面环氧沥青铺装设计与施工", 《交通科技》 *
陈亚苇: "环氧沥青混凝土铺装早期病害维修方案的选择与实施", 《黑龙江交通科技》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797397A (en) * 2018-09-11 2018-11-13 安徽建筑大学 A kind of reparation construction method suitable for large longitudinal slope bridge floor
CN112627046A (en) * 2020-12-30 2021-04-09 长城海工装备(江苏)有限公司 Assembling method of truss steel bridge

Similar Documents

Publication Publication Date Title
CN102173658B (en) Cement concrete pavement curing agent and preparation method thereof
CN102219441B (en) Wear-resistant, noise-reduction and heat-insulation epoxy resin emulsified asphalt mortar coating
CN105970761B (en) Primary mat formation formula heavy traffic asphalt pavement structure and construction method
CN101775893A (en) Epoxy floor material and installation construction method thereof
CN202323615U (en) Steel bridge road surface pavement structure
CN104499431A (en) Long-life pavement structure for steel bridge deck and pavement method of pavement structure
CN108084720B (en) Embedded anti-skid waterproof fog seal layer and preparation method thereof
CN110184933A (en) A kind of steel box girder bridge floor paving construction method
CN102431246B (en) Skidproof permeable road pad and manufacturing technology thereof
CN104652270A (en) Bridge deck pavement method for orthotropic steel bridge
CN105064207B (en) High-performance steel bridge deck paving structure
CN103966935B (en) ECC (engineered cementitious composite) durable type colored road pavement structure and paving method thereof
CN105507153A (en) Steel bridge deck composite structure paving method
CN106638295A (en) Pavement method of steel bridge deck made from epoxy asphalt
CN103696366B (en) Pavement structure and pavement method of combined steel bridge deck
CN103981813A (en) Method for constructing epoxy asphalt concrete bridge floor
Fowler et al. Long-term performance of polymer concrete for bridge decks
CN108863167B (en) Concrete repairing and protecting method and structure based on asphalt material
CN105694786A (en) Aqueous epoxy bonding agent for carpet bituminous mixture pavement and construction method thereof
CN110983962A (en) Construction process of EPP water-based epoxy bottom-coating closed fiber-reinforced bridge floor waterproof layer
KR100724163B1 (en) Repairing method of bridge or road using waste tire chip
CN203741710U (en) Steel bridge floor paving structure
CN214613596U (en) Pouring type steel bridge deck pavement structure
CN109811656A (en) A kind of making bilayer SMA pitch steel box girder bridge face waterproof and anticorrosion construction technology
CN204418011U (en) The bridge asphalt pavement structure of the triple water-proof system of a kind of rubber asphalt double sum

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160420

RJ01 Rejection of invention patent application after publication