CN105484760A - 大倾角采煤工作面超前支护结构 - Google Patents
大倾角采煤工作面超前支护结构 Download PDFInfo
- Publication number
- CN105484760A CN105484760A CN201610071613.3A CN201610071613A CN105484760A CN 105484760 A CN105484760 A CN 105484760A CN 201610071613 A CN201610071613 A CN 201610071613A CN 105484760 A CN105484760 A CN 105484760A
- Authority
- CN
- China
- Prior art keywords
- anchor cable
- top board
- upper side
- coal face
- section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000003245 coal Substances 0.000 title claims abstract description 23
- 238000004873 anchoring Methods 0.000 claims abstract description 10
- 229910000831 Steel Inorganic materials 0.000 claims description 18
- 239000010959 steel Substances 0.000 claims description 18
- 230000002787 reinforcement Effects 0.000 claims description 6
- 238000005728 strengthening Methods 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 10
- 238000005065 mining Methods 0.000 abstract description 3
- 230000002349 favourable effect Effects 0.000 abstract 1
- 230000003014 reinforcing effect Effects 0.000 abstract 1
- 230000007423 decrease Effects 0.000 description 7
- 239000003795 chemical substances by application Substances 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000011347 resin Substances 0.000 description 2
- 229920005989 resin Polymers 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 238000009423 ventilation Methods 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000003245 working effect Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
Abstract
本发明涉及采煤方法领域,尤其是一种大倾角采煤工作面超前支护结构。本发明所要解决的技术问题是提供一种安全高效的大倾角采煤工作面超前支护结构。本发明解决其技术问题所采用的技术方案是:大倾角采煤工作面超前支护结构,包括异形断面,包括分别设置异形断面顶部的顶板和设置于异形断面侧壁上帮一侧的上帮板,其中所述顶板通过加强锚索和中部锚索与锚索锚固段固定连接,顶板还通过顶板锚杆与锚杆锚固段固定连接;所述上帮板通过上帮锚杆与上帮锚索固定连接,其中顶板与上帮板交汇于顶板与巷道上帮交面线。本方法为高产高效创造了更加有利的条件,尤其适用于大倾角采煤工作面的支护架构之中。
Description
技术领域
本发明涉及采煤方法领域,尤其是一种大倾角采煤工作面超前支护结构。
背景技术
目前,大倾角采煤工作面的超前支护主要采用单体液压支柱和超前液压支架,但这都是沿用近水平采煤工作面的超前支护方式,没有根据大倾角煤层的特点设计出经济实用的超前支护方法。单体液压支柱与其它设备配合作为超前支护使用,具有工人劳动强度大、安全系数小等特点;超前液压支架作为超前支护使用,占用的空间较大,不仅增加掘进成本,也不利于综采设备的运输,经济投入大等特点;而采用大倾角采煤工作面超前支护方法不仅能克服上述缺点,还有利于通风、行人、运输,且投资少,效果好,更重要的是安全可靠。此方法在本矿的多个大倾角采煤工作面使用,效果显著。
发明内容
本发明所要解决的技术问题是提供一种安全高效的大倾角采煤工作面超前支护结构。
本发明解决其技术问题所采用的技术方案是:大倾角采煤工作面超前支护结构,包括异形断面,包括分别设置异形断面顶部的顶板和设置于异形断面侧壁上帮一侧的上帮板,其中所述顶板通过加强锚索和中部锚索与锚索锚固段固定连接,顶板还通过顶板锚杆与锚杆锚固段固定连接;所述上帮板通过上帮锚杆与上帮锚索固定连接,其中顶板与上帮板交汇于顶板与巷道上帮交面线。
进一步的是,所述顶板和上帮板内侧壁上设置有钢筋托梁结构。
进一步的是,包括凸形垫盘和π型钢梁托盘,所述凸形垫盘和π型钢梁托盘与加强锚索位于顶板一侧的端头连接。
进一步的是,包括锚索锁具,所述锚索锁具与中部锚索位于顶板一侧的端头连接。
本发明的有益效果是:与传统的结构相比,本申请的大倾角采煤工作面超前支护结构安全方便可靠;本方法减少了掘进巷道工程量,减少了超前支护的工作量,减少了工人的劳动强度,减少了回采巷道的有效断面积,减少了资金的投入;本方法节约了成本,节约了时间,提高了工作效率,提高了巷道的利用率,提高了安全效率;本方法为高产高效创造了更加有利的条件,尤其适用于大倾角采煤工作面的支护架构之中。
附图说明
图1是本发明的结构示意图。
图2是本发明的π型钢梁托盘的结构示意图。
图中标记为:锚索锚固段1、锚杆锚固段2、顶板锚杆3、加强锚索4、凸形垫盘5、π型钢梁托盘6、锚索锁具7、中部锚索8、异形断面9、钢筋托梁结构10、上帮锚索11、下帮延长线12、顶板与巷道上帮交面线13、金属网14、上帮锚杆15、顶板16、上帮板17。
具体实施方式
下面结合附图对本发明进一步说明。
如图1、图2所示的大倾角采煤工作面超前支护结构,包括异形断面9,包括分别设置异形断面9顶部的顶板16和设置于异形断面9侧壁上帮一侧的上帮板17,其中所述顶板16通过加强锚索4和中部锚索8与锚索锚固段1固定连接,顶板16还通过顶板锚杆3与锚杆锚固段2固定连接;所述上帮板17通过上帮锚杆15与上帮锚索11固定连接,其中顶板16与上帮板17交汇于顶板与巷道上帮交面线13。
在实际建构时,首先需要根据回采工作面通风、运输、行人、地质资料等情况设计出大倾角采煤工作面两巷断面为异形断面9。接下来的,根据围岩特征、常用的煤矿支护材料等,设计出各个锚索以及锚杆的支护参数,同时满足以下要求:A、靠近两帮的顶板16采用顶板锚杆3支护,顶板16其他部分采用顶板锚杆3、加强锚索4、中部锚索8间隔支护;B、巷道的上帮板17采用上帮锚杆15、上帮锚索11等支护。靠近巷道底板的上帮则采用上帮锚杆15支护,其余采用上帮锚杆15、上帮锚索11间隔支护。另外,中部锚索8和加强锚索4必须锚入稳定岩层1m以上,必须用2~3支树脂锚固剂(常采用K2360树脂锚固剂)。中部锚索8、加强锚索4、上帮锚索11锚固段长度不少于1m。中部锚索8和加强锚索4、上帮锚索11的锚固段分别在空间上成阶梯形,并且分别位于巷道下帮下帮延长线12、上帮的延长线之外。根据巷道断面大小,计算出顶板16以及巷道上帮板17共用的钢筋托梁结构10的长度。钢筋托梁结构10采用φ12的圆钢制成,并配合使用相应长度的金属网14。巷道的顶板16使用的锚索托盘采用有中空且弹性强度较高的材料制成,优选π型钢梁托盘6。
在现场施工的巷道掘进时,在临时支护情况下,先垂直于板顶按照设计要求布置锚索(杆)孔后,再铺上金属网14,挂好钢筋托梁结构10、安装上锚索锁具7(顶板锚杆3);之后再支护巷道上帮;上帮采用打设一个锚索(杆)孔就支护一个孔的方法作业。在加强锚索4、中部锚索8依次安装π型钢梁托盘6、凸形垫盘5、锚索锁具7后必须用千斤顶拉紧,使其初锚力达到36MPa以上,上帮锚索11初锚力达到30MPa以上。
为了保证整体结构的稳定性,从而进一步的保证生产的安全进行,可以选择在所述顶板16和上帮板17内侧壁上设置有钢筋托梁结构10。基于同样的构思,如图1所示的,还可以选择增设凸形垫盘5和π型钢梁托盘6,所述凸形垫盘5和π型钢梁托盘6与加强锚索4位于顶板16一侧的端头连接即可,以及选择增设锚索锁具7,所述锚索锁具7与中部锚索8位于顶板16一侧的端头连接。
本发明通过对结构的创新,减少了掘进巷道工程量,减少了超前支护的工作量,减少了工人的劳动强度,与此同时的,还保证了生产的顺利进行。本发明与传统的结构相比有明显的优势,也具有十分广阔的市场推广前景和经济效益。
Claims (4)
1.大倾角采煤工作面超前支护结构,包括异形断面(9),其特征在于:包括分别设置异形断面(9)顶部的顶板(16)和设置于异形断面(9)侧壁上帮一侧的上帮板(17),其中所述顶板(16)通过加强锚索(4)和中部锚索(8)与锚索锚固段(1)固定连接,顶板(16)还通过顶板锚杆(3)与锚杆锚固段(2)固定连接;所述上帮板(17)通过上帮锚杆(15)与上帮锚索(11)固定连接,其中顶板(16)与上帮板(17)交汇于顶板与巷道上帮交面线(13)。
2.如权利要求1所述的大倾角采煤工作面超前支护结构,其特征在于:所述顶板(16)和上帮板(17)内侧壁上设置有钢筋托梁结构(10)。
3.如权利要求2所述的大倾角采煤工作面超前支护结构,其特征在于:包括凸形垫盘(5)和π型钢梁托盘(6),所述凸形垫盘(5)和π型钢梁托盘(6)与加强锚索(4)位于顶板(16)一侧的端头连接。
4.如权利要求2所述的大倾角采煤工作面超前支护结构,其特征在于:包括锚索锁具(7),所述锚索锁具(7)与中部锚索(8)位于顶板(16)一侧的端头连接。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610071613.3A CN105484760B (zh) | 2016-02-01 | 2016-02-01 | 大倾角采煤工作面超前支护结构 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610071613.3A CN105484760B (zh) | 2016-02-01 | 2016-02-01 | 大倾角采煤工作面超前支护结构 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105484760A true CN105484760A (zh) | 2016-04-13 |
CN105484760B CN105484760B (zh) | 2019-05-28 |
Family
ID=55672005
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610071613.3A Expired - Fee Related CN105484760B (zh) | 2016-02-01 | 2016-02-01 | 大倾角采煤工作面超前支护结构 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105484760B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109681248A (zh) * | 2018-12-24 | 2019-04-26 | 中国矿业大学 | 一种注浆锚索超前支护方法 |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4091628A (en) * | 1976-09-27 | 1978-05-30 | Jay Hilary Kelley | Prestressed elastic arched mine roof support |
CN201190570Y (zh) * | 2008-03-12 | 2009-02-04 | 三一重型装备有限公司 | 倾斜顶板的巷道超前支护支架组 |
CN201560781U (zh) * | 2009-11-04 | 2010-08-25 | 沂源县鲁村煤矿有限公司 | 半煤岩沿空留巷巷道支护装置 |
CN103061788A (zh) * | 2013-01-11 | 2013-04-24 | 江苏建筑职业技术学院 | 一种松软破碎巷道顶板的加固支护方法 |
CN203145954U (zh) * | 2013-02-05 | 2013-08-21 | 神华集团有限责任公司 | 一种锚杆支护系统 |
CN103615273A (zh) * | 2013-12-04 | 2014-03-05 | 山东大学 | 方钢约束混凝土拱架壁后充填锚注支护体系及施工方法 |
CN103670426A (zh) * | 2013-12-31 | 2014-03-26 | 四川川煤华荣能源股份有限公司花山煤矿 | 大倾角、大断面巷道施工方法 |
CN104100287A (zh) * | 2013-04-15 | 2014-10-15 | 四川省煤炭产业集团有限责任公司 | 一种新型自移式采煤巷道超前支护支架 |
CN104265295A (zh) * | 2014-09-11 | 2015-01-07 | 四川达竹煤电(集团)有限责任公司铁山南煤矿 | 倾斜中厚煤层无人工巷旁充填及无煤柱沿空留巷方法 |
CN104358572A (zh) * | 2014-09-11 | 2015-02-18 | 四川达竹煤电(集团)有限责任公司铁山南煤矿 | 大倾角急倾斜煤层自然垮落充填护巷无煤柱开采技术 |
-
2016
- 2016-02-01 CN CN201610071613.3A patent/CN105484760B/zh not_active Expired - Fee Related
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4091628A (en) * | 1976-09-27 | 1978-05-30 | Jay Hilary Kelley | Prestressed elastic arched mine roof support |
CN201190570Y (zh) * | 2008-03-12 | 2009-02-04 | 三一重型装备有限公司 | 倾斜顶板的巷道超前支护支架组 |
CN201560781U (zh) * | 2009-11-04 | 2010-08-25 | 沂源县鲁村煤矿有限公司 | 半煤岩沿空留巷巷道支护装置 |
CN103061788A (zh) * | 2013-01-11 | 2013-04-24 | 江苏建筑职业技术学院 | 一种松软破碎巷道顶板的加固支护方法 |
CN203145954U (zh) * | 2013-02-05 | 2013-08-21 | 神华集团有限责任公司 | 一种锚杆支护系统 |
CN104100287A (zh) * | 2013-04-15 | 2014-10-15 | 四川省煤炭产业集团有限责任公司 | 一种新型自移式采煤巷道超前支护支架 |
CN103615273A (zh) * | 2013-12-04 | 2014-03-05 | 山东大学 | 方钢约束混凝土拱架壁后充填锚注支护体系及施工方法 |
CN103670426A (zh) * | 2013-12-31 | 2014-03-26 | 四川川煤华荣能源股份有限公司花山煤矿 | 大倾角、大断面巷道施工方法 |
CN104265295A (zh) * | 2014-09-11 | 2015-01-07 | 四川达竹煤电(集团)有限责任公司铁山南煤矿 | 倾斜中厚煤层无人工巷旁充填及无煤柱沿空留巷方法 |
CN104358572A (zh) * | 2014-09-11 | 2015-02-18 | 四川达竹煤电(集团)有限责任公司铁山南煤矿 | 大倾角急倾斜煤层自然垮落充填护巷无煤柱开采技术 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109681248A (zh) * | 2018-12-24 | 2019-04-26 | 中国矿业大学 | 一种注浆锚索超前支护方法 |
CN109681248B (zh) * | 2018-12-24 | 2020-01-17 | 中国矿业大学 | 一种注浆锚索超前支护方法 |
Also Published As
Publication number | Publication date |
---|---|
CN105484760B (zh) | 2019-05-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103161480B (zh) | 主动支撑巷旁充填沿空留巷的方法 | |
CN101514633B (zh) | 无巷旁支护的沿空留巷工艺 | |
CN103410515B (zh) | 一种三软煤层往复式无煤柱综采方法 | |
CN103233751B (zh) | 极软弱顶板煤巷双层锚固平衡拱支护系统 | |
CN104234749B (zh) | 一种综采工作面大断面回撤通道围岩控制方法 | |
CN104763434B (zh) | 一种无煤柱双巷掘进方法 | |
CN108087008B (zh) | 一种三软煤层沿空巷道支护方法 | |
CN103216244B (zh) | 巷道软弱顶板锚固梁-拱组合结构支护系统及支护方法 | |
CN103758529A (zh) | 一种煤矿沿空留巷巷旁支护方法 | |
CN101922292A (zh) | 煤矿沿空留巷巷旁分段承载不等强支护原理及应用 | |
CN105781597A (zh) | 深井软岩沿空留巷巷内锚注加固方法 | |
CN109209490B (zh) | 一种矸石充填辅助末采阶段工作面回撤方法 | |
CN103244122A (zh) | 沿空掘巷煤柱稳定性三位一体耦合支护控制方法 | |
CN110529144A (zh) | 一种小断面回采巷道混合式超前支护方法 | |
CN104533419B (zh) | 一种部分回收大煤柱残煤的方法 | |
CN104074534B (zh) | 一种综采/综放工作面的沿空留巷方法 | |
CN109630168A (zh) | 综采放顶煤工作面巷道沿底板岩层布置及支护方式 | |
CN103850708A (zh) | 一种采用混凝土充填体的沿空留巷方法 | |
CN102852532B (zh) | 一种防止煤壁片帮的注浆方法 | |
CN109707422A (zh) | 一种沿空送巷小煤柱高压注浆加固支护方法 | |
CN109630171A (zh) | 一种沿顶巷道沿底板布置卸压巷控制底鼓的方法 | |
CN104790991A (zh) | 一种回采巷道围岩强长顶锚固技术 | |
CN102493819B (zh) | 一种控制煤层巷道围岩稳定性的方法 | |
CN210948737U (zh) | 薄煤层倾斜小断面半煤岩巷的高效快速掘进巷道支护设施 | |
CN105484760A (zh) | 大倾角采煤工作面超前支护结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 617066 No. 11, taojiadu Middle Road, West District, Panzhihua City, Sichuan Province Patentee after: Huashan coal mine of Sichuan Chuanmei Huarong Energy Co.,Ltd. Address before: 617066 No. 11, taojiadu Middle Road, West District, Panzhihua City, Sichuan Province Patentee before: HUASHAN COAL MINING OF SICHUAN COAL GROUP HUARONG ENERGY Co.,Ltd. |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |