CN105464361B - Scaffolding board binding device - Google Patents

Scaffolding board binding device Download PDF

Info

Publication number
CN105464361B
CN105464361B CN201511024427.6A CN201511024427A CN105464361B CN 105464361 B CN105464361 B CN 105464361B CN 201511024427 A CN201511024427 A CN 201511024427A CN 105464361 B CN105464361 B CN 105464361B
Authority
CN
China
Prior art keywords
fixture block
ratchet
wire rope
steel wire
scaffolding board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201511024427.6A
Other languages
Chinese (zh)
Other versions
CN105464361A (en
Inventor
马刚
王进
郭建新
王建兴
李莉
刘沅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SEPCO Electric Power Construction Co Ltd
Original Assignee
NINGXIA ELECTRIC POWER BUILDING AND INSTALLING PROJECT Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NINGXIA ELECTRIC POWER BUILDING AND INSTALLING PROJECT Co filed Critical NINGXIA ELECTRIC POWER BUILDING AND INSTALLING PROJECT Co
Priority to CN201511024427.6A priority Critical patent/CN105464361B/en
Publication of CN105464361A publication Critical patent/CN105464361A/en
Application granted granted Critical
Publication of CN105464361B publication Critical patent/CN105464361B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/28Clips or connections for securing boards
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G7/00Connections between parts of the scaffold
    • E04G7/02Connections between parts of the scaffold with separate coupling elements
    • E04G7/28Clips or connections for securing boards
    • E04G2007/285Clips or connections for securing boards specially adapted for toe boards

Abstract

The present invention relates to a kind of scaffolding board binding device.It is characterized in:Including fixed substrate (5), hook-shaped steel pipe snap ring (9) and set lever (12) is separately installed with the fixation substrate (5), also include locker (13), one end of the locker (13) is arranged on set lever (12) and its other end is removably mounted on steel pipe snap ring (9);Rotating ratchet (4) also is installed by the way that rotating shaft is rotatable on the fixation substrate (5), one end of steel wire rope (1) is wound with the rotating ratchet (4), the other end of the steel wire rope (1) is connected with a cylinder fixture block (10), and the cylinder neck (11) coordinated with the cylinder fixture block (10) is provided with the fixation substrate (5).The invention provides being a kind of specific purpose tool that colligation is carried out to scaffolding board, Binding material uses steel wire rope, and improving bud grafting uses special locking member.

Description

Scaffolding board binding device
Technical field
The present invention relates to a kind of scaffolding board binding device.
Background technology
Steel pipe scaffold is commonly used during engineering construction high and medium operation, steel pipe scaffold is that a kind of provisional auxiliary is built Instrument is built, the scaffold board platform laid can provide the protection of safety for the workmen of work high above the ground.The laying of scaffold board After the completion of need just colligation, cumbersome using traditional iron wire process of binding, colligation efficiency is low, and iron wire used in colligation operation is reclaimed After can not reuse, construction cost is high.
The content of the invention
It is an object of the invention to provide a kind of scaffolding board binding device, the scaffold that can complete various width is tied up Prick, and the intensity of colligation is high, speed is fast, it is good to save material, adaptability.
A kind of scaffolding board binding device, it is particular in that:Including fixed substrate, distinguish on the fixation substrate Hook-shaped steel pipe snap ring and set lever, in addition to locker be installed, one end of the locker be arranged on set lever and Its other end is removably mounted on steel pipe snap ring;Rotation spine also is installed by the way that rotating shaft is rotatable on the fixation substrate Wheel, is wound with one end of steel wire rope, the other end of the steel wire rope is connected with a cylinder fixture block on the rotating ratchet, solid at this Determine to be provided with the cylinder neck coordinated with the cylinder fixture block on substrate, also pacify on the fixation substrate by the rotating ratchet in addition Equipped with ratchet fixture block.
The hollow tubule of one section of circular arc is wherein set with a steel cord.
Wherein also include fixture block spring, the two ends of the fixture block spring are connected with fixed substrate and ratchet fixture block respectively, and Ratchet fixture block is arranged on fixed substrate by fixture block fixing axle.
Set lever is wherein installed with rotating ratchet.
Wirerope-winding groove is provided with wherein on rotating ratchet.
The invention provides being a kind of specific purpose tool that colligation is carried out to scaffolding board, Binding material is using steel wire rope replacement Traditional iron wire, improving bud grafting can use special locking member.Apparatus of the present invention compact structure, be easy to carry, it is simple to operate, tie up Prick intensity and be higher than traditional binding method.Apparatus of the present invention, which can be repeated several times, to be used, and effectively reduces construction cost.Present invention dress Put light and handy, it is easy to operate, be conducive to operation of ascending a height, reduce the potential safety hazard in work progress.The present invention is easy to operate, can carry High construction efficiency, can meet the demand of engineering construction progress.
Brief description of the drawings
Accompanying drawing 1 is the structural representation of the present invention, and figure includes steel wire rope 1, rotary handle 2, fixing bolt 3, rotation spine Wheel 4, fixed substrate 5, fixture block spring 6, ratchet fixture block 7, fixture block fixing axle 8, snap ring 9, cylinder fixture block 10, neck 11, locking Handle 12, locker 13, hollow tubule 14.
Embodiment
As shown in figure 1, the invention provides a kind of scaffolding board binding device, including fixed substrate 5, in the fixed base Hook-shaped steel pipe snap ring 9 and set lever 12, in addition to locker 13, one end peace of the locker 13 are separately installed with plate 5 On set lever 12 and its other end is removably mounted on steel pipe snap ring 9;Can also by rotating shaft on the fixation substrate 5 Rotation the one end for being provided with rotating ratchet 4, steel wire rope 1 being wound with the rotating ratchet 4, the other end of the steel wire rope 1 with One cylinder fixture block 10 is connected, and the cylinder neck 11 coordinated with the cylinder fixture block 10 is provided with the fixation substrate 5, in addition Ratchet fixture block 7 is also equipped with the fixation substrate 5 on the side of rotating ratchet 4.
The hollow tubule 14 of one section of circular arc is wherein set with steel wire rope 1.
Wherein also include fixture block spring 6, the two ends of the fixture block spring 6 are connected with fixed substrate 5 and ratchet fixture block 7 respectively, And ratchet fixture block 7 is arranged on fixed substrate 5 by fixture block fixing axle 8.
Set lever 12 is wherein installed with rotating ratchet 4.
The winding groove of steel wire rope 1 is provided with wherein on rotating ratchet 4.
Binding material in the present invention uses φ 2mm steel wire rope 1, and locking member uses common carbon steel.Present invention bag Enclosing wire rope 1, the fixed composition such as substrate 5 and set lever 12 mounted thereto, rotating ratchet 4, ratchet fixture block 7, snap ring 9. Steel wire rope 1 of the present invention is fixed on ratchet, and ratchet is provided with the winding groove of steel wire rope 1, by rotating ratchet, is carried out steel wire rope 1 and is grown The regulation of degree.Ratchet of the present invention is provided with locking device, by the cooperation of rotating ratchet and locking device, reaches tying up for scaffold Prick and fasten.Fixing bolt 3 is used to install the parts such as steel wire rope block.
Rotating ratchet 4, steel pipe snap ring 9, locker 13 in the present invention are arranged on fixed substrate 5 by bolt respectively, spine Take turns fixture block 7 to be arranged on fixed substrate 5 by fixing axle, rotating ratchet 4 can be rotated on fixed substrate 5.The one of steel wire rope 1 End is fixed on rotating ratchet 4, and the other end is fixed with cylinder fixture block 10.Hollow tubule 14 is through on steel wire rope 1.Set lever 12 are fixed on rotating ratchet 4.
The present invention application method and operation principle be:
In the present invention, using the special binding tool of scaffolding board, embodiment is to take out cylinder from cylinder neck 11 Body fixture block 10, hollow tubule 14 is stuck in the side of square steel tube under scaffolding board, by bottom ratchet wheel fixture block 7, the adjustment steel of rotary handle 2 Cord 1 arrives optimum length, and steel wire rope 1 is passed through on scaffolding board, the steel pipe that steel pipe snap ring 9 is stuck in scaffolding board opposite side, Locker 13 is stuck on steel pipe snap ring 9, set lever 12 is pressed, by bottom ratchet wheel fixture block 7, the adjustment steel wire of rotary handle 2 is screwed Rope 1 until firmly unclamp ratchet fixture block 7 afterwards by scaffolding board colligation.

Claims (5)

1. a kind of scaffolding board binding device, it is characterised in that:Including fixed substrate (5), distinguish on the fixation substrate (5) Hook-shaped steel pipe snap ring (9) and set lever (12), in addition to locker (13) are installed, one end of the locker (13) is installed On set lever (12) and its other end is removably mounted on steel pipe snap ring (9);Also by turning on the fixation substrate (5) Axle is rotatable to be provided with rotating ratchet (4), and one end of steel wire rope (1), the steel wire rope are wound with the rotating ratchet (4) (1) the other end is connected with a cylinder fixture block (10), is provided with and is coordinated with the cylinder fixture block (10) on the fixation substrate (5) Cylinder neck (11), be also equipped with ratchet fixture block (7) on the other fixation substrate (5) of the rotating ratchet (4) in addition.
2. scaffolding board binding device as claimed in claim 1, it is characterised in that:Wherein it is set with steel wire rope (1) The hollow tubule (14) of one section of circular arc.
3. scaffolding board binding device as claimed in claim 1, it is characterised in that:Wherein also include fixture block spring (6), should The two ends of fixture block spring (6) are connected with fixed substrate (5) and ratchet fixture block (7) respectively, and ratchet fixture block (7) is solid by fixture block Dead axle (8) is arranged on fixed substrate (5).
4. scaffolding board binding device as claimed in claim 1, it is characterised in that:It is fixed wherein on rotating ratchet (4) Set lever (12) is installed.
5. the scaffolding board binding device as described in any one in Claims 1-4, it is characterised in that:Wherein in rotation Ratchet (4) is provided with steel wire rope (1) winding groove.
CN201511024427.6A 2015-12-31 2015-12-31 Scaffolding board binding device Active CN105464361B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201511024427.6A CN105464361B (en) 2015-12-31 2015-12-31 Scaffolding board binding device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201511024427.6A CN105464361B (en) 2015-12-31 2015-12-31 Scaffolding board binding device

Publications (2)

Publication Number Publication Date
CN105464361A CN105464361A (en) 2016-04-06
CN105464361B true CN105464361B (en) 2017-10-03

Family

ID=55602476

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201511024427.6A Active CN105464361B (en) 2015-12-31 2015-12-31 Scaffolding board binding device

Country Status (1)

Country Link
CN (1) CN105464361B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110778100B (en) * 2019-10-17 2021-12-28 国网河北省电力有限公司衡水供电分公司 Binding device for intersection point of wooden rod

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2864980B1 (en) * 2004-01-12 2006-08-11 Macc DEVICE FOR ADJUSTING, LOCKING AND UNLOCKING BODY BODY BRACKETS ON THE FLOOR SUPPORT BRACKET OF A WALL CONSOLE OR SCALE LATCH.
CN1844609A (en) * 2005-04-10 2006-10-11 李超 Building scaffold rope fastener
CN200961352Y (en) * 2006-07-18 2007-10-17 李占杰 Fixing device for scaffold
JP2009012799A (en) * 2007-07-03 2009-01-22 Yasunari Masumoto Fastening band
JP2011220082A (en) * 2010-04-05 2011-11-04 Tabata Biken:Kk Scaffold board clamp
CN201992195U (en) * 2010-12-09 2011-09-28 四川省晟茂建设有限公司 Cable fastener for scaffolding
CN203008350U (en) * 2012-12-29 2013-06-19 广西建工集团第三建筑工程有限责任公司 Safety belt fixing device for clip-holding steel-tube scaffold
CN203701569U (en) * 2013-11-29 2014-07-09 大连船舶重工集团有限公司 Special locking piece for fixing scaffold floor of scaffold
CN203654715U (en) * 2014-01-20 2014-06-18 古锦光 Scaffold fastener
CN205330147U (en) * 2015-12-31 2016-06-22 宁夏电力建设工程公司 Scaffold is ligature device for board

Also Published As

Publication number Publication date
CN105464361A (en) 2016-04-06

Similar Documents

Publication Publication Date Title
CN104110119B (en) A kind of construction ceiling suspension rod locating mounting method and easy device
CN204470473U (en) Screw concrete stirrup coiling shaped device
CN103618258B (en) A kind of electric transmission line erection tightener
CN105464361B (en) Scaffolding board binding device
CN103386381A (en) Mining long-distance paint spraying device
CN207134729U (en) A kind of parallel groove clamp installation tool
CN202250111U (en) Supporting tool
CN205330147U (en) Scaffold is ligature device for board
CN205664033U (en) Clamp device
CN201103200Y (en) Coiled material work car
CN206279771U (en) A kind of smart master fixture
CN202832296U (en) Drill rod lifting device on drilling equipment
CN202825086U (en) Adjustable type manual position changing machine capable of conveniently welding
CN103247966A (en) High-voltage aerial work elevator
CN204809753U (en) Turn -buckle is salvageed to electric power
CN203445577U (en) Cable drum rapid wire releaser
RU138511U1 (en) ELECTRIC SUPPORT JACK
CN203867147U (en) Construction ceiling lifting rod positioning installing method and simple device
CN210171757U (en) Novel spraying equipment is used in steel sheet construction
CN207810748U (en) Bar automatic aligning device
CN204265361U (en) Workover rig winch steel rope live line head locker
CN204152175U (en) Sizing railroad track shaped steel Mobile operating platform
CN204201824U (en) A kind of bulb erecting device
CN214689465U (en) Hydraulic column moving device
CN218844234U (en) Tunnel segment drilling device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 750001, No. 459, Fenghuang South Street, Xingqing District, the Ningxia Hui Autonomous Region, Yinchuan

Patentee after: China Power Construction Ningxia Engineering Co., Ltd.

Address before: 750001, No. 459, Fenghuang South Street, Xingqing District, the Ningxia Hui Autonomous Region, Yinchuan

Patentee before: Ningxia Electric Power Building and Installing Project Company

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20190508

Address after: 250000 Building No. 5, No. 3 District, Hanyu Financial and Business Center, Jinan City, Shandong Province

Patentee after: China Electric Construction Group Shandong Electric Power Construction Co., Ltd.

Address before: 750001 No. 459 South Fenghuang Street, Xingqing District, Yinchuan City, Ningxia Hui Autonomous Region

Patentee before: China Power Construction Ningxia Engineering Co., Ltd.

TR01 Transfer of patent right