CN105436285B - It is a kind of to increase the swollen building mortion of upsetting and method of tee branch height - Google Patents

It is a kind of to increase the swollen building mortion of upsetting and method of tee branch height Download PDF

Info

Publication number
CN105436285B
CN105436285B CN201510942278.5A CN201510942278A CN105436285B CN 105436285 B CN105436285 B CN 105436285B CN 201510942278 A CN201510942278 A CN 201510942278A CN 105436285 B CN105436285 B CN 105436285B
Authority
CN
China
Prior art keywords
axial thrust
drift
pipe
built
cavity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510942278.5A
Other languages
Chinese (zh)
Other versions
CN105436285A (en
Inventor
肖小亭
陈名涛
肖可畏
崔晓辉
章争荣
程永奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong University of Technology
Original Assignee
Guangdong University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong University of Technology filed Critical Guangdong University of Technology
Priority to CN201510942278.5A priority Critical patent/CN105436285B/en
Publication of CN105436285A publication Critical patent/CN105436285A/en
Application granted granted Critical
Publication of CN105436285B publication Critical patent/CN105436285B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21DWORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21D26/00Shaping without cutting otherwise than using rigid devices or tools or yieldable or resilient pads, i.e. applying fluid pressure or magnetic forces
    • B21D26/02Shaping without cutting otherwise than using rigid devices or tools or yieldable or resilient pads, i.e. applying fluid pressure or magnetic forces by applying fluid pressure
    • B21D26/033Deforming tubular bodies
    • B21D26/037Forming branched tubes

Abstract

The present invention is the swollen building mortion of upsetting and method of a kind of increase tee branch height.Including the first axial thrust drift, second axial thrust drift, first replenishing valve, second replenishing valve, shaping dies, back pressure drift, pipe, built-in plug etc., pipe is provided with three ports communicated respectively with tube chamber set by pipe, built-in plug is put into pipe, and pass through the first port and second port of pipe, pipe is placed in shaping dies, one end of first axial thrust drift and the first port of pipe are touched, one end of second axial thrust drift and the second port of pipe are touched, cavity set by cavity set by first axial thrust drift and the second axial thrust drift is communicated with the tube chamber of pipe, highly pressurised liquid is by set by the second replenishing valve energy topping up to the second axial thrust drift in cavity, back pressure drift is installed on shaping dies, one end of back pressure drift and the 3rd port of pipe are touched.The problems such as present invention solves thinning thickness during branch pipe bulging and feed supplement difficulty and easily corrugation and ruptured.

Description

It is a kind of to increase the swollen building mortion of upsetting and method of tee branch height
Technical field
The present invention is the swollen building mortion of upsetting and method of a kind of increase tee branch height, belongs to increase tee branch height The swollen building mortion of upsetting and method innovative technology.
Background technology
Traditional three-way pipe(Fig. 1)It is most of to use casting, be welded to connect shaping and the making of expansion forming technique, extensive use The fields such as chemical industry, daily life.In above-mentioned three kinds of manufacturing process, casting is forming technology the simplest, can obtain compared with The tee pipe fitting of complicated and higher branch pipe, but the characteristics of due to casting technique itself, its be molded three-way pipe material therefor and into Quality of item after shape, which is limited in certain scope, to be used;The technique for being welded to connect figuration manufacture three-way pipe is first in supervisor Upper drilling, then by branch pipe welding to supervisor, forms three-way pipe.Relative to casting three-way plumber's skill, being welded to connect shaping should High-quality tubing can be carried out being welded to connect shaping, and the height of branch pipe does not have any limitation, but the process program shortcoming be by In perforate is again by branch pipe welding on supervisor on supervisor, the sealing wire of so supervisor and branch pipe is exactly that a complicated space is bent Line, just because of the presence of space sealing wire, easily produces welding slag, hole in welding region, causes weld seam to be corroded, and causes leakage Water problems occurs;In order to overcome the shortcoming of casting and welding tee pipe, branch is formed it into using inner high voltage is subject to straight-through tubing The method of pipe can obtain the three-way pipe of monoblock type.Because inner high voltage formation three-way pipe is obtained by the method for Plastic Forming, institute It is good with its quality, the deficiency that casting and welding method are brought to product quality is overcome, this is also much to use three-way pipe at present Occasion wish apply expansion forming three-way pipe the reason for one of.Therefore the method for internal high pressure forming three-way pipeline is also closed Note and attention.However, the method for existing use internal high pressure forming three-way pipe, due to forming branch pipe by inner high voltage in straight-through tubing During generally branch pipe wall thickness it is thinning, cause the height by direct expansion forming three-way pipe branch pipe to be restricted, this is also serious It has impact on the use of internal high pressure forming three-way pipe.Therefore, a kind of method that can improve shaping three-way pipe branch pipe height of research and development, It is of great significance for obtaining higher-quality three-way pipe tool.
The content of the invention
A kind of swollen building mortion of upsetting of increase tee branch height is provided it is an object of the invention to consider above mentioned problem. It is of the invention to solve the problems such as thickness during branch pipe bulging is thinning seldom and easily to wrinkle and rupture with feed supplement.
It is a kind of simple to operate another object of the present invention is to provide, it is easy to accomplish increase tee branch height Upsetting is swollen manufacturing process.
The technical scheme is that:The swollen building mortion of upsetting of the increase tee branch height of the present invention, includes first Axial thrust drift, the second axial thrust drift, the first replenishing valve, the second replenishing valve, balancing spring built in first, built in second Balancing spring, shaping dies, back pressure drift, pipe, built-in plug, wherein pipe are provided with what is communicated respectively with tube chamber set by pipe Three ports, built-in plug is put into pipe, and through the first port and second port of pipe, pipe is placed on shaping dies In, the first axial thrust drift and the second axial thrust drift are all installed in shaping dies, and the first axial thrust drift The first port of one end and pipe is touched, and one end of the second axial thrust drift and the second port of pipe are touched, built in first Balancing spring is installed in the cavity set by the first axial thrust drift, and one end of balancing spring built in first and built-in plug One end touch, the cavity wall of the other end of balancing spring built in first and cavity set by the first axial thrust drift is touched, second Built-in balancing spring is installed in the cavity set by the second axial thrust drift, and one end of balancing spring built in second with it is built-in The other end of plug is touched, and the cavity wall of cavity set by the other end of balancing spring built in second and the second axial thrust drift is touched Connect, cavity set by cavity set by the first axial thrust drift and the second axial thrust drift is communicated with the tube chamber of pipe, first Replenishing valve is installed on the first axial thrust drift, and the second replenishing valve is installed on the second axial thrust drift, and highly pressurised liquid leads to Cross set by the first replenishing valve energy topping up to the first axial thrust drift in cavity, highly pressurised liquid is arrived by the second replenishing valve energy topping up Set by second axial thrust drift in cavity, back pressure drift is installed on shaping dies, and one end and the pipe of back pressure drift 3rd port is touched.
The manufacturing process of the swollen building mortion of upsetting of the increase tee branch height of the present invention, including have the following steps:
1)Built-in plug is put into set by pipe in tube chamber, pipe is placed into shaping dies, passes through the first built-in balance Balancing spring built in spring and second makes built-in plug be maintained at the position of requirement, at this moment, closes the first replenishing valve and second and fills Liquid valve;
2)The first axial thrust drift and the second axial thrust drift at two ends is moved to the direction of pipe, will manage Base upsetting squeeze carries out poly- material to centre;
3)When the first axial thrust drift and the second axial thrust drift reach certain position, after the completion of gathering material, the is opened One replenishing valve and the second replenishing valve, highly pressurised liquid by set by the first replenishing valve topping up to the first axial thrust drift in cavity, Highly pressurised liquid by set by the second replenishing valve topping up to the second axial thrust drift in cavity, meanwhile, back pressure drift is to pipe 3rd port direction is pushed;
4)In the pressure and the back of the body of the axial thrust and highly pressurised liquid of the first axial thrust drift and the second axial thrust drift Under the collective effect of back pressure for pressing drift, pipe is set to be configured to tee branch.
The present invention, can be by changing poly- hopper set by plug using the structure of the swollen process forming three-way pipe of inner high voltage upsetting Volume size controls the volume of branch pipe, solves the rare problem of branch pipe bulging feed supplement.In addition, by adding plug in pipe internal diameter, Upsetting is carried out to pipe and is expanded into shape, the problem of pipe flexing and corrugation is efficiently solved, the present invention is a kind of easy to operate, it is easy to The swollen building mortion of upsetting and manufacturing process of the increase tee branch height of realization.
Brief description of the drawings
Fig. 1 is the structural representation of three-way pipe of the present invention;
Fig. 2 is to place pipe and plug in mould, left and right thrust drift axial feed drift to pipe end it is initial State, tubing jumping-up causes material to fill the view of the poly- hopper of plug;
Fig. 3 is expanded into the end-state of shape for the upsetting of three-way pipe.
Embodiment
Embodiment:
As shown in Figure 1, 2, 3, the upsetting of increase tee branch height of the invention is expanded into shape dress to the structural representation of the present invention Put, include the first axial thrust drift 1, the second axial thrust drift 10, the first replenishing valve 2, in the second replenishing valve 9, first Balancing spring 8, shaping dies 4, back pressure drift 5, pipe 6, built-in plug 7 built in balancing spring 3, second are put, wherein pipe 6 is set There are three ports communicated respectively with tube chamber set by pipe 6, built-in plug 7 is put into pipe 6, and pass through the first end of pipe 6 Mouth and second port, pipe 6 are placed in shaping dies 4, and the first axial thrust drift 1 and the second axial thrust drift 10 are all filled It is located in shaping dies 4, and one end of the first axial thrust drift 1 and the first port of pipe 6 are touched, the punching of the second axial thrust First 10 one end and the second port of pipe 6 are touched, and balancing spring 3 built in first is installed in set by the first axial thrust drift 1 Cavity in, and one end of balancing spring 3 built in first and one end of built-in plug 7 touch, and balancing spring 3 is another built in first One end and the cavity wall of cavity set by the first axial thrust drift 1 are touched, and balancing spring 8 is installed in the second axial thrust built in second In cavity set by drift 10, and one end of balancing spring 8 built in second and the other end of built-in plug 7 are touched, built in second The cavity wall of the other end of balancing spring 8 and cavity set by the second axial thrust drift 10 is touched, set by the first axial thrust drift 1 Tube chamber of the cavity with pipe 6 set by cavity and the second axial thrust drift 10 is communicated, and the first replenishing valve 2 is installed in first axially On thrust drift 1, the second replenishing valve 9 is installed on the second axial thrust drift 10, and highly pressurised liquid can be filled by the first replenishing valve 2 Set by liquid to the first axial thrust drift 1 in cavity, highly pressurised liquid is rushed by the energy topping up of the second replenishing valve 9 to the second axial thrust Set by first 10 in cavity, back pressure drift 5 is installed on shaping dies 4, and one end and the 3rd port of pipe 6 of back pressure drift 5 Touch.The volume of branch pipe can be controlled by changing the volume size of poly- hopper set by plug 7, branch pipe bulging feed supplement is solved rare Problem.In addition, by the internal diameter of pipe 6 add plug, to pipe 6 carry out upsetting be expanded into shape, efficiently solve the flexing of pipe 6 and The problem of corrugation.
In the present embodiment, the other end of above-mentioned back pressure drift 5 is placed on outside shaping dies 4.Above-mentioned first axial thrust punching First 1 and second the other end of axial thrust drift 10 be placed on outside shaping dies 4.
The manufacturing process of the swollen building mortion of upsetting of the increase tee branch height of the present invention, including have the following steps:
1)Built-in plug 7 is put into set by pipe 6 in tube chamber, pipe 6 is placed into shaping dies 4, by built in first Balancing spring 8 built in balancing spring 3 and second makes built-in plug 7 be maintained at the position of requirement, at this moment, closes the first replenishing valve 2 With the second replenishing valve 9;
2)The first axial thrust drift 1 and the second axial thrust drift 10 at two ends is firmly set to be moved to the direction of pipe 6, The upsetting squeeze of pipe 6 to centre is subjected to poly- material;
3)When the first axial thrust drift 1 and the second axial thrust drift 10 reach certain position, gather after the completion of material, open First replenishing valve 2 and the second replenishing valve 9, highly pressurised liquid pass through chamber set by the topping up of the first replenishing valve 2 to the first axial thrust drift 1 In vivo, highly pressurised liquid is by set by the topping up of the second replenishing valve 9 to the second axial thrust drift 10 in cavity, meanwhile, back pressure drift 5 Pushed to the 3rd port direction of pipe 6;
4)The first axial thrust drift 1 and the second axial thrust drift 10 axial thrust and highly pressurised liquid pressure and Under the collective effect of the back pressure of back pressure drift 5, pipe 6 is set to be configured to tee branch.
In the present embodiment, axial thrust, the high pressure liquid of above-mentioned first axial thrust drift 1 and the second axial thrust drift 10 The pressure of body, the relation of the back pressure of back pressure drift 5 are the relations mutually constrained, in order to obtain high branch pipe, can pass through experiment Or by existing empirical data Reasonable adjustment axial thrust, s and back pressure, to meet the knot of formation of parts The requirement of structure size.

Claims (2)

1. a kind of manufacturing process for the swollen building mortion of upsetting for increasing tee branch height, the upsetting of the increase tee branch height is swollen Building mortion include the first axial thrust drift, the second axial thrust drift, the first replenishing valve, the second replenishing valve, in first Put balancing spring, balancing spring, shaping dies, back pressure drift, pipe, built-in plug built in second, wherein pipe is provided with difference Three ports communicated with tube chamber set by pipe, built-in plug is put into pipe, and built-in plug is provided with poly- hopper, and passes through pipe First port and second port, pipe is placed in shaping dies, the first axial thrust drift and the second axial thrust drift All it is installed in shaping dies, and one end of the first axial thrust drift and the first port of pipe are touched, the second axial thrust One end of drift and the second port of pipe are touched, and balancing spring built in first is installed in the chamber set by the first axial thrust drift In vivo, and one end of balancing spring built in first and one end of built-in plug are touched, the other end of balancing spring built in first with The cavity wall of cavity is touched set by first axial thrust drift, and balancing spring built in second is installed in set by the second axial thrust drift Cavity in, and one end of balancing spring built in second and the other end of built-in plug touch, balancing spring built in second it is another One end and the cavity wall of cavity set by the second axial thrust drift are touched, and cavity set by the first axial thrust drift and the second axial direction are pushed away Cavity set by power drift is communicated with the tube chamber of pipe, and the first replenishing valve is installed on the first axial thrust drift, the second topping up Valve is installed on the second axial thrust drift, and highly pressurised liquid passes through set by the first replenishing valve energy topping up to the first axial thrust drift In cavity, highly pressurised liquid is by the way that in cavity, back pressure drift is installed set by the second replenishing valve energy topping up to the second axial thrust drift On shaping dies, and one end of back pressure drift and the 3rd port of pipe are touched;It is characterized in that increase tee branch height The swollen building mortion of upsetting manufacturing process include have the following steps:
1)Built-in plug is put into set by pipe in tube chamber, pipe is placed into shaping dies, passes through balancing spring built in first And balancing spring built in second makes built-in plug be maintained at the position of requirement, at this moment, closes the first replenishing valve and the second replenishing valve;
2)The first axial thrust drift and the second axial thrust drift at two ends is firmly set to be moved to the direction of pipe, by pipe upsetting It is extruded into the poly- material of poly- hopper progress that built-in plug is provided with;Branch pipe is controlled by the volume size for changing poly- hopper set by built-in plug Volume, solve the problem of branch pipe bulging feed supplement is difficult;
3)When the first axial thrust drift and the second axial thrust drift reach certain position, gather after the completion of material, open first and fill Liquid valve and the second replenishing valve, highly pressurised liquid is by set by the first replenishing valve topping up to the first axial thrust drift in cavity, high pressure Liquid by set by the second replenishing valve topping up to the second axial thrust drift in cavity, meanwhile, back pressure drift is to the 3rd of pipe Port direction is pushed;
4)In pressure and the back pressure punching of the axial thrust and highly pressurised liquid of the first axial thrust drift and the second axial thrust drift Under the collective effect of the back pressure of head, pipe is set to be configured to tee branch.
2. the manufacturing process of the swollen building mortion of upsetting of increase tee branch height according to claim 1, it is characterised in that The axial thrust of above-mentioned first axial thrust drift and the second axial thrust drift, the pressure of highly pressurised liquid, the back of the body of back pressure drift The relation of pressure is the relation mutually constrained, and axial thrust, highly pressurised liquid are adjusted by experiment or by existing empirical data Pressure and back pressure, to meet the physical dimension requirement of formation of parts.
CN201510942278.5A 2015-12-16 2015-12-16 It is a kind of to increase the swollen building mortion of upsetting and method of tee branch height Expired - Fee Related CN105436285B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510942278.5A CN105436285B (en) 2015-12-16 2015-12-16 It is a kind of to increase the swollen building mortion of upsetting and method of tee branch height

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510942278.5A CN105436285B (en) 2015-12-16 2015-12-16 It is a kind of to increase the swollen building mortion of upsetting and method of tee branch height

Publications (2)

Publication Number Publication Date
CN105436285A CN105436285A (en) 2016-03-30
CN105436285B true CN105436285B (en) 2017-09-26

Family

ID=55547171

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510942278.5A Expired - Fee Related CN105436285B (en) 2015-12-16 2015-12-16 It is a kind of to increase the swollen building mortion of upsetting and method of tee branch height

Country Status (1)

Country Link
CN (1) CN105436285B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105921586B (en) * 2016-06-03 2017-08-25 广东工业大学 Swollen combined shaping method is rolled in a kind of double branch pipe upsetting side by side
CN106493213B (en) * 2016-12-26 2018-05-18 广东工业大学 The manufacture device and method of a kind of pipeline
CN108787845B (en) * 2018-05-28 2020-04-10 南京理工大学 Hydraulic forming device for large-diameter thin-wall metal pipe fitting
CN109719187B (en) * 2019-02-03 2019-12-06 哈尔滨工业大学 Asymmetric reducing thin-wall part circumferential flow forming device
CN111496053A (en) * 2020-06-11 2020-08-07 沈阳航空航天大学 Back pressure limiting type metal three-way pipe composite bulging device
CN113798382B (en) * 2021-08-03 2024-01-26 宁波金田铜管有限公司 Processing method for thinning back accumulation of tee joint

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1142192A1 (en) * 1982-09-10 1985-02-28 Ленинградский Ордена Ленина Политехнический Институт Им.М.И.Калинина Die for manufacturing hollow articles with branches
JPS61165235A (en) * 1985-09-09 1986-07-25 Hitachi Ltd Method and device for bulging
KR20140002203A (en) * 2012-06-28 2014-01-08 (주)성광기연 Manufacture device of t-type pipe resources
CN103909133A (en) * 2014-04-03 2014-07-09 南京航空航天大学 Composite punch device for forming of iso-wall-thickness multi-way tubes and forming method
CN205183456U (en) * 2015-12-16 2016-04-27 广东工业大学 Increase bloated shaper of rammer of tee branch height

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1142192A1 (en) * 1982-09-10 1985-02-28 Ленинградский Ордена Ленина Политехнический Институт Им.М.И.Калинина Die for manufacturing hollow articles with branches
JPS61165235A (en) * 1985-09-09 1986-07-25 Hitachi Ltd Method and device for bulging
KR20140002203A (en) * 2012-06-28 2014-01-08 (주)성광기연 Manufacture device of t-type pipe resources
CN103909133A (en) * 2014-04-03 2014-07-09 南京航空航天大学 Composite punch device for forming of iso-wall-thickness multi-way tubes and forming method
CN205183456U (en) * 2015-12-16 2016-04-27 广东工业大学 Increase bloated shaper of rammer of tee branch height

Also Published As

Publication number Publication date
CN105436285A (en) 2016-03-30

Similar Documents

Publication Publication Date Title
CN105436285B (en) It is a kind of to increase the swollen building mortion of upsetting and method of tee branch height
CN101362281B (en) Production method of ball valve core
CN101844164A (en) Production process of quick connecting pipe
CN203842988U (en) Hydraulic forming device with framework and rubber bag
CN105921587B (en) A kind of forming and machining method of three branch pipes side by side
CN205183456U (en) Increase bloated shaper of rammer of tee branch height
CN103658476B (en) A kind of thick-wall hollow forging integral forming method of special-shaped angle head cylindrical band boss
CN206870293U (en) Injection mold twice core pulling forced demoulding mechanism
CN206629874U (en) A kind of dumpling forming device
CN205393277U (en) Interior high -pressure forming device of double bend parallels
CN104624799A (en) Device for high temperature solid power medium assisting titanium alloy plate superplasticity drawing and bulging integration and method thereof
CN109127850B (en) Solid-liquid two-phase medium internal high-pressure forming method for special-shaped section thin-wall pipe fitting
CN106567976A (en) Double-compression three-way copper tube and forming method thereof
CN105710184B (en) A kind of double branch pipe internal high pressure forming device and method arranged side by side
CN207138628U (en) A kind of T-shaped three water flowing is risen mould
CN205966933U (en) Shaping processingequipment of three branch pipes side by side
CN205949600U (en) Double bend compound shaper that expands of passing through many hands or places of upsetting side by side
CN209716161U (en) The stamping die of integral type ball-type multi-way pipe fitting
CN202087666U (en) Water expansion type mould of pot body
CN207521996U (en) A kind of pressure volume pot production equipment
CN208628149U (en) A kind of seamless large-caliber thin-walled three-way forming device
CN105195625A (en) Necking tee joint processing die and method of processing tee joint by using same
CN111980645B (en) Seam making device, and system and process for simulating sand filling model displacement experiment process
CN107693923B (en) Manufacturing die of silicone rubber double-cavity anti-blocking catheter
CN114160666A (en) Thin-wall stainless steel clamping and pressing pipe fitting forming device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170926

Termination date: 20201216

CF01 Termination of patent right due to non-payment of annual fee