CN105421725B - 预留住宅通风道免支模一次成型施工方法 - Google Patents
预留住宅通风道免支模一次成型施工方法 Download PDFInfo
- Publication number
- CN105421725B CN105421725B CN201511004879.8A CN201511004879A CN105421725B CN 105421725 B CN105421725 B CN 105421725B CN 201511004879 A CN201511004879 A CN 201511004879A CN 105421725 B CN105421725 B CN 105421725B
- Authority
- CN
- China
- Prior art keywords
- hole
- fitting
- built
- ventilating duct
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F17/00—Vertical ducts; Channels, e.g. for drainage
- E04F17/04—Air-ducts or air channels
Abstract
本发明涉及一种预留住宅通风道免支模一次成型施工方法,楼板结构层混凝土浇筑前,在预留洞位置放置预埋件并将预埋件与模板固定;所述的预埋件是截面为“凸”字形的可拆除盒体,预埋件上部长度小于设计通风道尺寸,下部长度大于设计通风道尺寸,从而使浇筑结构层后形成的预留洞形成向内侧凸出的上角部;楼板结构层混凝土浇筑,浇筑完后拆除模板;然后拆除预埋件,通风道上口面与预留洞结构层下部嵌固,通风道下口面与预留洞结构层上部用楔块临时固定;预留洞口周边空隙进行封堵,在楼板地面施工时取出楔块,然后浇筑混凝土填缝。本发明工序简化,并能够提高施工质量。
Description
技术领域
本发明涉及住宅楼通风道施工,特别是普通住宅楼预留通风道免支模一次成型施工方法。
背景技术
目前多层、高层现代住宅建筑的排风系统中通风道工程的施工主要集中在主体完成后施工,在后期施工时,一般施工工序为:层托安装→吊线→安装通风道→临时固定→二次吊洞灌缝→养护→上层通风道安装,但这种方法在主体阶段留设洞口比安装成品料大5cm-10cm洞口,在安装层托时需采用植筋技术。通风道就位后,排风道与楼板预留洞之间的缝隙吊模用C20细石混凝土浇灌,存在以下问题与隐患:
1)在浇筑混凝土的过程中,容易造成二次浇筑时涨模或混凝土浇筑时振捣不密实,厨房、卫生间出现漏水等现象。
2)产生的间隙需要人工二次搭拆安全操作平台,加大人工工作量,同时加大了材料的使用量。加大了施工成本,减缓了施工进度。
发明内容
本发明要解决的技术问题是提供一种工序简化并能够提高施工质量的预留住宅通风道免支模一次成型施工方法。
为解决以上技术问题,本发明采用的技术方案是:一种预留住宅通风道免支模一次成型施工方法,包括步骤:
S1,楼板结构层混凝土浇筑前,在预留洞位置放置预埋件并将预埋件与模板固定;所述的预埋件是截面为“凸”字形的可拆除盒体,预埋件上部长度小于设计通风道尺寸,下部长度大于设计通风道尺寸,从而使浇筑结构层后形成的预留洞形成向内侧凸出的上角部;
S2,楼板结构层混凝土浇筑,浇筑完后拆除模板;
S3,拆除预埋件,通风道上口面与预留洞结构层下部嵌固,通风道下口面与预留洞结构层上部用楔块临时固定;
S4,预留洞口周边空隙进行封堵,在楼板地面施工前取出楔块,然后浇筑混凝土填缝。
作为优选的技术方案,楼板结构层混凝土浇筑前,预留洞口上角部的形成部位设置有角部加强筋。
作为优选的技术方案,所述的角部加强筋是在预留洞上角部的形成部位设置与预留洞边缘平行的角部加强钢筋。
作为优选的技术方案,预留洞两侧楼板顶部的受力钢筋内侧设置与角部加强钢筋垂直的角部钢筋并用三角支撑架固定。
作为优选的技术方案,步骤S1中,所述的预埋件四周和中心线与模板固定。
作为优选的技术方案,步骤S1中,所述的预埋件上部和下部的高度比例为7:3。
作为优选的技术方案,S4中,预留洞口周边空隙封堵时,预留洞口下部采用防水油密封胶、上部采用防火密封胶封堵。
作为优选的技术方案,S4中,浇筑混凝土填缝后采用防水材料对预留洞口进行局部防水施工。
本发明避免了二次浇筑时涨模或混凝土浇筑时振捣不密实,厨房、卫生间出现漏水,不需要二次搭拆安全操作平台,工序简单,较低了施工成本,缩短了施工工期。
附图说明
图1是主体施工阶段通风道预留洞示意图。
图2是通风道安装阶段的示意图。
1-结构层,2-预埋件,3-模板,4-上角部,5-通风道,6-楔块,7-角部加强钢筋,8-角部钢筋,9-防火密封胶,10-剪力墙,11-铁钉。
具体实施方式
本发明实施例的施工工艺流程: 施工准备→角部加强筋设置→放置并固定预埋件→复核检查→混凝土拆模→通风道安装→预留洞口周边空隙封堵。
1)施工准备
预制预埋件,图1所示的预埋件2是截面为“凸”字形的用挤塑板制作的可拆除盒体,预埋件2上部长度小于设计通风道尺寸,下部长度大于设计通风道尺寸,从而使浇筑结构层1后形成的预留洞形成向内侧凸出的上角部4。此外,预埋件2上部和下部的高度比例为7:3。
以楼板结构层厚度100mm为例,预埋件2上部切厚度为70mm,长度小于设计通风道尺寸50mm;预埋件2下部厚度为30mm,长度大于设计通风道尺寸50mm,切割完成后用封口胶带包裹。
2)角部加强筋设置
角部加强筋设置在混凝土浇筑后会形成预留洞上角部的部位,以增强上角部的强度同时避免拆模时阳角受到损坏。角部加强筋是在预留洞上角部的形成部位设置与预留洞边缘平行的角部加强钢筋7,如图1和图2所示,是在“凸”字形预埋件2的上部内凹的角部分分别设置2根HRB400级¢10的钢筋。在此基础上,预留洞两侧楼板顶部的受力钢筋内侧设置与角部加强钢筋7垂直的HRB400级¢10角部钢筋8并用三角支撑架固定。
3)放置并固定预埋件
楼板结构层1混凝土浇筑前,在预留洞位置放置制作好的预埋件2并将预埋件2与模板3固定。固定时,预埋件2四周和中心线用铁钉11与模板3固定。如图1所示,预埋件下部一端与剪力墙10紧贴。
4)复核检查并浇筑混凝土
在浇筑混凝土前,对预埋钢筋的位置、标高进行复核检查,防止漏留、移位。检查合格后开始楼板结构层1混凝土浇筑。
5)混凝土拆模
浇筑完后拆除模板3,混凝土模,3拆除时需达到设计强度的75%,并在拆模时不要用力过猛。
6)通风道安装
通风道安装是整体施工之关键,通风道长度为比楼层高度小2cm,首节安装前先用刀片切割拆除预埋件2,并将周边清理干净,通风道5上口面与预留洞结构层1下部嵌固,通风道下口面与预留洞结构层1上部用楔块6临时固定。
7)预留洞口周边空隙封堵
对预留洞口剩余的空隙封堵,预留洞口下部采用防水油密封胶,上部采用防火密封胶9进行封堵。在楼地面施工前将楔块6取出浇灌混凝土填缝,并采用同厨房、卫生间的防水材料对预留洞口处进行局部防水施工。
Claims (2)
1.一种预留住宅通风道免支模一次成型施工方法,其特征在于,包括步骤:
S1,楼板结构层(1)混凝土浇筑前,在预留洞位置放置预埋件(2)并将预埋件(2)与模板(3)固定;所述的预埋件(2)是截面为“凸”字形的用挤塑板制作的可拆除盒体,预埋件(2)四周和中心线用铁钉(11)与模板(3)固定,预埋件(2)上部长度小于设计通风道尺寸,下部长度大于设计通风道尺寸,从而使浇筑结构层(1)后形成的预留洞形成向内侧凸出的上角部(4);楼板结构层(1)混凝土浇筑前,预留洞口上角部的形成部位(4)设置有角部加强筋;所述的角部加强筋是在预留洞上角部的形成部位设置与预留洞边缘平行的角部加强钢筋(7);预留洞两侧楼板顶部的受力钢筋内侧设置与角部加强钢筋(7)垂直的角部钢筋(8)并用三角支撑架固定;
S2,楼板结构层(1)混凝土浇筑,浇筑完后拆除模板(3);
S3,用刀片切割拆除预埋件(2),通风道(5)上口面与预留洞结构层(1)下部嵌固,通风道下口面与预留洞结构层(1)上部用楔块(6)临时固定;
S4,预留洞口周边空隙进行封堵,预留洞口下部采用防水油密封胶、上部采用防火密封胶(9)封堵;在楼板地面施工前取出楔块(6),然后浇筑混凝土填缝,浇筑混凝土填缝后采用防水材料对预留洞口进行局部防水施工。
2.根据权利要求1所述的方法,其特征在于:步骤S1中,所述的预埋件(2)上部和下部的高度比例为7:3。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201511004879.8A CN105421725B (zh) | 2015-12-29 | 2015-12-29 | 预留住宅通风道免支模一次成型施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201511004879.8A CN105421725B (zh) | 2015-12-29 | 2015-12-29 | 预留住宅通风道免支模一次成型施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105421725A CN105421725A (zh) | 2016-03-23 |
CN105421725B true CN105421725B (zh) | 2017-12-19 |
Family
ID=55500230
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201511004879.8A Active CN105421725B (zh) | 2015-12-29 | 2015-12-29 | 预留住宅通风道免支模一次成型施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105421725B (zh) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109577571B (zh) * | 2018-12-25 | 2020-11-13 | 山西五建集团有限公司 | 预制装配式混凝土屋面通风道出口施工工法 |
CN114704048A (zh) * | 2022-05-01 | 2022-07-05 | 山西三建集团有限公司 | 高层建筑主体结构中的排烟气道的构筑方法 |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09250230A (ja) * | 1996-03-18 | 1997-09-22 | Sekisui Chem Co Ltd | 外壁の開口構造及びダクト取付構造 |
CN202866251U (zh) * | 2012-10-18 | 2013-04-10 | 中国核工业华兴建设有限公司 | 双层混凝土通风管道 |
CN204174931U (zh) * | 2014-09-28 | 2015-02-25 | 中建四局第三建筑工程有限公司 | 一种混凝土楼板上的预留孔及制作该预留孔的模具 |
CN104533081A (zh) * | 2014-12-26 | 2015-04-22 | 重庆辉钻贸易有限公司 | 楼层下水管道预留孔免拆模具 |
CN104947921B (zh) * | 2015-07-14 | 2018-02-02 | 成都市第八建筑工程公司 | 烟道结构及其安装施工方法 |
-
2015
- 2015-12-29 CN CN201511004879.8A patent/CN105421725B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN105421725A (zh) | 2016-03-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101818527B (zh) | 装配整体式剪力墙结构体系及其施工方法 | |
CN104652830B (zh) | 一种预制楼面板和预制墙板搭建的施工方法 | |
CN201687102U (zh) | 装配整体式剪力墙结构体系 | |
CN103806651B (zh) | 一种利用桥架预埋件安装桥架的方法 | |
CN106120870B (zh) | 地下室外墙后浇带超前封闭结构及施工方法 | |
CN208167956U (zh) | 一种采用逆作法施工的地下室内衬墙 | |
CN103410317A (zh) | 采用墙体预制构件现场拼装并浇筑的整体墙体施工方法 | |
CN106499070B (zh) | 装配式建筑构件与构件间连接缝的施工方法 | |
CN111335490A (zh) | 一种全混凝土外墙窗下填充墙与剪力墙接缝处抗裂结构及其施工方法 | |
CN103866885A (zh) | 采光窗的节能保温构造及其施工方法 | |
CN103485537A (zh) | 超高层水平二次结构预埋钢筋施工方法及其结构 | |
CN107059917A (zh) | 一种拆分构件预制式综合管廊及其施工方法 | |
CN110792200A (zh) | 一种无需后期剔打的砌体施工方法及其包管结构 | |
CN107119901A (zh) | 剪力墙转角节点的模板结构及剪力墙现浇体系及施工方法 | |
CN111997232A (zh) | 一种混凝土钢丝网架免拆模板保温系统的施工方法 | |
CN105421725B (zh) | 预留住宅通风道免支模一次成型施工方法 | |
CN103590841A (zh) | 一种暗挖地下洞室初期支护的支撑方法 | |
CN206233560U (zh) | 墙体支模结构 | |
CN108457411A (zh) | 一种装配式建筑的叠合楼板及其施工方法 | |
CN107269001A (zh) | 暗装配电箱随混凝土墙体结构整浇的施工方法 | |
CN206769180U (zh) | 一种型钢穿墙洞口预制块 | |
CN108240045A (zh) | 一种外墙预制板复合后浇带结构及其施工方法 | |
CN104314048B (zh) | 气囊式混凝土工程变形缝止水型腔模的制造及施工方法 | |
CN113445645A (zh) | 一种灌槽式装配式混凝土剪力墙及施工方法 | |
CN207110214U (zh) | 一种预制内填充混凝土墙板 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||