CN105399229A - Constructed rapid infiltration water treatment device suitable for town domestic wastewater - Google Patents

Constructed rapid infiltration water treatment device suitable for town domestic wastewater Download PDF

Info

Publication number
CN105399229A
CN105399229A CN201510880566.2A CN201510880566A CN105399229A CN 105399229 A CN105399229 A CN 105399229A CN 201510880566 A CN201510880566 A CN 201510880566A CN 105399229 A CN105399229 A CN 105399229A
Authority
CN
China
Prior art keywords
pool
water
tank
grating
pond
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510880566.2A
Other languages
Chinese (zh)
Inventor
甘华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHONGQING GANTAI ENVIRONMENTAL PROTECTION EQUIPMENT Co Ltd
Original Assignee
CHONGQING GANTAI ENVIRONMENTAL PROTECTION EQUIPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING GANTAI ENVIRONMENTAL PROTECTION EQUIPMENT Co Ltd filed Critical CHONGQING GANTAI ENVIRONMENTAL PROTECTION EQUIPMENT Co Ltd
Priority to CN201510880566.2A priority Critical patent/CN105399229A/en
Publication of CN105399229A publication Critical patent/CN105399229A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a constructed rapid infiltration water treatment device suitable for town domestic wastewater. A grating pool is composed of a buffer pool and a grating pool body which are arranged front and back. A water inlet pipe is arranged on the lower portion of the buffer pool, and an overflow pipe is arranged on the upper portion of the buffer pool. A manual gate valve is arranged on the lower portion of a partition wall of the buffer pool and the grating pool body. Longitudinal gratings are arranged on the lower portion of the grating pool body, and a maintenance steel ladder is arranged at the position, above the gratings, in the grating pool body. The grating pool body is communicated with an adjusting pool, and the adjusting pool comprises a preliminary settling pool and a water evening pool which are arranged side by side. The preliminary settling pool is located on the right side of the grating pool, and a sludge pump is arranged at the bottom of the preliminary settling pool. A water flow channel is arranged on the front side of a partition wall between the preliminary settling pool and the water evening pool, and a water suction pump is arranged at the bottom of the water evening pool. The water suction pump is controlled to be started and stopped through a water level indicator, a reuse water pool is connected with a back flush water inlet pipe of a sand filter, a back flush water outlet pipe of the sand filter is connected to a back wash settling pool, and sludge in the back wash settling pool and sludge in the adjusting pool enter a sludge drying pool.

Description

Be applicable to the manpower rapid-infiltration water treatment device of field town sanitary sewage
Technical field
The present invention relates to a kind of Sewage treatment systems, particularly relate to the manpower rapid-infiltration water treatment device of a kind of applicable field town sanitary sewage.
Background technology
Along with the enhancing of people's environmental consciousness, sewage disposal has become the Important Problems that national governments pay close attention to, China's sewage source mainly contains three, and the sewage produced in residents from villages and towns district dispersant type domestic wastewater, the centralized sanitary sewage in urban life district and Industrial processes.Utilize that to carry out purification to sewage in sandy soil be traditional wastewater treatment process, there are some shortcomings in existing this sewage water treatment method, the removal ability of TN and TP is lower, also needs to place the biochemical treatment tanks such as some denitrification ponds.
Summary of the invention
In order to solve the problems of the technologies described above, the invention provides the another kind of manpower rapid-infiltration water treatment device being applicable to field town sanitary sewage, being applicable to small towns sanitary sewage disposal.
To achieve these goals, technical scheme of the present invention is as follows: the manpower rapid-infiltration water treatment device of a kind of applicable field town sanitary sewage, is characterized in that: comprise grating tank, equalizing tank, sand filter, sand filter distribution reservoir, manpower rapid-infiltration pond and reuse pool;
The Buffer Pool that described grating tank is arranged side by side by front and back and grating tank body form, wherein grating tank body is positioned at rear side, the bottom of described Buffer Pool arranges water inlet pipe, the top of described Buffer Pool is provided with upflow tube, the bottom of the partition wall of described Buffer Pool and grating tank body arranges hand sluice valve, the bottom of described grating tank body arranges longitudinal grid, is provided with maintenance steel ladder in the grating tank body above the side of described grid;
Described grating tank body is communicated with equalizing tank, the preliminary sedimentation tank be arranged side by side about described equalizing tank comprises and even pond, described preliminary sedimentation tank is positioned at the right side of grating tank, the bottom of described preliminary sedimentation tank is provided with sludge pump, the front side of the partition wall between described preliminary sedimentation tank and even pond is provided with water stream channel, the bottom in described even pond is provided with lift pump, described sludge pump is near water stream channel, described lift pump is positioned at the position away from water stream channel, water level gauge is set in described even pond, the rising pipe of described lift pump arranges valve;
The rising pipe of described lift pump is connected with the water-in of sand filter, liquid in described sand filter is discharged to sand filter distribution reservoir from bottom liquid outlet, the water outlet of described sand filter distribution reservoir connects with multiple manpower rapid-infiltration pond, and the water outlet in described manpower rapid-infiltration pond drains into reuse pool; Described reuse pool is connected with the back flushing inlet channel of sand filter by pipeline, the back flushing rising pipe of described sand filter is connected to backwash settling tank, the described mud of backwash settling tank and the mud of equalizing tank enter sludge drying pond, arrange awning above described sludge drying pond.
Described sludge drying pond comprises sludge drying pond body, wash plate is set in the body of described sludge drying pond and described sludge drying pond body is divided into two chambers in left and right, about this, the top of two chambers is respectively equipped with mud import, the mud import of left and right chamber is connected with the sludge pump in equalizing tank with backwash settling tank respectively, the bottom of described left and right chamber distinguishes arranged transversely permeable geotechnique layer of cloth from top to bottom, gravel bed and double-edged fine-toothed comb, described double-edged fine-toothed comb is arranged by some bars longitudes and latitudes and forms, its aperture is less than 3mm, distance is had between the base plate of described double-edged fine-toothed comb and sludge drying pond body, the lower end of the left and right chamber of described sludge drying pond body is respectively equipped with water port, this water port is positioned at the below of double-edged fine-toothed comb, this water port is connected with equalizing tank by pipeline,
Also comprise controller, the lift pump control end of described controller connects lift pump, and the Valve controlling end of described controller connects valve, water level signal is passed to controller by described water level gauge, when water level exceedes appointment water level, controller by-pass valve control is opened, and controls lift pump work simultaneously; When water level is lower than appointment water level, described controller by-pass valve control and lift pump are closed.
In such scheme, grating tank is mainly used in the preliminary removal to foreign material thick in water after sewage network accesses sewage work.Equalizing tank, according to the practical situation of the sewage water yield, ensures that the normal table of sewage work's production facility runs, plays the effect of precipitation and homogeneous even amount.
Concrete: before grating tank, Buffer Pool is set, different local next sewage first here tentatively mixes, then grid is flowed through, after bulk sundries blocking, sewage enters the preliminary sedimentation tank of equalizing tank, preliminary sedimentation tank and even pond are separated, and channel setting is in the side away from grating tank, like this, make the flowing time of sewage in equalizing tank elongated, such one side makes the better effects if of sludge settling, makes the mixing of different sewage better on the other hand, makes the microorganism mixing carried in sewage evenly be conducive to follow-up process.Preliminary sedimentation tank and even pond are separated simultaneously, reduce the amount entering the mud of next step sand filter, reduce the processing pressure of sand filter.
Sand filter major function removes micro-impurities further, and ensure the normal operation of oozing pond soon, the major function of sand filter distribution reservoir is the uniform water distribution realizing manpower rapid-infiltration pond.Reuse pool is mainly used in backwash water, and the double sterilization pool that does is used simultaneously.
Mud enters the nature mummification of sludge drying pond, and the mud outward transport after mummification is disposed.
Sludge drying pond is divided into two chambers, and the mud at two places is separated mummification, better separately utilizes so that follow-up.Natural mummification on permeable geotechnique layer of cloth, slag wherein, successively through gravel and double-edged fine-toothed comb, stops by filtrate, and filtrate returns the equalizing tank of manual controlled infusion, and sludge drying is effective, and structure is simple, and cost is low.
Sewage treatment systems of the present invention, influent quality is as follows:
Project COD(mg/L) BOD5(mg/L) SS(mg/L) TN(mg/L) NH3-N(mg/L) TP(mg/L)
Water quality 350 150 230 35 25 4.0
Effluent quality is:
Project COD(mg/L) BOD5(mg/L) SS(mg/L) TN(mg/L) NH3-N(mg/L) TP(mg/L)
Water quality ≤60 ≤20 ≤20 ≤20 ≤8 ≤1
The contrast of above-mentioned two tables can be found out, this system architecture is simple, arranges that easily treatment effect is good.
Last: by the closedown of water level gauge auto-controlled water-pumping pump, to realize intellectualized operation, when night, sanitary sewage was few, lift pump will stop automatically, need not need artificial closedown again, time saving and energy saving.
In such scheme: the limit of the base plate in described preliminary sedimentation tank and even pond is equipped with a pit, described sludge pump and lift pump are arranged in pit.Be convenient to the extraction of mud and water.
Beneficial effect: structure of the present invention is simple, arranges that easily floor space is little, and construction cost is low, and running cost is low, and treatment effect is good, by the opening and closing of water level gauge auto-controlled water-pumping pump, realizes intellectualized operation.
Accompanying drawing explanation
Fig. 1 is schema of the present invention.
Fig. 2 is the partial enlarged drawing at A place in Fig. 1.
Fig. 3 be equalizing tank and grating tank assembly overlook enlarged view.
Fig. 4 is the vertical structure view of grating tank.
Fig. 5 is the A-A sectional view of Fig. 3.
Fig. 6 is the B-B sectional view of Fig. 3.
Fig. 7 is control flow chart.
Fig. 8 is the structural representation in sludge drying pond.
Fig. 9 is the structural representation of double-edged fine-toothed comb.
Embodiment
Below in conjunction with drawings and Examples, the invention will be further described:
The present invention waits the relative position of the noun of locality only in representative graph all around, does not represent the absolute location of product.
Embodiment 1, as shown in figs 1-9: the manpower rapid-infiltration water treatment device of applicable field of the present invention town sanitary sewage is by grating tank 1, equalizing tank 2, sand filter 3, sand filter distribution reservoir 4, manpower rapid-infiltration pond 5, reuse pool 6, backwash settling tank 7, sludge drying pond 8, awning 9, railing 10, and the parts such as water level gauge 13, valve 11, controller 12 form.
The Buffer Pool 1a that grating tank 1 is arranged side by side by front and back and grating tank body 1b forms, wherein grating tank body 1b is positioned at rear side, the bottom of Buffer Pool 1a arranges water inlet pipe 1c, the top of Buffer Pool 1a is provided with upflow tube 1d, the bottom of the partition wall of Buffer Pool 1a and grating tank body 1b arranges hand sluice valve 1e, the bottom of grating tank body 1b arranges longitudinal grid 1f, is provided with maintenance steel ladder 1g, facilitates grating slag removing and maintenance in the grating tank body 1b above the side of grid 1f.
Grating tank body 1b is communicated with equalizing tank 2, the preliminary sedimentation tank 2a be arranged side by side about equalizing tank 2 comprises and even pond 2b, preliminary sedimentation tank 2a is positioned at the right side of grating tank, the bottom of preliminary sedimentation tank 2a is provided with sludge pump 2c, the front side of the partition wall between preliminary sedimentation tank 2a and even pond 2b is provided with water stream channel 2d, the bottom of even pond 2b is provided with lift pump 2e, and sludge pump 2c is positioned at the position (near rear side) away from water stream channel near water stream channel 2d (near front side) lift pump 2e.The limit of the base plate of preferred preliminary sedimentation tank 2a and even pond 2b is equipped with a pit, sludge pump 2c and lift pump 2e is arranged in pit.Railing 10 is provided with around grating tank and equalizing tank.
Water level gauge 13 is set in described even pond 2b, the rising pipe of described lift pump 2e arranges valve 11.
The rising pipe of lift pump 2e is connected with the water-in of sand filter 3, and the liquid in sand filter 3 is discharged to sand filter distribution reservoir 4 from bottom liquid outlet, and the water outlet of sand filter distribution reservoir 4 connects with multiple manpower rapid-infiltration pond 5, selects four here.The water outlet in manpower rapid-infiltration pond 5 drains into reuse pool 6.Reuse pool 6 is connected with the back flushing inlet channel 3a of sand filter 3 by pipeline, and the back flushing rising pipe 3b of sand filter 3 is connected to backwash settling tank 7.The mud of backwash settling tank 7 and the mud of equalizing tank 2 enter sludge drying pond 8, are provided with awning 9 above sludge drying pond 8.
Sludge drying pond 8 comprises sludge drying pond body 81, wash plate 82 is set in sludge drying pond body 81 and sludge drying pond body 81 is divided into two chambers in left and right, about this, the top of two chambers is respectively equipped with mud import 83, the mud import 83 of left and right chamber is connected with the sludge pump in equalizing tank 2 with the sludge pump of backwash settling tank 7 respectively, the bottom of left and right chamber distinguishes arranged transversely permeable geotechnique layer of cloth 84 from top to bottom, gravel bed 85 and double-edged fine-toothed comb 86, double-edged fine-toothed comb 86 is arranged by some bars longitudes and latitudes and forms, its aperture is less than 3mm, preferred double-edged fine-toothed comb 86 is made up of batten or bamboo cane.Have distance between the base plate of double-edged fine-toothed comb 86 and sludge drying pond body 81, the lower end of the left and right chamber of sludge drying pond body 81 is respectively equipped with water port, and water port is connected by pipeline with equalizing tank 2, and filtrate returns in equalizing tank 2 and processes.This water port is positioned at the below of double-edged fine-toothed comb 86.Preferred water port is arranged water shoot 87, this water shoot 87 is layered on the base plate of sludge drying pond body 81, and this water shoot 87 arranges prosopyle.
Wherein the middle part of sand filter 3 is provided with quartz sand filler layer 3c, and the below of quartz sand filler layer 3c arranges gravel blanket 3d, and the water-in of sand filter is positioned at the top of quartz sand filler 3c, and its water outlet is positioned at the below of gravel blanket 3d;
CRI-1 type packing layer 5a, CRI-2 type packing layer 5b and manpower rapid-infiltration gravel padding layer 5c is filled from top to bottom successively in manpower rapid-infiltration pond 5, the water-in in manpower rapid-infiltration pond 5 is positioned at above CRI-1 type packing layer 5a, and its water outlet is positioned at below manpower rapid-infiltration gravel padding layer 5c.
The lift pump control end of controller 12 connects lift pump 2e, the Valve controlling end of controller 12 connects valve 11, and water level signal is passed to controller 12 by water level gauge 13, when water level exceedes appointment water level, controller 12 by-pass valve control 11 is opened, and controls lift pump 2e work simultaneously; When water level is lower than appointment water level, controller 12 by-pass valve control 11 and lift pump 2e close.
The present invention is not limited to above-mentioned specific embodiment, should be appreciated that those of ordinary skill in the art just design according to the present invention can make many modifications and variations without the need to creative work.In a word, all technician in the art, all should by the determined protection domain of claims under this invention's idea on the basis of existing technology by the available technical scheme of logical analysis, reasoning, or a limited experiment.

Claims (2)

1. a manpower rapid-infiltration water treatment device for applicable field town sanitary sewage, is characterized in that: comprise grating tank (1), equalizing tank (2), sand filter (3), sand filter distribution reservoir (4), manpower rapid-infiltration pond (5) and reuse pool (6);
The Buffer Pool (1a) that described grating tank (1) is arranged side by side by front and back and grating tank body (1b) form, wherein grating tank body (1b) is positioned at rear side, the bottom of described Buffer Pool (1a) arranges water inlet pipe (1c), the top of described Buffer Pool (1a) is provided with upflow tube (1d), the bottom of the partition wall of described Buffer Pool (1a) and grating tank body (1b) arranges hand sluice valve (1e), the bottom of described grating tank body (1b) arranges longitudinal grid (1f), maintenance steel ladder (1g) is provided with in grating tank body (1b) above the side of described grid (1f),
Described grating tank body (1b) is communicated with equalizing tank (2), the preliminary sedimentation tank (2a) be arranged side by side about described equalizing tank (2) comprises and even pond (2b), described preliminary sedimentation tank (2a) is positioned at the right side of grating tank, the bottom of described preliminary sedimentation tank (2a) is provided with sludge pump (2c), the front side of the partition wall between described preliminary sedimentation tank (2a) and even pond (2b) is provided with water stream channel (2d), the bottom of described even pond (2b) is provided with lift pump (2e), described sludge pump (2c) is near water stream channel (2d), described lift pump (2e) is positioned at the position away from water stream channel, in described even pond (2b), water level gauge (13) is set, the rising pipe of described lift pump (2e) is arranged valve (11),
The rising pipe of described lift pump (2e) is connected with the water-in of sand filter (3), liquid in described sand filter (3) is discharged to sand filter distribution reservoir (4) from bottom liquid outlet, the water outlet of described sand filter distribution reservoir (4) connects with multiple manpower rapid-infiltration pond (5), and the water outlet of described manpower rapid-infiltration pond (5) drains into reuse pool (6); Described reuse pool (6) is connected with the back flushing inlet channel (3a) of sand filter (3) by pipeline, the back flushing rising pipe of described sand filter (3) is connected to backwash settling tank (7), the mud of described backwash settling tank (7) and the mud of equalizing tank (2) enter sludge drying pond (8), described sludge drying pond (8) top arranges awning (9)
Described sludge drying pond (8) comprises sludge drying pond body (81), wash plate (82) is set in described sludge drying pond body (81) and described sludge drying pond body (81) is divided into two chambers in left and right, about this, the top of two chambers is respectively equipped with mud import (83), the mud import (83) of left and right chamber is connected with the sludge pump in equalizing tank (2) with backwash settling tank (7) respectively, arranged transversely permeable geotechnique's layer of cloth (84) is distinguished from top to bottom in the bottom of described left and right chamber, gravel bed (85) and double-edged fine-toothed comb (86), described double-edged fine-toothed comb (86) is arranged by some bars longitudes and latitudes and forms, its aperture is less than 3mm, distance is had between the base plate in described double-edged fine-toothed comb (86) and sludge drying pond body (81), the lower end of the left and right chamber of described sludge drying pond body (81) is respectively equipped with water port, this water port is positioned at the below of double-edged fine-toothed comb (86), this water port is connected with equalizing tank (2) by pipeline,
Also comprise controller (12), the lift pump control end of described controller (12) connects lift pump (2e), the Valve controlling end of described controller (12) connects valve (11), water level signal is passed to controller (12) by described water level gauge (13), when water level exceedes appointment water level, controller (12) by-pass valve control (11) is opened, and controls lift pump (2e) work simultaneously; When water level is lower than appointment water level, described controller (12) by-pass valve control (11) and lift pump (2e) are closed.
2. be applicable to the manpower rapid-infiltration water treatment device of field town sanitary sewage according to claim 1, it is characterized in that: the limit of the base plate of described preliminary sedimentation tank (2a) and even pond (2b) is equipped with a pit, described sludge pump (2c) and lift pump (2e) are arranged in pit.
CN201510880566.2A 2015-12-03 2015-12-03 Constructed rapid infiltration water treatment device suitable for town domestic wastewater Pending CN105399229A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510880566.2A CN105399229A (en) 2015-12-03 2015-12-03 Constructed rapid infiltration water treatment device suitable for town domestic wastewater

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510880566.2A CN105399229A (en) 2015-12-03 2015-12-03 Constructed rapid infiltration water treatment device suitable for town domestic wastewater

Publications (1)

Publication Number Publication Date
CN105399229A true CN105399229A (en) 2016-03-16

Family

ID=55465041

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510880566.2A Pending CN105399229A (en) 2015-12-03 2015-12-03 Constructed rapid infiltration water treatment device suitable for town domestic wastewater

Country Status (1)

Country Link
CN (1) CN105399229A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11165196A (en) * 1997-12-05 1999-06-22 Kimio Okamoto Sludge dehydration treatment device
CN1676469A (en) * 2004-09-17 2005-10-05 钟佐燊 Artificial rapid diafiltration sewage treating system
CN202237426U (en) * 2011-09-30 2012-05-30 机械工业第三设计研究院 Filter bed system of sludge drying tank

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11165196A (en) * 1997-12-05 1999-06-22 Kimio Okamoto Sludge dehydration treatment device
CN1676469A (en) * 2004-09-17 2005-10-05 钟佐燊 Artificial rapid diafiltration sewage treating system
CN202237426U (en) * 2011-09-30 2012-05-30 机械工业第三设计研究院 Filter bed system of sludge drying tank

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
余建朋 等: ""CRI工艺在三峡库区小城镇污水处理厂中的应用"", 《给水排水》 *
李正昱等: "人工快速渗滤系统的研究与应用", 《中国给水排水》 *
李璐 等: ""人工快渗污水处理工艺特点及在中小城镇污水处理中的应用"", 《2008小城镇及农村污水处理工程建设与技术应用研讨会》 *
潘彩萍 等: ""CRI工艺在生活污水处理回用中的应用"", 《节能与环保》 *
盛国荣: ""人工快渗工艺设计的若干问题探讨"", 《中国给水排水》 *

Similar Documents

Publication Publication Date Title
WO2015139484A1 (en) Constructed wetland sewage treatment device and sewage treatment method therefor
CN103693745A (en) Compound constructed wetland processing method and device for runoff pollutants in rivers
CN103112988B (en) Multilevel compound coupling artificial wetland system and its application
CN202849167U (en) Staged root zone sewage treatment ecological artificial wetland system
CN105502716A (en) Intelligent CRI (constructed rapid infiltration) treatment method for market-town life sewage
CN205442817U (en) Be fit for a domestic sewage purification system that town used
CN205313214U (en) Field town sewage treatment system that construction cost is low
CN105502810A (en) Drying treatment assembly for market-town domestic sewage and sludge
CN205472991U (en) Artifical rapid infiltration layer water processing system
CN205528026U (en) Be fit for town domestic sewage's an artifical rapid infiltration layer system
CN105314800A (en) Intelligent constructed rapid infiltration sewage treatment system
CN105399229A (en) Constructed rapid infiltration water treatment device suitable for town domestic wastewater
CN105347535A (en) Constructed domestic-sewage rapid infiltration and purification system
CN105417866A (en) Constructed rapid infiltration sewage treatment system
CN205313317U (en) Field town's sewage and sludge drying handle subassembly
CN205313318U (en) Artifical rapid infiltration layer clean system of field town domestic sewage
CN210887511U (en) Shunting pollution control system for initial rainwater
CN203845911U (en) Multi-medium biological contact vertical composite underflow artificial wetland
CN205528247U (en) Field town domestic sewage purification system
CN205313216U (en) Artifical rapid infiltration layer sewage treatment system
CN105314752A (en) Intelligent constructed rapid infiltration market town domestic sewage treatment system
CN203833761U (en) Biochemical filtration integrated device for advanced treatment of rural sewage
CN105289104A (en) Sewage treatment device
CN105293740A (en) Intelligent sewage treatment system suitable for market town
CN105502809A (en) Novel manual rapid infiltration sewage treatment device suitable for market town domestic sewage

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160316