CN105318860B - Building subsidence observation method and structure - Google Patents

Building subsidence observation method and structure Download PDF

Info

Publication number
CN105318860B
CN105318860B CN201410393266.7A CN201410393266A CN105318860B CN 105318860 B CN105318860 B CN 105318860B CN 201410393266 A CN201410393266 A CN 201410393266A CN 105318860 B CN105318860 B CN 105318860B
Authority
CN
China
Prior art keywords
building
auxiliary base
base point
steel
observation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410393266.7A
Other languages
Chinese (zh)
Other versions
CN105318860A (en
Inventor
陈红兵
张红卫
朱小周
夏盛鹏
牛超
张道利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Hao Rong Construction Work Co Ltd
Precious Xiang Building Materials In Wuhu Detect Co Ltd
Anhui Bao Xiang Construction Group LLC
Original Assignee
Anhui Hao Rong Construction Work Co Ltd
Precious Xiang Building Materials In Wuhu Detect Co Ltd
Anhui Bao Xiang Construction Group LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Hao Rong Construction Work Co Ltd, Precious Xiang Building Materials In Wuhu Detect Co Ltd, Anhui Bao Xiang Construction Group LLC filed Critical Anhui Hao Rong Construction Work Co Ltd
Priority to CN201410393266.7A priority Critical patent/CN105318860B/en
Publication of CN105318860A publication Critical patent/CN105318860A/en
Application granted granted Critical
Publication of CN105318860B publication Critical patent/CN105318860B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention relates to one kind to build detection structure, more particularly, to a kind of building subsidence observation method and structure.Some working base points are embedded with skin face, three datum marks and four auxiliary base points are embedded with surrounding's engineering foundation of building, auxiliary base point is observed by three datum marks, examines the relative stability of datum mark and auxiliary base point;Working base point is observed by four auxiliary base points, collection eccentricity determines Deposition Situation.The present invention has the features such as simple in construction, construction cost is relatively low, is not easy by Effects on Engineering, is not easy to be influenceed by Changes in weather, is not easy to be affected by thermal expansion and contraction, and measurement error is smaller.

Description

Building subsidence observation method and structure
Technical field
The present invention relates to one kind to build detection structure, more particularly, to a kind of building subsidence observation method and structure.
Background technology
Whether the purpose of building subsidence observation is uniform by observing grasp building settlement, to judge design and construction Whether situation is reasonable, if influences structure and provides data safely, true to reflect building settlement situation, this requires settlement observation As a result must be accurately and reliably.Under normal circumstances, in order to observe sedimentation situation, observation datum mark is buried in the surrounding of engineering, is passed through Observe datum mark and grasp sedimentation situation.It is easily heated but commonly observation datum mark is easily influenceed easily by Effects on Engineering by Changes in weather Swollen shrinkage influences, and causes error of observation data bigger than normal, so as to can not accurately reflect building settlement situation.
The content of the invention
The present invention is easily influenceed by Changes in weather primarily directed to easy by Effects on Engineering present in prior art, easily heated Swollen shrinkage influences, the technical problem of the larger grade of measurement error, there is provided a kind of simple in construction, construction cost is relatively low, is not easy by engineering Influence, be not easy to be influenceed by Changes in weather, be not easy to be affected by thermal expansion and contraction, the less settlement observation method of measurement error and structure.
The above-mentioned technical problem of the present invention is mainly what is be addressed by following technical proposals:Buried in skin face Provided with some working base points, three datum marks and four auxiliary base points, benchmark are embedded with surrounding's engineering foundation of building Point is made up of concrete pier and round steel, and concrete pier is coated with sand protective layer, and concrete pier top portion is provided with a cavity, and round steel is extended by concrete pier bottom To cavity, covered with reinforced mesh on cavity, concrete bed course has been poured outside reinforced mesh, in working base point is connected to by screw flight Formed on threaded steel pipe, fixed angle steel is fixedly connected with skin face, inner thread steel pipe is welded with fixed angle steel, it is interior It is cased with fixing steel box outside threaded steel pipe, screw rod outside weld is connected to a steel ball, and auxiliary base point is made up of concrete column, buried in concrete column There is reinforcing bar, reinforcing bar head is exposed at outside concrete column, and steel loop is welded with reinforcing bar.
Working base point is in same level.The elevation of water is tried one's best the position for being maintained at nearer from the ground, optimal Choosing height is 1 to 2 meter of height from the ground.
The distance of datum mark and building is 50 meters to 100 meters.The triangle formed between three datum marks is building It is enclosed in the delta-shaped region.
Auxiliary base point is arranged on the corner of building, and the distance of auxiliary base point and building is 10 meters to 20 meters.Four The quadrangle that individual auxiliary base point is connected into is in the delta-shaped region that three datum marks are connected into.
When detecting the sedimentation degree of building, the first step passes through three datum marks successively all auxiliary in observation visual angle Datum mark, examine the relative stability of datum mark and auxiliary base point;Second step is observed and regarded successively by four auxiliary base points All working basic point in angle, the eccentricity using special instrument through steel loop observation steel ball.When auxiliary base point or work base When point is blocked by building, this group of eccentricity data can be excluded;When the stability of auxiliary base point is bad, the auxiliary base is excluded The data gathered on schedule.
Under normal circumstances, special instrument is the high-precision level of in the market buying.
Therefore, the present invention has simple in construction, and construction cost is relatively low, is not easy by Effects on Engineering, is not easy by Changes in weather shadow The features such as sound, is not easy to be affected by thermal expansion and contraction, and measurement error is smaller.
Brief description of the drawings
Accompanying drawing 1 is the overall structure diagram of the present invention;
Accompanying drawing 2 is the working base point structural representation of the present invention;
Accompanying drawing 3 is the datum mark structural representation of the present invention;
Accompanying drawing 4 is the auxiliary base point structural representation of the present invention.
Embodiment
Below by embodiment, and with reference to accompanying drawing, technical scheme is described in further detail.
Embodiment 1:Building subsidence observation structure is used for the sedimentation degree for observing building, is buried on the wall face of building 4 Provided with four working base points 1, working base point 1 is in same level, and three bases are embedded with surrounding's engineering foundation of building 4 On schedule 2 and four auxiliary base points 3, three datum marks 2 divide for A, B, C, and four auxiliary base points 3 minutes are E, F, G, H, four works Make basic point 1 to divide for W, X, S, Z, the distance of datum mark 2 and building 4 is 70 meters, and auxiliary base point 3 is arranged on the four of building 4 Angle, the distance of auxiliary base point 3 and building 4 is 15 meters (as shown in Figure 1).
Working base point 1 is threaded on inner thread steel pipe 12 by screw rod 11 and formed, and is fixedly connected on the wall face of building 4 There is fixed angle steel 13, inner thread steel pipe 12 is welded with fixed angle steel 13, is cased with fixing steel box 14, screw rod outside inner thread steel pipe 12 11 outside welds are connected to a steel ball 15 (as shown in Figure 2).
Datum mark 2 is made up of concrete pier 21 and round steel 22, and concrete pier 21 is coated with sand protective layer 26, and the top of concrete pier 21 is provided with one Individual cavity 23, round steel 22 extend to cavity 23 by the bottom of concrete pier 21, poured outside covered with reinforced mesh 24, reinforced mesh 24 on cavity 23 Concrete bed course 25 (as shown in Figure 3) is built.
Auxiliary base point 3 is made up of concrete column 31, and reinforcing bar 32 is embedded with concrete column 31, and the head of reinforcing bar 32 is exposed at concrete column Outside 31, steel loop 33 (as shown in Figure 4) is welded with reinforcing bar 32.
When observing the sedimentation situation of building, first group of data acquisition:The first step is by datum mark A successively in observation visual angle Auxiliary base point E and F, examine datum mark A and auxiliary base point E and F stability;Second step by auxiliary base point E successively Working base point W and Z in observation visual angle and by auxiliary base point F successively the working base point W and X in observation visual angle, using special Industry instrument records after the eccentricity of steel ball 15 is observed through steel loop 33.
Second group of data acquisition:The first step examines benchmark by datum mark B successively auxiliary base point F and G in observation visual angle Point B and auxiliary base point F and G stability;Second step by the auxiliary base point F successively working base point W in observation visual angle and X, by the auxiliary base point G successively working base point X in observation visual angle, steel ball 15 is observed through steel loop 33 using special instrument Recorded after eccentricity.
3rd group of data acquisition:The first step examines benchmark by datum mark C successively auxiliary base point E and H in observation visual angle Point C and auxiliary base point E and H stability;Second step by the auxiliary base point E successively working base point W in observation visual angle and Z, by auxiliary base point H successively the working base point S and Z in observation visual angle, steel ball is observed through steel loop 33 using special instrument Recorded after 15 eccentricity.

Claims (5)

  1. A kind of 1. building subsidence observation structure, for observing the sedimentation degree of building, it is characterised in that the building (4) some working base points (1) are embedded with wall face, three datum marks (2) are embedded with surrounding's engineering foundation of building (4) With four auxiliary base points (3), datum mark (2) is made up of concrete pier (21) and round steel (22), and concrete pier (21) is coated with sand protection Layer (26), concrete pier (21) top are provided with a cavity (23), and round steel (22) extends to cavity (23), cavity by concrete pier (21) bottom (23) concrete bed course (25) has been poured outside covered with reinforced mesh (24), reinforced mesh (24) on, working base point (1) is by screw rod (11) It is threaded on inner thread steel pipe (12) and forms, fixed angle steel (13), fixed angles is fixedly connected with building (4) wall face Inner thread steel pipe (12) is welded with steel (13), is cased with fixing steel box (14), screw rod (11) external welding outside inner thread steel pipe (12) There is a steel ball (15), auxiliary base point (3) is made up of concrete column (31), and reinforcing bar (32), reinforcing bar are embedded with concrete column (31) (32) head is exposed at concrete column (31) outside, and steel loop (33) is welded with reinforcing bar (32).
  2. 2. building subsidence observation structure according to claim 1, it is characterised in that the working base point (1) is in same On one horizontal plane.
  3. 3. building subsidence observation structure according to claim 1, it is characterised in that the datum mark (2) and building (4) distance is 50 meters to 100 meters.
  4. 4. building subsidence observation structure according to claim 1, it is characterised in that the auxiliary base point (3) is set In the corner of building (4), the distance of auxiliary base point (3) and building (4) is 10 meters to 20 meters.
  5. 5. a kind of observation procedure for being used for the building subsidence observation structure as described in claim any one of 1-4, its feature exist In, the first step by three datum marks (2) successively all auxiliary base points (3) in observation visual angle, examine datum mark (2) with it is auxiliary Help the relative stability of datum mark (3);Second step passes through four auxiliary base points (3) the successively all working base in observation visual angle Point (1), the eccentricity using special instrument through steel loop (33) observation steel ball (15).
CN201410393266.7A 2014-08-04 2014-08-04 Building subsidence observation method and structure Active CN105318860B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410393266.7A CN105318860B (en) 2014-08-04 2014-08-04 Building subsidence observation method and structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410393266.7A CN105318860B (en) 2014-08-04 2014-08-04 Building subsidence observation method and structure

Publications (2)

Publication Number Publication Date
CN105318860A CN105318860A (en) 2016-02-10
CN105318860B true CN105318860B (en) 2018-02-13

Family

ID=55246770

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410393266.7A Active CN105318860B (en) 2014-08-04 2014-08-04 Building subsidence observation method and structure

Country Status (1)

Country Link
CN (1) CN105318860B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108931231A (en) * 2017-05-27 2018-12-04 中国二十冶集团有限公司 The observation method of high-precision rolling mill foundation settlement
CN111060070A (en) * 2020-01-13 2020-04-24 中国水利水电第四工程局有限公司 Method for observing uneven settlement of buildings around pipe gallery
CN111336985B (en) * 2020-02-27 2021-09-28 国网山西省电力公司晋城供电公司 Monitoring method and device for goaf iron tower, storage medium and electronic equipment
CN111609833B (en) * 2020-05-26 2021-12-31 武汉弘泰建筑工程质量检测有限公司 Settlement observation method for high-rise building
CN113202152B (en) * 2021-05-24 2022-02-22 浙江省第一水电建设集团股份有限公司 Building settlement safety monitoring method based on wireless sensor data acquisition technology

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007212430A (en) * 2006-08-07 2007-08-23 Kurabo Ind Ltd Photogrammetry device and system
JP2010185801A (en) * 2009-02-12 2010-08-26 Tokyo Keisoku:Kk State-change measurement system using imaging device
CN201828266U (en) * 2010-08-20 2011-05-11 许昌中原建设(集团)有限公司 Denoter for sedimentation observation points of buildings
CN201972063U (en) * 2011-03-14 2011-09-14 西南交通大学 Equipment for monitoring sedimentation of rapid transit railway works
CN102322266A (en) * 2011-06-17 2012-01-18 中铁十一局集团第五工程有限公司 Tunnel excavating and constructing method
CN203024760U (en) * 2012-11-05 2013-06-26 山西潞安环保能源开发股份有限公司 Similar material settlement monitoring device
CN203857965U (en) * 2014-05-15 2014-10-01 浙江乔兴建设集团有限公司 Settlement observation reference point protection structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007212430A (en) * 2006-08-07 2007-08-23 Kurabo Ind Ltd Photogrammetry device and system
JP2010185801A (en) * 2009-02-12 2010-08-26 Tokyo Keisoku:Kk State-change measurement system using imaging device
CN201828266U (en) * 2010-08-20 2011-05-11 许昌中原建设(集团)有限公司 Denoter for sedimentation observation points of buildings
CN201972063U (en) * 2011-03-14 2011-09-14 西南交通大学 Equipment for monitoring sedimentation of rapid transit railway works
CN102322266A (en) * 2011-06-17 2012-01-18 中铁十一局集团第五工程有限公司 Tunnel excavating and constructing method
CN203024760U (en) * 2012-11-05 2013-06-26 山西潞安环保能源开发股份有限公司 Similar material settlement monitoring device
CN203857965U (en) * 2014-05-15 2014-10-01 浙江乔兴建设集团有限公司 Settlement observation reference point protection structure

Also Published As

Publication number Publication date
CN105318860A (en) 2016-02-10

Similar Documents

Publication Publication Date Title
CN105318860B (en) Building subsidence observation method and structure
CN204479060U (en) A kind of subgrade stability recording geometry
CN103243747B (en) Deviation rectifying method of prestressed concrete pipe pile foundation
CN107131862B (en) Rock-fill dam panel deformation monitoring device and construction method
KR101162918B1 (en) Method of measuring underground displacement using inclinometer
CN103913145A (en) Crack opening two-direction deformation monitoring structure and measurement method
CN106813590A (en) External floating roof tank deformation detection method
CN106759548A (en) For the monitoring system and monitoring method of lattice suspension roof support cutting
CN110207655A (en) Subgrade settlement monitoring settlement gauge and monitoring method
CN115387221A (en) High pier line type control method for high altitude area
CN106759542A (en) The deformation monitoring of deep basal pit and the method for Deformation Prediction
CN206457859U (en) A kind of detachable apparatus for facilitating open caisson to observe skew and absolute altitude
CN103741726B (en) A kind of open caisson settlement measurement metering method
CN106638535B (en) Foundation pit construction local supervising and measuring equipment and monitoring method
CN102927944B (en) Land movement measuring method and device in large-scale experiment
CN205502092U (en) Testing arrangement of bored concrete pile burden frictional resistance neutral point in deep back filling
CN109811771A (en) Make the simple and easy method not bent when anchor bar steel waist rail tensioning
CN103276755A (en) Raft foundation bottom soil body void deformation monitoring device
CN107476327A (en) Narrow base list column step foundation construction method
CN109113040B (en) It is measured in observation platform and its construction method and water in water and measures observation system
CN206438544U (en) Monitoring system for lattice suspension roof support cutting
CN203795884U (en) Safe and reliable construction system for replacing columns by holding beams
CN106482621A (en) A kind of device of Bridge Pier sinking deformation monitoring and its chucking device
CN105841592A (en) Jacking axis offset measuring device and application method thereof
CN105862901B (en) Docking formula bedrock survey mark and its construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant