CN105303065A - Current transformer operation condition testing method - Google Patents

Current transformer operation condition testing method Download PDF

Info

Publication number
CN105303065A
CN105303065A CN201510889721.7A CN201510889721A CN105303065A CN 105303065 A CN105303065 A CN 105303065A CN 201510889721 A CN201510889721 A CN 201510889721A CN 105303065 A CN105303065 A CN 105303065A
Authority
CN
China
Prior art keywords
current transformer
value
current
operating condition
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510889721.7A
Other languages
Chinese (zh)
Other versions
CN105303065B (en
Inventor
刘毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Si Han Science And Technology Co Ltd
Original Assignee
Chengdu Si Han Science And Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Si Han Science And Technology Co Ltd filed Critical Chengdu Si Han Science And Technology Co Ltd
Priority to CN201510889721.7A priority Critical patent/CN105303065B/en
Publication of CN105303065A publication Critical patent/CN105303065A/en
Application granted granted Critical
Publication of CN105303065B publication Critical patent/CN105303065B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a current transformer operation condition testing method which is high in efficiency and comprehensive and accurate in test result. According to the testing method, by collecting basic information data and site operation data of a current transformer, the collected data are classified, and a current transformer operation state value RI is calculated, and by means of the corresponding relation between a preset current transformer operation condition value and the operation state, the actual operation state corresponding to an actual operation condition value of the current transformer is determined. The testing method is high in efficiency, the situation that due to man-made reasons, equipment normally operating originally breaks down is avoided, the influence on the current transformer from secondary load values, primary current percentage values, environment temperature, relative environment humidity, residual magnetism and an adjacent primary conductor magnetic field is considered in the testing method, the operation condition of the current transformer can be tested comprehensively, and it is ensured that the final obtained test result is accurate, comprehensive and high in reliability. The method is suitable for being applied to and popularized in the technical field of gateway metering equipment state evaluation.

Description

A kind of operating condition method of inspection of current transformer
Technical field
The present invention relates to energy metering equipment state assessment technology field, especially a kind of operating condition method of inspection of current transformer.
Background technology
In order to ensure that current transformer can normally run and the reliability of continuous data, usually need to carry out long-range estimation to the operating condition of current transformer, the existing current transformer operating condition method of inspection is mostly the mode adopting desk checking, the mode of desk checking needs a large amount of computation process of manually carrying out field test and complexity, inefficiency, secondly, manually when carrying out on-the-spot accuracy test to current transformer, repetitious operation being carried out to current transformer, causing the normal device fails run originally, there is larger potential faults, in addition, the existing current transformer operating condition method of inspection is only simple to be detected the equipment quality of current transformer, and the condition monitoring of current transformer is often out in the cold, and the impact that the fault of this part is brought is sometimes very larger, therefore, the existing current transformer operating condition method of inspection can not realize the complete examination of current transformer operating condition, cause the operating condition assay that finally draws inaccurate, and manual intervention easily makes mistakes and causes assay reliability low, accurately cannot grasp the operating condition dynamic security stability of electric energy current transformer, and then also cannot ensure each main electrical current mutual inductor safety, stable, accurate operation, shortage is dynamically followed the tracks of accident treatment information and is analyzed, Dynamic controlling can not be carried out to catastrophic failure.
Summary of the invention
Technical matters to be solved by this invention is to provide the high and operating condition method of inspection of the comprehensive and accurate current transformer of assay of a kind of efficiency.
The technical solution adopted for the present invention to solve the technical problems is: the operating condition method of inspection of this current transformer, comprises the following steps:
The basic information data of A, collected current mutual inductor and on-the-spot service data;
B, data to be classified, data are divided into following two classes: current transformer basic information data, current transformer Monitoring Data;
C, according to current transformer basic information data, current transformer Monitoring Data calculating current mutual inductor operating condition value R i; By the current transformer operating condition value preset and the corresponding relation of running status, determine the actual motion state corresponding to actual operating mode value of current transformer.
Further, described current transformer operating condition value R ifollowing formulae discovery is adopted to obtain:
Described R iiSe sI+ ω iIe iI+ ω iTe tI+ ω iHe hI+ ω iRe rI+ ω iMe mI, and ω iS+ ω iI+ ω iT+ ω iH+ ω iR+ ω iM=1;
E S I = 1 - | S I - S I 0 | / S I 0 &times; 100 % , 0 &le; S I < S I 0 1 , S I 0 &le; S I < S I n 1 - | S I - S I n | / S I n &times; 100 % , S I n < S I &le; 2 S I n 1 , S I > 2 S I n , Wherein, S ifor on-line monitoring obtains the secondary load of current transformer, S infor the rated load of current transformer, S i0for the secondary load lower limit of current transformer;
E I I = I I , 0 &le; I I < 1 1 , 1 &le; I I &le; I I m a x 0 , I I > I I m a x , Wherein, I ifor the primary current percentage value of current transformer, the primary current percentage value of current transformer refers to the ratio of the rated current of the current transformer primary current that on-line monitoring obtains and current transformer, I imaxfor the primary current number percent maximal value of current transformer;
wherein, T iambient temperature value residing for current transformer, T infor the specified ambient temperature value of current transformer, C tI1and C tI2for temperature causes the rate of change coefficient of variation;
wherein, H iambient humidity value residing for current transformer, H infor the specified ambient humidity of current transformer, C hIfor humidity causes the rate of change of variation;
wherein, t rIfor the time of defluidization appears in nearest primary current mutual inductor, τ rfor remanent magnetism damping time constant;
wherein, M ifor closing on Primary Conductor magnetic field intensity, M infor specified magnetic field intensity, C mIfor magnetic field intensity causes the rate of change coefficient of variation.
Further, described weights ω iS, ω iI, ω iT, ω iH, ω iR, ω iMadopt and determine with the following method, the method comprises the following steps:
G1, determine order relation: at { E sI, E iI, E tI, E hI, E rI, E mIin select proportion maximum a type be designated as G 1 *; Then the type selecting proportion maximum in five types of remainder is designated as G 2 *; The type selecting proportion maximum in four types of remainder is designated as G 3 *, the type selecting proportion maximum in three types of remainder is designated as G 4 *, the type selecting proportion maximum in two types of remainder is designated as G 5 *, finally remaining type is designated as G 6 *, its order relation is wherein represent type G 1 *proportion be greater than or be not less than G 2 *, determine E thus sI, E iI, E tI, E hI, E rI, E mIorder relation;
The ratio in judgement of g2, adjacent type proportion size: adjacent type G k-1with G kbetween the ratio G of proportion size k-1/ G kk, k=6,5,4,3,2, according to G k-1with G kproportion size, η kspan be 1.0-1.8;
G3, scale-up factor calculate: g2 step is drawn η kvalue brings following formula into:
&omega; m = ( 1 + &Sigma; k = 2 m &Pi; i = k m &eta; i ) - 1 &omega; k - 1 = &eta; k &omega; k , k = m , m - 1 , ... , 2 Wherein, m=6
G can be calculated 1, G 2, G 3, G 4, G 5, G 6weight vector ω=[ω 1, ω 2, ω 3, ω 4, ω 5, ω 6], ω 1, ω 2, ω 3, ω 4, ω 5, ω 6corresponding G 1, G 2, G 3, G 4, G 5, G 6weights, just correspondence can draw ω according to the order relation determined iS, ω iI, ω iT, ω iH, ω iR, ω iMvalue.
Beneficial effect of the present invention: the operating condition method of inspection of this current transformer passes through the basic information data of collected current mutual inductor and on-the-spot service data, carries out classification and calculating current mutual inductor operating condition value R to the data of collecting iby the current transformer operating condition value preset and the corresponding relation of running status, determine the actual motion state corresponding to actual operating mode value of current transformer, this method of inspection is the running status by drawing current transformer to the analysis of data, without the need to manually carrying out field test, efficiency is high, secondly, decrease artificial intervention, there will not be because artificial origin causes the normal device fails run originally, equipment failure hidden danger is lower, moreover, this method of inspection considers secondary load value, primary current percentage value, environment temperature, envionmental humidity, remanent magnetism, contiguous Primary Conductor magnetic field is on the impact of current transformer, the complete examination of current transformer operating condition can be realized, ensure that the operating condition assay finally drawn is accurate, comprehensively, reliability is high, accurately can grasp the dynamic security stability of electric energy current transformer operating condition, and then ensure each main electrical current mutual inductor safety, stable, accurate operation, can dynamically follow the tracks of accident treatment information and analyze, thus Dynamic controlling is carried out to catastrophic failure.
Embodiment
The operating condition method of inspection of current transformer of the present invention, comprises the following steps:
The basic information data of A, collected current mutual inductor and on-the-spot service data, the basic information data of current transformer can be obtained by existing metering production scheduling platform (MDS), metering production scheduling platform (MDS) summarizes all Back ground Informations of the current transformer supply of material, when the basic information data of collected current mutual inductor, the related data that metering production scheduling platform stores only need be called, the on-the-spot service data of current transformer can be obtained by existing power information acquisition system, power information acquisition system can realize the metering electricity of current transformer, the collection monitoring of the Various types of data such as operating condition and logout, wherein, on-line monitoring and intelligent diagnostics module are by image data, the compare of analysis of event and data mining, the ruuning situation of electric energy meter is diagnosed and analyzes, Timeliness coverage electricity, the abnormal conditions such as load, when the on-the-spot service data of collected current mutual inductor, only need call the related data that power information acquisition system gathers,
B, data to be classified, data are divided into following two classes: current transformer basic information data, current transformer Monitoring Data;
C, according to current transformer basic information data, current transformer Monitoring Data calculating current mutual inductor operating condition value R i; By the current transformer operating condition value preset and the corresponding relation of running status, determine the actual motion state corresponding to actual operating mode value of current transformer.
The corresponding relation of current transformer operating condition value and running status is as shown in the table:
The operating condition method of inspection of this current transformer passes through the basic information data of collected current mutual inductor and on-the-spot service data, carries out classification and calculating current mutual inductor operating condition value R to the data of collecting iby the current transformer operating condition value preset and the corresponding relation of running status, determine the actual motion state corresponding to actual operating mode value of current transformer, this method of inspection is the running status by drawing current transformer to the analysis of data, without the need to manually carrying out field test, efficiency is high, secondly, decrease artificial intervention, there will not be because artificial origin causes the normal device fails run originally, equipment failure hidden danger is lower, moreover, this method of inspection considers secondary load value, primary current percentage value, environment temperature, envionmental humidity, remanent magnetism, contiguous Primary Conductor magnetic field is on the impact of current transformer, the complete examination of current transformer operating condition can be realized, ensure that the operating condition assay finally drawn is accurate, comprehensively, reliability is high, accurately can grasp the dynamic security stability of electric energy current transformer operating condition, and then ensure each main electrical current mutual inductor safety, stable, accurate operation, can dynamically follow the tracks of accident treatment information and analyze, thus Dynamic controlling is carried out to catastrophic failure.
Described current transformer operating condition value R ifollowing formulae discovery is adopted to obtain:
Described R iiSe sI+ ω iIe iI+ ω iTe tI+ ω iHe hI+ ω iRe rI+ ω iMe mI, and ω iS+ ω iI+ ω iT+ ω iH+ ω iR+ ω iM=1;
E S I = 1 - | S I - S I 0 | / S I 0 &times; 100 % , 0 &le; S I < S I 0 1 , S I 0 &le; S I < S I n 1 - | S I - S I n | / S I n &times; 100 % , S I n < S I &le; 2 S I n 1 , S I > 2 S I n , Wherein, S ifor on-line monitoring obtains the secondary load of current transformer, Current Transformer Secondary side does not allow open circuit, and load is the smaller the better, and the on-line testing method of current transformer secondary load is for adopt wire laying mode at the scene to obtain voltage U from transformer circuit top 0, then from observation circuit, obtain current value, S i=U 0× I 2; S infor the rated load of current transformer, S i0for the secondary load lower limit of current transformer, when the secondary rated current of current transformer is 5A, the secondary load lower limit S of current transformer i0for 3.75VA, when the secondary rated current of current transformer is 1A, the secondary load lower limit S of current transformer i0for 1VA;
E I I = I I , 0 &le; I I < 1 1 , 1 &le; I I &le; I I m a x 0 , I I > I I m a x , Wherein, I ifor the primary current percentage value of current transformer, the primary current percentage value of current transformer refers to the ratio of the rated current of the current transformer primary current that on-line monitoring obtains and current transformer, I imaxfor the primary current number percent maximal value of current transformer, its maximal value is 120%;
wherein, T iambient temperature value residing for current transformer, T infor the specified ambient temperature value of current transformer, according to electric power mutual-inductor JJG1021-2007 standard verification, the current transformer error change that environment temperature independent role causes is no more than fundamental error limit value 1/4, and in test condition, temperature range is-25 ~ 55 DEG C, at rated temperature T inunder the variation that causes close to 0, and when temperature far exceeds the upper limit, lower range, its change caused close to fundamental error limit value 1/4, specified environment temperature T inbe 25 DEG C, C tI1and C tI2for temperature causes the rate of change coefficient of variation, get C respectively tI1=2, C tI2=3;
wherein, H iambient humidity value residing for current transformer, H infor the specified ambient humidity of current transformer, C hIfor humidity causes the rate of change of variation; Be not more than 95% according to regulation envionmental humidity in electric power mutual-inductor JJG1021-2007 standard verification, the current transformer error change that ambient humidity independent role causes is no more than fundamental error limit value 1/8, when ambient humidity is less than specified humidity H inin time, is deteriorated accordingly close to 0, specified ambient humidity H inbe 65%, humidity causes the rate of change C of variation hIbe 5%;
wherein, t rIfor the time of defluidization appears in nearest primary current mutual inductor, τ rfor remanent magnetism damping time constant, remanent magnetism damping time constant unit min, current transformer is when electric current declines suddenly, current transformer core may produce remanent magnetism, it will make iron core magnetic conductance decline, affect accuracy of instrument transformers, specify in current transformer JJG1021-2007 standard verification, for the variation limit value that remanence of current transformer independent role causes, be no more than 1/3 of fundamental error limit value, remanence of current transformer is cut off the electricity supply suddenly by big current situation, the Secondary Winding reason such as to open a way suddenly produces, main manifestations is Secondary Winding defluidization, remanent magnetism size and load current number percent are proportionate, along with passage of time remanent magnetism DC component decays to 0 gradually, the impact of current transformer error is also reduced gradually, for remanent magnetism damping time constant τ rfor 50min,
wherein, M ifor closing on Primary Conductor magnetic field intensity, it closes on Primary Conductor magnetic field intensity and is restricted to 100 μ T, M infor specified magnetic field intensity, C mIfor magnetic field intensity causes the rate of change coefficient of variation; Specify in electric power mutual-inductor JJG1021-2007 standard verification, for the variation limit value that current transformer contiguous Primary Conductor magnetic field independent role causes, be no more than 1/4 of fundamental error limit value, when magnetic field intensity is less than specified magnetic field intensity M inin time, is deteriorated accordingly close to 0, specified magnetic field intensity M inbe 50 μ T, magnetic field intensity causes the rate of change coefficient C of variation mIbe 10.
The current transformer operating condition value R utilizing said method to calculate iaccurately, comprehensively, reliability is high, accurately can grasp the operating condition dynamic security stability of current transformer, and then ensure current transformer safety, stable, accurately run, can current transformer accident treatment information dynamically be followed the tracks of and be analyzed, thus Dynamic controlling is carried out to current transformer catastrophic failure.
In the above-described embodiment, described weights ω iS, ω iI, ω iT, ω iH, ω iR, ω iMclassical layer fractional analysis can be adopted to draw, but this method not easily constructs the differentiation battle array meeting coherence request, therefore, the invention provides a kind of simple effective method to determine weights ω iS, ω iI, ω iT, ω iH, ω iR, ω iM, the method comprises the following steps:
G1, determine order relation: at { E sI, E iI, E tI, E hI, E rI, E mIin select proportion maximum a type be designated as G 1 *; Then the type selecting proportion maximum in five types of remainder is designated as G 2 *; The type selecting proportion maximum in four types of remainder is designated as G 3 *, the type selecting proportion maximum in three types of remainder is designated as G 4 *, the type selecting proportion maximum in two types of remainder is designated as G 5 *, finally remaining type is designated as G 6 *, its order relation is wherein represent type G 1 *proportion be greater than or be not less than G 2 *, determine E thus sI, E iI, E tI, E hI, E rI, E mIorder relation;
The ratio in judgement of g2, adjacent type proportion size: adjacent type G k-1with G kbetween the ratio G of proportion size k-1/ G kk, k=6,5,4,3,2, according to G k-1with G kproportion size, η kspan be 1.0-1.8; η kthe value rule judged is as described below:
G3, scale-up factor calculate: g2 step is drawn η kvalue brings following formula into:
&omega; m = ( 1 + &Sigma; k = 2 m &Pi; i = k m &eta; i ) - 1 &omega; k - 1 = &eta; k &omega; k , k = m , m - 1 , ... , 2 Wherein, m=6
G can be calculated 1, G 2, G 3, G 4, G 5, G 6weight vector ω=[ω 1, ω 2, ω 3, ω 4, ω 5, ω 6], ω 1, ω 2, ω 3, ω 4, ω 5, ω 6corresponding G 1, G 2, G 3, G 4, G 5, G 6weights, just correspondence can draw ω according to the order relation determined iS, ω iI, ω iT, ω iH, ω iR, ω iMvalue.
The weights utilizing said method to draw more tally with the actual situation the secondary load value of middle current transformer, primary current percentage value, environment temperature, envionmental humidity, remanent magnetism, contiguous proportion shared by Primary Conductor magnetic field, can make finally to draw that the operating condition state value of current transformer conforms to more with actual operating condition state, its matching degree and accuracy higher.

Claims (3)

1. an operating condition method of inspection for current transformer, is characterized in that comprising the following steps:
The basic information data of A, collected current mutual inductor and on-the-spot service data;
B, data to be classified, data are divided into following two classes: current transformer basic information data, current transformer Monitoring Data;
C, according to current transformer basic information data, current transformer Monitoring Data calculating current mutual inductor operating condition value R i; By the current transformer operating condition value preset and the corresponding relation of running status, determine the actual motion state corresponding to actual operating mode value of current transformer.
2. the operating condition method of inspection of current transformer as claimed in claim 1, is characterized in that: described current transformer operating condition value R ifollowing formulae discovery is adopted to obtain:
Described R iiSe sI+ ω iIe iI+ ω iTe tI+ ω iHe hI+ ω iRe rI+ ω iMe mI, and ω iS+ ω iI+ ω iT+ ω iH+ ω iR+ ω iM=1;
E SI = 1 - | S I - S I 0 | / S I 0 &times; 100 % , 0 &le; S I < S I 0 1 , S I 0 &le; S I &le; S In 1 - | S I - S In | / S In &times; 100 % , S In < S I &le; 2 S In 0 , S I > 2 S In , Wherein, S ifor on-line monitoring obtains the secondary load value of current transformer, S infor the rated load of current transformer, S i0for the secondary load lower limit of current transformer;
E II = I I , 0 &le; I I < 1 1 , 1 &le; I I &le; I I max 0 , I I > I I max , Wherein, I ifor the primary current percentage value of current transformer, the primary current percentage value of current transformer refers to the ratio of the rated current of the current transformer primary current that on-line monitoring obtains and current transformer, I imaxfor the primary current number percent maximal value of current transformer;
wherein, T iambient temperature value residing for current transformer, T infor the specified ambient temperature value of current transformer, C tI1and C tI2for temperature causes the rate of change coefficient of variation;
wherein, H iambient humidity value residing for current transformer, H infor the specified ambient humidity of current transformer, C hIfor humidity causes the rate of change of variation;
wherein, t rIfor the time of defluidization appears in nearest primary current mutual inductor, τ rfor remanent magnetism damping time constant;
wherein, M ifor closing on Primary Conductor magnetic field intensity, M infor specified magnetic field intensity, C mIfor magnetic field intensity causes the rate of change coefficient of variation.
3. the operating condition method of inspection of current transformer as claimed in claim 2, is characterized in that: described weights ω iS, ω iI, ω iT, ω iH, ω iR, ω iMadopt and determine with the following method, the method comprises the following steps:
G1, determine order relation: at { E sI, E iI, E tI, E hI, E rI, E mIin select proportion maximum a type be designated as G 1 *; Then the type selecting proportion maximum in five types of remainder is designated as G 2 *; The type selecting proportion maximum in four types of remainder is designated as G 3 *, the type selecting proportion maximum in three types of remainder is designated as G 4 *, the type selecting proportion maximum in two types of remainder is designated as G 5 *, finally remaining type is designated as G 6 *, its order relation is G 1 *> G 2 *> G 3 *> G 4 *> G 5 *> G 6 *, wherein G 1 *> G 2 *represent type G 1 *proportion be greater than or be not less than G 2 *, determine E thus sI, E iI, E tI, E hI, E rI, E mIorder relation;
The ratio in judgement of g2, adjacent type proportion size: adjacent type G k-1with G kbetween the ratio G of proportion size k-1/ G kk, k=6,5,4,3,2, according to G k-1with G kproportion size, η kspan be 1.0-1.8;
G3, scale-up factor calculate: g2 step is drawn η kvalue brings following formula into:
&omega; m = ( 1 + &Sigma; k = 2 m &Pi; i = k m &eta; i ) - 1 &omega; k - 1 = &eta; k &omega; k , k = m , m - 1 , ... , 2 Wherein, m=6
G can be calculated 1, G 2, G 3, G 4, G 5, G 6weight vector ω=[ω 1, ω 2, ω 3, ω 4, ω 5, ω 6], ω 1, ω 2, ω 3, ω 4, ω 5, ω 6corresponding G 1, G 2, G 3, G 4, G 5, G 6weights, just correspondence can draw ω according to the order relation determined iS, ω iI, ω iT, ω iH, ω iR, ω iMvalue.
CN201510889721.7A 2015-12-07 2015-12-07 A kind of operating condition method of inspection of current transformer Active CN105303065B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510889721.7A CN105303065B (en) 2015-12-07 2015-12-07 A kind of operating condition method of inspection of current transformer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510889721.7A CN105303065B (en) 2015-12-07 2015-12-07 A kind of operating condition method of inspection of current transformer

Publications (2)

Publication Number Publication Date
CN105303065A true CN105303065A (en) 2016-02-03
CN105303065B CN105303065B (en) 2018-04-13

Family

ID=55200328

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510889721.7A Active CN105303065B (en) 2015-12-07 2015-12-07 A kind of operating condition method of inspection of current transformer

Country Status (1)

Country Link
CN (1) CN105303065B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113203906A (en) * 2021-04-30 2021-08-03 国网重庆市电力公司电力科学研究院 Real-time monitoring method and device for voltage transformer

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06217556A (en) * 1993-01-14 1994-08-05 Shinko Electric Co Ltd Method and circuit for limiting current of inverter
CN101644752A (en) * 2009-08-14 2010-02-10 河南电力试验研究院 Online accuracy detection method and system of current transformer
CN104914394A (en) * 2015-06-15 2015-09-16 国网上海市电力公司 Current transformer operation evaluation method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06217556A (en) * 1993-01-14 1994-08-05 Shinko Electric Co Ltd Method and circuit for limiting current of inverter
CN101644752A (en) * 2009-08-14 2010-02-10 河南电力试验研究院 Online accuracy detection method and system of current transformer
CN104914394A (en) * 2015-06-15 2015-09-16 国网上海市电力公司 Current transformer operation evaluation method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
程瑛颖等: "电能计量装置运行误差分析及状态评价方法研究", 《电工电能新技术》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113203906A (en) * 2021-04-30 2021-08-03 国网重庆市电力公司电力科学研究院 Real-time monitoring method and device for voltage transformer

Also Published As

Publication number Publication date
CN105303065B (en) 2018-04-13

Similar Documents

Publication Publication Date Title
EP2466322B1 (en) Method and apparatus for transformer diagnosis
Peppanen et al. Leveraging AMI data for distribution system model calibration and situational awareness
JP5973716B2 (en) Method and system for monitoring transformer health
Bass et al. Impacts of electric vehicle charging on electric power distribution systems
Bhide et al. Analysis of winding inter-turn fault in transformer: A review and transformer models
CN103823201B (en) Method for checking current transformers for differential protection
CN104764985A (en) Method for estimating low-frequency dielectric loss of paper oil insulation system based on parameter identification
CN105550499A (en) Calculation method of health degree of metering device
CN110456299B (en) On-line detection method for turn-to-turn short circuit fault of secondary winding of current transformer
CN105548944B (en) A kind of metering device thermodynamic state verification method
CN111157939A (en) Live monitoring device and method for metering performance of voltage transformer
CN105548945A (en) Electric energy meter state testing method
CN105319528A (en) Method for checking operation working condition of electric energy meter
CN102590783A (en) Method for detecting error of indication of electric energy of high voltage energy meter and assessing qualification
CN113552443B (en) Hybrid connection high-voltage line fault identification method based on alternating current-direct current pulse and random forest
CN106324547A (en) Operation state prediction method used for metering device
CN105303065A (en) Current transformer operation condition testing method
CN105467354A (en) An operation condition examination method for a metering device
CN106644436B (en) A kind of assessment method of breaker mechanic property
Bongiorno et al. Experimental validation of the electric network model of the Italian 2x25 kV 50 Hz railway
CN105548940A (en) Operation condition detection method for voltage transformer
CN106575116B (en) Based on state the method, apparatus and computer program product of the maintenance deadline of computing technique equipment
CN105548939B (en) A kind of voltage transformer thermodynamic state verification method
Quan et al. The application of Bayesian network theory in transformer condition assessment
Davidenko et al. An algorithm for prioritizing the maintenance of power transformers

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant