CN105302183B - The timeliness control room of BOPP productions - Google Patents

The timeliness control room of BOPP productions Download PDF

Info

Publication number
CN105302183B
CN105302183B CN201510769245.5A CN201510769245A CN105302183B CN 105302183 B CN105302183 B CN 105302183B CN 201510769245 A CN201510769245 A CN 201510769245A CN 105302183 B CN105302183 B CN 105302183B
Authority
CN
China
Prior art keywords
control room
timeliness
truss
temperature
timeliness control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510769245.5A
Other languages
Chinese (zh)
Other versions
CN105302183A (en
Inventor
向红
乔胜秋
俞飞
陈新均
程训峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Kunlene Film Industries Co Ltd
Original Assignee
Suzhou Kunlene Film Industries Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Kunlene Film Industries Co Ltd filed Critical Suzhou Kunlene Film Industries Co Ltd
Priority to CN201510769245.5A priority Critical patent/CN105302183B/en
Publication of CN105302183A publication Critical patent/CN105302183A/en
Application granted granted Critical
Publication of CN105302183B publication Critical patent/CN105302183B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

Present invention is disclosed a kind of timeliness control room of BOPP productions, enclose to build based on timeliness frame and form, the bottom and side of the timeliness control room are the knife edge of color steel rock cotton board, the collapsible truss and collapsible truss that push-and-pull opening and closing is set at the top of timeliness control room form closed with knife edge in closed state, the timeliness control room is provided with by blower fan, box heater, thermal insulation wind pipe, some independent temperature conditioning units of temperature sensor composition, wherein thermal insulation wind pipe and temperature sensor are evenly arranged in the color steel rock cotton board of timeliness control room bottom, and blower fan, the outer timeliness that is coupled to controls outdoor temperature-controlling cabinet to box heater respectively with temperature sensor.Application implementation timeliness control room of the present invention, the convenience of turnover is hung during there is provided BOPP film parent roll Ageing Treatment, High Precision Automatic temperature control, the reduction subregion influence of Ageing Treatment are easily achieved, and improves the efficiency of film parent roll Ageing Treatment, light and flexible is operated.

Description

The timeliness control room of BOPP productions
Technical field
The present invention relates to a kind of structure of modification of BOPP production lines, more particularly to a kind of Ageing Treatment of BOPP film parent roll Equipment, belongs to membrane production equipment association area.
Background technology
So-called BOPP film parent roll Ageing Treatment, is the film semi-finished product parent roll that will be produced from film line, puts Put on film timeliness shelf, placed more than 48 hours under normal temperature effect.Ageing Treatment effect has at 2 points:One receives film Contracting reaches stable dimensions;The two makes the additive in film migrate to film surface, film is reached due characteristic.
At present, BOPP film parent roll aging regime is carries out Ageing Treatment under normal temperature environment, and process cycle is longer, influence life Produce efficiency.Due to being Ageing Treatment at ambient temperature, difference variation is big, the physical property change after the kind film timeliness of part Larger, product quality uniformity is poor.
The content of the invention
For long, the temperature control instability problem that solves the normal temperature film parent roll aging technique cycle, the present invention provides a kind of Timeliness control room, can not only shorten the Ageing Treatment cycle of film parent roll, and can guarantee that temperature stabilization and adjustable, improve simultaneously The physical property of part film.
The above-mentioned purpose of the present invention, will be achieved by the following technical programs:The timeliness control room of BOPP productions, is based on Timeliness frame, which encloses to build, to be formed, it is characterised in that:The bottom and side of the timeliness control room are the knife edge of color steel rock cotton board, when The collapsible truss and collapsible truss that push-and-pull opening and closing is set at the top of effect control room are formed with knife edge in closed state Closed, the timeliness control room is provided with some independences being made up of blower fan, box heater, thermal insulation wind pipe, temperature sensor Temperature conditioning unit, wherein thermal insulation wind pipe and temperature sensor be evenly arranged in the color steel rock cotton board of timeliness control room bottom, and Blower fan, box heater and temperature sensor are outer respectively to be coupled to the outdoor temperature-controlling cabinet of timeliness control.
Further, the collapsible truss is set to arrange to several independences side by side and be welded by zinc-plated square tube in film roll Into the gate truss of umbrella, have under the span of correspondence film roll length between anti-interference morphotropism, adjacent gate truss and be provided with Covering is provided with fiber aluminium foil cloth, and gate truss two at the top of at least attachment structure of cross fork-shearing frame, the gate truss Side is provided with transparent silicon offset plate.
Further, the crossbar of the cross fork-shearing frame is installed provided with one section of slide rail in same side end.
Further, arranged in film roll to gate truss packet and be set to more than three units, the list of side two The outside gate truss of member integrally connects and respective inner side gate truss folding and retraction, middle two cell positions with knife edge Slide between adjustable and gate truss folding and retraction, adjacent cells in gate truss end loose joint sealing.
Yet further, two gate truss in any outside of each unit are fixed welding knot at a distance Structure.
Yet further, each unit is being provided with silica gel sealing bar with the gate truss end face of adjacent cells opposite side.
Yet further, provided with more than one group portable hasp between two neighboring unit.
Further, each units match sets a set of temperature conditioning unit for being independently controllable by temperature-controlling cabinet, timeliness control room Interior forces to send phoenix thermostatic control aging temp by temperature conditioning unit formation horizontal cyclic.
Remarkable result after timeliness control room application implementation of the present invention is:Hung during there is provided BOPP film parent roll Ageing Treatment The convenience put into out, subregion control temperature can reduce the temperature shadow to other regions in partially open collapsible truss Ring, it is easy to accomplish the High Precision Automatic temperature control of Ageing Treatment, and improve the efficiency of film parent roll Ageing Treatment, operate light Flexibly.
Brief description of the drawings
Fig. 1 is the structural representation of timeliness control room of the present invention.
Fig. 2 is the structural representation of gate truss of the present invention.
Embodiment
Just accompanying drawing in conjunction with the embodiments below, the embodiment to the present invention is described in further detail, so that of the invention Technical scheme is more readily understood, grasped.It should be noted that data involved in following examples are characterizing portion, it is actual Production scale is changeable, therefore the implementation of this creation has polytropy, but with technical scheme described in the application claims Protection domain be defined.
From the point of view of medium production-scale specific implementation, BOPP timeliness control room is using the structure reconstruction of existing timeliness frame Into long 16 meters, high 2 meters, 9 meters of span.It can hang 1 meter more than of diameter inside timeliness control room, be about 9 meters of film parent roll 7 about Volume 10, gross weight is up to 60 tons.
As depicted in figs. 1 and 2, the bottom of timeliness control room lower floor and side are sealed using the color steel rock cotton boards 1 of 50mm, can To play excellent sealing insulation effect.And timeliness control room top section uses the collapsible truss structure that push-and-pull is opened and closed, fold Formula truss forms closed with knife edge in closed state, so as to realize thermostatic control.Also, the timeliness control room is provided with By blower fan 3, box heater 4, thermal insulation wind pipe 5, temperature sensor(It is not shown)Some independent temperature conditioning units of composition, wherein Thermal insulation wind pipe 5 and temperature sensor are evenly arranged in the color steel rock cotton board of timeliness control room bottom, and blower fan, box heater The outer timeliness that is coupled to controls outdoor temperature-controlling cabinet 6 respectively with temperature sensor.Pass through the simple operations in temperature-controlling cabinet, you can freely The thermostatic control of whole timeliness control room is realized in subregional.
From the point of view of more specifically structure,(1)Umbrella door shape is welded into using 5# zinc-plated square tubes at the top of truss structure shown in Fig. 2 Truss 21, can effectively solve big material degree of the disturbing problem on deformation of span.Multigroup cross fork-shearing frame is used between door shape truss 23 connections, each tie point installs one section of slide rail, and effect is that cross scissor rack position can when door shape truss is folded Flexibly to move, a shape truss deformation is prevented.Consider film parent roll size dimension, the present embodiment is designed nine groups of door shapes below Truss, which is constituted, do not use cross fork-shearing frame to connect between a unit 2, two groups of door shape truss of each unit both sides, but is adopted With form is directly welded and fixed, each other away from can be 0.8 meter or so, it is therefore an objective to ensure the stability of each unit.
(2)Sealed at the top of the door shape truss of each unit using 0.4mm thick fibers aluminium foil cloth 22, it is transparent with 2mm sideways Silica gel plate 24 seals fixation, so can both meet a natural deformation requirement when shape truss is folded, and weight is also light, can be with Situation inside timeliness control room is observed by transparent silicon offset plate.It is close that the door shape truss end face of each unit installs fixed silica gel Strip of paper used for sealing 26, as the sealing between unit.Four groups of quick hasps are also equipped between unit(It is not shown), can will be tight between unit Close connects., can be by untiing quick hasp simultaneously so in the case where carrying out aging technique when needing lifting to pick and place parent roll Certain two unit of collapsible truss are opened in separation.And when rigging out needs temperature control timeliness, two lists are closed by push-and-pull First and closed whole timeliness control room.
(3)The door shape truss bottom of each unit both sides is assembled with wheel, and timeliness control room arranges track simultaneously(Wheel Son is not shown with track, and those skilled in the art are understood that its deployment scenarios), so the door shape truss of each unit can Freely to be promoted to both sides in orbit, lighter, durability extension is operated.
The timeliness control room is set to automatic temperature control system, four units of correspondence above-described embodiment, mainly by four Fans, Four box heaters, switch board, some thermal insulation wind pipes and temperature sensor constitute the temperature control of four independent control temperature Unit, each temperature conditioning unit is connected with multigroup thermal insulation wind pipe in control room, and thermal insulation wind pipe is evenly arranged in control room bottom In the color steel rock cotton board in portion.The temperature control mode of timeliness control room is to be extracted the wind inside control room by box out by blower fan Heater is heated to suitable temperature and sends back to timeliness control room again, during by a large amount of forced air supplies of this horizontal cyclic to ensure Imitate the temperature homogeneity of control room.It is specific to have following optional embodiment.
(1)Automatic constant-temperature, the temperature value that temperature controller can be set according to user, the big of power output is calculated using PID automatically Small, during closer to desired temperature, power output is smaller, to reach thermostatically controlled purpose, and can save energy power saving.
(2)4 heating units can be carried out being separately provided temperature by subregion temperature control according to actual needs, individually open or Close heating system.
(3)Timing function, the time reach after alarm and automatically cut off heating.
(4)Overtemperature alarm, when measured temperature exceedes overtemperature prote temperature controller setting value, automatically cuts off heating electricity Source, plays duplicate protection.
From the detailed description of above-described embodiment, after application implementation technical solution of the present invention there is more significant technology to imitate Fruit and apply advantage, it is specific as follows.
Summarize effect:1. timeliness control room arbitrary region can be opened, parent roll can be hung into timeliness control with driving Room optional position;Required parent roll can also be hung out from optional position;
2. whole timeliness control room energy subregion controls temperature, open small on the temperature influence in other regions after control room;
3. timeliness control room temperature can be set as needed, temperature is automatically controlled according to the feedback of temperature sensor by air-heater Degree;
4. timeliness control room sealing is good, temperature homogeneity deviation meets process requirements;
5. can be with thermostatic control aging temp.
6. film parent roll aging time can be saved, efficiency is improved.
Summarize advantage:Light and flexible is operated, less manual labor's input, which can be rapidly completed, hangs film parent roll operation;Profile Attractive in appearance, reliable in quality.
In addition to the implementation, the present invention can also have other embodiment.All use equivalent or equivalent transformation shape Into technical scheme, all fall within scope of the present invention.

Claims (6)

  1. The timeliness control room of 1.BOPP productions, encloses to build and forms based on timeliness frame, it is characterised in that:The bottom of the timeliness control room With sealing fence of the side for color steel rock cotton board, the collapsible truss of push-and-pull opening and closing is set at the top of timeliness control room and collapsible Truss forms closed with sealing fence in closed state, and the timeliness control room is provided with by blower fan, box heater, insulation Some independent temperature conditioning units of airduct, temperature sensor composition, when wherein thermal insulation wind pipe and temperature sensor are evenly arranged in On the color steel scar plate for imitating control room bottom, and blower fan, box heater and temperature sensor are coupled to timeliness control room outside respectively Outer temperature-controlling cabinet;The collapsible truss is set to be welded several gate truss of umbrella by zinc-plated square tube, and gate truss exists Has anti-interference morphotropism under the span of correspondence film roll length, several gate truss are independent side by side along film roll orientation, and phase The attachment structure of cross fork-shearing frame is provided between adjacent gate truss, the top covering of gate truss is provided with fiber aluminium foil cloth, and Two sides of gate truss are provided with transparent silicon offset plate;
    Along film roll orientation, the gate truss packet is set to more than three units, the outside gate of the unit of side two Truss integrally connects and respective inner side gate truss folding and retraction with sealing fence, and middle two cell positions slide adjustable and door Sealed between type truss folding and retraction, adjacent cells in the loose joint of gate truss end.
  2. 2. the timeliness control room that BOPP is produced according to claim 1, it is characterised in that:The intersection of the cross fork-shearing frame Bar is installed provided with one section of slide rail in same side end.
  3. 3. the timeliness control room that BOPP is produced according to claim 1, it is characterised in that:Two of each any outside of unit Gate truss is fixation welding structure at a distance.
  4. 4. the timeliness control room that BOPP is produced according to claim 1, it is characterised in that:Each unit with adjacent cells phase The gate truss of offside.
  5. 5. the timeliness control room that BOPP is produced according to claim 1, it is characterised in that:Each unit is in door shape truss end face Provided with silica gel sealing bar and more than one group portable hasp.
  6. 6. the timeliness control room that BOPP is produced according to claim 1, it is characterised in that:Each units match sets a set of only The vertical temperature conditioning unit for being controlled by temperature-controlling cabinet.Fortune wind constant temperature control is forced by temperature conditioning unit formation horizontal cyclic in timeliness control room Aging temp processed.
CN201510769245.5A 2015-11-12 2015-11-12 The timeliness control room of BOPP productions Active CN105302183B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510769245.5A CN105302183B (en) 2015-11-12 2015-11-12 The timeliness control room of BOPP productions

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510769245.5A CN105302183B (en) 2015-11-12 2015-11-12 The timeliness control room of BOPP productions

Publications (2)

Publication Number Publication Date
CN105302183A CN105302183A (en) 2016-02-03
CN105302183B true CN105302183B (en) 2017-07-11

Family

ID=55199559

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510769245.5A Active CN105302183B (en) 2015-11-12 2015-11-12 The timeliness control room of BOPP productions

Country Status (1)

Country Link
CN (1) CN105302183B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109282690A (en) * 2018-09-25 2019-01-29 浙江金瑞薄膜材料有限公司 Timeliness frame heat and moisture preserving system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202934819U (en) * 2012-09-28 2013-05-15 江苏首义薄膜有限公司 Closed constant-temperature aging treatment equipment
CN103898471A (en) * 2014-03-08 2014-07-02 安徽麦特电子股份有限公司 Device and process for carrying out aging treatment on capacitor film
CN204529906U (en) * 2015-03-04 2015-08-05 宿迁市金田塑业有限公司 A kind of modified version insulation ageing device
CN205210723U (en) * 2015-11-12 2016-05-04 苏州昆岭薄膜工业有限公司 Prescription control room of BOPP production

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA1163683A (en) * 1981-04-02 1984-03-13 Akihiko Ueno Temperature control for cooking appliances

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202934819U (en) * 2012-09-28 2013-05-15 江苏首义薄膜有限公司 Closed constant-temperature aging treatment equipment
CN103898471A (en) * 2014-03-08 2014-07-02 安徽麦特电子股份有限公司 Device and process for carrying out aging treatment on capacitor film
CN204529906U (en) * 2015-03-04 2015-08-05 宿迁市金田塑业有限公司 A kind of modified version insulation ageing device
CN205210723U (en) * 2015-11-12 2016-05-04 苏州昆岭薄膜工业有限公司 Prescription control room of BOPP production

Also Published As

Publication number Publication date
CN105302183A (en) 2016-02-03

Similar Documents

Publication Publication Date Title
CN203951978U (en) A kind of dismountable dry-hot wind simulation canopy of temperature automatically controlled dehumidifying
CN205593341U (en) Novel stoving case
CN104855178B (en) Rope film heat seal manufacture method
CN105302183B (en) The timeliness control room of BOPP productions
CN204721944U (en) One controls greenhouse automatically
CN205210723U (en) Prescription control room of BOPP production
CN203896898U (en) Greenhouse temperature and humidity regulator
CN206237931U (en) A kind of lighting and ventilation edible fungus culturing greenhouse
CN103005701B (en) Cigar moisture drying process
CN206834150U (en) A kind of microscope thermal station
CN105549649A (en) Field temperature increasing control device
CN107278620A (en) A kind of intelligence adds the solar greenhouse that temperature control water is divulged information
CN106428815A (en) Air blowing mechanism used for thermal shrinkage box of membrane packer
CN216387878U (en) Device for simulating climate warming under field conditions
CN202618246U (en) Novel warming tobacco air-curing room
CN105475040B (en) A kind of greenhouse facade shading Collapsible rack
CN213881088U (en) Double-layer film heat preservation greenhouse
CN205056041U (en) Drying cabinet for chemistry experiments
CN205124530U (en) Large -span intelligent greenhouse's interior heat preservation system
CN205318254U (en) Field heats controlling means
CN206866177U (en) A kind of partition type intelligence greenhouse
CN105286068A (en) Full-automatic solar tobacco baking house capable of preserving heat
CN201246944Y (en) Drying furnace for rapidly solidifying accumulator cap sealant
CN205161745U (en) Make futilely device fast
CN205161834U (en) Automatic device is made futilely fast in control

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant