CN105260570A - PSD-BPA flow data element editing and bus switching method - Google Patents

PSD-BPA flow data element editing and bus switching method Download PDF

Info

Publication number
CN105260570A
CN105260570A CN201510755173.9A CN201510755173A CN105260570A CN 105260570 A CN105260570 A CN 105260570A CN 201510755173 A CN201510755173 A CN 201510755173A CN 105260570 A CN105260570 A CN 105260570A
Authority
CN
China
Prior art keywords
bus
transformer
circuit
file
psd
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510755173.9A
Other languages
Chinese (zh)
Other versions
CN105260570B (en
Inventor
李明珀
孙志媛
刘默斯
周柯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute of Guangxi Power Grid Co Ltd
Original Assignee
Electric Power Research Institute of Guangxi Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of Guangxi Power Grid Co Ltd filed Critical Electric Power Research Institute of Guangxi Power Grid Co Ltd
Priority to CN201510755173.9A priority Critical patent/CN105260570B/en
Publication of CN105260570A publication Critical patent/CN105260570A/en
Application granted granted Critical
Publication of CN105260570B publication Critical patent/CN105260570B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a PSD-BPA flow data element editing and bus switching method, belonging to the field of statistic data and analysis. The method comprises: 1) reading a flow file and a stabilization file, and building respective objects for circuits, transformers and buses in the flow file, wherein the properties of the objects comprise various parameters in the flow file and the stabilization file, a line number in each file, and whether being noted or not; 2) creating a directory tree; 3) creating a bus switching method; 4) synchronizing stabilization data files. Rapid editing on PSD flow and stabilization calculating data when the buses are added or deleted, and components (power transmission lines and the transformers) connected with the buses are switched, and a simple annotation editing function on the components (the power transmission lines, the buses and the transformers) is added, thus avoiding the problems of heavy workload and great error possibility during single and manual modification one by one, and greatly improving the work efficiency.

Description

A kind of PSD-BPA flow data element editor and transfer bus method
Technical field
The invention belongs to system data and analysis field, particularly relate to a kind of PSD-BPA flow data element editor and transfer bus method.
Background technology
PSD Power System Analysis program is the electric system simulation calculating analysis software bag developed by China Electric Power Research Institute, comprise multiple calculation procedures such as trend, stable, short-circuit current, minor interference computational analysis, be widely used in the fields such as electric system simulation computational analysis, planning.
In actual electric network wiring system, if it is when putting into operation for a long time that transformer station's electric pressure bus exists segmentation and bus connection switch, conventional method of operation Load flow calculation data generally only retain a bus nodes when arranging bus nodes to simplify workload.When carrying out stable researching and analysing to electrical network, need to check electrical network in case of a fault switch protection tripping time stability so that study corresponding countermeasure targetedly.Thus when carrying out relevant multilayer output feedback network, need relevant calculating data and electrical network physical cabling to be mapped to ensure that the fault actions process of simulation process and electrical network real system is consistent.
For guaranteeing the accuracy emulated, in Load flow calculation data, corresponding bus nodes and mother need be increased for the regional power grid of research, the transmission line of electricity of correspondence is articulated to corresponding bus, and synchronous vacations stability Calculation data." searching replacement " function provided in PSD software for calculation cannot adapt to; Data modification need respectively to power flow files, stablize file and carry out corresponding modify, cannot uniform synchronization amendment, easily cause the mistakes and omissions of amendment; Manually revise one by one, need modify to the hundreds of transformer station of whole regional power grid, work repeats loaded down with trivial details, and workload is huge, and the data in PSD software do not allow dislocation, very easily cause data to misplace.
Summary of the invention
Goal of the invention of the present invention is: for the deficiencies in the prior art, a kind of PSD-BPA flow data element editor and transfer bus method are provided, with realize to PSD trend and stability Calculation data increase or delete bus, bus institute Connection Element (transmission line of electricity, transformer) switches time quick editor, and add simple element (transmission line of electricity, mother, transformer) and annotate editting function.
For solving the problems of the technologies described above, the technical solution used in the present invention is:
A kind of PSD-BPA flow data element editor and transfer bus method, its feature is comprising the following steps:
1), read in power flow files and stable file, the circuit in power flow files, transformer, bus are set up respective object, the attribute kit of object is containing various parameters in power flow files and stable file, line number hereof, whether annotated;
2), create directory tree;
3) method of transfer bus, is created;
4), synchronism stability data file.
Further, described step 1) read in power flow files and stable file, comprising:
A, set up bus, circuit, transformer array;
Buses all in b, surface sweeping power flow files, circuit, transformer card and annotated fall bus, circuit, transformer card;
C, be that corresponding object set up by each card, arrange annotated fall the annotated attribute of card, after cancelling annotation, attribute is write into corresponding object.
Further: described step 2) tree that creaties directory comprises the following steps:
A, reading bus, circuit, transformer array;
B, identify the different buses of same transformer station, by method identifications such as naming rule identification, mother connections, for different transformer stations sets up object;
C, by bus according to subregion building topology directory tree, described directory tree totally three grades: subregion, transformer station, bus;
D, circuit, transformer to be articulated in respectively on corresponding bus, circuit two ends mount the different buses of two different substation respectively;
E, identification common line and mother, the line between the different bus of same transformer station is mother;
F, annotated and not annotated card show with different colours, and circuit marks with different background colors from bus, circuit and transformer, facilitate user to identify.
Further: described step 3) create the method for transfer bus, comprise interpolations, deletions, annotation, cancel and annotate components and parts, the bus of dragging circuit switched or transformer connection.
Further: described step 4) sync data file is that bus in power flow files switches record, synchronous vacations, in stable data file, realizes the unification of flow data and stable data.
In technique scheme: step 3) annotation or cancel annotation circuit, transformer: right click circuit, transformer sensor selection problem menu annotation or cancel annotation; Increase, delete bus: right click transformer station choice menus increases bus, right click bus choice menus deletes bus; Circuit switched, main transformer: drag on circuit, main transformer node to another bus and realize switching, card image corresponding to data file is stablized in amendment simultaneously; Divide, close mother: be dragged on other one section of bus by one section of bus, realize two sections of buses and close mothers, right click bus choice menus divides mother.
The invention has the beneficial effects as follows: the present invention can realize to PSD trend and stability Calculation data increase or delete bus, bus institute Connection Element (transmission line of electricity, transformer) switches time quick editor, and add simple element (transmission line of electricity, mother, transformer) and annotate editting function, when avoiding simple artificial amendment one by one, the problem of large, the fallibility of workload, increases work efficiency greatly.
Accompanying drawing explanation
Fig. 1 is the catalogue tree graph that the present invention sets up according to subregion, transformer station, bus, circuit or main transformer level Four electrical network.
Fig. 2 is the function menu figure that in the quick editting function that designs of the present invention, right mouse button clicks appearance.
Before bus is added in Fig. 3 position;
After Fig. 4 adds bus;
Before Fig. 5 deletes mother;
After Fig. 6 deletes mother;
Before Fig. 7 element annotation;
After Fig. 8 element annotation;
The female flow data of Fig. 9 Ping Ban-Long Lin transmission line of electricity transfer bus front hanging II;
I female flow data is hung after Figure 10 Ping Ban-Long Lin transmission line of electricity transfer bus;
Figure 11 Ping Ban-Long Lin transmission line of electricity transfer bus front hanging II mother stablizes data;
Hang I mother after Figure 12 Ping Ban-Long Lin transmission line of electricity transfer bus and stablize data.
Embodiment
Be described in further detail the specific embodiment of the present invention below in conjunction with accompanying drawing, wherein in institute's drawings attached, identical label represents same or similar parts, and the accompanying drawing in instructions is reduced form, only for understanding concrete structure of the present invention.Following examples only for technical scheme of the present invention is clearly described, and can not limit the scope of the invention.
As shown in Figure 1, be the directory tree that the present invention sets up according to subregion, transformer station, bus, circuit or main transformer level Four certain actual area electrical network.Wherein, N1, GX, NN, BS etc. are subregion; Auspicious week, moral treasured, old liberated area, that hero, Long Lin, Yun Ling etc. are the transformer station under BS subregion under a certain electric pressure; LONGL21, LONGL22 are two sections of buses of a certain electric pressure under Long Lin transformer station; TSQB220_1, TSQB221_2, LONGL21_, PINBA22_2, YOUSL222_, LONGL-Z2 are the element (transmission line of electricity, mother, the main transformer that are articulated under LONGL22 bus, wherein YOUSL222 transmission line of electricity in flow data annotated fall, but data retain, inoperative during calculating).
Be the function menu that in the quick editting function that designs of the present invention, right mouse button clicks appearance as shown in Figure 2, comprise: add bus, delete bus, delete mother, annotation, cancellation annotation." interpolation bus " function is the situation needing newly-increased bus when a certain electric pressure of transformer station has bus, and during transformer station's right-click therefore on directory tree, " interpolation bus " function is just effective." deletion bus " function need specify to delete which bus, and when the bus therefore on directory tree is clicked by right key, " deletion bus " function is just effective." deletion mother ", " annotation ", " cancelling annotation " are only for the element mounted under bus, and the element therefore on directory tree is clicked by right key just effective, it should be noted that, when element is mother, " deletion mother " function is just effective; When element does not have annotated, " annotation " function is effective; Otherwise " cancelling annotation " function is effective.
Below with certain actual area electrical network Long Lin transformer station for example, Fig. 3 to Fig. 8 main presentation be the implementation result of right-click menu function, the data modification effect of what Fig. 9 to Figure 11 showed is element handoff procedure
(1) bus is added.The a certain electric pressure of transformer station needs interpolation one section of bus.By clicking the grand woods station on directory tree by right key, click " interpolation bus ", as Fig. 3 in the menu ejected.After click completes, result, as Fig. 4, adds corresponding data in power flow files.
(2) mother is deleted.Click the mother element on directory tree by right key, click " deletion mother ", as Fig. 5 in the menu ejected.After click completes, result, as Fig. 6, deletes corresponding data in power flow files.
(3) annotate.Click the mother element on directory tree by right key, click " annotation ", as Fig. 7 in the menu ejected.After click completes, result is as Fig. 8, and the mother data in power flow files between the bus of grand woods two ends are annotated.
(4) element transfer bus.Directory tree finds the PINBA22_2 (flat class) be articulated under LONGL22 bus, " PINBA22_2 (flat class) " is clicked with left mouse button, pin left mouse button, " PINBA22_2 (flat class) " is drawn to " LONGL21 " bus on directory tree, now " LONGL21 " can deepen look, unclamps left mouse button and namely completes Ping Ban-Long Lin transmission line of electricity switches mounting bus data modification work at grand woods transformer substation side.Fig. 9 and Figure 11 respectively show Ping Ban-Long Lin transmission line of electricity and switches the flow data before mounting bus and stable data at grand woods transformer substation side, Figure 10 and Figure 11 is the amendment situation of flow data and stable data after transfer bus.
What the present invention proposed realizes bus changing method efficiently based on OO program technic and mentality of designing and has following outstanding advantages: 1. by adopting object-oriented programming method, building topology directory tree, provides operation interface interactive flexibly to user; 2. realize transfer bus and non-productive operation by mouse drag or right-click menu, the circuit or the main transformer that achieve same transformer station can freely switch between different buses, and ensure the unification of flow data and stable data; When 3. avoiding simple artificial amendment one by one, the problem such as large, the fallibility of workload, substantially increases the work efficiency of data edition; 4. method is short and sweet, simple to operate.

Claims (5)

1. PSD-BPA flow data element editor and a transfer bus method, is characterized in that comprising the following steps:
1), read in power flow files and stable file, the circuit in power flow files, transformer, bus are set up respective object, the attribute kit of object is containing various parameters in power flow files and stable file, line number hereof, whether annotated;
2), create directory tree;
3) method of transfer bus, is created;
4), synchronism stability data file.
2. a kind of PSD-BPA flow data element editor according to claim 1 and transfer bus method, is characterized in that: described step 1) read in power flow files and stable file, comprising:
A, set up bus, circuit, transformer array;
Buses all in b, surface sweeping power flow files, circuit, transformer card and annotated fall bus, circuit, transformer card;
C, be that corresponding object set up by each card, arrange annotated fall the annotated attribute of card, after cancelling annotation, attribute is write into corresponding object.
3. a kind of PSD-BPA flow data element editor according to claim 1 and transfer bus method, is characterized in that: described step 2) tree that creaties directory comprises the following steps:
A, reading bus, circuit, transformer array;
B, identify the different buses of same transformer station, by method identifications such as naming rule identification, mother connections, for different transformer stations sets up object;
C, by bus according to subregion building topology directory tree, described directory tree totally three grades: subregion, transformer station, bus;
D, circuit, transformer to be articulated in respectively on corresponding bus, circuit two ends mount the different buses of two different substation respectively;
E, identification common line and mother, the line between the different bus of same transformer station is mother;
F, annotated and not annotated card show with different colours, and circuit marks with different background colors from bus, circuit and transformer, facilitate user to identify.
4. a kind of PSD-BPA flow data element editor according to claim 1 and transfer bus method, it is characterized in that: described step 3) create the method for transfer bus, comprise interpolation, deletion, annotation, cancel annotation components and parts, drag the bus of circuit switched or transformer connection.
5. according to right a kind of PSD-BPA flow data element editor according to claim 1 and transfer bus method, it is characterized in that: described step 4) sync data file is that bus in power flow files switches record, synchronous vacations, in stable data file, realizes the unification of flow data and stable data.
CN201510755173.9A 2015-11-09 2015-11-09 A kind of PSD-BPA flow datas element editor and transfer bus method Active CN105260570B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510755173.9A CN105260570B (en) 2015-11-09 2015-11-09 A kind of PSD-BPA flow datas element editor and transfer bus method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510755173.9A CN105260570B (en) 2015-11-09 2015-11-09 A kind of PSD-BPA flow datas element editor and transfer bus method

Publications (2)

Publication Number Publication Date
CN105260570A true CN105260570A (en) 2016-01-20
CN105260570B CN105260570B (en) 2018-05-01

Family

ID=55100259

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510755173.9A Active CN105260570B (en) 2015-11-09 2015-11-09 A kind of PSD-BPA flow datas element editor and transfer bus method

Country Status (1)

Country Link
CN (1) CN105260570B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107578218A (en) * 2017-09-19 2018-01-12 广西电网有限责任公司电力科学研究院 Rated current batch data amending method and system based on PSD BPA
CN107732938A (en) * 2017-10-19 2018-02-23 广西电网有限责任公司电力科学研究院 A kind of PSD SSAP Small signal stability analysis intelligence screening methods of object-oriented
CN107742034A (en) * 2017-10-25 2018-02-27 中国电力工程顾问集团西南电力设计院有限公司 A kind of method for quickly generating line chart according to BPA cards
CN107908731A (en) * 2017-11-14 2018-04-13 广西电网有限责任公司电力科学研究院 Based on PSD BPA Guangxi Power Grids barrier load data batch modification method
CN109472006A (en) * 2018-11-30 2019-03-15 广西电网有限责任公司电力科学研究院 A kind of calculated result screening technique based on PSD-BPA
CN110489793A (en) * 2019-07-12 2019-11-22 广西电网有限责任公司电力科学研究院 The method that a kind of identification of the power station PSD and failed operation model generate
CN112329405A (en) * 2020-10-20 2021-02-05 贵州电网有限责任公司 Standardization method of BPA net rack model data

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7111018B1 (en) * 2000-10-30 2006-09-19 Margaret E Goodrich System and method for integrating electrical power grid and related data from various proprietary raw data formats into a single maintainable electrically connected database
CN103715685A (en) * 2013-12-25 2014-04-09 大连理工大学 Graph visualization system used for electric system load flow and stability analysis
CN104484546A (en) * 2014-10-30 2015-04-01 南方电网科学研究院有限责任公司 Method for generating automatic power flow check file of power grid planning project

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7111018B1 (en) * 2000-10-30 2006-09-19 Margaret E Goodrich System and method for integrating electrical power grid and related data from various proprietary raw data formats into a single maintainable electrically connected database
CN103715685A (en) * 2013-12-25 2014-04-09 大连理工大学 Graph visualization system used for electric system load flow and stability analysis
CN104484546A (en) * 2014-10-30 2015-04-01 南方电网科学研究院有限责任公司 Method for generating automatic power flow check file of power grid planning project

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
国建宝等: ""电力系统BPA与PSS_E潮流数据转换研究"", 《电工电能新技术》 *
罗彬等: ""基于PSD_BPA的电网潮流稳定计算分析平台开发与应用"", 《电力系统自动化》 *
罗彬等: ""基于PSD_BPA的省地一体化电力系统设备参数管理策略"", 《电力系统自动化》 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107578218B (en) * 2017-09-19 2020-10-30 广西电网有限责任公司电力科学研究院 PSD-BPA (phase-sensitive Detector-BPA) -based rated current data batch modification method and system
CN107578218A (en) * 2017-09-19 2018-01-12 广西电网有限责任公司电力科学研究院 Rated current batch data amending method and system based on PSD BPA
CN107732938A (en) * 2017-10-19 2018-02-23 广西电网有限责任公司电力科学研究院 A kind of PSD SSAP Small signal stability analysis intelligence screening methods of object-oriented
CN107732938B (en) * 2017-10-19 2021-01-05 广西电网有限责任公司电力科学研究院 Object-oriented PSD-SSAP small-interference stability analysis intelligent screening method
CN107742034A (en) * 2017-10-25 2018-02-27 中国电力工程顾问集团西南电力设计院有限公司 A kind of method for quickly generating line chart according to BPA cards
CN107908731A (en) * 2017-11-14 2018-04-13 广西电网有限责任公司电力科学研究院 Based on PSD BPA Guangxi Power Grids barrier load data batch modification method
CN107908731B (en) * 2017-11-14 2021-06-18 广西电网有限责任公司电力科学研究院 PSD-BPA-based Guangxi power grid area load data batch modification method
CN109472006A (en) * 2018-11-30 2019-03-15 广西电网有限责任公司电力科学研究院 A kind of calculated result screening technique based on PSD-BPA
CN109472006B (en) * 2018-11-30 2023-07-25 广西电网有限责任公司电力科学研究院 Calculation result screening method based on PSD-BPA
CN110489793A (en) * 2019-07-12 2019-11-22 广西电网有限责任公司电力科学研究院 The method that a kind of identification of the power station PSD and failed operation model generate
CN110489793B (en) * 2019-07-12 2022-05-31 广西电网有限责任公司电力科学研究院 PSD power station identification and fault operation model generation method
CN112329405A (en) * 2020-10-20 2021-02-05 贵州电网有限责任公司 Standardization method of BPA net rack model data
CN112329405B (en) * 2020-10-20 2024-03-15 贵州电网有限责任公司 Normalization method for BPA net rack model data

Also Published As

Publication number Publication date
CN105260570B (en) 2018-05-01

Similar Documents

Publication Publication Date Title
CN105260570A (en) PSD-BPA flow data element editing and bus switching method
CN106021684B (en) A kind of modular power source standardized designs system and its design method, application
CN105449676B (en) Power distribution network Area Node network generation method and system
US9459600B2 (en) Method and automation system for processing information extractable from an engineering drawing file using information modeling and correlations to generate output data
CN105488269A (en) CIM based automatic graph-forming system for power transmission and distribution network
CN102403718B (en) Generating method for power grid topological relationship based on Arcgis
CN103020360B (en) Intelligent substation integral design method based on three dimensional design platform and professional software
CN111027746A (en) Intelligent distribution network system ring network diagram automatic generation method and device
CN103093007A (en) Power transmission iron tower three-dimensional virtual assembly method
CN106970999B (en) BPA database modeling and maintaining method
CN107390089A (en) Transient zero-sequence current signal synchronizing method and device are realized in distributed system
CN103617318A (en) Method for modeling distribution automation power grid
CN103093493A (en) High-precision three-dimensional object modeling method with power grid equipment existing
CN103441988B (en) Across GIS platform data migration method
CN105977962B (en) Transmission network-distribution network joint fault analysis method based on improved node method
CN109830954A (en) The topological hierarchy recognition methods automatically generated suitable for power grid visualization simulation model
CN104573208A (en) GIS (Geographic Information System)-based distribution network wiring diagram mapping method
CN110854824B (en) Method and device for monitoring availability of relay protection service of power communication network
CN103942322A (en) Distribution network model discrepant data merging method based on XML files
Hong et al. Substation one-line diagram automatic generation and visualization
CN111476547A (en) Method for analyzing assets of distribution network line ring-out point arrangement in user
CN112632650B (en) Intelligent design system and method for nonstandard explosion-proof electric appliance product
CN106877320B (en) Intelligent micro-grid node layout's method in a kind of region
CN109492333B (en) Graph-model matching method for power grid discrete model and wiring mode
CN110852533B (en) Automatic power grid operation flow extraction and equivalence method based on CIM/E and QS files

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant