CN105256097A - Converter evaporation cooler for preventing scaling and scaling prevention method - Google Patents

Converter evaporation cooler for preventing scaling and scaling prevention method Download PDF

Info

Publication number
CN105256097A
CN105256097A CN201510770764.3A CN201510770764A CN105256097A CN 105256097 A CN105256097 A CN 105256097A CN 201510770764 A CN201510770764 A CN 201510770764A CN 105256097 A CN105256097 A CN 105256097A
Authority
CN
China
Prior art keywords
evaporative cooler
converter
evaporation cooler
fouling
preventing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510770764.3A
Other languages
Chinese (zh)
Inventor
李海英
王兰玉
王宝军
韩志杰
幺洪勇
郭少华
姚永奎
吴海东
张�杰
滕军华
张滔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China University of Science and Technology
Tangshan Iron and Steel Group Co Ltd
Original Assignee
North China University of Science and Technology
Tangshan Iron and Steel Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North China University of Science and Technology, Tangshan Iron and Steel Group Co Ltd filed Critical North China University of Science and Technology
Priority to CN201510770764.3A priority Critical patent/CN105256097A/en
Publication of CN105256097A publication Critical patent/CN105256097A/en
Pending legal-status Critical Current

Links

Landscapes

  • Cleaning By Liquid Or Steam (AREA)

Abstract

The invention discloses a converter evaporation cooler for preventing scaling. The converter evaporation cooler comprises an evaporation cooler body, wherein double medium atomization nozzles are mounted in an inlet of the evaporation cooler body; a scaling prevention coating layer is arranged on the inner wall of the evaporation cooler body; an ultrasonic vibration dust removing device is mounted in the evaporation cooler body; the double medium atomization nozzles are aslant installed along the inner periphery of the inlet of the evaporation cooler body; and each nozzle has the same mounting angle. The converter evaporation cooler is simple in spraying of the scaling prevention coating layer, free of influencing the smoke flow and the heat transfer, convenient for installation, excellent in dust removing effect, capable of preventing the wall surface of the evaporation cooler from scaling in all directions without dead angles, high in automation degree, reliable in working performance, simple in change of a nozzle arrangement mode, free of adverse effect on cooling, tempering and rough dust removing effects of the evaporation cooler after inclined spraying, and capable of preventing airflows at the bottom of the evaporation cooler from flowing back.

Description

Prevent the converter evaporative cooler of fouling and prevent the method for fouling
Technical field
The present invention relates to the maintaining method in converter dry dust removal installation, a kind ofly specifically prevent the converter evaporative cooler of fouling and prevent the method for fouling.
Background technology
Along with country is to the increasingly stringent of environmental requirement, steel mill's converter gas dedusting technology development, dry dedusting technology is subject to attention and the employing of each steel mill.Converter dry dedusting technology has that efficiency of dust collection is high, water-saving result good, energy conversion efficiency is high, working cost is low, energy consumption is few, floor space is little, be convenient to advantages such as administering and maintaining, be expected to the target realizing the steel-making of converter incapability, be identified as developing direction from now in the world.Evaporative cooler is the key equipment in converter dry dust-removal system, mainly lowers the temperature to flue gas, the process of modified and thick dedusting, and its operation conditions directly affects the efficiency of dust collection of electric precipitator below.Evaporative cooler inwardly projecting orifice water spray is uneven, or smoke moisture is excessive, or the evaporative cooler body design dust (Fe caused in flue gas such as unreasonable 2o 3, FeO, CaO, SiO 2and the compound etc. of complexity) be bonded together stick on the wall of evaporative cooler with water, cause wall scale formation.In actual production process, this is the operating technical barrier of dry-dedusting system, and the generation of scale formation can make outlet temperature for evaporation cooler rise, and affects the efficiency of dust collection of electrostatic precipitator below, and then affects the efficiency of whole dust removal process.The formation of schmutzband, decreases the open area of exhaust gases passes in evaporative cooler, causes resistance to flow to increase, and the energy consumption of blower fan can be made to increase.In addition, wall fouling in irregular shape, can cause flue gas vortex, reduces fluency and the homogeneity of flow of flue gas, is degrading dust removing effects.
Summary of the invention
The present invention be directed to the many deficiencies existed in prior art, one is to provide a kind of converter evaporative cooler that effectively can prevent fouling, and two are to provide the method that this evaporative cooler prevents fouling.
The technical scheme realizing the employing of foregoing invention object is: a kind of converter evaporative cooler preventing fouling, and comprise evaporative cooler body, two medium atomization nozzles are arranged on the ingress of evaporative cooler body,
Described evaporative cooler inner body wall is provided with good antiscale property coating;
Described evaporative cooler body interior is provided with ultrasonic vibration cleaning apparatus;
Described two medium atomization nozzles tilt to install along the inner periphery of evaporative cooler body entrance, and the setting angle of each nozzle is identical.
The angle of inclination of two medium atomization nozzle is clockwise.
The angle of inclination of two medium atomization nozzle is counterclockwise.
Ultrasonic vibration cleaning apparatus is arranged on the position of the easy fouling of evaporative cooler inwall.
A kind of method preventing the fouling of converter evaporative cooler, the method, based on evaporative cooler body, evaporative cooler body interior sidewall surface sprays good antiscale property coating, installs ultrasonic vibration cleaning apparatus in tactical deployment of troops water cooler wall inside, installed by same angular slope by all two medium atomization nozzles being arranged on evaporative cooler body ingress.
The angle of inclination of two medium atomization nozzle is all clockwise or is all counterclockwise, and angle of inclination is to ensure that in tower, flue gas is that cyclone mode flowing is as the criterion.
Ultrasonic vibration cleaning apparatus is arranged on the position of the easy fouling of evaporative cooler inwall.
Owing to have employed technique scheme, the present invention utilizes good antiscale property coating, ultrasonic vibration cleaning apparatus and changes the method for flue gas flow field and effectively to avoid evaporating water cooler fouling.Its unusual effect is also: good antiscale property coating spraying is simple, bonds firmly, do not affect flow of flue gas and heat transfer with wall; Ultrasonic vibration cleaning apparatus is easy for installation, ash disposal scope is large, effective, can dust that is comprehensive, that adhere to without the removing evaporative cooler wall at dead angle, and sound wave dust separator running cost and maintenance cost are very low, the work of energy on-line continuous, level of automation are high, reliable working performance; Change nozzle placement mode simply, after tiltedly spraying on evaporative cooler cooling, the impact of modified and thick dust removing effects not quite.
Accompanying drawing explanation
Fig. 1 is one-piece construction schematic diagram of the present invention.
Fig. 2 is the A direction view in Fig. 1.
In figure: evaporative cooler body 1, ultrasonic vibration cleaning apparatus 2, evaporative cooler body outlet 3, good antiscale property coating 4, two medium atomization nozzle 5, evaporative cooler body entrance 6.
Embodiment
Below in conjunction with drawings and Examples, the present invention will be further described.
See accompanying drawing 1-2, this method of fouling that prevents disclosed in this invention is applicable to coverter pig evaporative cooler, be improve on the basis of conventional evaporative coolers, and in actually operating, carry out use restriction based on this improvement, thus the water cooler encrustation that effectively avoids evaporating.
Converter evaporative cooler after this improvement, comprises evaporative cooler body 1, ultrasonic vibration cleaning apparatus 2, evaporative cooler body outlet 3, good antiscale property coating 4, two medium atomization nozzle 5, evaporative cooler body entrance 6.Two medium atomization nozzles are arranged on the ingress of evaporative cooler body, and the outlet of evaporative cooler body is arranged on its body side.Improvement part is: one sprays good antiscale property coating in evaporative cooler inner body wall; Two are provided with ultrasonic vibration cleaning apparatus in evaporative cooler body interior; The inner periphery of two medium atomization nozzle along evaporative cooler body entrance tilts to install by three, and the setting angle of each nozzle is identical.
Based on the evaporative cooler after above-mentioned modified node method, the method (i.e. principle) of its good antiscale property is: converter gas enters evaporative cooler body by evaporative cooler entrance, the atomizing droplet sprayed with atomizing nozzle carries out mass transfer, heat transfer reaction, the angle of inclination of two medium atomization nozzle is clockwise or counterclockwise, the scope at its angle of inclination is to ensure that in tower, flue gas is that cyclone mode flowing is as the criterion, the atomizing droplet of the atomizing nozzle ejection of tilting drives flue gas rotational flow can add the residence time of flue gas, drive flue gas swirling motion together, reduce the topical hypothermia of tower wall, make drop near wall rapid evaporation, prevent the dust accumulation in atomizing droplet and flue gas, bonding, be attached on evaporative cooler wall and produce scale formation, in evaporative cooler inner body wall, even application has good antiscale property coating, and this coating can reduce converter along the adhesion of dust on evaporative cooler inwall wherein, does not hinder the flowing along it simultaneously, in addition, in the position of evaporative cooler inner body wall easy fouling, vibration of ultrasonic wave cleaning apparatus is installed, as body and outlet connection etc., this device can produce ultrasonic wave, ultrasonic wave can cause the dirty matter hardened on wall to follow wall to shake together, because the form of dirty matter is different from metal with elastic impedance, shear stress can be formed on interface between dirt matter and wall, cause hardening dirty matter fatigue on wall, crackle, loose, broken and come off, thus reach the object of antiscale, scale removal.
The above-mentioned relevant texture improvement in order to the water cooler fouling that avoids evaporating and method, the water cooler wall fouling that avoids evaporating that can be permanently effective, does not affect the efficiency of dust collection of converter dry dust-removal system simultaneously.

Claims (7)

1. prevent a converter evaporative cooler for fouling, comprise evaporative cooler body, two medium atomization nozzles are arranged on the ingress of evaporative cooler body, it is characterized in that,
Described evaporative cooler inner body wall is provided with good antiscale property coating;
Described evaporative cooler body interior is provided with ultrasonic vibration cleaning apparatus;
Described two medium atomization nozzles tilt to install along the inner periphery of evaporative cooler body entrance, and the setting angle of each nozzle is identical.
2. the converter evaporative cooler preventing fouling according to claim 1, is characterized in that, the angle of inclination of described two medium atomization nozzles is clockwise.
3. the converter evaporative cooler preventing fouling according to claim 1, is characterized in that, the angle of inclination of described two medium atomization nozzles is counterclockwise.
4. the converter evaporative cooler preventing fouling according to claim 1, is characterized in that, described ultrasonic vibration cleaning apparatus is arranged on the position of the easy fouling of evaporative cooler inwall.
5. one kind prevents the method for converter evaporative cooler fouling, the method is based on evaporative cooler body, it is characterized in that, evaporative cooler body interior sidewall surface sprays good antiscale property coating, ultrasonic vibration cleaning apparatus is installed in tactical deployment of troops water cooler wall inside, all two medium atomization nozzles being arranged on evaporative cooler body ingress are installed by same angular slope.
6. the method preventing the fouling of converter evaporative cooler according to claim 5, its feature exists, and the angle of inclination of described two medium atomization nozzles is all clockwise or is all counterclockwise, and angle of inclination is to ensure that in tower, flue gas is that cyclone mode flowing is as the criterion.
7. the method preventing the fouling of converter evaporative cooler according to claim 5, its feature exists, and described ultrasonic vibration cleaning apparatus is arranged on the position of the easy fouling of evaporative cooler inwall.
CN201510770764.3A 2015-11-12 2015-11-12 Converter evaporation cooler for preventing scaling and scaling prevention method Pending CN105256097A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510770764.3A CN105256097A (en) 2015-11-12 2015-11-12 Converter evaporation cooler for preventing scaling and scaling prevention method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510770764.3A CN105256097A (en) 2015-11-12 2015-11-12 Converter evaporation cooler for preventing scaling and scaling prevention method

Publications (1)

Publication Number Publication Date
CN105256097A true CN105256097A (en) 2016-01-20

Family

ID=55096022

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510770764.3A Pending CN105256097A (en) 2015-11-12 2015-11-12 Converter evaporation cooler for preventing scaling and scaling prevention method

Country Status (1)

Country Link
CN (1) CN105256097A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113684340A (en) * 2021-08-27 2021-11-23 南京常荣声学股份有限公司 Converter flue gas treatment and waste heat recovery method and system based on dry dedusting
CN113831768A (en) * 2021-09-24 2021-12-24 山东钢铁股份有限公司 Anti-scaling coating for dry dedusting evaporative cooler
CN114622056A (en) * 2020-12-14 2022-06-14 中冶京诚工程技术有限公司 Converter flue gas chiller, cooling device and method for improving cooling efficiency

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202032599U (en) * 2011-01-31 2011-11-09 无锡三达环保科技有限公司 Spray evaporation type cooler
WO2014052072A1 (en) * 2012-09-26 2014-04-03 3M Innovative Properties Company Coatable composition, soil-resistant composition, soil-resistant articles, and methods of making the same
CN104388627A (en) * 2014-11-20 2015-03-04 中冶南方工程技术有限公司 Dust removing method for coal gas of converter and system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202032599U (en) * 2011-01-31 2011-11-09 无锡三达环保科技有限公司 Spray evaporation type cooler
WO2014052072A1 (en) * 2012-09-26 2014-04-03 3M Innovative Properties Company Coatable composition, soil-resistant composition, soil-resistant articles, and methods of making the same
CN104388627A (en) * 2014-11-20 2015-03-04 中冶南方工程技术有限公司 Dust removing method for coal gas of converter and system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
盖东兴 等: "转炉煤气干法除尘系统创新及工程应用", 《世界金属导报》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114622056A (en) * 2020-12-14 2022-06-14 中冶京诚工程技术有限公司 Converter flue gas chiller, cooling device and method for improving cooling efficiency
CN114622056B (en) * 2020-12-14 2023-11-10 中冶京诚工程技术有限公司 Converter flue gas chiller, cooling device and method for improving cooling efficiency
CN113684340A (en) * 2021-08-27 2021-11-23 南京常荣声学股份有限公司 Converter flue gas treatment and waste heat recovery method and system based on dry dedusting
CN113831768A (en) * 2021-09-24 2021-12-24 山东钢铁股份有限公司 Anti-scaling coating for dry dedusting evaporative cooler
CN113831768B (en) * 2021-09-24 2023-02-10 山东钢铁股份有限公司 Anti-scaling coating for dry dedusting evaporative cooler

Similar Documents

Publication Publication Date Title
CN104226479B (en) The high-efficient wet-type electric precipitation purifier and method of a kind of wet-method desulfurized fume
CN105256097A (en) Converter evaporation cooler for preventing scaling and scaling prevention method
CN107213984A (en) A kind of electromagnetic duster and flue gas purification system
CN101435663A (en) Reversed flow heat transfer eddy flow secondary atomizing induced draft cooling tower
CN206549892U (en) A kind of mounting structure of smoke processing system and sprayer
CN101893390B (en) Sand protecting and dust removing device for cooling tower
CN204107255U (en) A kind of combination venturi scrubber
CN112682814A (en) Blockage clearing device and method for multiple air preheater systems
CN202263505U (en) Wet type gas purifying device
CN202061509U (en) Tail gas purification and treatment device
CN201154279Y (en) Wet-type smoke removal device
CN110433643A (en) A kind of highly effective energy-conserving environmental-protecting type chilling tower
CN216062585U (en) Counter-flow wet dust-removing tower
CN206198985U (en) A kind of desulfurization carries effect device and a kind of wet desulfuration tower
CN204699546U (en) A kind of Wet-type dust-removal fan
CN212441660U (en) Cyclone nozzle of pneumatic soot blowing system of coal-fired boiler
CN209221854U (en) A kind of new side position spray smoke absorption tower
CN211245922U (en) Humidification formula industrial dust collector
CN210473424U (en) Particle pretreatment device
CN209696582U (en) A kind of novel suspended floating ball refined dedusting device
CN209138167U (en) A kind of cyclone dust collector with cooling structure
CN208536642U (en) A kind of centrifugation cross-flow induced draft cooling tower
CN209985126U (en) A water sprays dust collector for essential oil production
CN210544051U (en) High-efficient rotatory nozzle in water film gas wash tower
CN208372722U (en) A kind of water spray electrostatic precipitator

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160120