CN105240021A - 超大断面黄土隧道改进cd法施工方法 - Google Patents

超大断面黄土隧道改进cd法施工方法 Download PDF

Info

Publication number
CN105240021A
CN105240021A CN201510735435.5A CN201510735435A CN105240021A CN 105240021 A CN105240021 A CN 105240021A CN 201510735435 A CN201510735435 A CN 201510735435A CN 105240021 A CN105240021 A CN 105240021A
Authority
CN
China
Prior art keywords
tunnel
excavating
excavation
soil
base tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510735435.5A
Other languages
English (en)
Inventor
米小强
李善英
闫有民
单静云
范标
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GANSU WANTAI CONSTRUCTION ENGINEERING Co Ltd
Gansu Road and Bridge Construction Group Co Ltd
Original Assignee
GANSU WANTAI CONSTRUCTION ENGINEERING Co Ltd
Gansu Road and Bridge Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GANSU WANTAI CONSTRUCTION ENGINEERING Co Ltd, Gansu Road and Bridge Construction Group Co Ltd filed Critical GANSU WANTAI CONSTRUCTION ENGINEERING Co Ltd
Priority to CN201510735435.5A priority Critical patent/CN105240021A/zh
Publication of CN105240021A publication Critical patent/CN105240021A/zh
Pending legal-status Critical Current

Links

Abstract

本发明涉及一种超大断面黄土隧道改进CD法施工方法,该方法包括以下步骤:⑴开挖先行上导坑,施做初期支护和临时支护,并开挖拱架间距;⑵待先行上导坑开挖深度达10m后,再开挖后行上导坑,并开挖拱架间距;⑶开挖先行下导坑,并开挖拱架间距,预留临时支撑中土柱土体,同时利用挖出的土对已完成的先行下导坑进行回填反压;⑷开挖后行下导坑,并开挖拱架间距,预留临时支撑中土柱土体,同时利用挖出的土对已完成的后行下导坑进行回填反压;⑸拆除临时支护,开挖中土柱,并全幅开挖中心水沟和仰拱,仰拱一次成环,施做二衬仰拱及填充,二衬紧跟施做即可。本发明大型机械可以同时到达上下导坑工作面,施工互不干扰,施工进度快且成本低。

Description

超大断面黄土隧道改进CD法施工方法
技术领域
本发明涉及隧道施工技术领域,尤其涉及超大断面黄土隧道改进CD法施工方法。
背景技术
隧道开挖是隧道施工的重点控制工序,而国内以Q3黄土为主,天然含水率为5~12%,埋深大于20m的超大断面黄土隧道施工采用传统CD法施工。传统CD法开挖顺序为先开挖先行上导坑,再开挖先行下导坑,第三步开挖后行上导坑,第四步开挖后行下导坑,该开挖方式有以下几种缺点:下导坑开挖支护时,大型机械无法到达上导坑,上导坑主要以人工开挖方式施工,施工效率低,施工进度缓慢;上下导坑临时支护拼接速度缓慢,工序复杂,拼接完成后临时支护长细比大,临时支护稳定性差;临时支护较多,拆除量大,整体进度缓慢,施工工期较长。
发明内容
本发明所要解决的技术问题是提供一种施工成本低、施工速度快的超大断面黄土隧道改进CD法施工方法。
为解决上述问题,本发明所述的超大断面黄土隧道改进CD法施工方法,包括以下步骤:
⑴开挖先行上导坑,施做初期支护和临时支护,并开挖进尺1~2倍的拱架间距;
⑵待所述先行上导坑开挖深度达10m后,再开挖后行上导坑,并开挖进尺1~2倍的拱架间距;
⑶开挖先行下导坑,并开挖进尺3~4倍的拱架间距,预留临时支撑中土柱土体,同时利用挖出的土对已完成的所述先行下导坑进行回填反压;
⑷开挖后行下导坑,并开挖进尺3~4倍的拱架间距,预留临时支撑中土柱土体,同时利用挖出的土对已完成的所述后行下导坑进行回填反压;
⑸拆除所述临时支护,开挖中土柱,并全幅开挖中心水沟和仰拱,开挖间距3m,仰拱一次成环,施做二衬仰拱及填充,二衬紧跟施做即可。
所述先行上导坑与所述后行上导坑的间距为10m~15m。
所述先行下导坑与所述后行上导坑的距离应大于15m。
所述后行下导坑与所述先行下导坑的距离大于10m。
所述中土柱开挖与所述后行下导坑的距离大于15m。
本发明与现有技术相比具有以下优点:
1、本发明开挖顺序变为先两侧上导坑,后两侧下导坑,使得同侧的上下导坑拉开距离,大型机械可以同时到达上下导坑工作面,施工互不干扰,施工进度明显加快。
2、本发明利用预留中土柱代替下导坑临时支护,简化上下导临时支护拼接及拆除,施工进度明显加快,临时支护总长度变短,稳定性提高,同时降低了施工成本。
3、采用本发明方法施工后,较传统CD法节约下导坑临时支护,且施工进度增快。
附图说明
下面结合附图对本发明的具体实施方式作进一步详细的说明。
图1为本发明施工顺序示意图。
图2为本发明的施工工作面立体示意图。
图中:1—先行上导坑2—后行上导坑3—先行下导坑4—后行下导坑5—中土柱6—临时支护。
具体实施方式
如图1、图2所示,超大断面黄土隧道改进CD法施工方法,包括以下步骤:
⑴开挖先行上导坑1,施做初期支护和临时支护6,并开挖进尺1~2倍的拱架间距,视围岩状况而定。
⑵待先行上导坑1开挖深度达10m后,再开挖后行上导坑2,并开挖进尺1~2倍的拱架间距,视围岩状况而定。先行上导坑1与后行上导坑2的间距为10m~15m,以减小两导坑同时开挖对同一区域围岩的扰动。
⑶开挖先行下导坑3,并开挖进尺3~4倍的拱架间距,预留临时支撑中土柱5土体,同时利用挖出的土对已完成的先行下导坑3进行回填反压,抑制收敛。先行下导坑3与后行上导坑2的距离应大于15m,方便施工机械转弯行驶。
⑷开挖后行下导坑4,并开挖进尺3~4倍的拱架间距,预留临时支撑中土柱5土体,同时利用挖出的土对已完成的后行下导坑4进行回填反压,抑制收敛。后行下导坑4与先行下导坑3的距离大于10m。
⑸拆除临时支护6,开挖中土柱5,并全幅开挖中心水沟和仰拱,开挖间距3m,仰拱一次成环,施做二衬仰拱及填充,二衬紧跟施做即可。中土柱5开挖与后行下导坑4的距离大于15m。

Claims (5)

1.超大断面黄土隧道改进CD法施工方法,包括以下步骤:
⑴开挖先行上导坑(1),施做初期支护和临时支护(6),并开挖进尺1~2倍的拱架间距;
⑵待所述先行上导坑(1)开挖深度达10m后,再开挖后行上导坑(2),并开挖进尺1~2倍的拱架间距;
⑶开挖先行下导坑(3),并开挖进尺3~4倍的拱架间距,预留临时支撑中土柱(5)土体,同时利用挖出的土对已完成的所述先行下导坑(3)进行回填反压;
⑷开挖后行下导坑(4),并开挖进尺3~4倍的拱架间距,预留临时支撑中土柱(5)土体,同时利用挖出的土对已完成的所述后行下导坑(4)进行回填反压;
⑸拆除所述临时支护(6),开挖中土柱(5),并全幅开挖中心水沟和仰拱,开挖间距3m,仰拱一次成环,施做二衬仰拱及填充,二衬紧跟施做即可。
2.如权利要求1所述的超大断面黄土隧道改进CD法施工方法,其特征在于:所述先行上导坑(1)与所述后行上导坑(2)的间距为10m~15m。
3.如权利要求1所述的超大断面黄土隧道改进CD法施工方法,其特征在于:所述先行下导坑(3)与所述后行上导坑(2)的距离应大于15m。
4.如权利要求1所述的超大断面黄土隧道改进CD法施工方法,其特征在于:所述后行下导坑(4)与所述先行下导坑(3)的距离大于10m。
5.如权利要求1所述的超大断面黄土隧道改进CD法施工方法,其特征在于:所述中土柱(5)开挖与所述后行下导坑(4)的距离大于15m。
CN201510735435.5A 2015-11-03 2015-11-03 超大断面黄土隧道改进cd法施工方法 Pending CN105240021A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510735435.5A CN105240021A (zh) 2015-11-03 2015-11-03 超大断面黄土隧道改进cd法施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510735435.5A CN105240021A (zh) 2015-11-03 2015-11-03 超大断面黄土隧道改进cd法施工方法

Publications (1)

Publication Number Publication Date
CN105240021A true CN105240021A (zh) 2016-01-13

Family

ID=55037812

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510735435.5A Pending CN105240021A (zh) 2015-11-03 2015-11-03 超大断面黄土隧道改进cd法施工方法

Country Status (1)

Country Link
CN (1) CN105240021A (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105863677A (zh) * 2016-04-12 2016-08-17 中国电建集团成都勘测设计研究院有限公司 隧道初期支护的加固方法
CN107676099A (zh) * 2017-11-22 2018-02-09 北京市政建设集团有限责任公司 一种扩大墙脚隧道分部开挖施工方法
CN108708739A (zh) * 2018-04-12 2018-10-26 中铁四局集团有限公司 一种适用于超大断面硬岩隧道的浅埋外露施工方法
CN108843332A (zh) * 2018-07-15 2018-11-20 中铁二十局集团有限公司 穿越断层破碎带大断面隧道开挖及支护方法
CN109681212A (zh) * 2018-12-17 2019-04-26 中交第二航务工程局有限公司 小断面黄土隧道的开挖施工方法
CN113931660A (zh) * 2021-10-25 2022-01-14 四川省交通建设集团股份有限公司 一种适用连拱隧道无导洞法的预留单侧壁土柱法
CN115949411A (zh) * 2023-02-24 2023-04-11 中国十七冶集团有限公司 一种大断面软弱围岩隧道施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4139320A (en) * 1976-08-20 1979-02-13 Japanese National Railways Process for excavating and constructing tunnel and excavating device
CN102220868A (zh) * 2011-05-23 2011-10-19 重庆中环建设有限公司 城市浅埋大断面隧道五部开挖工法
CN102322266A (zh) * 2011-06-17 2012-01-18 中铁十一局集团第五工程有限公司 一种隧道开挖施工方法
CN104165056A (zh) * 2014-03-11 2014-11-26 中交一公局厦门工程有限公司 一种富水浅埋暗挖隧道的开挖施工方法
CN104879131A (zh) * 2015-05-06 2015-09-02 中国电建集团华东勘测设计研究院有限公司 上软下硬复合地层的大跨度隧道开挖方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4139320A (en) * 1976-08-20 1979-02-13 Japanese National Railways Process for excavating and constructing tunnel and excavating device
CN102220868A (zh) * 2011-05-23 2011-10-19 重庆中环建设有限公司 城市浅埋大断面隧道五部开挖工法
CN102322266A (zh) * 2011-06-17 2012-01-18 中铁十一局集团第五工程有限公司 一种隧道开挖施工方法
CN104165056A (zh) * 2014-03-11 2014-11-26 中交一公局厦门工程有限公司 一种富水浅埋暗挖隧道的开挖施工方法
CN104879131A (zh) * 2015-05-06 2015-09-02 中国电建集团华东勘测设计研究院有限公司 上软下硬复合地层的大跨度隧道开挖方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
宰紧珉等: "《岩土工程测试与监测技术》", 31 July 2008 *
褚晓晖: "上台阶CD 法在客专某浅埋隧道中的开发应用", 《科学之友》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105863677A (zh) * 2016-04-12 2016-08-17 中国电建集团成都勘测设计研究院有限公司 隧道初期支护的加固方法
CN105863677B (zh) * 2016-04-12 2018-11-13 中国电建集团成都勘测设计研究院有限公司 隧道初期支护的加固方法
CN107676099A (zh) * 2017-11-22 2018-02-09 北京市政建设集团有限责任公司 一种扩大墙脚隧道分部开挖施工方法
CN108708739A (zh) * 2018-04-12 2018-10-26 中铁四局集团有限公司 一种适用于超大断面硬岩隧道的浅埋外露施工方法
CN108708739B (zh) * 2018-04-12 2019-07-26 中铁四局集团有限公司 一种适用于超大断面硬岩隧道的浅埋外露施工方法
CN108843332A (zh) * 2018-07-15 2018-11-20 中铁二十局集团有限公司 穿越断层破碎带大断面隧道开挖及支护方法
CN109681212A (zh) * 2018-12-17 2019-04-26 中交第二航务工程局有限公司 小断面黄土隧道的开挖施工方法
CN109681212B (zh) * 2018-12-17 2021-05-11 中交第二航务工程局有限公司 小断面黄土隧道的开挖施工方法
CN113931660A (zh) * 2021-10-25 2022-01-14 四川省交通建设集团股份有限公司 一种适用连拱隧道无导洞法的预留单侧壁土柱法
CN113931660B (zh) * 2021-10-25 2024-04-09 四川省交通建设集团股份有限公司 一种适用连拱隧道无导洞法的预留单侧壁土柱法
CN115949411A (zh) * 2023-02-24 2023-04-11 中国十七冶集团有限公司 一种大断面软弱围岩隧道施工方法

Similar Documents

Publication Publication Date Title
CN105240021A (zh) 超大断面黄土隧道改进cd法施工方法
CN106869944B (zh) 复杂环境下地下立交交叉口超小净距隧道施工方法
CN102182466B (zh) 隧道双侧壁导坑结合拱部跳挖开挖方法
CN102155232B (zh) 地形偏压条件下大跨不对称双连拱铁路隧道施工方法
CN102644466B (zh) 岩质地层中修建超浅埋大跨度暗挖地铁车站的托梁拱盖法
CN101963060B (zh) 基于钢管拱肋支护结构的隧道施工方法
CN104806251B (zh) 一种用于复杂环境下城市地铁车站附属仰挖施工方法
CN103244133B (zh) 煤系地层隧道铣挖与爆破联合施工工法
CN104653187B (zh) 富水砂层地质大断面隧道开挖方法
CN103899318B (zh) 中硬地层隧道铣挖及配套机械化施工工法
CN208220817U (zh) 超大断面浅埋软弱围岩隧道井字形双侧壁支护体系
CN103628889A (zh) 千枚岩地层隧道开挖快速封闭方法
CN103277106A (zh) 公路隧道三台阶五步开挖施工方法
CN104895575A (zh) 上软下硬地层大断面隧道高效快速施工方法
CN102720504A (zh) 双侧壁导坑分部台阶法施工方法
CN106979013A (zh) 一种偏压浅埋软弱围岩的超大断面隧道的开挖施工方法
CN103775095A (zh) 山岭软基隧道超前双导洞及其施工方法
CN110924952A (zh) 超大断面隧道三台阶七步法向中岩柱法转换的施工方法
CN107575237A (zh) 一种暗挖法与盾构法相结合建造地铁车站的施工方法
CN103628890A (zh) 软弱千枚岩隧道开挖变形控制方法
CN104265305A (zh) 从两个小断面洞室合并到一个大断面洞室的扩挖方法
CN114352292A (zh) 用于风化千枚岩地层的浅埋偏压连拱隧道施工方法
CN109594995B (zh) 一种软弱围岩隧道微扰动机械分部掘进工法
CN107218044A (zh) 一种挤压性围岩小净距隧道的开挖方法
CN203716985U (zh) 一种山岭软基隧道超前双导洞

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160113

RJ01 Rejection of invention patent application after publication