CN105179808B - Pipe laying construction method after the pre- ditching of long range submerged pipeline - Google Patents

Pipe laying construction method after the pre- ditching of long range submerged pipeline Download PDF

Info

Publication number
CN105179808B
CN105179808B CN201510609139.0A CN201510609139A CN105179808B CN 105179808 B CN105179808 B CN 105179808B CN 201510609139 A CN201510609139 A CN 201510609139A CN 105179808 B CN105179808 B CN 105179808B
Authority
CN
China
Prior art keywords
mrow
pipeline
msub
ditching
grab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510609139.0A
Other languages
Chinese (zh)
Other versions
CN105179808A (en
Inventor
高兆鑫
付春丽
赵海
高海峰
杜书鑫
曹秋媛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum Group Ocean Engineering (qingdao) Co Ltd
Original Assignee
China Petroleum Group Ocean Engineering (qingdao) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum Group Ocean Engineering (qingdao) Co Ltd filed Critical China Petroleum Group Ocean Engineering (qingdao) Co Ltd
Priority to CN201510609139.0A priority Critical patent/CN105179808B/en
Publication of CN105179808A publication Critical patent/CN105179808A/en
Application granted granted Critical
Publication of CN105179808B publication Critical patent/CN105179808B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/12Laying or reclaiming pipes on or under water
    • F16L1/16Laying or reclaiming pipes on or under water on the bottom

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Sewage (AREA)
  • Pipeline Systems (AREA)

Abstract

The present invention relates to a kind of pipe laying construction method after pre- ditching of long range submerged pipeline, it comprises the following steps:Step 1, the pre- ditching of sub-sea location progress to being intended to pipeline installation, form pipeline groove;Step 2, calculating are intended to prestress value of the pipeline installation in each axial positions of pipeline groove;Step 3, the prestress value of each axial positions calculated is compared with prestressing force level threshold value respectively;Step 4, according to comparative result, determine that the prestress value in pipeline groove exceedes the axial location of prestressing force level threshold value, and carry out rectification construction.

Description

Pipe laying construction method after the pre- ditching of long range submerged pipeline
Technical field
The present invention relates to the technical field of undersea pipe-laying, and in particular to is spread after a kind of pre- ditching of long range submerged pipeline Pipe construction method.
Background technology
As offshore oil and gas field exploitation constantly extends to deep layer and frontier, offshore platform PROCESS FOR TREATMENT flow is more and more simpler Change, increasing submerged pipeline is used, inevitably occur during pipe installation and pass through busy navigation channel, harbour Buried depth is increased Deng the phenomenon in high traffic section marine site, therefore for protection pipeline.Embedded depth be traditional rear ditcher without What method was realized, it is therefore desirable to pipe laying after the pre- ditching of long range.
At present, domestic and international specification is to pipe laying construction technology after the pre- ditching of long range submerged pipeline, only in DNV-OS-F101 In requirement to pipe trench be " sufficiently smooth ", i.e., qualitative regulation (the trench " enough smoothly " shallbe excavated to a sufficiently smooth profile to minimise thepossibility Of damages to the pipeline, coating and anodes), but operability is very poor in practice of construction, very Hardly possible judges the stable case of pipeline.The domestic and international construction precedent without pipe laying after the pre- ditching of long range submerged pipeline.
The content of the invention
For case above, present inventor is on the basis of data at home and abroad is consulted, by largely analyzing and trying Test, develop a set of method for meeting pipe laying construction after the pre- ditching of long range submerged pipeline.This method is based on FEM model The pre- ditching bottom of trench flatness of long range submerged pipeline is analyzed, the mount stress control to pipe laying after pre- ditching over long distances is realized System, solves the construction difficult problem of pipe laying after the pre- ditching of long range submerged pipeline.This method proposes long range submerged pipeline first The solution of pipe laying construction after pre- ditching, has ensured the safety of new laying pipeline.This method considers controlled investment, shortening Duration, facilitate factor in terms of site operation, ditching mode after traditional first pipe laying is breached first, formed and be applied to over long distances The technical scheme of pipe laying construction after the pre- ditching of submerged pipeline, pipe laying construction technology after the pre- ditching of long range submerged pipeline is successfully answered In the branch line submarine pipeline state key project financing of the second west to east gas pipeline project Hong Kong.
The features such as this method has economic, efficient, pollution-free, strong operability, meets construction requirement.
Embodiments in accordance with the present invention are there is provided a kind of pipe laying construction method after pre- ditching of long range submerged pipeline, and it is wrapped Include following steps:Step 1, the pre- ditching of sub-sea location progress to being intended to pipeline installation, form pipeline groove;Step 2, calculating are intended to spread If pipeline is in the prestress value of each axial positions of pipeline groove;Step 3, by the pre- of each axial positions calculated Stress value is compared with prestressing force level threshold value respectively;Step 4, according to comparative result, determine the prestressing force in pipeline groove Value exceedes the axial location of prestressing force level threshold value, and carries out rectification construction.
The invention has the advantages that:
1st, it is pipe laying construction after the domestic pre- ditching of long range submerged pipeline first, pipeline specifications do not recommend way, and long The pipe laying construction after the pre- ditching of submerged pipeline, at home and abroad all beyond example;
2nd, economic, efficient, strong operability.Can effectively solve marine area function zoning complexity where engineering, ship frequent activity, The requirement that program practice is tight, the implementing plan duration is tight.
3rd, pipe laying construction after the pre- ditching of long range submerged pipeline, the control of bottom of trench flatness is improper in ditching, easily causes new Build pipeline local stress excessive, cause deformation or even damage, produce immeasurable consequence.The program disclosure satisfy that the engineering The characteristics of mesh control of investment is tight, the implementing plan duration is tight, meets field engineering requirement.
4th, pipe laying construction method after the pre- ditching of long range submerged pipeline, achieves good effect in engineering, it is possible to resolve The practical problem of pipe laying construction and duration anxiety, produces obvious economic benefit after the pre- ditching of long range submerged pipeline.
5th, pipe laying construction after the pre- ditching of long range submerged pipeline, at home and abroad all beyond example, first in transfering natural gas from the west to the east two Applied in the branch line submarine pipeline engineering of line spices port, successfully solve the problem of pipe laying after nearly 20 kilometers of pre- ditchings.Therefore, this skill The breakthrough of art, to fill the domestic gaps, solve after the pre- ditching of China's submerged pipeline technical barrier of pipe laying construction etc. have it is important Meaning.Strong reference reference value is provided for the construction of submarine pipeline of the same trade.
Brief description of the drawings
Fig. 1 is the pipe canal digging sectional drawing according to embodiments of the invention;
Fig. 2 is the segmentation according to embodiments of the invention and slitting ditching figure;
Fig. 3 is to be excavated to scheme according to the layering ladder of embodiments of the invention;
Fig. 4 is to be dredged figure according to the grab boat of embodiments of the invention.
Embodiment
Pipe laying construction scheme after the pre- ditching of long range submerged pipeline:
This application provides following technical scheme:
(1) piping design figure and pipe laying environmental analysis
Fig. 1 is the pipe canal digging sectional drawing according to embodiments of the invention.By to piping design figure and pipe laying marine site The depth of water, geology, wind, wave, the analysis for flowing situation, determine the excavation that grab bucket dredger is adapted to design pipe trench.
(2) pipe laying risk point analysis after pre- ditching
Influence of the maximum risk sources in pipe trench flatness to the On-bottom stability of pipeline in construction operation.With ocean work Ditching is different after common first pipe laying in journey, and the bedding that the sea pre- ditching technique of pipe is similar in dredging work is excavated, and section is small, long Degree is big, and bottom of trench flatness is the principal risk point of pipe laying construction after pre- ditching, and the steady safety for directly affecting pipeline enters ditch.
(3) pipe canal digging method is analyzed
By the research to pipe canal digging equipment its own system, clearly coordinate the pipe canal digging method of pipe laying construction.Fig. 4 is Grab boat is dredged figure according to an embodiment of the invention.Grab bucket dredger is the stronger ship of a kind of adaptability in dredger Type, it is adaptable to the dredging operation of pipe trench.As shown in figure 4, the main construction of grab bucket dredger includes grab claw and grab bucket two Point.Wherein grab claw is equipped with transmission system and control system.Transmission system is made up of the interior diesel engine set and transmission device, is used for Drive the lifting and opening and closing of grab bucket;Control system is made up of elevator scoop roller, opening and closing bucket roller and luffing roller, and roller is equipped with Clutch and brake, using hydraulic control mode, can automatically control bucket speed and dig deep, slow down falling speed automatically, steady bottom, And ensure that grab bucket is all opened.The luffing roller is connected by wirerope with derrick, the length for controlling derrick. During work, rise to above the water surface of position of dredging, opened completely by controlling opening and closing bucket roller to grab bucket by grabbing bucket, then by grabbing Bucket deadweight is poured in water, and grab bucket is inserted into mud layer certain depth, is then lifted out wirerope, and closure is grabbed bucket to excavate and capture silt, Finally, control elevator scoop roller and opening and closing bucket roller, water surface certain altitude, and rotating lifting are lifted out by the grab bucket for filling silt Bar, the silt of excavation is discharged into by refuting the hopper by ship side of dredging, grab bucket is back to a top of dredging, completes an operation and follow Ring.
Fig. 2 is the segmentation according to embodiments of the invention and slitting ditching figure, and Fig. 3 is point according to embodiments of the invention Layer ladder excavates figure.As shown in Figure 2,3, more than pipeline top surface slightly dug using large-scale grab boat, bottom 0.5m~1m Smart digging is carried out using the small-sized grab boat with depthkeeping function.Mode of dredging is carried out using subregion, segmentation, slitting, every layer Excavate the thick mud layers of 2m, it is a section length that grab bucket dredger is per 100m or so, is a slitting width per 12m.Hong Kong branch line is dug Mud side slope is 1:4 and 1:7, layering ladder need to be carried out and excavated, according to the principle of " lower super deficient, super underbalance ", side slope after slightly digging Zigzag is formed, layer of not dredging is disturbed in digging process, and disturbed soil collapses into 1 naturally under gravity:1 side Slope, rear local finding slope, eventually forms 1:4 and 1:7 side slope.
(4) the qualified control standard of pipe laying (that is, the prestressed upper limit that pipeline can bear) is determined
Submarine pipeline intensity in place is analyzed according to DNV1981 specifications, circumference stress, axial stress are calculated respectively (including thermal expansion stress and route bending stress), then carries out equivalent stress calculating, finally draws the qualified control of pipe laying Standard processed.
Circumference stress:
Wherein, piFor pipeline internal pressure, peFor hydrostatic pressure (hydraulic pressure in marine site), D is pipeline nominal diameter, and t is that steel pipe is minimum Wall thickness.
Thermal expansion stress:Axial stress comprising temperature stress and internal pressure effect generation
Temperature stress:
σlT=α E Δs t (2)
Wherein, α is pipe linear expansion coefficient, and E is steel modulus of elasticity, and Δ t is maximum or minimum running temperature with installing Temperature difference between temperature.
The stress of internal pressure effect generation is calculated according to below equation:
Wherein, υ is Poisson's ratio, diFor pipe diameter,
It route bending stress:
σlR=DE/2R (4)
Wherein, D is outer diameter tube, and E is steel modulus of elasticity, and R is route bending radius.
According to thermal expansion stress and route bending stress, axial stress is obtained:
σllTPlR
Next, equivalent stress is calculated as follows:
Wherein, τxyShear stress (it is assumed that 0).
Thus obtaining the qualified prestress control standard value of pipe laying is:
ηepσFe (6)
Wherein, ηepCoefficient of utilization, σFYield strength.That is, the pipe alley bottom dug in advance at each position it is pre- should Above-mentioned prestress control standard value is not to be exceeded in power, to meet the flatness requirement for pipeline installation.
As a specific example, for the second west to east gas pipeline project Hong Kong branch line, in above formula, each parameter is corresponding is worth such as following table It is shown:
Parameter Pipeline internal pressure, pi Pipeline external pressure, pe Pipeline nominal diameter, D Minimum wall thickness (MINI W.), t
Numerical value 7MPa 0 813mm 20.7mm
Parameter Pipe linear expansion coefficient, α Steel modulus of elasticity, E Temperature difference, Δ t Poisson's ratio, υ
Numerical value 1.17×10-5 207000MPa 43℃ 0.3
Parameter Pipe diameter, di It route bending radius, R Coefficient of utilization, ηep Yield strength, σF
Numerical value 768.6mm 1500m 0.72 448MPa
Design and tubing physical parameter more than, Hong Kong branch line sea as obtained by being calculated above-mentioned calculation formula (1)-(6) Pipe, which is laid, qualified controls standard value to be 85.3MPa.
(5) prestressing force of the pipeline at bottom of trench each extension position is obtained
For example, setting up bottom of trench flatness by OFFPIPE softwares analyzes mathematical calculation model, the pipeline of OFFPIPE softwares Span analysis " Pipe span analysis option " models, can not only obtain the height and length of extra large pipe suspended span, and The pipeline prestress value caused by pipe trench out-of-flatness can be obtained.To improve the accuracy that simulation is calculated, guarantee the safety of construction, sea The boundary condition of the vertical hardness (vertical soil deflection) of bed soil earth is conservatively set to 0;Check and accept and close because of pipe trench After lattice can pipe laying, therefore only consider distribution situation of the pipeline on sea bed, the relative depth (reference depth) of sea bed Boundary condition is set to 0;Tubing tension boundary condition is set to 20kN.Primary condition be by Site Detection obtain it is right every 10 meters Answer transverse direction, the longitudinal coordinate value of pipeline.The bottom of trench absolute altitude at each position is measured by heave the lead.Using the bottom of trench absolute altitude of measurement as Input condition, bottom of trench irregularity degree analysis is carried out using OFFPIPE softwares, determine prestressing force at each position whether not less than Above-mentioned prestress control standard value, i.e. it is determined that whether dug pipe trench meets the prestressing force requirement of pipe laying.
That is, by above-mentioned model, calculate pipeline prestress value at each position caused by pipe trench flatness, And compared with above-mentioned control standard value, so that it is determined that whether the prestressing force of each position meets control standard, further determine that Dug pipe trench, if being not suitable for, takes corresponding measures to rectify and reform if appropriate for pipe laying.
It is briefly described as follows field conduct process.
During the branch line undersea pipe-laying of the second west to east gas pipeline project Hong Kong, substantially 500 meters of ditching is once checked and accepted, Bottom of trench absolute altitude is measured by heave the lead.Water stone roller is made by 50 × 455mm of Φ round steel, can be penetrated the Mud Layer of pipe trench, be measured pipe The actual elevation of ditch.Operated during with water stone roller measurement absolute altitude by veteran measurement work.Using the bottom of trench absolute altitude of measurement as input bar Part, bottom of trench irregularity degree analysis is carried out using OFFPIPE softwares, it is determined that dug pipe trench is if appropriate for pipe laying, to being adapted to pipe laying Pipelaying work need to be carried out in time, to reduce the influence that pipe trench back-silts;The less Grab of bucket capacity need to be used to unsuitable pipe trench Carry out smooth processing.
By taking wherein two section 500 mitron section of the second west to east gas pipeline project Hong Kong branch line as an example, whether qualified bottom of trench flatness is illustrated Decision method, to determine this section of pipe trench if appropriate for progress pipe laying.As shown in table 1, simulation is calculated the bottom of trench absolute altitude of measurement Corresponding each point stress is as shown in table 2.
The corresponding ttom of pipe absolute altitude of 1 Hong Kong branch line of table, two section of 500 mitron section
The corresponding pipeline each point stress of table 2
From table 2 it can be seen that the corresponding stress of each point is satisfied by step (4) identified pipe laying conjunction in first paragraph The control standard value 85.3MPa of lattice, therefore this section of pipe trench is adapted to pipe laying;And 270m, 280m, 310m, 320m in second segment, 8 points of corresponding stress of 330m, 460m, 470m, 480m have exceeded 85.3MPa, therefore need to be handled accordingly.
Finally it should be noted that, it is clear that, above-described embodiment is only intended to clearly illustrate example of the present invention, and simultaneously The non-restriction to embodiment.For those of ordinary skill in the field, it can also do on the basis of the above description Go out other various forms of changes or variation.There is no necessity and possibility to exhaust all the enbodiments.And thus drawn Among the obvious changes or variations that Shen goes out is still in protection scope of the present invention.

Claims (7)

1. a kind of pipe laying construction method after pre- ditching of long range submerged pipeline, comprises the following steps:
Step 1, the pre- ditching of sub-sea location progress to being intended to pipeline installation, form pipeline groove;
Step 2, calculating are intended to prestress value of the pipeline installation in each axial positions of pipeline groove;
Step 3, the prestress value of each axial positions calculated is compared with prestressing force level threshold value respectively;And
Step 4, according to comparative result, determine that the prestress value in pipeline groove exceedes the axial location of prestressing force level threshold value, And carry out rectification construction,
Wherein, in the step 1, more than pipeline top surface slightly dug using large-scale grab boat, slightly digging back domatic Into zigzag,
Bottom uses the small-sized grab boat with depthkeeping function to carry out smart digging, wherein, every layer is excavated certain thickness thick mud Layer, is excavated according to every section length, per slitting width,
Wherein, grab boat excavates width and is more than slitting width, the excavation width of adjacent slitting when every slitting is excavated Have overlapping.
2. pipe laying construction method after the pre- ditching of long range submerged pipeline according to claim 1, wherein, in the step 1 In, there is 0.5 to 1 meter of use of bottom the small-sized grab boat of depthkeeping function to carry out smart digging, and mode of dredging uses subregion, divided Section, slitting are carried out, and every layer is excavated 2 meters thick mud layer, and every 100 meters of grab boat is a section length, and every 12 meters are that a slitting is wide Degree.
3. pipe laying construction method after the pre- ditching of long range submerged pipeline according to claim 1, wherein, in the step 2 In, by OFFPIPE softwares, bottom of trench flatness analysis mathematical calculation model is set up, by the border of the vertical hardness of sea bed soil Condition is set to 0, and the relative depth boundary condition of sea bed is set into 0, tubing tension boundary condition is set into 20kN, with the pipe of measurement The bottom of trench absolute altitude of road groove is input condition, obtains the prestressing force for being intended to pipeline installation in each axial positions of pipeline groove Value.
4. pipe laying construction method after the pre- ditching of long range submerged pipeline described in one in claims 1 to 3, wherein, The prestressing force level threshold value through the following steps that obtain:
According to below equation, circumference stress is calculated:
<mrow> <msub> <mi>&amp;sigma;</mi> <mi>h</mi> </msub> <mo>=</mo> <mfrac> <mrow> <mo>(</mo> <msub> <mi>p</mi> <mi>i</mi> </msub> <mo>-</mo> <msub> <mi>p</mi> <mi>e</mi> </msub> <mo>)</mo> <mi>D</mi> </mrow> <mrow> <mn>2</mn> <mi>t</mi> </mrow> </mfrac> <mo>-</mo> <mo>-</mo> <mo>-</mo> <mrow> <mo>(</mo> <mn>1</mn> <mo>)</mo> </mrow> </mrow>
Wherein, piFor pipeline internal pressure, peFor hydrostatic pressure (hydraulic pressure in marine site), D is pipeline nominal diameter, and t is steel pipe minimal wall Thickness,
According to below equation calculation of temperature stresses:
σlT=α E Δs t (2)
Wherein, α is pipe linear expansion coefficient, and E is steel modulus of elasticity, and Δ t is maximum or minimum running temperature with installing temperature Between temperature difference,
The stress of internal pressure effect generation is calculated according to below equation:
<mrow> <msub> <mi>&amp;sigma;</mi> <mi>P</mi> </msub> <mo>=</mo> <mo>-</mo> <msub> <mi>&amp;upsi;&amp;sigma;</mi> <mi>h</mi> </msub> <mo>+</mo> <mfrac> <mrow> <msub> <mi>p</mi> <mi>i</mi> </msub> <msub> <mi>d</mi> <mi>i</mi> </msub> </mrow> <mrow> <mn>4</mn> <mi>t</mi> </mrow> </mfrac> <mo>-</mo> <mo>-</mo> <mo>-</mo> <mrow> <mo>(</mo> <mn>3</mn> <mo>-</mo> <mn>1</mn> <mo>)</mo> </mrow> </mrow>
Wherein, υ is Poisson's ratio, diFor pipe diameter,
According to below equation, route bending stress is calculated:
σlR=DE/2R (3-2)
Wherein, D is outer diameter tube, and E is steel modulus of elasticity, and R is route bending radius,
According to below equation, axial stress is obtained:
σllTPlR,
Next, according to below equation, calculating equivalent stress:
<mrow> <msub> <mi>&amp;sigma;</mi> <mi>e</mi> </msub> <mo>=</mo> <msqrt> <mrow> <msubsup> <mi>&amp;sigma;</mi> <mi>h</mi> <mn>2</mn> </msubsup> <mo>+</mo> <msubsup> <mi>&amp;sigma;</mi> <mi>l</mi> <mn>2</mn> </msubsup> <mo>-</mo> <msub> <mi>&amp;sigma;</mi> <mi>h</mi> </msub> <msub> <mi>&amp;sigma;</mi> <mi>l</mi> </msub> <mo>+</mo> <mn>3</mn> <msubsup> <mi>&amp;tau;</mi> <mrow> <mi>x</mi> <mi>y</mi> </mrow> <mn>2</mn> </msubsup> </mrow> </msqrt> <mo>-</mo> <mo>-</mo> <mo>-</mo> <mrow> <mo>(</mo> <mn>4</mn> <mo>)</mo> </mrow> </mrow>
Wherein, τxyFor shear stress,
According to below equation, the prestressing force level threshold value is obtained:
ηepσFe (5)
Wherein, ηepFor coefficient of utilization, σFFor yield strength.
5. pipe laying construction method after the pre- ditching of long range submerged pipeline according to claim 3, wherein, dug by grab type Mud ship carries out the step 1, and the grab bucket dredger includes grab claw and grab bucket, wherein, grab claw be equipped with transmission system and Control system, transmission system includes the interior diesel engine and transmission device set, lifting and opening and closing for driving grab bucket;Control system Including elevator scoop roller, opening and closing bucket roller and luffing roller, roller is equipped with clutch and brake, and the luffing roller passes through steel Cable is connected with derrick, the length for controlling derrick,
When carrying out pre- ditching, risen to grabbing bucket above the water surface of position mud layer to be dug, will by control system opening and closing bucket roller Grab bucket is opened completely, then by grab bucket deadweight, grab bucket is inserted into mud layer certain depth,
Then, the wirerope of lifting connection grab bucket, closure grab bucket, to excavate and capture silt,
Finally, control system elevator scoop roller and bucket roller is opened and closed, the grab bucket for filling silt is lifted out water surface certain altitude, And be rotatably connected grab bucket and control system derrick, by the silt of excavation be discharged into by refute dredger ship side by hopper, Grab bucket is back to above the water surface of position mud layer to be dug, and completes a work cycle.
6. pipe laying construction method after the pre- ditching of long range submerged pipeline according to claim 3, wherein, surveyed by heave the lead Bottom of trench absolute altitude is measured, water stone roller is made by 50 × 455mm of Φ round steel, can penetrate the Mud Layer of pipeline groove.
7. pipe laying construction method after the pre- ditching of long range submerged pipeline according to claim 5, wherein, carrying out pre- ditching When, part more than pipeline top surface is slightly dug using large-scale grab boat, and bottom above 0.5m~1m part is using tool The small-sized grab boat for having depthkeeping function carries out smart digging, and every layer is excavated 2 meters thick mud layer, and every 100 meters or so are a section length, Every 12 meters are a slitting width, and layer of not dredging is disturbed in digging process, and disturbed soil caves in naturally under gravity Into 1:1 side slope, rear local finding slope, eventually forms 1:4 and 1:7 side slope.
CN201510609139.0A 2015-09-23 2015-09-23 Pipe laying construction method after the pre- ditching of long range submerged pipeline Active CN105179808B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510609139.0A CN105179808B (en) 2015-09-23 2015-09-23 Pipe laying construction method after the pre- ditching of long range submerged pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510609139.0A CN105179808B (en) 2015-09-23 2015-09-23 Pipe laying construction method after the pre- ditching of long range submerged pipeline

Publications (2)

Publication Number Publication Date
CN105179808A CN105179808A (en) 2015-12-23
CN105179808B true CN105179808B (en) 2017-08-29

Family

ID=54902097

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510609139.0A Active CN105179808B (en) 2015-09-23 2015-09-23 Pipe laying construction method after the pre- ditching of long range submerged pipeline

Country Status (1)

Country Link
CN (1) CN105179808B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106555387A (en) * 2017-01-18 2017-04-05 深圳海油工程水下技术有限公司 A kind of sea bed preprocess method based on jet
CN107169240B (en) * 2017-06-22 2020-09-11 贵州财经大学 Back-dragging calculation method and device based on stepped hole
CN108193713A (en) * 2017-12-25 2018-06-22 中冶天工集团有限公司 Large-diameter Steel pipeline Immersed tunnel technique under a kind of no precipitation condition

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3605865A1 (en) * 1986-02-24 1987-08-27 Wolfgang Dipl Ing Zeilinger Process for laying pipelines
CN102777686A (en) * 2011-12-29 2012-11-14 中国石油大学(北京) Grading seabed pipeline construction method via ditching twice and stopping bending through preheating
CN103123017A (en) * 2012-11-23 2013-05-29 上海市基础工程有限公司 Shallow sea long-distance submarine pipeline tension-free laying construction technology
CN103912721A (en) * 2014-04-23 2014-07-09 中国化学工程第三建设有限公司 Underwater grooving and pipe sinking river traversing construction method
CN104653863A (en) * 2013-11-22 2015-05-27 天津市海王星海上工程技术股份有限公司 Single-ship marine hose ditching-laying synchronous operation method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7963721B2 (en) * 2004-09-21 2011-06-21 Kellogg Brown & Root Llc Distributed buoyancy subsea pipeline apparatus and method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3605865A1 (en) * 1986-02-24 1987-08-27 Wolfgang Dipl Ing Zeilinger Process for laying pipelines
CN102777686A (en) * 2011-12-29 2012-11-14 中国石油大学(北京) Grading seabed pipeline construction method via ditching twice and stopping bending through preheating
CN103123017A (en) * 2012-11-23 2013-05-29 上海市基础工程有限公司 Shallow sea long-distance submarine pipeline tension-free laying construction technology
CN104653863A (en) * 2013-11-22 2015-05-27 天津市海王星海上工程技术股份有限公司 Single-ship marine hose ditching-laying synchronous operation method
CN103912721A (en) * 2014-04-23 2014-07-09 中国化学工程第三建设有限公司 Underwater grooving and pipe sinking river traversing construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
预挖沟海底管道铺设监测方案;牛怀磊;《科技创新导报》;20120930(第9期);第106页 *

Also Published As

Publication number Publication date
CN105179808A (en) 2015-12-23

Similar Documents

Publication Publication Date Title
CN104196034B (en) A kind of utilize steel sheet pile as the foundation ditch construction method in supporting cofferdam
CN102454167B (en) The construction method of especially big &amp; deep open caisson
CN101315139B (en) Immersed pipe construction technique of river crossing pipe
CN105804758A (en) Shallow-earthing, large-section and small-distance construction method for rectangular pipe jacking overpass subway tunnel
CN105179808B (en) Pipe laying construction method after the pre- ditching of long range submerged pipeline
CN1256531C (en) Construction method for river crossing pipeline
CN106245652B (en) A kind of construction method of deep foundation pit earthwork digging near a river
CN104631438A (en) Method for constructing long auger bored cast-with-pressure concrete uplift pile
CN104776268B (en) Mechanical construction method for mounting large-caliber reinforced concrete drainage pipe
CN102261519B (en) Method for assisting sliding, floating and down-ditching of pipeline by air bags
CN103591377B (en) Directly-buried thermal insulation pipes is by the method for construction of marsh district
CN210263062U (en) Anti construction structures that floats of shallow earthing subway tunnel foundation ditch earthwork excavation in pit bottom
CN205101675U (en) Long distance submarine pipe line is pipe laying construction system after ditching in advance
CN202969343U (en) Diffusion device in discharging thick seawater into sea
CN1242194C (en) Down-ditch construction method for laying heavy caliber pipeline
CN113216142A (en) Grouting treatment method and system for underwater karst cave in karst development area
CN115823351B (en) Installation method and installation parameter design method for submarine pipeline at shoal section
CN110565589A (en) Water conservancy project diaphragm wall and construction method thereof
CN105672251A (en) Construction method of underground diaphragm wall trench section for bestriding conventional sewage pipe
CN215165969U (en) Major diameter sea area pipeline notching device
CN112253848B (en) Sand geology water network swamp area pipeline construction method
CN210216519U (en) Submarine pipeline landing section interval type soil body liquefaction resistance improving device
CN105952969A (en) Deep sea water taking pipe protecting mode and laying construction process
CN112900440A (en) Grouting system for enhancing bearing capacity of offshore wind power pile foundation and construction method
CN114526374B (en) Push pipe in submarine shallow coverage stratum, design method and installation method of push pipe

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant