CN105156115A - 一种s形地下通道小半径曲线段的施工方法 - Google Patents
一种s形地下通道小半径曲线段的施工方法 Download PDFInfo
- Publication number
- CN105156115A CN105156115A CN201510515242.9A CN201510515242A CN105156115A CN 105156115 A CN105156115 A CN 105156115A CN 201510515242 A CN201510515242 A CN 201510515242A CN 105156115 A CN105156115 A CN 105156115A
- Authority
- CN
- China
- Prior art keywords
- steelframe
- passage
- passages
- small
- curved sections
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
一种S形地下通道小半径曲线段的施工方法,先开挖对应于通道小半径曲线段的小导洞A,随挖随作初期支护,初期支护的内外壁分别喷涂混凝土;在通道挖至钢架纵距≥0.5m处时,在曲线段上设置边墙径向花管,花管直径为32-42mm,间距为0.5-0.8m,花管长度为3-5m;花管中注入由水泥和水玻璃制成的双液浆;注浆初压为0.5-1MPa,终压为2-2.5MPa,注浆体加固直径≥0.3m。架设工字钢架。当浆体强度≥10MPa时,采用相同办法挖第二小导洞B、第三小导洞C和第四小导洞D,直至S形通道小半径曲线段挖掘完成为止。本发明能提高了建筑物地下通道的安全性能和使用寿命。
Description
技术领域
本发明属于建筑技术领域,具体是涉及一种连接已有建筑物S形地下通道小半径曲线段的施工方法。
背景技术
连接既有建筑物地下通道工程由于受路面交通、市政管网等现状条件限制多采用浅埋暗挖法施工。有些地下通道平面线形较为复杂,由几组小半径曲线段组成,见图1。在浅埋暗挖施工时,初支内钢架纵向间距多为0.5m~0.75m,但曲线段钢架展线放样时,控制曲线内侧控制钢架施工最小间距后,致使曲线段外侧钢架间间距过大,且此段落为应力集中区域,曲线段纵向超前支护无法施工,按常规方法开挖处理后,常产生钢架间土体失稳问题,易造成较大的生命和财产损失。
发明内容
本发明的目的,是为解决上述技术问题,而提供一种S形地下通道小半径曲线段的施工方法,从而提高了建筑物地下通道的安全性能和使用寿命。
采用的技术方案是:
一种S形地下通道小半径曲线段的施工方法,其特征在于包括下述步骤:
1、施工S形地下通道中小半径曲线段,采用浅埋暗挖施工,配合CRD(即中隔壁法)开挖方法;
第一步先开挖对应于通道小半径曲线段的小导洞A,随挖随作初期支护,(包括中隔墙和临时仰拱)并及时封闭成环,初期支护的内外壁分别喷涂厚度为40-80mm的混凝土。
2、为对小半径曲线段外土层的土体加固,在土体内形成小型桩体土拱效应,在通道挖至钢架纵距≥0.5m处时,在曲线段上设置边墙径向花管,花管直径为32-42mm,间距为0.5-0.8m,花管长度为3-5m。花管布设好后,在每一根花管中注入由水泥和水玻璃制成的双液浆,双液浆浓度现场施工时,依据实际需要配制。注浆初压为0.5-1MPa,终压为2-2.5MPa,注浆体加固直径≥0.3m。
3、架设工字钢钢架:架设工字钢钢架时,保证通道中线处钢架纵向间距为0.5~0.8m,由于曲线展现的原因,使曲线内侧钢架间距小于0.5m,可采用直径25~28mm钢筋对钢架进行纵向连接,钢筋环向间距为0.5~0.8m;曲线外侧钢架纵向间距大于0.5m,为保证钢架间土体稳定,采用角钢对钢架进行纵向连接,角钢端部与钢架翼缘焊接牢固,角钢环向间距为0.5~0.8m,纵向交错布设。
4、当浆体强度≥10MPa时,采用相同办法挖第二小导洞B、第三小导洞C和第四小导洞D,直至S形通道小半径曲线段挖掘完成为止。
本发明成功解决了小半径曲线段造成侧墙土失稳问题,增加了通道的安全性,提高了使用寿命,同时也减少了由于土层失稳引起的地面移动变形对环境造成的影响。
附图说明
图1是S形地下通道结构示意图。
图2是小半径曲线小导洞A结构示意图。
图3是架设工字钢钢架示意图。
图4是小半径曲线段小导洞挖掘顺序示意图。
具体实施方式
实施例一
一种S形地下通道小半径曲线段的施工方法,S形地下通道中间为直线段,两端为小半径曲线段,小半径曲线段的曲面夹角为40o57′29″,R=9300。本发明的技术特征是小半径曲线段初支钢架间土体稳定施工方法,包括下述步骤:
1、首先开挖小号洞A,随挖随作初期支护1,包括中隔墙和临时仰拱,并及时封闭成环,初喷C25砼2,厚40mm。当通道挖至钢架纵距≥0.5m处,开始在曲线段的曲面上设置边墙径向花管3,花管3直径42mm,间距0.8m,花管长5m,花管3布设好后在每一根花管内注入水泥水玻璃双浆液,双浆液配比为1:0.5。注浆初压为1MPa,终压2.5MPa,注浆体加固直径≥0.3m。
2、架设工字钢钢架:架设工字钢钢架时,保证通道中线处钢架纵向间距为0.8m,由于曲线展现的原因,使曲线内侧钢架间距小于0.5m,采用直径28mm钢筋对钢架进行纵向连接,钢筋环向间距为0.8m;曲线外侧钢架纵向间距大于0.5m,为保证钢架间土体稳定,采用角钢对钢架进行纵向连接,角钢端部与钢架翼缘焊接牢固,角钢环向间距为0.8m,纵向交错布设。
3、当浆体强度≥10MPa时,采用相同办法挖第二小导洞B、第三小导洞C和第四小导洞D,直至S形通道小半径曲线段挖掘完成为止。
实施例二
一种S形地下通道小半径曲线段的施工方法,其施工步骤与实施例一基本相同,其不同之处在于:所述初喷C25砼厚度为80mm,花管直径为32mm,间距0.5m,花管长为4m,花管注入水泥水玻璃双浆液初压为0.5MPa,终压为2MPa。采用直径为25mm钢筋,对钢架进行纵向连接,钢筋环向间距为0.5m,角钢环向间距为0.5m。
Claims (1)
1.一种S形地下通道小半径曲线段的施工方法,其特征在于包括下述步骤:
(1)、施工S形地下通道中的小半径曲线段,采用浅埋暗挖施工,配合CRD开挖方法;
第一步先开挖对应于通道小半径曲线段的小导洞A,随挖随作初期支护,包括中隔墙和临时仰拱,并及时封闭成环,初期支护的内外壁分别喷涂厚度为40-80mm的混凝土;
(2)、在通道挖至钢架纵距≥0.5m处时,在曲线段上设置边墙径向花管,花管直径为32-42mm,间距为0.5-0.8m,花管长度为3-5m;花管布设好后,在每一根花管中注入由水泥和水玻璃制成的双液浆,双液浆浓度现场施工时,依据实际需要配制;注浆初压为0.5-1MPa,终压为2-2.5MPa注浆体加固直径≥0.3m;
(3)、架设工字钢钢架:架设工字钢钢架时,保证通道中线处钢架纵向间距为0.5~0.8m,曲线内侧钢架间距小于0.5m,采用直径25~28mm钢筋对钢架进行纵向连接,钢筋环向间距为0.5~0.8m;曲线外侧钢架纵向间距大于0.5m,采用角钢对钢架进行纵向连接,角钢端部与钢架翼缘焊接牢固,角钢环向间距为0.5~0.8m,纵向交错布设;
(4)、当浆体强度≥10MPa时,采用相同办法挖第二小导洞B、第三小导洞C和第四小导洞D,直至S形通道小半径曲线段挖掘完成为止。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510515242.9A CN105156115B (zh) | 2015-08-21 | 2015-08-21 | 一种s形地下通道小半径曲线段的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510515242.9A CN105156115B (zh) | 2015-08-21 | 2015-08-21 | 一种s形地下通道小半径曲线段的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105156115A true CN105156115A (zh) | 2015-12-16 |
CN105156115B CN105156115B (zh) | 2017-12-05 |
Family
ID=54797117
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510515242.9A Active CN105156115B (zh) | 2015-08-21 | 2015-08-21 | 一种s形地下通道小半径曲线段的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105156115B (zh) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004183441A (ja) * | 2002-12-06 | 2004-07-02 | Taisei Corp | 地下道の施工方法 |
CN102155233A (zh) * | 2011-04-21 | 2011-08-17 | 上海市城市建设设计研究院 | 一种隧道开挖施工方法 |
CN103334761A (zh) * | 2013-06-28 | 2013-10-02 | 中国一冶集团有限公司 | 浅埋暗挖地下通道变截面交叉中隔墙施工方法 |
CN103643973A (zh) * | 2013-12-03 | 2014-03-19 | 中铁十三局集团有限公司 | 一种crd工法隧道防水施工方法 |
CN104295301A (zh) * | 2014-08-14 | 2015-01-21 | 山东科技大学 | 一种浅埋暗挖碎裂岩体地铁隧道交叉点的施工方法 |
-
2015
- 2015-08-21 CN CN201510515242.9A patent/CN105156115B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004183441A (ja) * | 2002-12-06 | 2004-07-02 | Taisei Corp | 地下道の施工方法 |
CN102155233A (zh) * | 2011-04-21 | 2011-08-17 | 上海市城市建设设计研究院 | 一种隧道开挖施工方法 |
CN103334761A (zh) * | 2013-06-28 | 2013-10-02 | 中国一冶集团有限公司 | 浅埋暗挖地下通道变截面交叉中隔墙施工方法 |
CN103643973A (zh) * | 2013-12-03 | 2014-03-19 | 中铁十三局集团有限公司 | 一种crd工法隧道防水施工方法 |
CN104295301A (zh) * | 2014-08-14 | 2015-01-21 | 山东科技大学 | 一种浅埋暗挖碎裂岩体地铁隧道交叉点的施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN105156115B (zh) | 2017-12-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103306683B (zh) | 一种开挖深埋隧道时洞内综合降水的施工方法 | |
CN100529329C (zh) | 一种管节盾构机施工法 | |
CN103899323B (zh) | 一种盾构穿越铁路站场的施工方法 | |
CN205154174U (zh) | 软弱围岩隧道管棚超前支护施工结构 | |
CN105298517A (zh) | 软弱围岩隧道超前加强支护施工方法 | |
CN104533446A (zh) | 一种大断面软弱围岩隧道双层初期支护预防地质灾害发生的施工方法及其结构 | |
CN205117357U (zh) | 基于自钻式螺旋管棚的软弱围岩隧道超前支护结构 | |
CN103306687A (zh) | 软岩隧道长悬臂水平旋喷变形控制施工方法 | |
CN103835729A (zh) | 深部长距离巷道围岩地面预注浆加固工艺 | |
CN102606168B (zh) | 防止浅埋暗挖隧道开挖时沉降变形的施工方法 | |
CN108252719B (zh) | 一种城市浅埋隧道下穿软流塑状红黏土层施工方法 | |
CN205117356U (zh) | 自钻式螺旋管棚 | |
CN101701646B (zh) | 地下管道的泥水平衡式拉管施工方法 | |
CN109630151A (zh) | 矩形顶管掘进施工方法 | |
CN104389618A (zh) | 一种连拱隧道洞身无室大管棚支护施工方法 | |
CN104612696A (zh) | 大断面暗挖地铁车站在粉细砂层中穿越高架桥柱洞法施工方法 | |
CN103321235A (zh) | 一种复合土钉墙边坡支护方法 | |
CN103089277A (zh) | 砂层巷道的空间加固施工工艺 | |
CN105298514A (zh) | 一种现浇连续混凝土支架及其安装方法 | |
CN109944600A (zh) | 盾构接收端加固施工方法 | |
CN206888992U (zh) | 一种水底矿山盾构隧道组合对接结构形式 | |
CN108915702B (zh) | 一种圆形小断面隧道内盾构接收方法 | |
CN108180018A (zh) | 一种浅埋湿陷性黄土隧道核心土与玻纤锚杆加固施工方法 | |
CN105909262A (zh) | 一种暗挖隧道掘进方法 | |
CN104963693A (zh) | 矩形平行顶管联络通道施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20200520 Address after: 110000 room 332, No. 5-8, Xincai street, Hunnan New District, Shenyang City, Liaoning Province Patentee after: ZHONGJIAN DONGSHE ROCK AND SOIL ENGINEERING Co.,Ltd. Address before: 110003 65 glorious Street, Heping District, Liaoning, Shenyang Patentee before: CHINA NORTHEAST ARCHITECTURAL DESIGN AND RESEARCH INSTITUTE Co.,Ltd. |
|