CN105148718B - Double-turbulence ultraclean desulfurization and dust removal compound tower - Google Patents

Double-turbulence ultraclean desulfurization and dust removal compound tower Download PDF

Info

Publication number
CN105148718B
CN105148718B CN201510658837.XA CN201510658837A CN105148718B CN 105148718 B CN105148718 B CN 105148718B CN 201510658837 A CN201510658837 A CN 201510658837A CN 105148718 B CN105148718 B CN 105148718B
Authority
CN
China
Prior art keywords
tower
pipeline
king
desulfurization
flue
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510658837.XA
Other languages
Chinese (zh)
Other versions
CN105148718A (en
Inventor
胡建华
付颖
武俊鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING WEIKEN ZHONGHE ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd
Original Assignee
BEIJING WEIKEN ZHONGHE ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING WEIKEN ZHONGHE ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd filed Critical BEIJING WEIKEN ZHONGHE ENVIRONMENTAL PROTECTION TECHNOLOGY Co Ltd
Priority to CN201510658837.XA priority Critical patent/CN105148718B/en
Publication of CN105148718A publication Critical patent/CN105148718A/en
Application granted granted Critical
Publication of CN105148718B publication Critical patent/CN105148718B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention relates to a double-turbulence ultraclean desulfurization and dust removal compound tower and belongs to the technical field of gas purification. The compound tower comprises an auxiliary spray tower and a main spray tower, wherein a flue gas inlet, a flue gas outlet and a slurry discharge port are arranged on the lower side wall and at the top of the auxiliary tower and at the bottom of the conical tower respectively, a jet device is mounted in a flue of the flue gas inlet, a turbo-charging composite desulfurization and dust-removal device consisting of a plurality of cyclones are arranged in the tower body above the flue of the flue gas inlet, multiple layers of spray pipes are arranged above the turbo-charging composite desulfurization and dust-removal device, and a plurality of nozzles are mounted on the spray pipes; a flue gas inlet, a flue gas outlet and a slurry discharge port are arranged on the tower body of the main tower, and a slurry discharge pump, a liquid storage area with a disturbance device, a jet device, a plurality of turbulence cyclone devices, multiple rows of spray devices and multiple layers of demisters are arranged on the main tower from bottom to top. The composite tower can improve the desulfurization and dust removal effects to the largest extent under the condition that the minimum resistance, the shortest time, the smallest space and the lowest liquid-gas ratio are realized.

Description

The ultra-clean desulfurization and dedusting combination tower of a kind of pair of turbulent flow
Technical field
The invention belongs to gas purification technique field, more particularly to large, medium and small power plant, chemical plant, the boiler of smelting industry Flue gas desulfurization and dedusting device structure is designed.
Background technology
The main equipment of wet desulfurization system is absorption tower, employs various ways in various technological processes both at home and abroad Tower, from the water-bath tower of early stage to spray column, grid tower and recently multiplex spray tower, its purpose is provided to improve in tower SO2With the mass transfer absorption process of liquid.Wherein eddy flow tower is higher than the technology content of void tower desulfurization and dedusting.Cyclone desulfuration gas wash tower Basic operation principle is after the flue gas that boiler is discharged is entered from cyclone lower section, to rise with cyclone rotation, while absorbing liquid Flow downward after introducing from cyclone top, the mutual high speed rotary-cut in absorption tower of flue gas and absorbing liquid is blended, the continuous quilt of liquid Gas breaking, and more cut more carefully, increase liquid specific surface area, the contact surface of gas and liquid is expanded, specific surface area is high In even tens times of general more than ten times of void tower wet method sulphur removing and dust removing technology, gas-liquid-solid three-phase blending enhances the biography between them Matter process, when flue gas passes through filter tube, makes absorbing liquid in emulsified state, and the absorbing liquid emulsifying for suspending is formed above cyclone Floor area, SO in flue gas2Desulfurization and dedusting purpose is reached by absorption neutralization in this liquid.When this emulsion layer, to be stacked into constant weight backward Under drain, and the absorbing liquid flow down from top replaces it, forms new emulsion layer, and such transition from the old to the new emulsion layer is constantly more Higher desulfuration efficiency is kept in new, while and more tiny dust can be removed than general boiler cyclone dust extractor, desulfurization is removed Two kinds of functions of dirt combine together.But it is technically also difficult to reach ultra-clean dust emission standard.
The content of the invention
The purpose of the present invention is to overcome the weak point of existing tower technology, the ultra-clean desulfurization and dedusting of a kind of pair of turbulent flow of proposition Tower, the tower may be implemented in minimum drag, and the most short time, minimum space under minimum liquid-gas ratio, reaches gas-liquid and fully connects Touch, flue gas is efficient under least energy consumption to improve desulfurization and dedusting effect to greatest extent in the gas-liquid-solid emulsifying mass transfer of high speed, Desulfurization dust-removing efficiency can reach ultra-clean standard limit of smog release or even can reach zero-emission flue gas.
The ultra-clean desulfurized dust collection column of a kind of pair of turbulent flow proposed by the present invention, it is characterised in that the combination tower includes:Spray secondary tower With spray king-tower, in the secondary tower body lower sides, top and tapered tower bottom gas approach, exhanst gas outlet and row are respectively arranged with Slurry mouth, thick liquid discharge mouth is connected to the lowermost side wall of king-tower fluid reservoir by pipeline;Desulfurization breast is installed in the flue of gas approach The injection apparatus for playing Venturi-tube action that liquid is blended with flue gas, injection apparatus are connected by pipeline with Pulp pump, Pulp pump Entrance is connected on the bottom of king-tower fluid reservoir;The formula of multiple cyclone compositions is disposed with the tower body of the top of gas approach flue Turbocharging is combined desulfation dust-extraction device, in the top arranging multiplayer shower of the compound desulfation dust-extraction device of turbocharging, spray Multiple shower nozzles are installed on pipe;Every layer of shower is connected by pipeline with a circulating pump, and the entrance of circulating pump is by with valve Pipeline be connected to the lower sides of king-tower slurry can, the exhanst gas outlet of secondary tower is connected to entering for king-tower flue gases duct by flue Mouthful;In king-tower tower body lower sides, top and bottom are respectively arranged with gas approach, exhanst gas outlet and thick liquid discharge mouth, king-tower flue gas Import is arranged on the top of the pump entry pipeline of secondary tower;It is provided with from bottom to up and bottom of towe thick liquid discharge mouth phase in the king-tower Slurry pump even;The liquid storage area that king-tower inner bottom part is made up of reaction tank and tube seat is arranged on, is provided with liquid storage area by aeration tube, The disturbance device that the roots blower being connected with aeration tube is constituted, the disturbance pump that disturbance device is connected by the pipeline with valve;Tower Smoke inlet flue arrangement injection apparatus, multiple turbulent flow swirl-flow devices, the turbulent flow cyclone are arranged in the top of tower gas approach Multiple rows of spray equipment is arranged in the top of device, often arranges spray equipment and is connected with a circulating pump by pipeline, every circulating pump Entrance is connected by the pipeline with valve with liquid storage area, and the entrance of every circulating pump is also by the pipeline with valve and carbide slag Pump is connected, and the entrance of carbide pulp pump is connected to carbide slag liquid pool and is connected;King-tower spray equipment top arranging multiplayer demister;Secondary tower Flue entrance arrangement injection apparatus, be connected with the Pulp pump of king-tower by pipeline.
The population structure of each cyclone that the spray secondary tower body is arranged includes:Housing, is fixed on the pipe of the casing center Road, the multiple blades between the housing and pipeline, the upper end of each blade is connected with the housing, and lower end is connected with pipeline Connect.
The population structure of each rapid ball cyclone that the spray king-tower tower body is arranged includes:Housing, in being fixed on the housing The pipeline of the heart, the multiple blades between the housing and pipeline, the upper end of each blade is connected with the housing, lower end with pipe Road is connected;The lower end connection one of the pipeline hides petticoat pipe, and in the housing lower end connection one for hiding petticoat pipe periphery petticoat pipe is hidden;In the pipeline Helix(ribbon type) agitator is installed, the helix(ribbon type) agitator is the strip plate of the helically banding being arranged in the pipeline;In the shell The pipe outlet at body center also sets up an extension tube, and the extension tube upper and lower port is provided with the upper and lower closure plate of porous;In the prolongation Baton round is placed with pipe.
The present invention is important to be characterized in that:
Desulfurization and dedusting double-column in series is proposed, using double pH value desulfurization agent emulsion operations, can be with maximum using double injection apparatus The resistance of the reduction desulphurization system of change can make air-introduced machine increase the motive force of pa more than 600, and obtaining the effect of flue gas cool-down prevents Because the cigarette temperature difference causes flue gas dry and wet to be overlapped on fouling at cyclone inlet, desulfuration efficiency and the safe operation of cyclone are affected.Cigarette Gas starts the uniform cigarette pressure of preliminary desulfurization and dedusting prevents short circuit at indivedual cyclone inlets from improving desulfurization dust-removing efficiency as far as possible, using double The cyclone of different leaves angle multi-form is to reach different purposes of design.Secondary tower uses wide-angle rapids ball cyclone Can under the high-temperature flue gas of big flow with less resistance under keep high desulfurization dust-removing efficiency, be used in series double spray equipments Desulfurization emulsion is set to be fully used.Secondary tower spray equipment injection emulsion from king-tower liquid storage tank bottommost, after desulfurization Emulsion is flowed automatically to the bottommost of king-tower by the feed pipe for mortar of secondary tower bottom, is sent to vacuum belt machine by Pulp pump after aeration and is made Gypsum Fibrosum. The purpose of so design is exactly desulfurization emulsion is greatly utilized, the Jing three-levels spray again of king-tower cyclone clean flue gas out The emulsion cleaning of high pH value is drenched, the flue gas of ultra-clean is obtained even up to zero-emission.
Compound fuel gas desulfurization gas wash tower proposed by the present invention designs an energy based on research and development for many years and engineering practice work Enough integrate the advantage of numerous such desulfurizing tower, and while the double turbulent flows of the double ph values that can improve such desulfurizing tower shortcoming are super clean Only it is combined desulfurized dust collection column.By using double spray equipments, double pH value desulfurizing agents, in secondary tower king-tower flue gas in compound desulfurizing tower Install emulsion flue gas mixed injection device in gas approach additional, install the turbulent flow eddy flow of different eddy flow angles, different types in double tower additional Device,.The tower may be implemented in minimum drag, and the most short time, minimum space under minimum liquid-gas ratio, reaches gas-liquid and fully connects Touch, flue gas is efficient under least energy consumption to improve desulfurization and dedusting effect to greatest extent in the gas-liquid-solid emulsifying mass transfer of high speed, Desulfurization dust-removing efficiency can reach ultra-clean standard limit of smog release or even can reach the purpose of zero-emission flue gas.
Description of the drawings
Fig. 1 is the general structure schematic diagram of the present invention.
Fig. 2 is secondary tower cyclone layout drawing.
Fig. 3 is the general structure schematic diagram of a cyclone in secondary tower of the invention.
Fig. 4 is the horizontal schematic diagram of cyclone of Fig. 2.
Fig. 5 is king-tower rapids ball cyclone layout drawing.
Fig. 6 is the general structure schematic diagram of a rapid ball cyclone in king-tower of the invention.
Fig. 7 is the horizontal schematic diagram of rapid ball cyclone of Fig. 5.
Specific embodiment
The ultra-clean compound desulfurized dust collection column Structure Figure of the present invention a kind of pair of turbulent flow of proposition and embodiment describe in detail as follows:
Embodiments of the invention population structure as shown in figure 1, including:Spray secondary tower 1 and spray king-tower 2, in the secondary tower body Lower sides, top and tapered tower bottom are respectively arranged with gas approach 101, exhanst gas outlet 102 and thick liquid discharge mouth 103, thick liquid discharge mouth The 103 lowermost side walls that the fluid reservoir of king-tower 2 is connected to by pipeline;In the flue of gas approach 101 install desulfurization emulsion with The injection apparatus 105 for playing Venturi-tube action of flue gas blending, injection apparatus are connected by pipeline with Pulp pump, and Pulp pump enters Mouth is connected on the bottom (Pulp pump connecting pipe is omitted in figure) of king-tower fluid reservoir.In the tower of the top of the flue of gas approach 101 The compound desulfation dust-extraction device 104 of formula turbocharging of 24 cyclone compositions is disposed with vivo, is removed in the compound desulfurization of turbocharging Three layers of shower 106 are arranged in the top of dirt device 104, and 84 shower nozzles are installed on shower;Every layer of shower passes through pipeline and Individual circulating pump 107 is connected, and the entrance of circulating pump is by being connected to the lower sides of king-tower slurry can, secondary tower with valvular pipeline 1 exhanst gas outlet is connected to the entrance of the flue gases duct of king-tower 2 by flue;In the tower body lower sides of king-tower 2, top and bottom point Gas approach 201, exhanst gas outlet 202 and thick liquid discharge mouth 203 are not provided with, gas approach 201 is arranged on the circulating pump 107 of secondary tower and enters The top of mouth pipeline;It is provided with the slurry pump 2071 being connected with bottom of towe thick liquid discharge mouth from bottom to up in the king-tower;It is arranged on master The liquid storage area 209 that tower inner bottom part is made up of reaction tank and tube seat, is provided with by aeration tube 2091, with aeration tube in liquid storage area 209 The disturbance device that connected roots blower 2092 is constituted, the disturbance pump 2093 that disturbance device is connected by the pipeline with valve;Tower Smoke inlet flue arrangement injection apparatus 205, the top of tower gas approach arranges 32 swirl-flow devices 204 (for rapid ball whirlpool The compound desulfation dust-extraction device of wheel supercharging), the cyclone device pattern is different from the turbulent flow cyclone of the angle of blade and secondary tower, rotation Three row's spray equipments 206 are arranged in the top of stream device, are connected with three circulating pumps 2072 by pipeline, three circulating pumps 2072 Entrance is connected by the pipeline with valve with liquid storage area 209, the entrance of three circulating pumps 2072 also by the pipeline with valve with Carbide pulp pump 2073 is connected, and the entrance of carbide pulp pump 2073 is connected to carbide slag liquid pool and is connected;The top of spray equipment 206 arrangement two Layer demister 208.The flue entrance arrangement injection apparatus of secondary tower, are connected by pipeline with the Pulp pump of king-tower.
The operation principle of this combination tower is:Flue gas from boiler is sent to desulfurization secondary tower Jing after boiler dust remover and air-introduced machine Gas approach, desulfurization emulsion and the flue gas sprayed by injection apparatus in flue stir hybrid cooling, be reduced blower fan resistance Power and separation fluid effect, desulfurization slurry falls into wet flue gas in tower and enters blade rapids ball cyclone, in the pipe of helix(ribbon type) agitator region Ball make irregular turbulence campaign, flue gas and desulfurization slurry revolve at a high speed to rub stirring with the hands and form emulsifying and obtain pole in the top of cyclone High desulfuration efficiency, king-tower is entered by the spray desulfurization fume of the clean flue gas Jing two-layer spray equipments of cyclone by flue Flue entrance, desulfurization slurry fall into secondary tower conical tower bottom by pipeline self to king-tower liquid storage tank bottommost.In the cigarette of king-tower Road entrance installs another injection apparatus, and the lower section of uniform cyclone enters rotation in the U-shaped entrance tower of flue gas under its twitch Stream device, cyclone is that, without rapid ball, blade is low-angle blade, is increased in cyclone because flue gas resistance becomes big flue gas flow rate Top is held the rotation of desulfurization emulsion high-speed stirred and is rubbed with the hands, and the doctor solution of one layer of suspension is formed in desulfurization unit, absorbs two in flue gas Sulfur oxide, gas-to-liquid contact specific surface area is big, and with little circulating fluid volume higher desulfurization dust-removing efficiency is reached.When due to weight When reason flue gas support does not live desulfurization emulsion, the new emulsion of liquid storage tank that old emulsion deadweight flows downwardly into tower is suspended in cyclone again Top continue desulfurization.The flue gas of cyclone outlet is quite clean, then through the washing of three floor height pH value desulfurization emulsions, then Small water droplet in the washing and removal flue gas of two-layer demister clear water is discharged into air by chimney.At this moment reached super clean Net flue gas has even reached the standard of zero-emission.The oxidation and aeration of pulp storage tank Jing air compressors and disturbance pump are uninterrupted in tower Stirring, Jing slurries are pumped into vacuum belt machine and make final gypsum product when the density and pH value of desulfurization emulsion reach design load.
The specific embodiment of each part of this combination tower is respectively described below:
24 cyclones that spray secondary tower body is arranged on gas approach are as shown in Fig. 2 the overall knot of each cyclone Structure as shown in Figure 3,4, including:Housing 1041, is fixed on the pipeline 1042 of the casing center, between the housing and pipeline Multiple blades 1043, the upper end of each blade is connected with the housing, and lower end is connected with pipeline;
The rapid ball cyclones of spray king-tower tower body arranges on gas approach 32, as shown in figure 5, each rapid ball revolve Flow the population structure of device as shown in Figure 6,7, including:Housing 2041, is fixed on the pipeline 2044 of the casing center, installed in the shell Multiple blades 2042 between body and pipeline, the upper end of each blade is connected with the housing, and lower end is connected with pipeline;The pipeline Lower end connection one hide petticoat pipe 2045, hide petticoat pipe 2046 in the housing lower end connection one for hiding petticoat pipe 2045 periphery;Peace in the pipeline Equipped with helix(ribbon type) agitator 2043, the strip plate of helically banding of the helix(ribbon type) agitator 2043 to be arranged in the pipeline. An extension tube 2047 is also set up in the pipe outlet of the casing center, the extension tube upper and lower port is provided with the upper and lower stifled of porous Plate 20481,20482;Baton round 2049 is placed with the extension tube.
The diameter of the housing of each cyclone of turbine type super-charging accelerating gas fume desulfuration dedusting and rapid ball cyclone is general For 400-800 millimeters【Such as 600 millimeters】, the pipe diameter at center is 100-200 millimeters【Such as 150 millimeters】Each blade table Face can be in 150-180【Such as 165】Radian, it is 28 ° -45 ° that its short axle adds angle with horizontal plane【Such as 35 °】;Its major axis is in level Face angle is 20 ° -50 °【Such as 45 °】.The width of blade reaches 100-400 millimeters【Such as 200 millimeters】, two adjacent blades mutually overlap Folded 0-20 millimeters【Such as 10 millimeters】.There are 1.6 meters of long filter tubes above each cyclone and rapid ball cyclone 【1044】, as shown in fig. 6, the two ends of overanxious pipe are closed by card forms a casing, whole casing lifting is seated in the three of tower On root crossbeam, the lower section of casing grows card 200mm or so by the filter tube of figure arrangement, the termination soldering stainless steel flange of pipe, Cyclone is bolted on flange fixed.The cyclone of king-tower and secondary tower is made using 316L rustless steels.Except 316L not Outer other all the exposed carbon-steel parts of rust head tower internals will serve as a contrast glass flake carries out anti-corrosion.
The diameter of major and minor tower is determined by process exhaust gas volumn and flue gas flow rate in designed tower.By taking king-tower as an example in tower Maximum processes exhaust gas volumn and is designed as 580,000 M3, and flue gas flow rate presses 3.3m towers diameter design for distance between 7.8m. cyclones in tower 【200mm】Not affect installation.32 cyclones of king-tower conservative design.The cyclone of king-tower and the cyclone of secondary tower It is otherwise varied, blade that secondary tower is adopted and horizontal plane angle for 50 ° of angles turbine type cyclone 24, the blade that king-tower is adopted with Horizontal plane angle is the rapid ball cyclone 32 of 45° angle.Tower diameter is according to set by handled exhaust gas volumn and Ta Nei flue gases Meter flow velocity determines, carries out the cyclone size of space according to tower diameter and the individual of determination cyclone is evenly arranged in rational scope Number.
Three layers of spray are arranged in the top of cyclone, and each layer trickles through pipeline and is connected with the circulating pump of king-tower.Spraying layer Top arrangement two-layer demister.Tower liquid storage tank base fabric is put disturbance device and is connected with disturbance pump by pipeline, top arrangement drum oxygen dress Put and be connected with roots blower by pipeline.Bottom of towe arrangement blow-off pipe is connected with Pulp pump.Desulfurization slurry after oxidation is by Pulp pump Take out toward vacuum belt machine and make Gypsum Fibrosum.Ultra-clean flue gas is discharged into greatly by chimney after tower exhaust pass connection chimney desulfurization and dedusting Gas.
Secondary tower is entirely from security and stability using the turbine type rustless steel cyclone of 50 ° of angle blades and ensures desulfuration efficiency Consider.The fast temperature of the big flow velocity of flue gas flow of secondary tower flue entrance is high, and flue gas resistance when through turbocyclone is big.In phase The big blade of angle is adopted in the case of with quantity cyclone and the stream that can reduce system is engaged using flue gas injection device Logical resistance.And the reduction of desulfuration efficiency with reduce circulating resistance and asynchronous, that is to say, that the reduction of desulfuration efficiency is affected compared with It is few.Boiler is abnormal in short-term high temperature turbulent cyclone occurs also will not damage, if will be damaged using rapid ball cyclone baton round Desulfurization work is set to be unable to safe and stable operation.And be that saturated air will not be caused normally to baton round because of high temperature into the flue gas of king-tower Damage.The desulfurization dust-removing efficiency of turbulent flow cyclone is very high, and the desulfurization dust-removing efficiency of secondary tower is void tower desulfurization dust-removing efficiency and rapids The sum of stream cyclone desulfurization dust-removing efficiency, so the flue gas from secondary tower out is very clean flue gas, if flue gas flow over loading Or the ature of coal sulfur content that changes is too high, can also improve the PH of desulfurization slurry improve desulfuration efficiency to ensure by emulsion pumps The fume emission parameter of whole desulphurization system.Secondary tower clean flue gas out take the shape of the letter U into king-tower under the drive of injection apparatus The route and time for extending flue gas is evenly distributed on the lower section of rapid ball cyclone and enters cyclone.The rapid ball of 45° angle swirl vane Cyclone desulfurization dust-removing efficiency is more taller than turbulent flow cyclone desulfurization dust-removing efficiency, and the sky of high pH value desulfurization slurry is sprayed at three layers Under the efficient desulfurization and dedusting of the lower and rapid ball cyclone of tower spray, then Jing two-layer demisters drying and clean water under king-tower The flue gas of discharge is exactly the flue gas of ultra-clean.Boiler induced-draft fan at least can increase in the presence of two ejectors of secondary tower and king-tower Plus the motive force of whole desulphurization system 600pa.Double turbulent flow desulfurization and dedusting combination towers can reach according to ammonia process alkaline process magnesium oxide method To zero-emission, environmental protection engineering is really achieved.The ultra-clean desulfurization and dedusting combination tower of double turbulent flows will have from now on very big performance prospect.
Double ultra-clean desulfurization and dedusting combination tower embodiments of turbulent flow of the invention are applied to 240 tons of coal-burning boilers or recirculating fluidized bed pot Stove desulfurization and dedusting is newly-built or transformation project.Desulfurizing agent can use ammonia, alkali, magnesium oxide, Calx, limestone, carbide slag etc..This enforcement Example adopts carbide slag.The present embodiment equipment design parameter is as follows:
Spray secondary tower:Diameter 6.6m 660000m3/ h materials:Carbon steel glass inner-lining scale
Secondary tower circulating pump A flows:441m3/ h lifts:45m powers of motor:110kw
Secondary tower circulating pump B flows:441m3/ h lifts:47m powers of motor:110kw
Tower circulating pump C flows:441m3/ h lifts:49m powers of motor:110kw
Turbulent flow cyclone:24
Spray king-tower:Diameter 7.8m materials:Carbon steel glass inner-lining scale
King-tower circulating pump A flows:1322m3/ h, lift:25m powers of motor:185kw
King-tower circulating pump B flows:1322m3/ h, lift:27m powers of motor:185kw
King-tower circulating pump C flows:1322m3/ h, lift:29m powers of motor:200kw
Turbulent flow cyclone:32
Disturbance pump discharge:250m3/ h lifts:30m powers of motor:55kw the using and the reserved
Carbide slag emulsion pump discharge:30m3/ h, lift:30m powers of motor:7.5kw the using and the reserved
Carbide slag slurry pump discharge:85m3/ h lifts:40m powers of motor:18.5kw dual-purposes one are standby
Oxidation fan flow:148m3/ min, blast:68.6kpa powers of motor:220kw the using and the reserved
Secondary tower burner design:Spiral is heart cone material:Carborundum 84
King-tower burner design:The solid material of spiral:Carborundum 144
The two-layer of king-tower demister 7800 × 200
Using a flow 100m3The fresh water (FW) water supplying pump of/h lift 40m;
Above each equipment is domestic conventional products.
Flue gas SO after the present embodiment purification2Content is less than 35mg/m3Dust content is less than 10mg/m3Desulfuration efficiency is more than 99.5%, efficiency of dust collection is more than 95%, and using ammonia process, alkaline process, magnesium oxide method flue gas can reach zero-emission.Single stove year desulfurization 27581/y。

Claims (6)

1. the ultra-clean desulfurization and dedusting combination tower of a kind of pair of turbulent flow, it is characterised in that the combination tower includes:Spray secondary tower and spray master Tower, in the secondary tower body lower sides, top and tapered tower bottom gas approach, exhanst gas outlet and thick liquid discharge mouth are respectively arranged with, row Slurry mouth is connected to the lowermost side wall of king-tower fluid reservoir by pipeline;In the flue of secondary tower gas approach install desulfurization emulsion with The injection apparatus for playing Venturi-tube action of flue gas blending, injection apparatus are connected by pipeline with Pulp pump, the entrance of Pulp pump It is connected on the bottom of king-tower fluid reservoir;The whirlpool of multiple cyclone compositions is disposed with the tower body of the top of secondary tower gas approach flue The compound desulfation dust-extraction device of wheel supercharging, in the top arranging multiplayer shower of the compound desulfation dust-extraction device of turbocharging, shower It is upper that multiple shower nozzles are installed;Every layer of shower is connected by pipeline with a circulating pump, and the entrance of circulating pump is by with valvular Pipeline is connected to the lower sides of king-tower fluid reservoir, and the exhanst gas outlet of secondary tower is connected to entering for king-tower flue gases duct by flue Mouthful;In king-tower tower body lower sides, top and bottom are respectively arranged with gas approach, exhanst gas outlet and thick liquid discharge mouth, king-tower flue gas Import is arranged on the top of the pump entry pipeline of secondary tower;The slurry pump being connected with bottom of towe thick liquid discharge mouth is provided with the king-tower; The liquid storage area that king-tower inner bottom part is made up of reaction tank and tube seat is arranged on, aeration tube is provided with liquid storage area, be connected with aeration tube Roots blower constitute disturbance device, disturbance device by the pipeline with valve be connected disturbance pump;The gas approach of king-tower Flue arranges injection apparatus, and multiple turbulent flow swirl-flow devices, the top of the turbulent flow swirl-flow devices are arranged in the top of king-tower gas approach Multiple rows of spray equipment is arranged, spray equipment is often arranged and is connected with a circulating pump by pipeline, the entrance of every circulating pump passes through Pipeline with valve is connected with liquid storage area, and the entrance of every circulating pump is also connected by the pipeline with valve with carbide pulp pump, electricity The entrance of rock ballast pump is connected to carbide slag liquid pool;King-tower spray equipment top arranging multiplayer demister;The flue entrance cloth of secondary tower Injection apparatus are put, is connected with the Pulp pump of king-tower by pipeline.
2. combination tower as claimed in claim 1, it is characterised in that the population structure of each cyclone that the spray secondary tower body is arranged Including:Housing, is fixed on the pipeline of the casing center, the multiple blades between the housing and pipeline, each blade Upper end is connected with the housing, and lower end is connected with pipeline.
3. combination tower as claimed in claim 1, it is characterised in that each turbulent flow swirl-flow devices that the spray king-tower tower body is arranged Population structure includes:Housing, is fixed on the pipeline of the casing center, the multiple blades between the housing and pipeline, often The upper end of individual blade is connected with the housing, and lower end is connected with pipeline;The lower end connection one of the pipeline hides petticoat pipe, is hiding outside petticoat pipe The housing lower end in week connects another screening petticoat pipe;Helix(ribbon type) agitator is installed in the pipeline, the helix(ribbon type) agitator is to be arranged on The strip plate of the helically banding in the pipeline;An extension tube is also set up in the pipe outlet of the casing center, the extension tube Upper and lower port is provided with the upper and lower closure plate of porous;Baton round is placed with the extension tube.
4. the combination tower as described in Claims 2 or 3, it is characterised in that the diameter of the housing of each cyclone and turbulent flow swirl-flow devices For 400-800 millimeters, the pipe diameter at center is 100-200 millimeters, and each blade surface is in 150-180 radians, blade and water Plane included angle is 20 ° -50 °;The width of blade reaches 100-400 millimeters, and two adjacent blades overlap 0-20 millimeters;Each cyclone And have a filter tube above turbulent flow swirl-flow devices.
5. combination tower as claimed in claim 4, it is characterised in that the swirl vane that the secondary tower is adopted and horizontal plane angle for 50 °, the swirl vane that king-tower is adopted is with horizontal plane angle for 45 °.
6. combination tower as claimed in claim 1, it is characterised in that the main and auxiliary tower uses the double pH value desulfurization emulsion fortune of Two-way Cycle OK, in secondary tower the density of desulfurization emulsion 1.1,5.5,1.05, pH value is 6.5 for the desulfurization emulsion density in king-tower for pH value.
CN201510658837.XA 2015-10-12 2015-10-12 Double-turbulence ultraclean desulfurization and dust removal compound tower Active CN105148718B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510658837.XA CN105148718B (en) 2015-10-12 2015-10-12 Double-turbulence ultraclean desulfurization and dust removal compound tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510658837.XA CN105148718B (en) 2015-10-12 2015-10-12 Double-turbulence ultraclean desulfurization and dust removal compound tower

Publications (2)

Publication Number Publication Date
CN105148718A CN105148718A (en) 2015-12-16
CN105148718B true CN105148718B (en) 2017-04-19

Family

ID=54789944

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510658837.XA Active CN105148718B (en) 2015-10-12 2015-10-12 Double-turbulence ultraclean desulfurization and dust removal compound tower

Country Status (1)

Country Link
CN (1) CN105148718B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105521680A (en) * 2016-02-02 2016-04-27 中南大学 Desulphurization and dust removal integrated wet type flue gas purification device and method
CN107158922A (en) * 2017-07-12 2017-09-15 江苏新春兴再生资源有限责任公司 The desulfurizer and method of absorbing sulfur dioxide in flue are starched with lime/lime stone
CN107261808A (en) * 2017-08-03 2017-10-20 北京威肯众合环保科技有限公司 A kind of double ultra-clean desulfurized dust collection columns of spray of the double turbulent flows of single cycle
CN114835239A (en) * 2022-05-19 2022-08-02 通辽第二发电有限责任公司 Concentration tower and flue gas wet desulphurization waste water concentration tower system with same

Also Published As

Publication number Publication date
CN105148718A (en) 2015-12-16

Similar Documents

Publication Publication Date Title
CN202569944U (en) Cyclone pneumatic vortex desulfurization emulsifier and vortex emulsification desulfurization tower with Venturi tubes
CN105148718B (en) Double-turbulence ultraclean desulfurization and dust removal compound tower
CN106861350A (en) The biomass electric power plant gas cleaning handling process and system of dry desulfurization and low-temperature denitration
CN1114467C (en) Dry cyclic suspension bed fume desulfurizing process and system
CN107261808A (en) A kind of double ultra-clean desulfurized dust collection columns of spray of the double turbulent flows of single cycle
CN103316553A (en) Efficient wet-type variable flow fog-spraying sprinkling dust-removing purification device
CN104128106A (en) Novel swirl dispersing device
CN102805999B (en) Turbulent ball type turbocharging compound desulfurization dust removal tower
CN100467100C (en) Circulating suspension state dried method desulfurizing technology and special purpose desulfurizing tower thereof
CN106731403A (en) The flue gas high-efficiency low energy consumption dedusting of metallurgical slag processing procedure and device for deep cleaning
CN208757202U (en) A kind of ash-laden gas processing unit
CN110898584A (en) Low-temperature wet type flue gas dust and white removal device and using method thereof
CN207187488U (en) A kind of double ultra-clean desulfurized dust collection columns of spray of the double turbulent flows of single cycle
CN103007728A (en) Operating method of annular pipe rotational flow wet process flue gas desulfurization tower
CN203002194U (en) Turbulent ball turbocharged composite desulphurization dedusting tower
CN201389423Y (en) Flue gas desulphurization dust removing tower for coal burning boiler
CN206454434U (en) The flue gas high-efficiency low energy consumption dedusting of metallurgical slag processing procedure and device for deep cleaning
CN108607312A (en) A kind of ash-laden gas processing method and its device
CN105381695B (en) A kind of high-efficiency energy-saving desulfurizing denitration dust removal system
CN203355529U (en) Efficient dedusting purification device adopting wet-type variable-flow mist spraying
CN201586463U (en) Combined type boiler dust-removal and desulfurization device
CN106975338A (en) A kind of intelligent spray formula desulfurization and dust-removal method and its device
CN205032079U (en) Two torrent ultra -clean desulfurization dust removal combination towers
CN206355734U (en) A kind of circulation type semi-dry desulphurization type pulsed is combined sack cleaner
CN102228781B (en) SDFGD (semi-dry flue gas desulfurization) device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant