CN105133649A - Inspection well capable of performing reliable sealing of branch pipe and production technology of inspection well - Google Patents

Inspection well capable of performing reliable sealing of branch pipe and production technology of inspection well Download PDF

Info

Publication number
CN105133649A
CN105133649A CN201510521753.1A CN201510521753A CN105133649A CN 105133649 A CN105133649 A CN 105133649A CN 201510521753 A CN201510521753 A CN 201510521753A CN 105133649 A CN105133649 A CN 105133649A
Authority
CN
China
Prior art keywords
manhole
ring
sealing
inspection well
type umbrella
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510521753.1A
Other languages
Chinese (zh)
Other versions
CN105133649B (en
Inventor
吴文露
王磊
傅锐南
郭文真
刘一峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Lutong pipe industry Polytron Technologies Inc
Original Assignee
QUANZHOU LUTONG PIPELINE TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QUANZHOU LUTONG PIPELINE TECHNOLOGY Co Ltd filed Critical QUANZHOU LUTONG PIPELINE TECHNOLOGY Co Ltd
Priority to CN201510521753.1A priority Critical patent/CN105133649B/en
Publication of CN105133649A publication Critical patent/CN105133649A/en
Application granted granted Critical
Publication of CN105133649B publication Critical patent/CN105133649B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Sewage (AREA)

Abstract

The invention discloses an inspection well capable of performing reliable sealing of a branch pipe. The inspection well comprises an inspection well chamber. A well chamber opening for the branch pipe to be inserted and matched is formed in the side wall of the inspection well chamber. An annular umbrella-shaped sealing ring surrounding the inner wall of the well chamber opening by a circle is arranged on the well chamber opening. The end, far away from the inner wall of the well chamber opening, of the annular umbrella-shaped sealing ring is provided with a left sealing lug and a right sealing lug. Due to the fact that the annular umbrella-shaped sealing ring is arranged on the well chamber opening of the inspection well, after the branch pipe is installed, the annular umbrella-shaped sealing ring inclines to one side under extrusion of the branch pipe, the sealing lugs on the two sides of the annular umbrella-shaped sealing ring act on the inner wall of the well chamber opening and the outer wall of the branch pipe respectively, two-way sealing is achieved, a good sealing effect can be achieved from both the inner side and the outer side of the inspection well, and therefore the problem that the joint of the inspection well and the branch pipe is prone to leakage is solved; and meanwhile, plugging operation does not need to be performed on an installing site, on-site fast construction of the inspection well is better facilitated, and sealing quality is guaranteed.

Description

A kind of manhole and production technology thereof of reliably propping up the seal of tube
Technical field
The invention belongs to manhole manufacturing technology field, be specifically related to a kind of manhole and production technology thereof of reliably propping up the seal of tube.
Background technology
The fields such as the communications cable, electric power cable, plumbing and other infrastructure constructions, all indispensable equipment of manhole, its maintenance for pipeline and medium thereof is all extremely important.Existing manhole is by well room mostly, pit shaft, closing in circle and adjusting ring are formed, current urban road bottom need bury rainwater underground, sewage, the various pipelines such as water supply, surface course is just provided with corresponding manhole, and connection between manhole and Inlet and outlet water arm whether sealing relationship the safety of circulates, connection between conventional manhole and arm comprises and adopts gluing mode, by direct for arm fill-in well room opening, make to stick with glue and connect, though this kind of mode can firmly connect for the moment, but symmetrical backfill can not can affect glue and come unstuck in backfill process, thus cause seepage leakage phenomenon, also have in addition to adopt and adopt cement mortar or polyurethane cement mortar filleting at well room opening part and arm, one is need extra site operation, both bothered and again reduced installation effectiveness, two is that it very easily to leak at this link position place by site operation ambient influnence, thus causes seepage leakage phenomenon.
Summary of the invention
Technical problem to be solved by this invention is for above-mentioned the deficiencies in the prior art, a kind of manhole and production technology thereof of reliably propping up the seal of tube are provided, it can solve the problem that manhole and arm junction easy to leak leak effectively, simultaneously without the need to carrying out construction plugging operations in erecting bed, be more conducive to the on-the-spot rapid construction of manhole, and ensure airtight quality.
The technical solution adopted in the present invention is: a kind of manhole reliably propping up the seal of tube, comprise manhole room, described manhole room sidewall is provided with the well room opening coordinated for arm grafting, described well room opening is provided with around its inwall ring-type umbrella sealing circle of a week, this ring-type umbrella sealing circle has two, left and right sealing ear away from one end of described well room opening inwall.
As preferably, described sealing ear is that both sides strut shape, and in beveled structure, its distraction angle is acute angle.
As preferably, on the pre-buried inwall being arranged on described well room opening of described ring-type umbrella sealing circle.
As preferably, described ring-type umbrella sealing circle is the annular special circle mated with described well room opening.
As preferably, described ring-type umbrella sealing circle inside is provided with extruded hole.
Reliably prop up a production technology for the manhole of the seal of tube, it comprises the following steps:
A, precast inspection well are prepared burden: prepare burden by precast inspection well material requested and proportioning thereof;
B, installation check well mould: arrange working pit, working pit bottom surface arranges shaking platform, this shaking platform fixedly mounts mould assembling inside and outside manhole;
C, sealing ring mould is installed: according to the well room opening diameter of manhole and profile design processing ring-type umbrella sealing circle and sealing ring mould, above-mentioned sealing ring mould is made up of matrix in docking and outer matrix, then ring-type umbrella sealing circle is clamped between above-mentioned interior matrix and outer matrix, finally the integral sealing ring mould gripping ring-type umbrella sealing circle is fixed on the outer mold of manhole;
D, to build: the manhole prepared batching is poured in the mould of manhole by running channel frock, and while building, control shaking platform vibration, and vibration compacting;
E, cure and demold: treat resin mixture curing and demolding;
F, Post RDBMS: the product after the demoulding is carried out Post RDBMS process to Post RDBMS station, Post RDBMS temperature is at 50 DEG C-100 DEG C, and rear curing time is at 2h-6h;
G, cleaning burr shaping: as required reconditioning processing is carried out to the end face of manhole and connecting portion.
Beneficial effect of the present invention is: because the present invention is provided with ring-type umbrella sealing circle at the aperture position place, well room of manhole, after installing arm, under arm extruding, make ring-type umbrella sealing circle to lopsidedness, the sealing ear of such ring-type umbrella sealing circle side opens and touch arm outer wall, form leather cup structure, in self sealss state, (hydraulic pressure effect is larger, seal tighter), sealing is formed to well outdoor underground water and Zhi Guanbi, underground water is avoided to enter well room, the umbrella point of ring-type umbrella sealing circle also touch arm outer wall at opposite side on the other hand, form leather cup structure, in self sealss state, sealing is formed to the media such as the sewage of well chamber interior and branch pipe wall, well room medium is avoided to enter well outdoor soil, achieve two way seal, namely no matter be inside manhole or outside it, all can reach good sealing effectiveness, thus efficiently solve the problem that manhole and arm junction easy to leak leak, simultaneously without the need to carrying out construction plugging operations in erecting bed, be more conducive to the on-the-spot rapid construction of manhole, and guarantee airtight quality.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention.
Fig. 2 is A place enlarged diagram in Fig. 1 of the present invention.
Fig. 3 is B place enlarged diagram in Fig. 1 of the present invention.
Fig. 4 is ring-type umbrella sealing circle profile of the present invention.
Fig. 5 is another enforcement structure section of ring-type umbrella sealing circle of the present invention figure.
In figure: 1, manhole room; 2, well room opening; 3, ring-type umbrella sealing circle; 31, ear is sealed; 32, extruded hole; 4, arm.
Detailed description of the invention
Below in conjunction with the accompanying drawings and the specific embodiments the present invention is described in further detail.
As shown in Figure 1, a kind of manhole reliably propping up the seal of tube, comprises manhole room 1, and described manhole room 1 sidewall is provided with the well room opening 2 coordinated for arm 4 grafting.As shown in Fig. 2, Fig. 3, Fig. 4 and Fig. 5, described well room opening 2 is provided with around its inwall ring-type umbrella sealing circle 3 of a week, ring-type umbrella sealing circle 3 is the annular special circle mated with described well room opening 2, and on its pre-buried inwall being arranged on described well room opening 2, ring-type umbrella sealing circle 3 has two, left and right sealing ear 31 away from one end of described well room opening 2 inwall, sealing ear 31 struts shape for both sides, and in beveled structure, its distraction angle is acute angle.
Because the present invention is provided with ring-type umbrella sealing circle 3 in opening 2 position, well room of manhole, after installing arm 4, under arm 4 extrudes, make ring-type umbrella sealing circle 3 to lopsidedness, the sealing ear 31 of such ring-type umbrella sealing circle 3 side opens and touch arm 4 outer wall, form leather cup structure, in self sealss state, (hydraulic pressure effect is larger, seal tighter), sealing is formed to well outdoor underground water and arm 4 wall, underground water is avoided to enter well room, the umbrella point of ring-type umbrella sealing circle 3 also touch arm 4 outer wall at opposite side on the other hand, form leather cup structure, in self sealss state, sealing is formed to the media such as the sewage of well chamber interior and arm 4 tube wall, well room medium is avoided to enter well outdoor soil, achieve two way seal, namely no matter be inside manhole or outside it, all can reach good sealing effectiveness, thus efficiently solve the problem that manhole and arm 4 junction easy to leak leak, simultaneously without the need to carrying out construction plugging operations in erecting bed, be more conducive to the on-the-spot rapid construction of manhole, and guarantee airtight quality.
Ring-type umbrella sealing circle 3 inside is provided with extruded hole 32 around it, is beneficial to the distortion of ring-type umbrella sealing circle 3, prevents sealing ring from dislocating under arm 4 extrudes.
Reliably prop up a production technology for the manhole of the seal of tube, it comprises the following steps:
A, precast inspection well are prepared burden: prepare burden by precast inspection well material requested and proportioning thereof;
B, installation check well mould: arrange working pit, working pit bottom surface arranges shaking platform, this shaking platform fixedly mounts mould assembling inside and outside manhole;
C, sealing ring mould is installed: according to well room opening 2 diameter of manhole and profile design processing ring-type umbrella sealing circle 3 and sealing ring mould, above-mentioned sealing ring mould is made up of matrix in docking and outer matrix, then ring-type umbrella sealing circle 3 is clamped between above-mentioned interior matrix and outer matrix, finally the integral sealing ring mould gripping ring-type umbrella sealing circle 3 is fixed on the outer mold of manhole; The well room opening 2 that namely shaping rear ring-type umbrella sealing circle 3 is inlaid in abnormity is inner, the present invention adopts the method for premounting sealing circle fixed mould, first pre-fix ring-type umbrella sealing circle 3, and then carry out process such as building, solve the problem that the ring-type umbrella sealing circle 3 of abnormity cannot be inlaid in opening 2 inside, well room of abnormity by the later stage well, without the need to later stage installation process, use more convenient;
D, to build: the manhole prepared batching is poured in the mould of manhole by running channel frock, and while building, control shaking platform vibration, and vibration compacting;
E, cure and demold: treat resin mixture curing and demolding;
F, Post RDBMS: the product after the demoulding is carried out Post RDBMS process to Post RDBMS station, Post RDBMS temperature is at 50 DEG C-100 DEG C, and rear curing time is at 2h-6h;
G, cleaning burr shaping: as required reconditioning processing is carried out to the end face of manhole and connecting portion.
The above, be only present pre-ferred embodiments, therefore can not limit scope of the invention process with this, and the equivalence namely done according to the present patent application the scope of the claims and description changes and modifies, and all should still remain within the scope of the patent.

Claims (6)

1. one kind reliably can be propped up the manhole of the seal of tube, comprise manhole room (1), described manhole room (1) sidewall is provided with well room opening (2) coordinated for arm (4) grafting, it is characterized in that: described well room opening (2) is provided with around its inwall ring-type umbrella sealing circle (3) of a week, this ring-type umbrella sealing circle (3) has two, left and right sealing ear (31) away from one end of described well room opening (2) inwall.
2. a kind of manhole reliably propping up the seal of tube according to claim 1, is characterized in that: on the pre-buried inwall being arranged on described well room opening (2) of described ring-type umbrella sealing circle (3).
3. a kind of manhole reliably propping up the seal of tube according to claim 1, is characterized in that: described ring-type umbrella sealing circle (3) is the annular special circle mated with described well room opening (2).
4. a kind of manhole reliably propping up the seal of tube according to claim 1, is characterized in that: described ring-type umbrella sealing circle (3) inside is provided with extruded hole (32).
5. a kind of manhole reliably propping up the seal of tube according to claim 1, is characterized in that: described sealing ear (31) struts shape for both sides, and in beveled structure, its distraction angle is acute angle.
6. a kind of production technology of reliably propping up the manhole of the seal of tube according to claim 1, is characterized in that: it comprises the following steps:
A, precast inspection well are prepared burden: prepare burden by precast inspection well material requested and proportioning thereof;
B, installation check well mould: arrange working pit, working pit bottom surface arranges shaking platform, this shaking platform fixedly mounts mould assembling inside and outside manhole;
C, sealing ring mould is installed: according to well room opening (2) diameter of manhole and profile design processing ring-type umbrella sealing circle (3) and sealing ring mould, above-mentioned sealing ring mould is made up of matrix in docking and outer matrix, then ring-type umbrella sealing circle (3) is clamped between above-mentioned interior matrix and outer matrix, finally the integral sealing ring mould gripping ring-type umbrella sealing circle (3) is fixed on the outer mold of manhole;
D, to build: the manhole prepared batching is poured in the mould of manhole by running channel frock, and while building, control shaking platform vibration, and vibration compacting;
E, cure and demold: treat resin mixture curing and demolding;
F, Post RDBMS: the product after the demoulding is carried out Post RDBMS process to Post RDBMS station, Post RDBMS temperature is at 50 DEG C-100 DEG C, and rear curing time is at 2h-6h;
G, cleaning burr shaping: as required reconditioning processing is carried out to the end face of manhole and connecting portion.
CN201510521753.1A 2015-08-24 2015-08-24 One kind can carry out the sealed inspection shaft of reliable branch pipe and its production technology Active CN105133649B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510521753.1A CN105133649B (en) 2015-08-24 2015-08-24 One kind can carry out the sealed inspection shaft of reliable branch pipe and its production technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510521753.1A CN105133649B (en) 2015-08-24 2015-08-24 One kind can carry out the sealed inspection shaft of reliable branch pipe and its production technology

Publications (2)

Publication Number Publication Date
CN105133649A true CN105133649A (en) 2015-12-09
CN105133649B CN105133649B (en) 2017-07-28

Family

ID=54719196

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510521753.1A Active CN105133649B (en) 2015-08-24 2015-08-24 One kind can carry out the sealed inspection shaft of reliable branch pipe and its production technology

Country Status (1)

Country Link
CN (1) CN105133649B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2204716A1 (en) * 1997-05-06 1998-11-06 Ismail Cemil Suatac Pre-cast manhole basin and method and apparatus for connecting a pipe thereto
CN1555446A (en) * 2002-07-16 2004-12-15 早川橡胶株式会社 Man hole structure, flexible water joint for man hole structure and construction method for man hole structure
CN102296634A (en) * 2011-06-16 2011-12-28 天津市泽宝水泥制品有限公司 Concrete inspection well chamber with flexible interface connection branch
CN104762994A (en) * 2015-02-27 2015-07-08 浙江邦德管业有限公司 Pre-formed plastic water meter chamber and water meter mounting method
CN204940340U (en) * 2015-08-24 2016-01-06 泉州市路通管业科技有限公司 A kind of manhole reliably propping up the seal of tube

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2204716A1 (en) * 1997-05-06 1998-11-06 Ismail Cemil Suatac Pre-cast manhole basin and method and apparatus for connecting a pipe thereto
CN1555446A (en) * 2002-07-16 2004-12-15 早川橡胶株式会社 Man hole structure, flexible water joint for man hole structure and construction method for man hole structure
CN102296634A (en) * 2011-06-16 2011-12-28 天津市泽宝水泥制品有限公司 Concrete inspection well chamber with flexible interface connection branch
CN104762994A (en) * 2015-02-27 2015-07-08 浙江邦德管业有限公司 Pre-formed plastic water meter chamber and water meter mounting method
CN204940340U (en) * 2015-08-24 2016-01-06 泉州市路通管业科技有限公司 A kind of manhole reliably propping up the seal of tube

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
汪刚波等: "T型插入式防滑脱橡胶圈在球墨铸铁管道弯头防漏中的应用", 《给水排水》 *

Also Published As

Publication number Publication date
CN105133649B (en) 2017-07-28

Similar Documents

Publication Publication Date Title
CN106149764B (en) A kind of precast assembly pipe gallery bell and spigot waterproof construction
CN207332121U (en) A kind of PC components grout sleeve fixation kit
CN203514481U (en) Inspection well
CN105019476A (en) Prefabricated reinforced concrete inspection well
CN204940340U (en) A kind of manhole reliably propping up the seal of tube
CN206617686U (en) A kind of quick connection high-pressure glass steel oil pipeline
CN105235056A (en) Hole forming method for prefabricated component
CN216131506U (en) Hydraulic engineering prefabricated inspection shaft and drain pipe connection structure
CN101307854A (en) Excavation-free underground pipe line rehabilitation method
CN201917498U (en) Pressure test device for glass reinforced plastic pipe ends
CN108239993B (en) A kind of sealed Grouting Pipe molding positioning device of reinforced concrete sewer pipe and its application method
CN105133649A (en) Inspection well capable of performing reliable sealing of branch pipe and production technology of inspection well
CN211312769U (en) Connecting member of plastic pipe and concrete prefabricated inspection well
CN201628031U (en) Spigot-and-socket connecting pipe fitting
CN104452816A (en) High-stiffness leakage-proof plastic inspection well and production method thereof
CN101016966A (en) Plastic wound structure wall faucet pipe and manufacture method therefor
CN102200207A (en) Bell and spigot joint pipe fitting and connecting method thereof
CN206752632U (en) Plastic reinforcing steel composite construction municipal drainage inspection shaft
CN202416361U (en) Inspection well for improving sealing performance of interface and branch pipe connected with inspection well
CN214090253U (en) Urban municipal drainage pipeline inspection shaft structure
CN203927102U (en) Polyester concrete Pressure pipe and assembly thereof
CN204326105U (en) A kind of plastic inspection well
KR20130128289A (en) Manufacture of concrete blocks for sewer manhole
CN201129585Y (en) Bidirectional socket pipe parts
CN206888029U (en) A kind of prefabricated box culvert structure containing glass fiber-reinforced polymer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: Yi Feng Lu, Quangang District of Quanzhou city in northeastern Fujian province 362800 seaside village

Patentee after: Fujian Lutong pipe industry Polytron Technologies Inc

Address before: Yi Feng Lu, Quangang District of Quanzhou city in northeastern Fujian province 362800 seaside village

Patentee before: Quanzhou Lutong Pipeline Technology Co., Ltd.

CP01 Change in the name or title of a patent holder