CN105133461A - Concrete colored die floor construction process - Google Patents

Concrete colored die floor construction process Download PDF

Info

Publication number
CN105133461A
CN105133461A CN201510341833.9A CN201510341833A CN105133461A CN 105133461 A CN105133461 A CN 105133461A CN 201510341833 A CN201510341833 A CN 201510341833A CN 105133461 A CN105133461 A CN 105133461A
Authority
CN
China
Prior art keywords
concrete
colored
completing
construction
casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510341833.9A
Other languages
Chinese (zh)
Inventor
马国栋
黄伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Haichuan Construction Group Co Ltd
Original Assignee
Qingdao Haichuan Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Haichuan Construction Group Co Ltd filed Critical Qingdao Haichuan Construction Group Co Ltd
Priority to CN201510341833.9A priority Critical patent/CN105133461A/en
Publication of CN105133461A publication Critical patent/CN105133461A/en
Pending legal-status Critical Current

Links

Landscapes

  • Curing Cements, Concrete, And Artificial Stone (AREA)

Abstract

The invention provides a concrete colored die floor construction process including eight steps of basal treatment, concrete casting, spraying of a strengthening powder for first time, surface drawing and press polishing, spraying of the strengthening powder for second time, full polishing, compression molding, and maintenance and correction. On one hand, the adopted construction method avoids use of a large number of stone material and other raw materials and splicing process in a traditional construction, greatly simplifies the construction process and improves the construction efficiency, on the other hand, the construction method also greatly avoids the loss of natural stone material and other raw materials, is beneficial for reducing natural resource loss, and can effectively improve the use performance of a floor, and reduces construction costs.

Description

The colored die floor construction technology of a kind of concrete
Technical field
The present invention relates to the colored die floor construction technology of a kind of concrete, face, possession, road surface, terrace technology field.
Background technology
At present when to view class road surfacings such as some road surfaces, lawn, in order to meet the requirement with environment compatibility and aesthetic property, often need to lay by material road pavement such as a large amount of lithotomes, although this construction can meet the needs of actual use, but its construction technology is very complicated, efficiency of construction is low, also can cause the use of the materials such as a large amount of lithotomes simultaneously, be unfavorable for the protections such as environment and resources conservation, and functional performance stability is relatively poor, also cause construction cost and routine servicing cost also relatively high simultaneously, therefore for this present situation, a kind of brand-new road surface of exploitation is needed to beautify construction technology, with the needs that satisfied reality uses.
Summary of the invention
The object of this invention is to provide and the invention provides the colored die floor construction technology of a kind of concrete.
In order to achieve the above object, the invention provides following technical scheme:
The colored die floor construction technology of a kind of concrete, comprises the steps:
The first step, base treatment, the laitance be bonded in basic unit, the pollutants of impression construction quality such as ash that land thoroughly are cleaned out, and it is levelling to carry out compacting to substrate surface;
Second step, casting concrete, utilize concrete casting casting machine, predetermined construction basic unit carries out concrete casting operation, and casting is simultaneously another to vibrate operation to concrete, after concrete casting completes, separately according to designing requirement, domatic rest and reorganization and floating process are carried out to concrete surface, and carry out watering process at concrete surface layer after completing domatic rest and reorganization and floating process, check impeded drainage position and repair;
3rd step, sends primary reinforcement powder forth, after completing concrete casting construction, and after surface is without free state water, and uniform broadcasting first floor colour strengthening material, and colored strengthening material broadcasts sowing point at least twice completes, and the amount of broadcasting sowing is colored strengthening expects 1/2-2/3 of total amount;
4th step, receives face press polish, sprays once colored strengthening material, and after itself and the abundant hydration reaction of fine-stone concrete basic unit, adopts the floating receipts light of large-scale spatula;
5th step, sends secondary hardening powder forth, by once spray rear remaining colour strengthening material all be sprayed onto on the concrete surface that processes through receipts face, and make concrete surface uniform in color;
6th step, receives light comprehensively, utilizes the floating instrument of steel to carry out artificial floating receipts light to concrete surface, and must not colour mixture to colour strengthening material color intersection when receiving light;
7th step, moulded section, treat concrete surface colour strengthening material sclerosis and before concrete initial set, separating powder is broadcasted sowing equably on the surface of colour strengthening material, and in spraying process, separately synchronously carry out the operation of receipts light, and carry out decorative pattern compacting to completing the mould receiving the default decorative pattern of light Seeding location utilization simultaneously, after completing compacting, mould is removed;
8th step; maintenance and correction, after completing pressing mold and constructing at least 12 hours in 36 hours, carry out shrinkage joint cutting operation to concrete structure; after completing cutting; use felt sub-covering immediately, and water seasoning, and curing time must not be less than 7 days; polishing correcting process is carried out with grinding apparatus with surface after completing maintenance; and residue polishing produced and dust clean, and after bone dry, then in the agent of surface brush seal protection.
Further, described concrete strength is not less than C20, and small particle diameter stone in adopting; Little water/binder ratio, the slump of job mix concrete controls at 4 ~ 6 ㎝; The slump of commercial concrete controls at 12 ~ 14 ㎝; The maximum particle diameter diameter of basic unit is no more than 30 ㎜.
Further, the described total consumption of colored hardening agent is 5.0kg/m2.
Further, described separating powder is colored release agent, and be made up of materials such as nanoscale powder base-material, import inorganic pigment, activating agents, total consumption is 0.3kg/m2.
Further, the described total consumption of seal protection agent is 0.4kg/m2.
Construction method of the present invention; to avoid on the one hand in traditional construction raw-material use and the splicing process such as a large amount of stone materials; thus greatly simplify construction technology; improve efficiency of construction; also avoid the loss of the raw materials such as lithotome on the other hand greatly, contribute to reducing loss of natural resource, and can the protections such as environment and resources conservation be conducive to; and functional performance stability is relatively high, also reduce construction cost and routine servicing cost simultaneously.
Accompanying drawing explanation
In order to be illustrated more clearly in the embodiment of the present invention or technical scheme of the prior art, be briefly described to the accompanying drawing used required in embodiment or description of the prior art below, apparently, accompanying drawing in the following describes is only some embodiments of the present invention, for those of ordinary skill in the art, under the prerequisite not paying creative work, other accompanying drawing can also be obtained according to these accompanying drawings.
Fig. 1 is manufacturing process flow diagram of the present invention.
Detailed description of the invention
Be clearly and completely described technical scheme of the present invention below in conjunction with accompanying drawing of the present invention, obviously, described embodiment is only the present invention's part embodiment, instead of whole embodiments.Based on the embodiment in the present invention, those of ordinary skill in the art, not making the every other embodiment obtained under creative work prerequisite, belong to the scope of protection of the invention.
The colored die floor construction technology of a kind of concrete as shown in Figure 1, comprises the steps:
The first step, base treatment, the laitance be bonded in basic unit, the pollutants of impression construction quality such as ash that land thoroughly are cleaned out, and it is levelling to carry out compacting to substrate surface;
Second step, casting concrete, utilize concrete casting casting machine, predetermined construction basic unit carries out concrete casting operation, and casting is simultaneously another to vibrate operation to concrete, after concrete casting completes, separately according to designing requirement, domatic rest and reorganization and floating process are carried out to concrete surface, and carry out watering process at concrete surface layer after completing domatic rest and reorganization and floating process, check impeded drainage position and repair;
3rd step, send primary reinforcement powder forth, after completing concrete casting construction, and after surface is without free state water, uniform broadcasting first floor colour strengthening material, and colored strengthening material broadcasts sowing point at least twice completes, and the amount of broadcasting sowing is colored strengthening expects 1/2-2/3 of total amount, and sprinkling is Ying Xiancong, and zone line far away starts, and then progressively constructs to position, sideline.
4th step, receives face press polish, sprays once colored strengthening material, and after itself and the abundant hydration reaction of fine-stone concrete basic unit, adopts the floating receipts light of large-scale spatula;
5th step, sends secondary hardening powder forth, by once spray rear remaining colour strengthening material all be sprayed onto on the concrete surface that processes through receipts face, and make concrete surface uniform in color;
6th step, receives light comprehensively, utilizes the floating instrument of steel to carry out artificial floating receipts light to concrete surface, and must not colour mixture to colour strengthening material color intersection when receiving light;
7th step, moulded section, treat concrete surface colour strengthening material sclerosis and before concrete initial set, separating powder is broadcasted sowing equably on the surface of colour strengthening material, and in spraying process, separately synchronously carry out the operation of receipts light, and carry out decorative pattern compacting to completing the mould receiving the default decorative pattern of light Seeding location utilization simultaneously, after completing compacting, mould is removed;
8th step; maintenance and correction, completing pressing mold construction after at least 48 hours, carry out shrinkage joint cutting operation to concrete structure; after completing cutting; use felt sub-covering immediately, and water seasoning, and curing time must not be less than 7 days; polishing correcting process is carried out with grinding apparatus with surface after completing maintenance; and residue polishing produced and dust clean, and after bone dry, then in the agent of surface brush seal protection.
In the present embodiment, described concrete strength is not less than C20, and small particle diameter stone in adopting; Little water/binder ratio, the slump of job mix concrete controls at 4 ~ 6 ㎝; The slump of commercial concrete controls at 12 ~ 14 ㎝; The maximum particle diameter diameter of basic unit is no more than 30 ㎜.
In the present embodiment, described colored hardening agent is made up of materials such as import inorganic pigment, high grade white cement, classified quartz sands, hardening agent, hardener, activating agent, colour stabilizer, silicon ashes, and its total consumption is 5.0kg/m2.
In the present embodiment, described separating powder is colored release agent, and be made up of materials such as nanoscale powder base-material, import inorganic pigment, activating agents, total consumption is 0.3kg/m2.
In the present embodiment, described seal protection agent is made up of materials such as epoxy resin, organic Thief zone solvent, antioxidant, ultraviolet (UV) resistant agent, stabilizing agents, and its total consumption is 0.4kg/m2.
Construction method of the present invention, to avoid on the one hand in traditional construction raw-material use and the splicing process such as a large amount of stone materials, thus greatly simplify construction technology, improve efficiency of construction, also the loss of the raw materials such as lithotome is avoided on the other hand greatly, contribute to reducing loss of natural resource, and effectively can improve the functional performance of building, reduce construction cost.
Construction method of the present invention is easy and simple to handle, and construction is simple, and effectively can shorten the construction period, reduce difficulty of construction, thus construction cost is significantly reduced, meanwhile, structural performance is reliable and stable, long service life and keep in repair easy.
The above; be only the specific embodiment of the present invention, but protection scope of the present invention is not limited thereto, is anyly familiar with those skilled in the art in the technical scope that the present invention discloses; change can be expected easily or replace, all should be encompassed within protection scope of the present invention.Therefore, protection scope of the present invention should described be as the criterion with the protection domain of claim.

Claims (5)

1. the colored die floor construction technology of concrete, is characterized in that: the colored die floor construction technology of described concrete comprises the steps:
The first step, base treatment, the laitance be bonded in basic unit, the pollutants of impression construction quality such as ash that land thoroughly are cleaned out, and it is levelling to carry out compacting to substrate surface;
Second step, casting concrete, utilize concrete casting casting machine, predetermined construction basic unit carries out concrete casting operation, and casting is simultaneously another to vibrate operation to concrete, after concrete casting completes, separately according to designing requirement, domatic rest and reorganization and floating process are carried out to concrete surface, and carry out watering process at concrete surface layer after completing domatic rest and reorganization and floating process, check impeded drainage position and repair;
3rd step, sends primary reinforcement powder forth, after completing concrete casting construction, and after surface is without free state water, and uniform broadcasting first floor colour strengthening material, and colored strengthening material broadcasts sowing point at least twice completes, and the amount of broadcasting sowing is colored strengthening expects 1/2-2/3 of total amount;
4th step, receives face press polish, sprays once colored strengthening material, and after itself and the abundant hydration reaction of fine-stone concrete basic unit, adopts the floating receipts light of large-scale spatula;
5th step, sends secondary hardening powder forth, by once spray rear remaining colour strengthening material all be sprayed onto on the concrete surface that processes through receipts face, and make concrete surface uniform in color;
6th step, receives light comprehensively, utilizes the floating instrument of steel to carry out artificial floating receipts light to concrete surface, and must not colour mixture to colour strengthening material color intersection when receiving light;
7th step, moulded section, treat concrete surface colour strengthening material sclerosis and before concrete initial set, separating powder is broadcasted sowing equably on the surface of colour strengthening material, and in spraying process, separately synchronously carry out the operation of receipts light, and carry out decorative pattern compacting to completing the mould receiving the default decorative pattern of light Seeding location utilization simultaneously, after completing compacting, mould is removed;
8th step; maintenance and correction, completing pressing mold construction after at least 48 hours, carry out shrinkage joint cutting operation to concrete structure; after completing cutting; use felt sub-covering immediately, and water seasoning, and curing time must not be less than 7 days; polishing correcting process is carried out with grinding apparatus with surface after completing maintenance; and residue polishing produced and dust clean, and after bone dry, then in the agent of surface brush seal protection.
2. the colored die floor construction technology of a kind of concrete according to claim 1, is characterized in that: described concrete strength is not less than C20, and small particle diameter stone in adopting; Little water/binder ratio, the slump of job mix concrete controls at 4 ~ 6 ㎝; The slump of commercial concrete controls at 12 ~ 14 ㎝; The maximum particle diameter diameter of basic unit is no more than 30 ㎜.
3. the colored die floor construction technology of a kind of concrete according to claim 1, is characterized in that: the described total consumption of colored hardening agent is 5.0kg/m 2.
4. the colored die floor construction technology of a kind of concrete according to claim 1, is characterized in that: described separating powder is colored release agent, and be made up of materials such as nanoscale powder base-material, import inorganic pigment, activating agents, total consumption is 0.3kg/m 2.
5. the colored die floor construction technology of a kind of concrete according to claim 1, is characterized in that: the described total consumption of seal protection agent is 0.4kg/m 2.
CN201510341833.9A 2015-06-19 2015-06-19 Concrete colored die floor construction process Pending CN105133461A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510341833.9A CN105133461A (en) 2015-06-19 2015-06-19 Concrete colored die floor construction process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510341833.9A CN105133461A (en) 2015-06-19 2015-06-19 Concrete colored die floor construction process

Publications (1)

Publication Number Publication Date
CN105133461A true CN105133461A (en) 2015-12-09

Family

ID=54719011

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510341833.9A Pending CN105133461A (en) 2015-06-19 2015-06-19 Concrete colored die floor construction process

Country Status (1)

Country Link
CN (1) CN105133461A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284015A (en) * 2016-08-26 2017-01-04 盼石(上海)新材料科技股份有限公司 High service life embossing ground floor and preparation method thereof
CN107571372A (en) * 2017-09-07 2018-01-12 李文斌 Colour is embossed from concrete prefabricated roads plate of dust suppression and its preparation method and application
CN108071056A (en) * 2016-11-09 2018-05-25 上海秀城景观工程有限公司 A kind of production technology of embossing ground floor
CN108727062A (en) * 2018-07-02 2018-11-02 东莞市泰华建设工程有限公司 Crack autogenous healing cement base colour hardening agent artistic floors and construction method
CN109025167A (en) * 2018-09-10 2018-12-18 王海 A kind of construction method of colour die floor
CN110080227A (en) * 2019-04-28 2019-08-02 浙江省围海建设集团股份有限公司 A kind of dam colour pressing mold construction method
CN111455786A (en) * 2020-04-30 2020-07-28 上海宝冶集团有限公司 Ramp forming die and using method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1442580A (en) * 2003-04-11 2003-09-17 郭四龙 Construction method of walking typhlosole with integrally poured decorative concrete on site
CN1492105A (en) * 2003-09-04 2004-04-28 俞子平 Concrete colour embossing ground floor technology
JP2007283607A (en) * 2006-04-14 2007-11-01 Hachiya Kenzai Kogyo Kk Molding method of concrete
CN104631270A (en) * 2015-01-15 2015-05-20 杭州比亚姆新型建材有限公司 Construction technology for dyeing, polishing and hardening concrete floor

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1442580A (en) * 2003-04-11 2003-09-17 郭四龙 Construction method of walking typhlosole with integrally poured decorative concrete on site
CN1492105A (en) * 2003-09-04 2004-04-28 俞子平 Concrete colour embossing ground floor technology
JP2007283607A (en) * 2006-04-14 2007-11-01 Hachiya Kenzai Kogyo Kk Molding method of concrete
CN104631270A (en) * 2015-01-15 2015-05-20 杭州比亚姆新型建材有限公司 Construction technology for dyeing, polishing and hardening concrete floor

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284015A (en) * 2016-08-26 2017-01-04 盼石(上海)新材料科技股份有限公司 High service life embossing ground floor and preparation method thereof
CN106284015B (en) * 2016-08-26 2019-01-18 盼石(上海)新材料科技股份有限公司 High service life embossing ground floor and preparation method thereof
CN108071056A (en) * 2016-11-09 2018-05-25 上海秀城景观工程有限公司 A kind of production technology of embossing ground floor
CN107571372A (en) * 2017-09-07 2018-01-12 李文斌 Colour is embossed from concrete prefabricated roads plate of dust suppression and its preparation method and application
CN108727062A (en) * 2018-07-02 2018-11-02 东莞市泰华建设工程有限公司 Crack autogenous healing cement base colour hardening agent artistic floors and construction method
CN109025167A (en) * 2018-09-10 2018-12-18 王海 A kind of construction method of colour die floor
CN110080227A (en) * 2019-04-28 2019-08-02 浙江省围海建设集团股份有限公司 A kind of dam colour pressing mold construction method
CN111455786A (en) * 2020-04-30 2020-07-28 上海宝冶集团有限公司 Ramp forming die and using method thereof

Similar Documents

Publication Publication Date Title
CN105133461A (en) Concrete colored die floor construction process
US7607859B2 (en) Surface seeded fine aggregate concrete simulating quarried stone
CN110761508B (en) Construction method for aesthetic presentation of vicious texture of plastering and ramming soil veneer
US8936411B1 (en) Architectural concrete
CN106517904B (en) A kind of cementing water-permeable brick of organo-mineral complexing and preparation method thereof
CN101886457B (en) Method for constructing wear-resistant and crack-resistant hardened ground
CN109761538B (en) Exposed aggregate concrete and construction method thereof
CN102733289A (en) Water-borne acrylic resin plastic runway and production method thereof
KR100309155B1 (en) Method of manufacturing porous cement block having natural stone like surface layer
CN103216076B (en) A kind of epoxy color sand construction method of ground
CN100552136C (en) Spary forms on the honeycombed cement concrete pavement colored road surface and job practices
CN101016713A (en) Color pavement formed by spraying on porous polymer concrete facing and construction method therefor
CN103556557A (en) Manufacturing method of color concrete granite flamed-surface terrace
CN102838334A (en) Concrete member repairing agent, preparation method and construction method
CN107642217A (en) Efficient seamless stone level ground construction technology
CN113250033A (en) Construction process of modified permeable terrace
KR20110058609A (en) Artificial volcanic rock for structure
CN104411786A (en) A surface composition and method of application thereof
CN106625992B (en) A kind of prefabricated complicated architectural concrete craftwork method for prefabricating of gypsum mold
CN107540314A (en) A kind of post-cast strip basal plane inorganic agent and its construction method
CN105060928B (en) A kind of method that lightweight imitation wood component product is made using high wet mud
CN204510735U (en) A kind of have the concrete structure exposing sand face structure
RU2372304C1 (en) Method for manufacturing of coarse filler for concretes
RU2334712C1 (en) Method for manufacturing coarse aggregate for concrete
JP2005008841A (en) Special adhesive, method for producing special adhesive at normal temperature and method for utilizing the same at normal temperature

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20151209

RJ01 Rejection of invention patent application after publication