CN105119256A - Method for preventing power grid distance protection misoperation under condition of voltage loss after start - Google Patents
Method for preventing power grid distance protection misoperation under condition of voltage loss after start Download PDFInfo
- Publication number
- CN105119256A CN105119256A CN201510650070.6A CN201510650070A CN105119256A CN 105119256 A CN105119256 A CN 105119256A CN 201510650070 A CN201510650070 A CN 201510650070A CN 105119256 A CN105119256 A CN 105119256A
- Authority
- CN
- China
- Prior art keywords
- distance protection
- voltage
- electrical network
- voltage jump
- phase
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Emergency Protection Circuit Devices (AREA)
Abstract
The invention relates to a method for preventing power grid distance protection misoperation under the condition of voltage loss after start. The method is used for judging whether secondary circuit breaking of a three-phase voltage transformer happens after a distance protection device in a power grid is started due to external faults, so that misoperation of the distance protection device is prevented. The method comprises steps as follows: continuous n sampling points meet following criteria: 1, the voltage sudden change variable of any phase is higher than a set voltage sudden change threshold; 2, three-phase voltage calculated with a semi-cycle algorithm is lower than 2V; 3, three phase current sudden change variables in 20 ms are smaller than a starting definite value of the distance protection device; n is a positive integer; the situation that the breaking of the three-phase voltage transformer happens is determined; the distance protection device is prevented from misoperation according to a determination result. According to the method, whether breaking of the three-phase voltage transformer happens after the distance protection is started can be judged, then distance protection misoperation is prevented, and the system security is improved.
Description
Technical field
The invention belongs to dispatching of power netwoks control field, be specifically related to be used for preventing voltage transformer disconnection from causing the method for malfunction after a kind of distance protection equipment at electrical network starts.
Background technology
Distance protection take electric current as actuating quantity, and voltage is the deficient amount formula protection of braking amount.When losing voltage braking amount after voltage transformer disconnection, measurement impedance trends towards zero, and distance protection will malfunction under through fault current or load current effect outside district.What current distance protection extensively adopted prevents the method for malfunction from being carry out the differentiation of voltage transformer disconnection decompression, usually detects a phase or two-phase voltage transformer disconnection with three-phase voltage vector sum is non-vanishing; Detect threephase potential transformer broken string by the method that positive sequence voltage is low, general time delay 1-2s latch-up protection also sends alarm signal, and is generally all self-healing.The prerequisite of above-mentioned criterion is that protective device does not start.Generally believe once system jam at present, just no longer sentence voltage transformer disconnection after starting component starts, because any one fault all has voltage transformer disconnection feature, do not consider the system failure and the simultaneous situation of voltage transformer disconnection.
But; practical operation situation shows; the system failure and the absolute simultaneous possibility of voltage transformer disconnection very little; but the accident that the inducement due to the system failure causes at short notice (after 20ms) that voltage transformer disconnection occurs in succession but repeatedly occurs; and the multi circuit transmission lines distance protection malfunction that same bus is run, serious threat system safety operation.
The situation analysis that distance protection first starts rear voltage transformer disconnection false protection is as follows:
1, double bus scheme transformer station as shown in Figure 1; circuit 1,2,3,4 is system interconnection; double-bus paired running; when I bus-bar potential transformer maintenance; general operation method is that two groups of bus-bar potential transformer secondary voltage circuits are arranged side by side, makes the distance protection of circuit 1,2,3,4 all use II bus-bar potential transformer secondary voltage.If but now II bus breaks down; circuit 1,2,3,4 distance protection all can start; when all elements of II bus are excised in bus protection action; measuring voltage is lost upon actuation by causing the distance protection of circuit 1,2 on I bus; because protective device starts time broadening generally at 5-7s; now the distance protection of load current effect line 1,2 all exist malfunction may, there is the risk of the dead electricity that causes entirely standing.In like manner, if fault point is on circuit 1 or circuit 2 outlet, but during wire-outgoing breaker tripping, also same consequence will be caused.
2, the voltage transformer disconnection of intermittence is also by malfunction when causing circuit distance protection formerly to start rear decompression.Scene often can run into the voltage transformer disconnection that voltage secondary circuit terminal screw loosens or secondary line loose contact causes; sometimes this broken string phenomenon cuts in and out; intermittence occurs; if the raw fault of this time zone outgoing; intermittence generation voltage transformer disconnection again after distance protection starts; then relevant circuit distance protection is by malfunction under the short circuit current effect of passing through character; even if external area error is cut; during protective device starts broadening, under load current effect, the voltage transformer disconnection of intermittence still makes distance protection there is the risk of malfunction.
3, bus-bar potential transformer secondary voltage circuit generally all needs to arrange and prevents voltage transformer secondary to the heavily dynamic loop of voltage of a reverse charge, this loop is generally often opened auxiliary contact with voltage transformer disconnecting link and is driven heavily dynamic auxiliary relay to realize, when voltage transformer is out of service, when one time disconnecting link is opened, relay discharges, and secondary voltage circuit and voltage transformer disconnect; When voltage transformer puts into operation, one time disconnecting link closes, and this heavy motor type relay excitation, secondary voltage circuit accesses voltage transformer secondary side automatically.Heavy motor type relay working power uses the power supply of transformer station direct current system.The operational reliability of this electric power loop is directly connected to the proterctive equipment reliability of operation using bus-bar potential transformer voltage, and distance protection stands in the breach.The DC supply that voltage heavily dynamic loop repeatedly occurs in actual motion in succession loses after primary system breaks down, main cause, the direct current sky that after having plenty of primary system fault, direct current signal loop fault causes opens overstep tripping, the direct current sky that external disturbance when having plenty of the system failure causes opens tripping operation, after having plenty of the system failure, direct current system storage battery float charger loses, and the DC power supply that storage battery open circuit causes loses.Primary system fault becomes the direct inducement of secondary direct current system dead electricity; all there is the risk of malfunction in the distance protection run with bus in such cases; certain urban district, megapolis one 220kV transformer station in 2007 stands dead electricity entirely; the direct current signal loop short circuit after the interior 110kV system failure of standing exactly of its reason causes the empty overstep tripping of direct current; after the heavily dynamic power supply of the voltage transformer secondary of 220kV is lost; the distance protection of four times 220kV power circuits loses measuring voltage upon actuation, under load current effect caused by successive tripping.Accident loads loss is serious, and lesson is painful.
In sum; although the probability that distance protection first starts the situation generation losing measuring voltage is afterwards not very too large; but once there is the malfunction in succession of many circuit distance protections run with bus often, there is the risk of full station dead electricity, consequence serious threat system safety.Therefore necessary setting about on protection philosophy is taken precautions against; being necessary that proposition is adjusted the distance protects voltage transformer disconnection criterion to carry out perfect; distance protection is made to continue upon actuation to differentiate voltage transformer disconnection, distance protection malfunction when preventing external area error.
Summary of the invention
The object of this invention is to provide a kind of for after distance protection equipment startup, prevent the method causing malfunction owing to there is threephase potential transformer broken string.
For achieving the above object, the technical solution used in the present invention is:
A kind of method preventing electrical network distance protection from first starting rear decompression malfunction; after starting due to external area error for the distance protection equipment in electrical network; judge whether threephase potential transformer secondary circuit broken string occurs; thus prevent described distance protection equipment malfunction, the method is: n sampled point meets following criterion continuously:
1. the voltage jump amount of any phase is greater than the voltage jump threshold value of setting;
2. the three-phase voltage utilizing half cycle algorithm to calculate all is less than 2V;
3. in 20ms, three-phase current Sudden Changing Rate is all less than the startup definite value of described distance protection equipment;
Wherein n is positive integer;
Then judge threephase potential transformer broken string occurs;
Described distance protection equipment malfunction is prevented according to result of determination.
Described voltage jump threshold value is greater than voltage jump amount during minimum cycle of oscillation.
Described minimum cycle of oscillation is 200ms.
Further, voltage jump amount when described voltage jump threshold value is described minimum cycle of oscillation and floating threshold sum.
Further, the basis of the voltage jump amount of described voltage jump threshold value when described minimum cycle of oscillation and floating threshold sum increases and sets nargin and formed.
Described voltage jump threshold value is 0.4U
n, wherein U
nfor voltage rating.
N value is 3.
Because technique scheme is used; the present invention compared with prior art has following advantages: can after distance protection starts by this method; whether there is threephase potential transformer broken string after judging 20ms, and then avoid distance protection malfunction, improve the fail safe of system.
Accompanying drawing explanation
Accompanying drawing 1 is the wiring schematic diagram of double bus scheme transformer station.
Accompanying drawing 2 is the criterion theory diagram of method of the present invention.
Embodiment
Below in conjunction with embodiment, the invention will be further described.
Embodiment one: a kind of method preventing electrical network distance protection from first starting rear decompression malfunction; after the method distance protection equipment be used in electrical network starts due to external area error; threephase potential transformer secondary circuit broken string and the decompression that causes whether is there is after judging 20ms; thus prevent distance protection equipment malfunction; concrete; the method is: continuous n (n is positive integer; usually 3 are got) sampled point meets following criterion; namely judge threephase potential transformer broken string occurs, and then distance protection equipment malfunction can be prevented according to result of determination.
Criterion comprises following three conditions, need meet simultaneously:
1. the voltage jump amount of any phase is greater than the voltage jump threshold value of setting;
2. the three-phase voltage utilizing half cycle algorithm to calculate all is less than 2V;
3. in 20ms, three-phase current Sudden Changing Rate is all less than the startup definite value of distance protection equipment.
First start during external area error from several in the maloperation analysis of cases of rear decompression and learn, voltage transformer secondary is three-phase pressure loss, and analyze from its recorder data, the stray voltage of secondary remnants is very low, two sub-values are maximum is generally no more than 2V, the generation moment of decompression general lagging current amount sudden change more than Startup time 20ms simultaneously, therefore draw above-mentioned criterion.
The 1. item criterion: when there is threephase potential transformer broken string, voltage has certain Sudden Changing Rate, and can be larger, simultaneously too low cause erroneous judgement because voltage jump threshold value obtains in order to prevent in oscillatory process, so voltage jump amount when voltage jump threshold value is greater than minimum cycle of oscillation.The system oscillation cycle is considered according to minimum 200ms, in time protecting installation place to be positioned at oscillation center, and voltage jump amount | U (t)-U (t-T) | just have maximum.U (t) take 200ms as the sinusoidal waveform in cycle, and T is 20ms.Then
According to difference eliminate indigestion formula
Can be found out by above-mentioned formula, as t=10, voltage jump amount has maximum.
After increasing floating threshold, the maximum sudden change amount of the voltage in a cycle is:
Can be found out by above-mentioned formula, as t=70, voltage jump amount has maximum
Consider that threshold puts certain nargin, so threshold value gets 0.4Un, consider when likely there is a phase or phase to phase fault outside district simultaneously, when there is threephase potential transformer broken string again, there is Sudden Changing Rate in the voltage only perfecting phase, therefore this criterion is when detecting that any phase voltage Sudden Changing Rate of three-phase voltage satisfies condition.
The 2. item criterion: when there is voltage transformer disconnection, the Sudden Changing Rate of voltage can be experienced in one cycle, but based on the reason of full-wave fourier algorithm fourier window, voltage fourier value can't reduce to 0, as used half cycle algorithm, after 10ms then after voltage transformer disconnection, the voltage fourier value of calculating is 0, so the three-phase voltage fourier value utilizing half-wave algorithm to calculate.2V is less than, as the condition of voltage transformer generation three-phase pressure loss with three-phase voltage stable state amplitude.
The 3. item criterion: because this condition does not consider that voltage transformer disconnection breaks down while occurring, therefore while voltage has Sudden Changing Rate electric current without any variable quantity, all be less than start the condition of definite value so add three-phase current Sudden Changing Rate, this condition is mainly used in distinguishing voltage that fault causes and reduces and still only there occurs voltage transformer disconnection.
When above three conditions all meet, and continue three sampled points, just can be determined as circuit after starting and there occurs voltage transformer disconnection again, as shown in Figure 2.
In the process started in distance protection by said method; if differentiate and there occurs voltage transformer disconnection; locking distance protection; and in whole start-up course, no longer carry out the differentiation of voltage transformer disconnection; until protection full resetting, then proceed the differentiation of voltage transformer disconnection by conventional voltage transformer disconnection criterion.
Current, the pilot protection of taking as the leading factor with the protection of optical fiber differential current is the main protection of ultra-high-tension power transmission line, is the important guarantee of power network safety operation.The stage distance protected in support, zero-sequenceprotection are again necessary the supplementing of ultra-high-tension power transmission line protection, are only improved the reliability of backup protection, just can embody the powerful advantages of main protection, significant to guarantee electric power netting safe running.
Above-described embodiment, only for technical conceive of the present invention and feature are described, its object is to person skilled in the art can be understood content of the present invention and implement according to this, can not limit the scope of the invention with this.All equivalences done according to Spirit Essence of the present invention change or modify, and all should be encompassed within protection scope of the present invention.
Claims (7)
1. the method preventing electrical network distance protection from first starting rear decompression malfunction; after starting due to external area error for the distance protection equipment in electrical network; judge whether threephase potential transformer secondary circuit broken string occurs; thus prevent described distance protection equipment malfunction, it is characterized in that: the method is: n sampled point meets following criterion continuously:
1. the voltage jump amount of any phase is greater than the voltage jump threshold value of setting;
2. the three-phase voltage utilizing half cycle algorithm to calculate all is less than 2V;
3. in 20ms, three-phase current Sudden Changing Rate is all less than the startup definite value of described distance protection equipment;
Wherein n is positive integer;
Then judge threephase potential transformer broken string occurs;
Described distance protection equipment malfunction is prevented according to result of determination.
2. the method preventing electrical network distance protection from first starting rear decompression malfunction according to claim 1, is characterized in that: described voltage jump threshold value is greater than voltage jump amount during minimum cycle of oscillation.
3. the method preventing electrical network distance protection from first starting rear decompression malfunction according to claim 2, is characterized in that: described minimum cycle of oscillation is 200ms.
4. the method preventing electrical network distance protection from first starting rear decompression malfunction according to claim 2, is characterized in that: voltage jump amount when described voltage jump threshold value is described minimum cycle of oscillation and floating threshold sum.
5. the method preventing electrical network distance protection from first starting rear decompression malfunction according to claim 2, is characterized in that: the basis of the voltage jump amount of described voltage jump threshold value when described minimum cycle of oscillation and floating threshold sum increases and sets nargin and formed.
6. the method preventing electrical network distance protection from first starting rear decompression malfunction according to claim 5, is characterized in that: described voltage jump threshold value is 0.4U
n, wherein U
nfor voltage rating.
7. the method preventing electrical network distance protection from first starting rear decompression malfunction according to claim 1, is characterized in that: n value is 3.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510650070.6A CN105119256B (en) | 2015-10-10 | 2015-10-10 | Prevent power network distance protection first start after decompression malfunction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510650070.6A CN105119256B (en) | 2015-10-10 | 2015-10-10 | Prevent power network distance protection first start after decompression malfunction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105119256A true CN105119256A (en) | 2015-12-02 |
CN105119256B CN105119256B (en) | 2017-12-19 |
Family
ID=54667182
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510650070.6A Active CN105119256B (en) | 2015-10-10 | 2015-10-10 | Prevent power network distance protection first start after decompression malfunction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105119256B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106908649A (en) * | 2017-03-14 | 2017-06-30 | 南京保合太和电力科技有限公司 | Generator power pick-up device voltage sample system and method |
CN109599836A (en) * | 2018-12-05 | 2019-04-09 | 上海思源弘瑞自动化有限公司 | Sudden Changing Rate determines method, apparatus, equipment and medium |
CN115166603A (en) * | 2022-06-24 | 2022-10-11 | 北京天能继保电力科技有限公司 | Virtual connection judgment method and device for secondary circuit wiring terminal of power grid voltage transformer |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101707361A (en) * | 2009-11-19 | 2010-05-12 | 四川省电力公司 | Circuit weak feedback side protection self-adapting start distinguishing method |
JP2014166127A (en) * | 2013-02-28 | 2014-09-08 | Daihen Corp | Disconnection prediction device and disconnection prediction method |
CN104332967A (en) * | 2014-10-15 | 2015-02-04 | 国家电网公司 | Distance protection III segment fault opening judging method |
CN104836330A (en) * | 2015-04-16 | 2015-08-12 | 广东电网有限责任公司揭阳供电局 | Method for quickly detecting bus PT three-phase disconnection of automatic switching device of standby power supply and method for preventing maloperation of bus PT three-phase disconnection of automatic switching device of standby power supply |
CN104901284A (en) * | 2015-04-16 | 2015-09-09 | 广东电网有限责任公司揭阳供电局 | Detection method and false tripping preventive method of three-phase PT broken line of distance protector |
-
2015
- 2015-10-10 CN CN201510650070.6A patent/CN105119256B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101707361A (en) * | 2009-11-19 | 2010-05-12 | 四川省电力公司 | Circuit weak feedback side protection self-adapting start distinguishing method |
JP2014166127A (en) * | 2013-02-28 | 2014-09-08 | Daihen Corp | Disconnection prediction device and disconnection prediction method |
CN104332967A (en) * | 2014-10-15 | 2015-02-04 | 国家电网公司 | Distance protection III segment fault opening judging method |
CN104836330A (en) * | 2015-04-16 | 2015-08-12 | 广东电网有限责任公司揭阳供电局 | Method for quickly detecting bus PT three-phase disconnection of automatic switching device of standby power supply and method for preventing maloperation of bus PT three-phase disconnection of automatic switching device of standby power supply |
CN104901284A (en) * | 2015-04-16 | 2015-09-09 | 广东电网有限责任公司揭阳供电局 | Detection method and false tripping preventive method of three-phase PT broken line of distance protector |
Non-Patent Citations (2)
Title |
---|
戴运清: "110KV变电站TV断线对保护及自动装置的影响", 《广东科技》 * |
梁广宇: "PT断线与振荡闭锁", 《电力系统保护与控制》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106908649A (en) * | 2017-03-14 | 2017-06-30 | 南京保合太和电力科技有限公司 | Generator power pick-up device voltage sample system and method |
CN109599836A (en) * | 2018-12-05 | 2019-04-09 | 上海思源弘瑞自动化有限公司 | Sudden Changing Rate determines method, apparatus, equipment and medium |
CN115166603A (en) * | 2022-06-24 | 2022-10-11 | 北京天能继保电力科技有限公司 | Virtual connection judgment method and device for secondary circuit wiring terminal of power grid voltage transformer |
CN115166603B (en) * | 2022-06-24 | 2023-02-28 | 北京天能继保电力科技有限公司 | Virtual connection judgment method and device for secondary circuit wiring terminal of power grid voltage transformer |
Also Published As
Publication number | Publication date |
---|---|
CN105119256B (en) | 2017-12-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3605768B1 (en) | Safe processing method for active voltage reduction of ground fault phase of non-effective grounding system | |
Blackburn et al. | Protective relaying: principles and applications | |
CN101651329B (en) | Judgment method of line breakage of special TV for inter-turn protection of generator | |
CN106129971B (en) | A kind of dual failure fault partition method of busbar protective device breaker and system | |
CN105244859B (en) | Prevent power network distance protection first start after decompression malfunction method | |
CN112710931B (en) | Method and system for detecting earth leakage current of secondary side long-distance cable pair of alternating current system | |
CN103954879B (en) | A kind of band shunt reactor double circuit lines character method of discrimination | |
CN105006810A (en) | Fault processing method of neutral-point non-effective grounding system and corresponding processing system | |
JPH1051949A (en) | Power reception protective device | |
CN105576621B (en) | A kind of arc light protection method | |
CN105119256A (en) | Method for preventing power grid distance protection misoperation under condition of voltage loss after start | |
Jancke et al. | Series capacitors in power systems | |
CN106786368B (en) | The guard method of dry type hollow shunt reactor based on voltage-phase variable quantity | |
CN105244857B (en) | Prevent power network distance protection first start after decompression malfunction method | |
CN101505051A (en) | Turn-to-turn short circuit protection method for generator stator based on negative sequence distribution | |
CN105244858B (en) | Prevent power grid distance protection first start after decompression malfunction method | |
CN104269831B (en) | By recognizing the distance protecting method of overload and failure in a kind of transmission line of electricity | |
CN105514948A (en) | Backup automatic switching (BZT) apparatus breaker breakdown detection method and BZT apparatus | |
CN116780747B (en) | Method for improving action accuracy rate during disconnection of sectional spare power automatic switching voltage | |
CN109980612A (en) | A kind of method that line differential protection realizes weak feedback starting using zero-sequence fault component | |
CN104009453B (en) | A kind of fault detection method for micro-capacitance sensor off-grid operation situation | |
CN105552855B (en) | Prevent 3/2 mode of connection list CT saturations from causing the method for distance protection malfunction | |
CN105024366A (en) | Method for preventing false operation of distance III-section protection when power transmission line is overloaded | |
CN201590657U (en) | Microcomputer directional current quick-break bus protection device | |
CN204886421U (en) | Electric energy quality analysis device suitable for subway middling pressure power supply system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |