CN105108462B - A kind of partition board of steam turbine full circle welding method - Google Patents

A kind of partition board of steam turbine full circle welding method Download PDF

Info

Publication number
CN105108462B
CN105108462B CN201510619736.1A CN201510619736A CN105108462B CN 105108462 B CN105108462 B CN 105108462B CN 201510619736 A CN201510619736 A CN 201510619736A CN 105108462 B CN105108462 B CN 105108462B
Authority
CN
China
Prior art keywords
full circle
split
dividing plate
partition board
steam turbine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510619736.1A
Other languages
Chinese (zh)
Other versions
CN105108462A (en
Inventor
蒋超静
王斌
黄斌
欧定明
王大勇
王俊宝
张从平
彭刚
王晓东
唐绍军
王喆
赵鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DEC Dongfang Turbine Co Ltd
Original Assignee
DEC Dongfang Turbine Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DEC Dongfang Turbine Co Ltd filed Critical DEC Dongfang Turbine Co Ltd
Priority to CN201510619736.1A priority Critical patent/CN105108462B/en
Publication of CN105108462A publication Critical patent/CN105108462A/en
Application granted granted Critical
Publication of CN105108462B publication Critical patent/CN105108462B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23PMETAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
    • B23P15/00Making specific metal objects by operations not covered by a single other subclass or a group in this subclass
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F01MACHINES OR ENGINES IN GENERAL; ENGINE PLANTS IN GENERAL; STEAM ENGINES
    • F01DNON-POSITIVE DISPLACEMENT MACHINES OR ENGINES, e.g. STEAM TURBINES
    • F01D25/00Component parts, details, or accessories, not provided for in, or of interest apart from, other groups
    • F01D25/24Casings; Casing parts, e.g. diaphragms, casing fastenings

Abstract

The invention discloses a kind of partition board of steam turbine full circle welding method, including inner and outer rings full circle mode turning plate ring roughing method optimizing step, the two blade steam output side parts integral shroud tip across split is removed split stator processing optimization step, leaf grating and internal ring are carried out full circle gap assembles the assembly of outer shroud and leaf grating and internal ring to carry out the plate ring assembly technology optimization step and the main weld narrow gap welding optimization step welded using full circle mode of full circle assembling;The present invention improves dividing plate main weld quality, reduces repair rate;Dividing plate machining accuracy is made further to improve, it is ensured that the total quality of dividing plate;Effectively overcome the big problem of breach built-up welding welding capacity simultaneously, improve production efficiency.

Description

A kind of partition board of steam turbine full circle welding method
Technical field
The present invention relates to partition board of steam turbine welding field, specifically a kind of partition board of steam turbine full circle welding method.
Background technology
Narrow gap welding dividing plate is a kind of diaphragm structure forms of a large amount of employings at present.Though assembled using " full circle " mode, But it is actual in welding to be welded using " semicircle " mode, i.e.,:Dividing plate leaf grating adopts full circle welding equipment;Dividing plate plate body, outer shroud are Synthesize full circle Jing after semicircle processing to be assembled with leaf grating again.When main weld is welded using the interruption welding of narrow gap method, in The main weld at facet two ends respectively stays 20mm not weld, and treats that split heap postwelding does not weld section using the full main weld of GMAW welderings again.Due to reality After the welding of border, the starting the arc of horizontal flange weld seam is received can be different according to groove depth at arc, reserve about 20~100mm and do not weld, treat every After plate is split into two halves, then dig to fall welding line joint plane using carbon arc vapour, polished groove with grinding wheel, manual electric arc welding is by remaining weldering It is seam welding full.
Aforementioned barriers welding is primarily present three below problem:
1. groove is deeper, grinder buffing cannot completely will carbon arc vapour dig after carburized layer polishing it is clean, joint penetration is poor, Weldquality it is difficult to ensure that, easily produce pore, slag inclusion, the weld defect such as incomplete fusion;
2. breach built-up welding welding capacity is big, and one secondary dividing plate split breach of people's built-up welding needs four classes, consumes substantial amounts of manpower.
3. built-up welding amount is big and shroud is relatively thin, it is easy to draws shroud steam passage face and deforms, causes shroud vapour at split The quality problems of lower half dislocation on road face.
The content of the invention
The invention aims to solve above-mentioned technical problem, there is provided a kind of partition board of steam turbine full circle welding method, use The method can improve dividing plate main weld quality, reduce repair rate, and improve production efficiency is carried out to dividing plate main weld welding manner Optimization.
Realization the technical scheme is that:A kind of partition board of steam turbine full circle welding method, it is characterised in that including as follows Step:
A, plate ring roughing method optimizing;
a)Optimization dividing plate outer shroud roughing mode, using full circle mode turning, does not stay split line, treats main weld postwelding again Carry out separating;So as to dividing plate outer shroud ovality and dimensional accuracy is effectively ensured;
b)Optimization dividing plate internal ring roughing mode, using full circle mode turning, respectively stay at split it is a bit of do not split section, Treat that main weld postwelding carries out separating again;So as to dividing plate internal ring ovality and dimensional accuracy is effectively ensured;
B, the processing optimization of split stator;
Two blade steam output side parts integral shroud tip across split is removed, so as to after dividing plate main weldering seam welding points Upper and lower half;
C, the optimization of plate ring assembly technology;
a)Leaf grating and internal ring are carried out into the assembling of full circle gap, control pitch circle size and leaf grating ovality;
b)Assembly by outer shroud with leaf grating and internal ring carries out full circle assembling, control fit-up gap and ovality again;
D, the optimization of main weld narrow gap welding;
a)Welded using full circle mode during main weldering seam welding, do not stay split not weld section;
b)Separate inner and outer rings, so as to dividing plate is divided into upper and lower half.
The b of step A)In step by step, 30mm at split, is respectively stayed not split section.
In step B, at split, two blade steam output side parts integral shroud tip is removed using wire cutting mode.
The b of step D)In step by step, the mode that drilling main weld and sawing inner and outer rings is respectively adopted separates inside and outside Ring.
The drilling main weld is carried out on drilling machine.
The drilling internal ring is carried out on drilling machine.
The sawing outer shroud is carried out on sawing machine.
The invention has the beneficial effects as follows:
1st, the uninterrupted welding manner of main weld full circle is taken, dividing plate main weld quality is improve, is reduced repair rate.
2nd, processed by plate ring roughing mode, split stator, plate ring assembly technology and to dividing plate main weldering seam welding side Formula is optimized, and dividing plate machining accuracy is further improved, it is ensured that the total quality of dividing plate.
3rd, the big problem of breach built-up welding welding capacity is effectively overcome, production efficiency is improve.
Description of the drawings
Fig. 1 is diaphragm structure schematic diagram of the present invention;
Fig. 2 is internal ring structural representation;
Fig. 3 is split guide vane structure schematic diagram;
Fig. 4 is the split stator schematic diagram after processing.
Label in figure:1-split, 2-internal ring, 3-outer shroud, 4-main weld, 5-blade, 6-leaf grating, 7-integral shroud Tip, 8-do not split section, 9-dividing plate upper half, 10-dividing plate lower half, 11-steam output side.
Specific embodiment
As shown in Figures 1 to 4, a kind of partition board of steam turbine full circle welding method, comprises the steps:
A, plate ring roughing method optimizing;
a)3 roughing mode of optimization dividing plate outer shroud, using full circle mode turning, does not stay split line, treats 4 postwelding of main weld Carry out again separating;So as to 3 ovality of dividing plate outer shroud and dimensional accuracy is effectively ensured;
b)2 roughing mode of optimization dividing plate internal ring, using full circle mode turning, the two ends of split 1 respectively stay 30mm regardless of Section 8 is cut, treats that 4 postwelding of main weld carries out separating again;So as to 2 ovality of dividing plate internal ring and dimensional accuracy is effectively ensured;
B, the processing optimization of 1 stator of split;
Two 5 steam output sides of blade, 11 part integral shroud tip 7 across split 1 is removed using wire cutting mode, so as to Dividing plate main weld 4 divides upper and lower half after welding;
C, the optimization of plate ring assembly technology;
a)Leaf grating 6 and internal ring 2 are carried out into the assembling of full circle gap, 6 ovality of pitch circle size and leaf grating is controlled;
b)Assembly by outer shroud 3 with leaf grating 6 and internal ring 2 carries out full circle assembling, control fit-up gap and ovality again;
D, the optimization of 4 narrow gap welding of main weld;
a)Main weld 4 is welded using full circle mode when welding, and does not stay split 1 not weld section;
b)Drilling main weld 4 and internal ring 2 is respectively adopted, the mode of sawing outer shroud 3 separates inner and outer rings 2,3, so as to by dividing plate It is divided into upper and lower half 9,10.The drilling main weld 4 and internal ring 2 are carried out on drilling machine.The sawing outer shroud 3 is carried out on sawing machine.

Claims (7)

1. a kind of partition board of steam turbine full circle welding method, it is characterised in that comprise the steps:
A, plate ring roughing method optimizing;
a)Optimization dividing plate outer shroud roughing mode, using full circle mode turning, does not stay split line, treats that main weld postwelding is carried out again Separate;So as to dividing plate outer shroud ovality and dimensional accuracy is effectively ensured;
b)Optimization dividing plate internal ring roughing mode, using full circle mode turning, respectively stay at split it is a bit of do not split section, wait to lead Weld seam postwelding carries out separating again;So as to dividing plate internal ring ovality and dimensional accuracy is effectively ensured;
B, the processing optimization of split stator;
Two blade steam output side parts integral shroud tip across split is removed, to divide upper and lower after dividing plate main weldering seam welding Half;
C, the optimization of plate ring assembly technology;
a)Leaf grating and internal ring are carried out into the assembling of full circle gap, control pitch circle size and leaf grating ovality;
b)Assembly by outer shroud with leaf grating and internal ring carries out full circle assembling, control fit-up gap and ovality again;
D, the optimization of main weld narrow gap welding;
a)Welded using full circle mode during main weldering seam welding, do not stay split not weld section;
b)Separate inner and outer rings, so as to dividing plate is divided into upper and lower half.
2. partition board of steam turbine full circle welding method according to claim 1, it is characterised in that:The b of step A)Step by step In, respectively stay 30mm not split section at split.
3. partition board of steam turbine full circle welding method according to claim 1, it is characterised in that:In step B, at split Two blade steam output side parts integral shroud tip is removed using wire cutting mode.
4. partition board of steam turbine full circle welding method according to claim 1, it is characterised in that:The b of step D)Step by step In, drilling main weld is respectively adopted and internal ring, the mode of sawing outer shroud separate inner and outer rings.
5. partition board of steam turbine full circle welding method according to claim 4, it is characterised in that:The drilling main weld is in drilling machine On carry out.
6. partition board of steam turbine full circle welding method according to claim 4, it is characterised in that:The drilling internal ring is on drilling machine Carry out.
7. partition board of steam turbine full circle welding method according to claim 4, it is characterised in that:The sawing outer shroud is on sawing machine Carry out.
CN201510619736.1A 2015-09-25 2015-09-25 A kind of partition board of steam turbine full circle welding method Active CN105108462B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510619736.1A CN105108462B (en) 2015-09-25 2015-09-25 A kind of partition board of steam turbine full circle welding method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510619736.1A CN105108462B (en) 2015-09-25 2015-09-25 A kind of partition board of steam turbine full circle welding method

Publications (2)

Publication Number Publication Date
CN105108462A CN105108462A (en) 2015-12-02
CN105108462B true CN105108462B (en) 2017-04-05

Family

ID=54656686

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510619736.1A Active CN105108462B (en) 2015-09-25 2015-09-25 A kind of partition board of steam turbine full circle welding method

Country Status (1)

Country Link
CN (1) CN105108462B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109848593B (en) * 2019-03-19 2021-02-12 哈尔滨汽轮机厂有限责任公司 Method for eliminating steam turbine low-pressure hollow partition plate outer ring middle split surface closing-up deformation
CN110102970B (en) * 2019-04-25 2020-12-29 沈阳透平机械股份有限公司 Method for processing centrifugal compressor partition plate
CN110936110B (en) * 2019-11-29 2022-03-18 中国航发沈阳黎明航空发动机有限责任公司 Machining process method for semi-ring parts
CN113579661A (en) * 2021-08-23 2021-11-02 成都市新美加机械设备制造有限公司 Partition plate processing technology
CN114542213B (en) * 2022-03-09 2023-12-01 中国船舶重工集团公司第七0三研究所 Marine steam turbine baffle structure

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102019540A (en) * 2009-09-23 2011-04-20 上海电气电站设备有限公司 Manufacturing method of fixed blade welding type clapboard of steam turbine
CN102606224A (en) * 2011-12-19 2012-07-25 山东青能动力股份有限公司 Impulse steam turbine welding partition board with embedded fixed blades and assembling process of impulse steam turbine welding partition board
CN202391478U (en) * 2011-12-19 2012-08-22 山东青能动力股份有限公司 Static blade embedded type welding partition plate for impulse turbine

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE519781C2 (en) * 2001-08-29 2003-04-08 Volvo Aero Corp Process for producing a stator or rotor component

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102019540A (en) * 2009-09-23 2011-04-20 上海电气电站设备有限公司 Manufacturing method of fixed blade welding type clapboard of steam turbine
CN102606224A (en) * 2011-12-19 2012-07-25 山东青能动力股份有限公司 Impulse steam turbine welding partition board with embedded fixed blades and assembling process of impulse steam turbine welding partition board
CN202391478U (en) * 2011-12-19 2012-08-22 山东青能动力股份有限公司 Static blade embedded type welding partition plate for impulse turbine

Also Published As

Publication number Publication date
CN105108462A (en) 2015-12-02

Similar Documents

Publication Publication Date Title
CN105108462B (en) A kind of partition board of steam turbine full circle welding method
CN203972970U (en) A kind of machining PCD cutter
CN104923894B (en) Large H-shaped steel full penetration angle welding exempts from back chipping welding procedure
CN203918200U (en) A kind of copper liner
CN108942107A (en) A kind of manufacturing method of impact type waterturbine wheel
CN101885099A (en) Welding process applying submerged automatic arc welding to wind power generation tower foundation seat
CN202317168U (en) Double-drill point angle drill bit
CN106624611A (en) Thick-wall tee joint solid curve surface groove welding technology
CN203918077U (en) Novel without burr steel tube cutting machine
CN204686045U (en) A kind of PCD gang tool for machining composite material
CN103100742B (en) A kind of rough milling method of fir tree blade root
CN201895134U (en) Processing tool of rotor wheel groove profile lines
CN116604334A (en) Composite manufacturing method and system for increasing and decreasing materials of centrifugal wheel structure
CN110076443A (en) A kind of agitating friction weldering welding cleans synchronization system with weld seam
RU2524472C1 (en) Preparation of pipe or sheet edges with plating layer for butt welding (versions)
CN107803539A (en) A kind of four sword cutter with staight grooves
CN105127685B (en) Method for sealing weld of pipe end of mechanical bimetal composite pipe
CN203599607U (en) Milling cutter for side chamfer of steel plate type workpiece
CN202447756U (en) Diamond composite reamer for gear box
CN202741764U (en) Sleeve bore cutter
CN208230874U (en) A kind of machine folder compound chamfers cutter
CN206474764U (en) A kind of milling threading tool
CN106623982B (en) The processing method of the special seam allowance undercut of DK cylinder body
CN204075526U (en) The transition structure of cylindrical shell longitudinal joint not back chipping full penetration component
CN205393581U (en) Multifunctional cutting tool for lathe

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant