CN105098785A - Method for identifying whether gears of parallel main transformers of AVC system are consistent - Google Patents

Method for identifying whether gears of parallel main transformers of AVC system are consistent Download PDF

Info

Publication number
CN105098785A
CN105098785A CN201510523875.4A CN201510523875A CN105098785A CN 105098785 A CN105098785 A CN 105098785A CN 201510523875 A CN201510523875 A CN 201510523875A CN 105098785 A CN105098785 A CN 105098785A
Authority
CN
China
Prior art keywords
main
idle
criterion
epsiv
main transformers
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510523875.4A
Other languages
Chinese (zh)
Other versions
CN105098785B (en
Inventor
杨洛
陆进军
杜磊
黄华
陈天华
钱玉妹
李烽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Jiangsu Electric Power Co Ltd
Nari Technology Co Ltd
NARI Nanjing Control System Co Ltd
Nantong Power Supply Co of Jiangsu Electric Power Co Ltd
Original Assignee
State Grid Jiangsu Electric Power Co Ltd
Nari Technology Co Ltd
NARI Nanjing Control System Co Ltd
Nantong Power Supply Co of Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Jiangsu Electric Power Co Ltd, Nari Technology Co Ltd, NARI Nanjing Control System Co Ltd, Nantong Power Supply Co of Jiangsu Electric Power Co Ltd filed Critical State Grid Jiangsu Electric Power Co Ltd
Priority to CN201510523875.4A priority Critical patent/CN105098785B/en
Publication of CN105098785A publication Critical patent/CN105098785A/en
Application granted granted Critical
Publication of CN105098785B publication Critical patent/CN105098785B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a method for identifying whether the gears of parallel main transformers of an AVC system are consistent, comprising the following steps: reactive power of two main transformers running in parallel is sampled and analyzed multiple times, the reactive power ratio of the two main transformers is calculated, and abnormal values are eliminated; whether impedance parameters are filled in correctly is inspected; once that the voltage is abnormal is detected, the AVC system sends a voltage regulation command to the two main transformers running in parallel, and records the reactive power of the two main transformers; whether there is change in gear is judged, and that the gears of the two parallel main transformers are consistent is determined if there is change in gear; or a composite criterion is implemented further, and whether there is change in field gear is judged based on time; if that there is change in field gear is decided according to the composite criterion, that the gear adjustment succeeds is determined, namely, the gears of the two parallel main transformers are consistent, and a voltage regulation command is no longer sent, or there is a need to continue sending a voltage regulation command. The problem that whether gear adjustment succeeds or not is judged only based on a single criterion and is not reliable in the voltage regulation process of AVC is solved effectively.

Description

The discrimination method that whether consistent AVC system main shift arranged side by side is
Technical field
The present invention relates to the discrimination method that whether consistent a kind of AVC system main shift arranged side by side is, belong to technical field of power system operation control.
Background technology
In AVC (AutomaticVoltageControl, automatism voltage control) system, transformer is the capital equipment of regulation voltage.For the consideration of reliability and economy, two transformers run mainly with juxtaposition.AVC system is once detect that voltage is defective, will pressure regulation order be sent out to the transformer of paired running simultaneously, once the tap change telemetry intelligence (TELINT) of transformer returns to AVC system, then can confirm this pressure regulation event success, otherwise, continuation is sent out pressure regulation order to the transformer of paired running by AVC system, until AVC is delivered in regulation stall change remote measurement.
But when some automatic channel, front end processor situation are bad, after AVC system sends pressure regulation order to parallel transformer, the change information of gear can not in time on give, such as there is A, the transformer of B two paired runnings, after AVC sends out pressure regulation order to these two transformers, wherein transformer A transfers the files successfully, the change information of its gear also can be sent to main website end timely, and transformer B may slow in one's movements due to primary equipment, tunnel condition is bad or the reason such as load tap changer tripping, the change information of gear in for a long time cannot on give.So AVC system will think that transformer B transfers the files unsuccessful in this event of transferring the files, in order to avoid the harm that circulating power brings to transformer, AVC can continue to repeat to send out last pressure regulation order to the transformer B of failure of transferring the files, make B action again, so repeatedly regulate, until action frequency is finished.
The pattern again sending pressure regulation order is ensure main transformer paired running reliable, effective for the situation of load tap changer tripping.But when primary equipment is slow in one's movements, tunnel condition is bad time, this method is but incorrect.In fact, when primary equipment is slow in one's movements, time tunnel condition is bad, the gear of transformer B changes, A, B has been in the consistent running status of gear, only gear change information delay delivers to AVC system, if AVC system only sends out pressure regulation order according to gear change information as successfully foundation of transferring the files again, by causing, the transformer gear of two paired runnings is inconsistent, if be in this state for a long time, the operation of the system of giving and fail safe are brought great hidden danger, also be easy to the fault causing on-load voltage regulating switch simultaneously, reduce transformer life.
Paired running transformer whether transfer the files successfully with and paired running transformer transfer the files after the conforming judgement of gear be inherently a problem, from the above analysis, the transfer the files method of success or not of traditional judgement is defective, needs to propose new criterion and comes.
Summary of the invention
The object of the invention is to overcome deficiency of the prior art, the discrimination method that whether consistent a kind of AVC system main shift arranged side by side is is provided, in solution prior art, two wrong shelves of transformer run and bring very big hidden danger large to system, also easily cause the fault of voltage adjustment of on-load switch simultaneously, reduce the technical problem of transformer life.
For solving the problems of the technologies described above, the technical solution adopted in the present invention is: the discrimination method that whether consistent AVC system main shift arranged side by side is, comprises the steps:
Step one: carry out multiple repairing weld analysis to the idle of two paired running main transformers, calculates the idle ratio of two main transformers, and rejecting abnormalities value; By the idle ratio of two main transformers compared with the impedance inverse ratio of two main transformers, whether fill in correctly to check impedance parameter;
Step 2: once detect that voltage is abnormal, AVC sends pressure regulation order to two of paired running main transformers:
For two winding main transformers, AVC, to before main transformer pressure regulation, records the idle situation of two main transformers;
For three winding main transformer, AVC to before main transformer pressure regulation, record main transformer low-pressure side respectively according to the difference of operational mode or medium voltage side idle;
Step 3: judge whether gear changes, if had, then represent that this transfers the files successfully, namely two main shifts arranged side by side are consistent; Otherwise, perform compound criterion further, and binding time judges whether on-the-spot gear changes;
Step 4: change if go out on-the-spot gear by compound Criteria Decision, then show that this transfers the files successfully, and namely two main shifts arranged side by side are consistent, no longer send pressure regulation order, otherwise, need to continue to send out pressure regulation order.
Further, the concrete steps of step one are as follows:
Step 101): for main transformer A and the main transformer B of two paired runnings, put into operation the starting stage in AVC system, record the idle Q of m time of two main transformer the same sides respectively a1, Q a2..., Q am, Q b1, Q b2..., Q bm, calculate respectively ratio R n, wherein n=1,2 ..., m, and R naverage E (R) and variance V (R), remove exceptional value [E (R)-3*V (R), E (R)+3*V (R)] R outward n, and then computation of mean values E (R) ';
Step 102): the impedance obtaining two main transformers from SCADA database, calculates the impedance inverse ratio of two main transformers
Step 103): a given threshold epsilon 1, compare E (R) ' with might as well establish if then think that the impedance parameter of SCADA database is correct, record otherwise idle m time of real time record two main transformers, calculate average, after rejecting abnormalities value, retain this mean value in real time E ( Q A n Q B n ) .
Preferably, when carrying out idle collection to two main transformers, select the idle of the low-pressure side in not same date different moment, number of times m is greater than 30 times.
Further, the concrete steps of step 2 are as follows:
Step 201): once detect that voltage is abnormal, AVC sends pressure regulation order to respectively main transformer A, main transformer B, and records the idle Q before two main transformer pressure regulation a0and Q b0;
Step 202): the gear k obtaining two main transformers in real time from SCADA a, k b, idle Q a, Q b, and record two main transformers and whether be still in paired running;
Step 203): if k a=k b, represent and gear send successfully, then think that pressure regulation is successful, otherwise, represent and gear send failure.
Further, for two two winding main transformers, if Q a>=Q b, | Q a-Q a0|>=| Q b-Q b0|, described in step 3, compound criterion is as follows:
Criterion 1: given threshold epsilon 2, ε 3, when impedance parameter is correct, judge 1 &le; Q A Q B &le; ( 1 + &epsiv; 2 ) Q A 0 Q A 0 1 < Q A Q B &le; ( 1 + &epsiv; 3 ) X B X A Whether set up; When impedance parameter is filled in wrong, judge 1 &le; Q A Q B &le; ( 1 + &epsiv; 2 ) Q A 0 Q A 0 1 < Q A Q B &le; ( 1 + &epsiv; 3 ) E ( Q A Q B ) Whether set up;
Criterion 2: given threshold epsilon 4, judge whether set up;
Criterion 3: given threshold epsilon 5, Bu Fangshe ( n Q A + n Q B ) &GreaterEqual; ( n Q A 0 + n Q B 0 ) , Judge 1 &le; n Q A + n Q B n Q A 0 + n Q B 0 &le; ( 1 + &epsiv; 5 ) Whether set up;
Wherein: Q a0and Q b0idle for front two main transformers of pressure regulation, Q a, Q bfor two main transformers idle of Real-time Obtaining, n is integer, n ∈ [2,6];
For two three winding main transformers, be divided into medium voltage side side by side/the equal paired running of low-pressure side split operation, medium voltage side and low-pressure side two kinds of operational modes:
When adopt medium voltage side side by side/low-pressure side split operation mode time, if Q a1>=Q b1, | Q a1-Q a10|>=| Q b1-Q b10| described in step 3, compound criterion is as follows:
Criterion 1: given threshold epsilon 6, judge whether set up;
Criterion 2: given threshold epsilon 7, judge whether set up;
Criterion 3: given threshold epsilon 7, ε 8, Bu Fangshe ( n Q A 2 + n Q B 2 ) &GreaterEqual; ( n Q A 20 + n Q B 20 ) , Judge 1 &le; n Q A 1 + n Q B 1 n Q A 10 + n Q B 10 &le; ( 1 + &epsiv; 7 ) 1 &le; n Q A 2 + n Q B 2 n Q A 20 + n Q B 20 &le; ( 1 + &epsiv; 8 ) Whether set up;
Wherein: Q a10, Q b10idle for front two the main transformer medium voltage sides of pressure regulation; Q a1, Q b1for two main transformer medium voltage sides idle of Real-time Obtaining;
When adopting medium voltage side and the equal paired running mode of low-pressure side, if Q a1>=Q b1, Q a2>=Q b2, | Q a1-Q a10|>=| Q b1-Q b10|, | Q a2-Q a20|>=| Q b2-Q b20|, described in step 3, compound criterion is as follows:
Criterion 1: given threshold epsilon 9, ε 10, judge 1 &le; Q A 1 Q B 1 &le; ( 1 + &epsiv; 9 ) Q A 10 Q A 10 1 < Q A 2 Q B 2 &le; ( 1 + &epsiv; 10 ) Q A 20 Q B 20 Whether set up;
Criterion 2: given threshold epsilon 11, ε 12, judge | Q A 1 - Q A 10 Q B 1 - Q B 10 | < ( 1 + &epsiv; 11 ) | Q A 2 - Q A 20 | | Q B 2 - Q B 20 | &le; ( 1 + &epsiv; 12 ) Whether set up;
Criterion 3: given threshold epsilon 13, ε 14, Bu Fangshe ( n Q A 2 + n Q B 2 ) &GreaterEqual; ( n Q A 20 + n Q B 20 ) , Judge 1 &le; n Q A 1 + n Q B 1 n Q A 10 + n Q B 10 &le; ( 1 + &epsiv; 13 ) 1 &le; n Q A 2 + n Q B 2 n Q A 20 + n Q B 20 &le; ( 1 + &epsiv; 14 ) Whether set up;
Wherein: Q a20, Q b20idle for front two the main transformer low-pressure sides of pressure regulation; Q a2, Q b2for two main transformer low-pressure sides idle of Real-time Obtaining;
Send out in the s second after pressure regulation order to parallel transformer from AVC, if three compound criterions meet all simultaneously, then can think that transformer is transferred the files successfully above, but gear telemetry intelligence (TELINT) in time on give; If s did not all meet after second in these three criterions, then two transformer mistake gears are described, there is circulation, can be judged as transferring the files unsuccessfully, the span of s is: 180 ~ 360 seconds.
Compared with prior art, the beneficial effect that the present invention reaches is: utilize the transformer of paired running transfer the files before and after idlely judge whether to exist circulation and then obtain the whether consistent information of gear, introduce the idle measurement of redundancy in transformer station, by the compound criterion of idle/impedance, even if when guaranteeing to send on gear is not timely, AVC system also can analyze be because gear change information in time on to return be load tap changer tripping, and then send out make correct decision-making, AVC can be strengthened to transfer the files the correctness of decision logic, thus the mistake avoiding transformer to cause because of toning gear runs,
This method mathematical derivation is strict, algorithm there is clear and definite physical significance, effectively solve in AVC pressure regulation process the single insecure defect of successful basis for estimation of transferring the files;
The present invention is not only applicable to two-winding transformer, also can make correct judgement reliably for the three-winding transformer of different running method (medium voltage side side by side, low-pressure side division/medium voltage side is arranged side by side, low-pressure side is arranged side by side).
Embodiment
The present invention proposes to utilize the idle measurement/impedance of redundancy to judge that the conforming method of transformer gear is based on SCADA (SupervisoryControlAndDataAcquisition, data acquisition and supervisor control) system, basic premise gathers idle and information that is gear second every T.Core concept of the present invention be utilize the transformer of paired running transfer the files before and after idlely judge whether to exist circulation and then obtain the whether consistent information of gear.
The invention will be further described below, and following examples only for technical scheme of the present invention is clearly described, and can not limit the scope of the invention with this.
The discrimination method that whether consistent AVC system main shift arranged side by side is, comprises the steps:
Step one: carry out multiple repairing weld analysis to the idle of two paired running main transformers, calculates the idle ratio of two main transformers, and rejecting abnormalities value; By the idle ratio of two main transformers compared with the impedance inverse ratio of two main transformers, whether fill in correctly to check impedance parameter.Concrete steps are as follows:
Step 101): for main transformer A and the main transformer B of two paired runnings, put into operation the starting stage in AVC system, record the idle Q of m time of two main transformer the same sides respectively a1, Q a2..., Q am, Q b1, Q b2..., Q bm, calculate respectively ratio R n, and R naverage E (R) and variance V (R), remove exceptional value [E (R)-3*V (R), E (R)+3*V (R)] R outward n, and then computation of mean values E (R) '; Wherein n=1,2 ..., m, number of times m is greater than 30 times.When idle collection is carried out to two main transformers, select the idle of the low-pressure side in not same date different moment.
Step 102): the impedance obtaining two main transformers from SCADA database, calculates the impedance inverse ratio of two main transformers
Step 103): a given threshold epsilon 1, compare E (R) ' with might as well establish if then think that the impedance parameter of SCADA database is correct, record otherwise idle m time of real time record two main transformers, calculate average, after rejecting abnormalities value, retain this mean value in real time E ( Q A n Q B n ) .
Step 2: for two winding main transformers: once detect that voltage is abnormal, AVC sends pressure regulation order to two of paired running main transformers, records the idle Q before two main transformer pressure regulation a0and Q b0; The gear k of two main transformers is obtained in real time from SCADA a, k b, idle Q a, Q b, and record two main transformers and whether be still in paired running; If k a=k b, represent and gear send successfully, then think that pressure regulation is successful, otherwise, represent and gear send failure.
For three winding main transformer: once detect that voltage is abnormal, AVC sends pressure regulation orders to two of paired running main transformers, record main transformer low-pressure side respectively according to the difference of operational mode or medium voltage side idle, be specially:
When two three winding main transformers adopt medium voltage sides side by side/low-pressure side split operation mode time, after AVC sends pressure regulation order to main transformer arranged side by side, the gear k of Real-time Obtaining two main transformers a, k b, medium voltage side is idle Q a1, Q b1, might as well Q be established a1>=Q b1, | Q a1-Q a10|>=| Q b1-Q b10|.If k a=k b, be considered as gear successfully on give, then think pressure regulation success, otherwise, enter step 3 and perform compound criterion;
When two three winding main transformer medium voltage sides, low-pressure side all adopt paired running mode, after AVC sends pressure regulation order to main transformer arranged side by side, the gear k of Real-time Obtaining two transformers a, k b, medium voltage side is idle Q a1, Q b1, low-pressure side is idle Q a2, Q b2, and check whether two transformers are in paired running.If k a=k b, be considered as gear successfully on give, then think pressure regulation success, otherwise, enter step 3 and perform compound criterion.
Step 3: judge whether gear changes, if had, then represent that this transfers the files successfully, namely two main shifts arranged side by side are consistent; Otherwise, perform compound criterion further, and binding time judges whether on-the-spot gear changes.
For two two winding main transformers, if Q a>=Q b, | Q a-Q a0|>=| Q b-Q b0|, compound criterion is as follows:
Criterion 1: given threshold epsilon 2, ε 3, when impedance parameter is correct, judge 1 &le; Q A Q B &le; ( 1 + &epsiv; 2 ) Q A 0 Q A 0 1 < Q A Q B &le; ( 1 + &epsiv; 3 ) X B X A Whether set up; When impedance parameter is filled in wrong, judge 1 &le; Q A Q B &le; ( 1 + &epsiv; 2 ) Q A 0 Q A 0 1 < Q A Q B &le; ( 1 + &epsiv; 3 ) E ( Q A Q B ) Whether set up;
Criterion 2: given threshold epsilon 4, judge whether set up;
Criterion 3: given threshold epsilon 5, Bu Fangshe ( n Q A + n Q B ) &GreaterEqual; n Q A 0 + n Q B 0 , Judge 1 &le; n Q A + n Q B n Q A 0 + n Q B 0 &le; ( 1 + &epsiv; 5 ) Whether set up;
Wherein: Q a0and Q b0idle for front two main transformers of pressure regulation, Q a, Q bfor two main transformers idle of Real-time Obtaining, n is integer, n ∈ [2,6].
For two three winding main transformers, have medium voltage side side by side/low-pressure side split operation mode and medium voltage side, the equal paired running mode of low-pressure side, respectively the compound criterion of two kinds of operational modes is described in detail below:
When adopt medium voltage side side by side/low-pressure side split operation mode time, if Q a1>=Q b1, | Q a1-Q a10|>=| Q b1-Q b10| described in step 3, compound criterion is as follows:
Criterion 1: given threshold epsilon 6, judge whether set up;
Criterion 2: given threshold epsilon 7, judge whether set up;
Criterion 3: given threshold epsilon 7, ε 8, Bu Fangshe ( n Q A 2 + n Q B 2 ) &GreaterEqual; ( n Q A 20 + n Q B 20 ) , Judge 1 &le; n Q A 1 + n Q B 1 n Q A 10 + n Q B 10 &le; ( 1 + &epsiv; 7 ) 1 &le; n Q A 2 + n Q B 2 n Q A 20 + n Q B 20 &le; ( 1 + &epsiv; 8 ) Whether set up;
Wherein: Q a10, Q b10idle for front two the main transformer medium voltage sides of pressure regulation; Q a1, Q b1for two main transformer medium voltage sides idle of Real-time Obtaining.
When adopting medium voltage side and the equal paired running mode of low-pressure side, if Q a1>=Q b1, Q a2>=Q b2, | Q a1-Q a10|>=| Q b1-Q b10|, | Q a2-Q a20|>=| Q b2-Q b20|, described in step 3, compound criterion is as follows:
Criterion 1: given threshold epsilon 9, ε 10, judge 1 &le; Q A 1 Q B 1 &le; ( 1 + &epsiv; 9 ) Q A 10 Q A 10 1 < Q A 2 Q B 2 &le; ( 1 + &epsiv; 10 ) Q A 20 Q B 20 Whether set up;
Criterion 2: given threshold epsilon 11, ε 12, judge | Q A 1 - Q A 10 Q B 1 - Q B 10 | < ( 1 + &epsiv; 11 ) | Q A 2 - Q A 20 | | Q B 2 - Q B 20 | &le; ( 1 + &epsiv; 12 ) Whether set up;
Criterion 3: given threshold epsilon 13, ε 14, Bu Fangshe ( n Q A 2 + n Q B 2 ) &GreaterEqual; ( n Q A 20 + n Q B 20 ) , Judge 1 &le; n Q A 1 + n Q B 1 n Q A 10 + n Q B 10 &le; ( 1 + &epsiv; 13 ) 1 &le; n Q A 2 + n Q B 2 n Q A 20 + n Q B 20 &le; ( 1 + &epsiv; 14 ) Whether set up;
Wherein: Q a20, Q b20idle for front two the main transformer low-pressure sides of pressure regulation; Q a2, Q b2for two main transformer low-pressure sides idle of Real-time Obtaining;
Send out in the s second after pressure regulation order to parallel transformer from AVC, if three compound criterions meet all simultaneously, then can think that transformer is transferred the files successfully above, but gear telemetry intelligence (TELINT) in time on give; If s did not all meet after second in these three criterions, then two transformer mistake gears are described, there is circulation, can be judged as transferring the files unsuccessfully, the span of s is: 180 ~ 360 seconds, preferably 240 seconds.
Step 4: change if go out on-the-spot gear by compound Criteria Decision, then show that this transfers the files successfully, and namely two main shifts arranged side by side are consistent, no longer send pressure regulation order, otherwise, need to continue to send out pressure regulation order.
The above is only the preferred embodiment of the present invention; it should be pointed out that for those skilled in the art, under the prerequisite not departing from the technology of the present invention principle; can also make some improvement and distortion, these improve and distortion also should be considered as protection scope of the present invention.

Claims (5)

  1. The discrimination method that whether consistent 1.AVC system main shift arranged side by side is, is characterized in that, comprise the steps:
    Step one: carry out multiple repairing weld analysis to the idle of two paired running main transformers, calculates the idle ratio of two main transformers, and rejecting abnormalities value; By the idle ratio of two main transformers compared with the impedance inverse ratio of two main transformers, whether fill in correctly to check impedance parameter;
    Step 2: once detect that voltage is abnormal, AVC sends pressure regulation order to two of paired running main transformers:
    For two winding main transformers, AVC, to before main transformer pressure regulation, records the idle situation of two main transformers;
    For three winding main transformer, AVC to before main transformer pressure regulation, record main transformer low-pressure side respectively according to the difference of operational mode or medium voltage side idle;
    Step 3: judge whether gear changes, if had, then represent that this transfers the files successfully, namely two main shifts arranged side by side are consistent; Otherwise, perform compound criterion further, and binding time judges whether on-the-spot gear changes;
    Step 4: change if go out on-the-spot gear by compound Criteria Decision, then show that this transfers the files successfully, and namely two main shifts arranged side by side are consistent, no longer send pressure regulation order, otherwise, need to continue to send out pressure regulation order.
  2. 2. the discrimination method that whether consistent AVC system according to claim 1 main shift arranged side by side is, it is characterized in that, the concrete steps of step one are as follows:
    Step 101): for main transformer A and the main transformer B of two paired runnings, put into operation the starting stage in AVC system, record the idle Q of m time of two main transformer the same sides respectively a1, Q a2..., Q am, Q b1, Q b2..., Q bm, calculate respectively ratio R n, wherein n=1,2 ..., m, and R naverage E (R) and variance V (R), remove exceptional value [E (R)-3*V (R), E (R)+3*V (R)] R outward n, and then computation of mean values E (R) ';
    Step 102): the impedance obtaining two main transformers from SCADA database, calculates the impedance inverse ratio of two main transformers
    Step 103): a given threshold epsilon 1, compare E (R) ' with might as well establish if then think that the impedance parameter of SCADA database is correct, record otherwise idle m time of real time record two main transformers, calculate average, after rejecting abnormalities value, retain this mean value in real time
  3. 3. the discrimination method that whether consistent AVC system according to claim 2 main shift arranged side by side is, is characterized in that, when carrying out idle collection to two main transformers, select the idle of the low-pressure side in not same date different moment, number of times m is greater than 30 times.
  4. 4. the discrimination method that whether consistent AVC system according to claim 1 main shift arranged side by side is, it is characterized in that, the concrete steps of step 2 are as follows:
    Step 201): once detect that voltage is abnormal, AVC sends pressure regulation order to respectively main transformer A, main transformer B, and records the idle Q before two main transformer pressure regulation a0and Q b0;
    Step 202): the gear k obtaining two main transformers in real time from SCADA a, k b, idle Q a, Q b, and record two main transformers and whether be still in paired running;
    Step 203): if k a=k b, represent and gear send successfully, then think that pressure regulation is successful, otherwise, represent and gear send failure.
  5. 5. the discrimination method that whether consistent AVC system according to claim 1 main shift arranged side by side is, is characterized in that,
    For two two winding main transformers, if Q a>=Q b, | Q a-Q a0|>=| Q b-Q b0|, described in step 3, compound criterion is as follows:
    Criterion 1: given threshold epsilon 2, ε 3, when impedance parameter is correct, judge 1 &le; Q A Q B &le; ( 1 + &epsiv; 2 ) Q A 0 Q A 0 1 < Q A Q B &le; ( 1 + &epsiv; 3 ) X B X A Whether set up; When impedance parameter is filled in wrong, judge 1 &le; Q A Q B &le; ( 1 + &epsiv; 2 ) Q A 0 Q A 0 1 < Q A Q B &le; ( 1 + &epsiv; 3 ) E ( Q A Q B ) Whether set up;
    Criterion 2: given threshold epsilon 4, judge whether set up;
    Criterion 3: given threshold epsilon 5, Bu Fangshe ( n Q A + n Q B ) &GreaterEqual; ( n Q A 0 + n Q B 0 ) , Judge 1 &le; n Q A + n Q B n Q A 0 + n Q B 0 &le; ( 1 + &epsiv; 5 ) Whether set up;
    Wherein: Q a0and Q b0idle for front two main transformers of pressure regulation, Q a, Q bfor two main transformers idle of Real-time Obtaining, n is integer, n ∈ [2,6];
    For two three winding main transformers, be divided into medium voltage side side by side/the equal paired running of low-pressure side split operation, medium voltage side and low-pressure side two kinds of operational modes:
    When adopt medium voltage side side by side/low-pressure side split operation mode time, if Q a1>=Q b1, | Q a1-Q a10|>=| Q b1-Q b10| described in step 3, compound criterion is as follows:
    Criterion 1: given threshold epsilon 6, judge whether set up;
    Criterion 2: given threshold epsilon 7, judge whether set up;
    Criterion 3: given threshold epsilon 7, ε 8, Bu Fangshe
    ( n Q A 2 + n Q B 2 ) &GreaterEqual; ( n Q A 20 + n Q B 20 ) , Judge 1 &le; n Q A 1 + n Q B 1 n Q A 10 + n Q B 10 &le; ( 1 + &epsiv; 7 ) 1 &le; n Q A 2 + n Q B 2 n Q A 20 + n Q B 20 &le; ( 1 + &epsiv; 8 ) Whether set up;
    Wherein: Q a10, Q b10idle for front two the main transformer medium voltage sides of pressure regulation; Q a1, Q b1for two main transformer medium voltage sides idle of Real-time Obtaining;
    When adopting medium voltage side and the equal paired running mode of low-pressure side, if Q a1>=Q b1, Q a2>=Q b2, | Q a1-Q a10|>=| Q b1-Q b10|, | Q a2-Q a20|>=| Q b2-Q b20|, described in step 3, compound criterion is as follows:
    Criterion 1: given threshold epsilon 9, ε 10, judge 1 &le; Q A 1 Q B 1 &le; ( 1 + &epsiv; 9 ) Q A 10 Q A 10 1 &le; Q A 2 Q B 2 &le; ( 1 + &epsiv; 10 ) Q A 20 Q B 20 Whether set up;
    Criterion 2: given threshold epsilon 11, ε 12, judge | Q A 1 - Q A 10 Q B 1 - Q B 10 | < ( 1 + &epsiv; 11 ) | Q A 2 - Q A 20 | | Q B 2 - Q B 20 | &le; ( 1 + &epsiv; 12 ) Whether set up;
    Criterion 3: given threshold epsilon 13, ε 14, Bu Fangshe
    ( n Q A 2 + n Q B 2 ) &GreaterEqual; ( n Q A 20 + n Q B 20 ) , Judge 1 &le; n Q A 1 + n Q B 1 n Q A 10 + n Q B 10 &le; ( 1 + &epsiv; 13 ) 1 &le; n Q A 2 + n Q B 2 n Q A 20 + n Q B 20 &le; ( 1 + &epsiv; 14 ) Whether set up;
    Wherein: Q a20, Q b20idle for front two the main transformer low-pressure sides of pressure regulation; Q a2, Q b2for two main transformer low-pressure sides idle of Real-time Obtaining;
    Send out in the s second after pressure regulation order to parallel transformer from AVC, if three compound criterions meet all simultaneously, then can think that transformer is transferred the files successfully above, but gear telemetry intelligence (TELINT) in time on give; If s did not all meet after second in these three criterions, then two transformer mistake gears are described, there is circulation, can be judged as transferring the files unsuccessfully, the span of s is: 180 ~ 360 seconds.
CN201510523875.4A 2015-08-24 2015-08-24 The whether consistent discrimination method of AVC systems main shift arranged side by side Active CN105098785B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510523875.4A CN105098785B (en) 2015-08-24 2015-08-24 The whether consistent discrimination method of AVC systems main shift arranged side by side

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510523875.4A CN105098785B (en) 2015-08-24 2015-08-24 The whether consistent discrimination method of AVC systems main shift arranged side by side

Publications (2)

Publication Number Publication Date
CN105098785A true CN105098785A (en) 2015-11-25
CN105098785B CN105098785B (en) 2017-08-29

Family

ID=54578652

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510523875.4A Active CN105098785B (en) 2015-08-24 2015-08-24 The whether consistent discrimination method of AVC systems main shift arranged side by side

Country Status (1)

Country Link
CN (1) CN105098785B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105720584A (en) * 2016-04-13 2016-06-29 国电南瑞科技股份有限公司 Integer programming based reactive power instruction optimal allocation method for province dispatcher during automatic volume control (AVC) province and local coordinated control process
CN111327059A (en) * 2020-03-31 2020-06-23 福建福清核电有限公司 Control method for increasing and decreasing magnetic relay contact adhesion prevention of automatic voltage control system
CN114325067A (en) * 2021-11-19 2022-04-12 国网新疆电力有限公司电力科学研究院 Rapid judgment and detection method and detection device for circulation between parallel operation transformers

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102761128A (en) * 2011-04-25 2012-10-31 河海大学 On-line coordinated automatic control method for economical operation and reactive power optimization of transformer
CN103312040A (en) * 2013-07-02 2013-09-18 国家电网公司 Control method for improving reliability of AVC (Automatic Voltage Control) system of electric power monitoring center

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102761128A (en) * 2011-04-25 2012-10-31 河海大学 On-line coordinated automatic control method for economical operation and reactive power optimization of transformer
CN103312040A (en) * 2013-07-02 2013-09-18 国家电网公司 Control method for improving reliability of AVC (Automatic Voltage Control) system of electric power monitoring center

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黎少楠 等: "有载调压变压器并列运行控制技术", 《电力建设》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105720584A (en) * 2016-04-13 2016-06-29 国电南瑞科技股份有限公司 Integer programming based reactive power instruction optimal allocation method for province dispatcher during automatic volume control (AVC) province and local coordinated control process
CN105720584B (en) * 2016-04-13 2018-06-29 国电南瑞科技股份有限公司 A kind of AVC saves ground and coordinates the optimum allocation method that the province based on integer programming during controlling adjusts reactive command
CN111327059A (en) * 2020-03-31 2020-06-23 福建福清核电有限公司 Control method for increasing and decreasing magnetic relay contact adhesion prevention of automatic voltage control system
CN114325067A (en) * 2021-11-19 2022-04-12 国网新疆电力有限公司电力科学研究院 Rapid judgment and detection method and detection device for circulation between parallel operation transformers
CN114325067B (en) * 2021-11-19 2023-10-20 国网新疆电力有限公司电力科学研究院 Method and device for rapidly judging and detecting circulating current between parallel operation transformers

Also Published As

Publication number Publication date
CN105098785B (en) 2017-08-29

Similar Documents

Publication Publication Date Title
CN107194476B (en) aging prevention maintenance strategy making method of transformer based on half Markov chain
CN105098785A (en) Method for identifying whether gears of parallel main transformers of AVC system are consistent
CN103048036B (en) A kind of on-line monitoring method of on-load tap changers of transformers running status
CN106208049B (en) Practical method for estimating simple state of power distribution network
CN102195291B (en) Automatically identifying control method for main transformer overload joining-cutting load based on running mode
CN101431238A (en) Power distribution network power supply capacity evaluation method considering N-1 criterion
CN105527541B (en) A method of judgement distribution line failure tripping
CN104198884A (en) Differential principle based large-scale power grid intelligent trouble diagnosis method
CN101917063A (en) Method and system for automatically switching master station-centralized spare power source
CN105244865A (en) Power system safe and stable operation control method
WO2016058435A1 (en) Winding state evaluation method under external fault of transformer
CN103048567B (en) Method for judging parallel reactor-containing transmission line malfunction properties based on wave form estimation
Guan et al. Assessing circuit breaker life cycle using condition-based data
CN106710164A (en) Power distribution network fault early warning method aiming at multiple factors
CN107453354A (en) A kind of weak link recognition methods of power distribution network
CN105911424A (en) Identification method based on fault indicator false alarm signal
CN107067126A (en) It is a kind of based on power flow transfer than thermally-stabilised key transmission channel recognition method
CN106602530A (en) Anti-misoperation method and anti-misoperation system for one-tower double-circuit zero-sequence pilot protection
CN106487004B (en) One electrical secondary system of intelligent substation runs hidden danger Intelligent drainage checking method
CN113471864A (en) Transformer substation secondary equipment field maintenance device and method
CN104537161A (en) Medium voltage distribution network diagnostic analysis method based on power supply safety standards
CN117420380A (en) Power distribution network fault early warning and handling method and system
CN107730070A (en) A kind of intelligent substation relay protection system repair method based on status monitoring
CN104036131A (en) Transformer aging fault rate estimation method
CN110021933B (en) Power information system control function reliability assessment method considering component faults

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant