CN105084220B - A kind of double case synchronization handling systems of container - Google Patents

A kind of double case synchronization handling systems of container Download PDF

Info

Publication number
CN105084220B
CN105084220B CN201510471847.2A CN201510471847A CN105084220B CN 105084220 B CN105084220 B CN 105084220B CN 201510471847 A CN201510471847 A CN 201510471847A CN 105084220 B CN105084220 B CN 105084220B
Authority
CN
China
Prior art keywords
arm
jacking
frame
container
underarm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510471847.2A
Other languages
Chinese (zh)
Other versions
CN105084220A (en
Inventor
朱正中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Topsun Logistic Control Co Ltd
Original Assignee
Zhejiang Topsun Logistic Control Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Topsun Logistic Control Co Ltd filed Critical Zhejiang Topsun Logistic Control Co Ltd
Priority to CN201510471847.2A priority Critical patent/CN105084220B/en
Publication of CN105084220A publication Critical patent/CN105084220A/en
Application granted granted Critical
Publication of CN105084220B publication Critical patent/CN105084220B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C19/00Cranes comprising trolleys or crabs running on fixed or movable bridges or gantries

Abstract

The invention provides a kind of double case synchronization handling systems of container, belong to field of mechanical technique.It solves existing container crane in loading and unloading container, and the operating space of arm can produce interference with cable, and the arm of container crane is difficult the top for extending container, causes the technical problems such as unloading operation is troublesome, safety coefficient is low.This pair of case synchronization handling system includes frame, jacking arm two and two jacking arms one for being arranged on jacking arm two both sides, two jacking arms one be arranged in parallel with jacking arm two and can stretch out frame the same side, mobile support is equipped between jacking arm two and each jacking arm one, mobile bracket slide is connected in frame and can stretch out frame side, two jacking arms one can be by translating the hole for hoist clamping with container, and the front end of jacking arm two is parallel to each other with two and spaced connection-peg.The present invention can load and unload two containers simultaneously and handling are more stable, safe.

Description

A kind of double case synchronization handling systems of container
Technical field
The invention belongs to field of mechanical technique, it is related to a kind of double case synchronization handling systems of container.
Background technology
Container, English name container.Refer to have some strength, rigidity and specification specialize in be used in turn it is large-scale Goods container.It using container transshipment goods, can directly be freighted in the warehouse of consignor, transport to the warehouse unloading of consignee, in Way is more changed trains, ship time, is changed the outfit without goods is taken out out of case.Therefore container is a kind of great invention.Container is maximum Success a whole set of transportation system for being the standardization of its product and thus establishing.It can allow the Pang of tens tons of a load-carrying So big thing realizes standardization, and be done step-by-step based on this in global range ship, harbour, course line, highway, transfer Stand, the logistics system that bridge, tunnel, multimodal transport match, this can be rated as really the great miracle created since the dawn of human civilization it One.
The main handling mode of Nowadays, Container shipping realizes that container crane first will by container crane Its arm extends the top of container, then is sling container by arm, is then transferred to defined unloading area and puts down.
Invention such as Patent No. DE202010001496U1 is exactly loaded and unloaded in this way.But due to train All setting up above track has cable, therefore, during using common container crane to realize the handling of container, the behaviour of arm Interference can be produced with cable by making space, and the arm of container crane is difficult the top for extending container, causes unloading operation numb Tired, safety coefficient is low.
The content of the invention
The present invention is directed to above mentioned problem existing for existing technology, there is provided a kind of double case synchronization handling systems of container, The technical problems to be solved by the invention are:How Simultaneous Stabilization, safety two containers of handling.
The purpose of the present invention can be realized by following technical proposal:
A kind of double case synchronization handling systems of container, double case synchronization handling systems include frame, it is characterised in that Double case synchronization handling systems also include jacking arm two and two jacking arms one for being arranged on jacking arm two both sides, two Jacking arm one be arranged in parallel with jacking arm two and can stretch out frame the same side, jacks between arm two and each jacking arm one Provided with mobile support, the mobile bracket slide is connected in frame and can stretch out frame side, and two jacking arms one can By translating the hole for hoist clamping with container, the frame is provided with the driving source that mobile support can be driven to stretch out frame side One, the jacking arm one is provided with the driving source two that jacking arm one can be driven to move up and down, and the jacking arm two is provided with energy The driving source three that enough driving jacking arms two move up and down, the front end of the jacking arm two have two and are parallel to each other and are arranged at intervals Connection-peg.
Its operation principle is as follows:In this pair of case synchronization handling system, two jacking arms one can be with two containers outsides Hole for hoist clamping, and jack the connection-peg of the front end of arm two then respectively with the hole for hoist clamping on the inside of two containers, and lead to Cross that the two are parallel to each other and spaced connection-peg interfixes two containers, jacking arm one and jacking arm two are driving Two containers can be jacked up simultaneously under the driving of dynamic source two and driving source three and make the bottom surface of container hanging;In jacking arm Mobile support is set between one and jacking arm two, make to move support under the driving of driving source one from container base and flatcar it Between insert, by two containers be individually positioned in corresponding on mobile support, then withdraw jacking arm one and jacking arm two, simultaneously Mobile support drives container synchronization translation under the driving of driving source one, by transporting container to frame, the movement support Design realize transfer of the container flat car to frame, and the transfer process will not occur with the cable above rail it is dry Relate to, transfer process is more stable and safe;Jack that arm two front end is parallel and spaced two connection-pegs can be by two Container interfixes, and improves stability of two containers during synchronization of jacking up and transfer.Above-mentioned driving source one can Can also be hydraulic cylinder or cylinder with the combination for being screw mandrel and motor.
In a kind of double case synchronization handling systems of above-mentioned container, the jacking arm two includes upper arm and underarm, institute State underarm to be slidably connected in frame, the frame is provided with the driving source four for being used for driving the underarm to slide, the upper arm It is stacked above underarm and upper arm can moves up and down with respect to underarm, the front end of the upper arm is connected with connecting plate, two grafting Head is fixed on the connecting plate, and the front end of the upper arm is also hinged with the driving source three for driving upper arm to move up and down.This In double case synchronization handling systems, underarm is connected with housing slide and upper arm can ensure that with respect to the design that underarm moves up and down The height and upper arm of arm and the distance of container are controllable, so as to by slide underarm and regulation upper arm height can make upper arm before The connection-peg at end can realize the interlocking of two containers more accurately with the hole for hoist clamping on container, improve same The stability and security of step two containers of jacking;Driving source three is located at the front end of upper arm, shortens driving source three and packaging The bang path of power between case, so as to improve the structural strength of upper arm, make this pair of case synchronization handling system more stable and safe. Above-mentioned driving source four can be that the combination of screw mandrel and motor can also be hydraulic cylinder or cylinder.
In a kind of double case synchronization handling systems of above-mentioned container, the driving source three is hydraulic cylinder one, it is described on Arm front end has two pieces of installing plates, resigning chamber is formed between two pieces of installing plates, the hydraulic cylinder one is between two pieces of installing plates And be hinged respectively with two pieces of installing plates, the connecting plate is connected with the hydraulic cylinder one, and the upper arm is provided with band hydrodynamic pressure Cylinder one is rotated to the drive mechanism of resigning intracavitary.What resigning chamber and hydraulic cylinder one and two pieces of installing plates were hinged is designed to make liquid Cylinder pressure one is rotated to resigning intracavitary, is avoided container and is blocked during frame is moved to from flatcar by hydraulic cylinder one, Make the handling of container more stable and safe.Alternatively, the driving source three can also be cylinder, can also be The combination of screw mandrel and motor.
In a kind of double case synchronization handling systems of above-mentioned container, offered in the frame along underarm length direction Chute two, the underarm are slidably connected in the chute two, and the both ends of the chute two are opening, the both ends of the underarm Extend at the both ends of chute two, the chute two has smooth bottom wall and two relative side walls, has length in the side wall The lug boss of strip, the lug boss extend along the length direction of chute two, and buckling groove is offered in the side wall of the underarm, described Lug boss is slidably connected in buckling groove, the lower spigot surface of outer end tool of the connection-peg.In order to allow the grafting of jacking arm two front end The hole for hoist clamping of head and container, underarm must stretch out chute two, but underarm stretches out after going and is certain to some vacantly, and The design ensure that the bearing length of underarm is longer, the still old preferable supporting role in the case that a part is hanging, Improve the stability and security of this lifting body;Lug boss in the side wall of chute two matches with the buckling groove in underarm side wall Close, avoid situations such as underarm is moved left and right or teetertottered when being slided on chute two, make the slip of underarm more steady Fixed, safety;Simultaneously because the limitation of underarm, upper arm need to only adjust above and below height carry out hole for hoist clamping with container, therefore In order to strengthen the structural strength of connection-peg, the outer end of connection-peg is only provided with lower spigot surface, jacking arm two is more stablized, Safety jacks up container.
In a kind of double case synchronization handling systems of above-mentioned container, the drive mechanism includes V-type plate and hydraulic cylinder Two, one end of the V-type plate is hinged with hydraulic cylinder one and the V-type plate and the pin joint and hydraulic cylinder one of hydraulic cylinder one and installation The pin joint of plate is overlapped, and the piston rod of the other end and hydraulic cylinder two of the V-type plate is hinged, and the front end of the installing plate is provided with limit Position block, the limited block are located at the top of the V-type plate, and the lower surface of the limited block is confined planes.V-type plate and hydraulic cylinder one Pin joint and hydraulic cylinder one overlapped with the pin joint of installing plate be designed to make V-type plate and the synchronous axial system of hydraulic cylinder one, then Rotated by the driving hydraulic cylinder two of hydraulic cylinder two being hinged with V-type plate, hydraulic cylinder two is rotated to resigning intracavitary, so that mobile The more stable safety of transfer of the support to container;Above-mentioned confined planes and plane-parallel, the design of the limited block can make liquid Cylinder pressure two from resigning intracavitary spin out when be vertical state, hydraulic cylinder two is more stablized, the jack-up two of safety collection Vanning.
In a kind of double case synchronization handling systems of above-mentioned container, the jacking arm one includes trave lling girder and jacking Beam, the trave lling girder are slidably connected in frame, and the lifting beam is stacked above trave lling girder and lifting beam can relatively move Beam moves up and down, and the outer end and the inner of the lifting beam are equipped with jig arm, and the jig arm is provided with inserting column and driving jig arm The driving source two of lower movement.The trave lling girder of above-mentioned jacking arm one is slidably connected in frame, so as to realize the jacking horizontal position of arm one The adjustment put, and moved up and down because lifting beam is stacked above trave lling girder and can relatively move beam, realize jacking arm one The adjustment of in the vertical direction, ensure that the inserting column in jig arm can be inserted accurately in the hole for hoist of container, make jacking arm One can more safely jack up container;Jig arm will be arranged on for the driving source two for driving jig arm to move up and down, shortened When lifting container between driving source two and container power bang path, enhance the structural strength of jacking arm one, improve The stability and security of this pair of case synchronization handling system.Above-mentioned driving source two can be hydraulic cylinder or cylinder can also be The combination of motor and screw mandrel.
In a kind of double case synchronization handling systems of above-mentioned container, the mobile support includes guide rail bracket and transfer Frame, the guide rail bracket are slidably connected in frame, and the transfer frame is slidably connected on guide rail bracket, the transfer frame and guide rail bracket Moving direction it is parallel.One end of support body will not be hanging when the design of double-layer rack body makes transfer container, improves mobile support Structural strength, enhance the stability and security of this pair of case synchronization handling system.
Compared with prior art, advantages of the present invention is as follows:
1st, in this pair of case synchronization handling system, two jacking arm one can with the hole for hoist clamping on the outside of two containers, And the connection-peg of the front end of arm two is jacked then respectively with the hole for hoist clamping on the inside of two containers, it is and mutually flat by the two Capable and spaced connection-peg interfixes two containers, and jacking arm one and jacking arm two are in driving source two and driving source Two containers can be jacked up simultaneously under three driving and make the bottom surface of container hanging;
2nd, this pair of case synchronization handling system sets mobile support between jacking arm one and jacking arm two, makes to move support and exists Inserted under the driving of driving source one between container base and flatcar, two containers are individually positioned in corresponding mobile branch On frame, jacking arm one and jacking arm two are then withdrawn, while mobile support drives container synchronous under the driving of driving source one Translation, by transporting container to frame, the design of the movement support realizes transfer of the container flat car to frame, and should Transfer process will not interfere with the cable above rail, and transfer process is more stable and safe;
3rd, the front end of liter arm two of this pair of case synchronization handling system is parallel and spaced two connection-pegs can be by two Container interfixes, and improves stability of two containers during synchronization of jacking up and transfer.
Brief description of the drawings
Overall schematic when Fig. 1 is this pair of case synchronization handling system transfer.
Fig. 2 is the overall structure diagram of this pair of case synchronization handling system.
Fig. 3 is the structural representation of this pair of case synchronization handling system jacking arm two.
Fig. 4 is the structural representation of this pair of case synchronization handling system connecting plate and connection-peg.
Fig. 5 is the structural representation of this pair of case synchronization handling system jacking arm two front end.
Fig. 6 is the structural representation of this pair of case synchronization handling system jacking arm one.
In figure, 1 frame;2 jacking arms one;3 jacking arms two;4 movement supports;5 containers;6 holes for hoist;7 driving sources one;8 Driving source two;9 driving sources three;10 connection-pegs;11 upper arm;12 underarms;13 driving sources four;14 connecting plates;15 installing plates;16 step down Chamber;17 chutes two;18 times spigot surfaces;19V templates;20 hydraulic cylinders two;21 limited blocks;22 trave lling girders;23 lifting beams;24 jig arm; 25 guide rail brackets;26 transfer framves;27 hydraulic cylinders one.
Embodiment
It is the specific embodiment of the present invention and with reference to accompanying drawing below, technical scheme is further described, But the present invention is not limited to these embodiments.
As shown in figures 1 to 6, this pair of case synchronization handling system is arranged on the jacking including frame 1, jacking arm 23 and two The jacking arm 1 of the both sides of arm 23, two jacking arms 1 be arranged in parallel with jacking arm 23 and can stretch out the same side of frame 1, The jacking arm 1 is provided with the driving source 28 that jacking arm 1 can be driven to move up and down, and the jacking arm 1 includes moving Dynamic beam 22 and lifting beam 23, the trave lling girder 22 are slidably connected in frame 1, and the lifting beam 23 is stacked at the top of trave lling girder 22 And lifting beam 23 can relatively move beam 22 and move up and down, the outer end and the inner of the lifting beam 23 are equipped with jig arm 24, described The driving source 28 that jig arm 24 is provided with inserting column and drives jig arm 24 to move up and down.The trave lling girder 22 of above-mentioned jacking arm 1 slides It is connected in frame 1, so as to realize the adjustment of the jacking horizontal level of arm 1, and because lifting beam 23 is stacked on trave lling girder 22 Side and beam 22 can be relatively moved move up and down, realize the adjustment of the jacking in the vertical direction of arm 1, ensure in jig arm 24 Inserting column can be inserted accurately in the hole for hoist 6 of container 5, jacking arm 1 is more safely jacked up container 5; Jig arm 24 will be arranged on for the driving source 28 for driving jig arm 24 to move up and down, have shortened driving source two when lifting container 5 The bang path of power between 8 and container 5, the structural strength of jacking arm 1 is enhanced, improves this pair of case synchronization handling system Stability and security.Above-mentioned driving source 28 can be hydraulic cylinder or cylinder can also be the combination of motor and screw mandrel.
As depicted in figs. 1 and 2, jack and mobile support 4 is equipped between arm 23 and each jacking arm 1, the mobile branch Frame 4 is slidably connected in frame 1 and can stretch out the side of frame 1, and two jacking arms 1 can be by translating and container 5 The clamping of hole for hoist 6, the frame 1 are provided with the driving source 1 that mobile support 4 can be driven to stretch out the side of frame 1, the mobile branch Frame 4 includes guide rail bracket 25 and transfer frame 26, and the guide rail bracket 25 is slidably connected in frame 1, and the transfer frame 26 is slidably connected On guide rail bracket 25, the transfer frame 26 is parallel with the moving direction of guide rail bracket 25.The design of double-layer rack body makes transfer container 5 When support body one end will not be hanging, improve the structural strength of mobile support 4, enhance the stabilization of this pair of case synchronization handling system Property and security.Above-mentioned driving source 1 can be that the combination of screw mandrel and motor can also be hydraulic cylinder or cylinder.
As shown in Fig. 3, Fig. 4 and Fig. 5, the jacking arm 23 includes upper arm 11 and underarm 12, it is described jack arm 23 before There are two to be parallel to each other at end and spaced connection-peg 10, the underarm 12 are slidably connected in frame 1, the frame 1 The driving source 4 13 for being used for driving the underarm 12 to slide is provided with, the upper arm 11 is stacked at the top of underarm 12 and the energy of upper arm 11 Enough relative underarms 12 move up and down, and the front end of the upper arm 11 is connected with connecting plate 14, and two connection-pegs 10 are fixed on the company On fishplate bar 14, the front end of the upper arm 11 is also hinged with the driving source 39 for driving upper arm 11 to move up and down.This pair of case synchronization In handling system, underarm 12 ensure that with the design that frame 1 is slidably connected and upper arm 11 can move up and down with respect to underarm 12 The height of arm 11 and the distance of upper arm 11 and container 5 are controllable, so as to highly may be used by sliding underarm 12 and regulation upper arm 11 So that the connection-peg 10 of the front end of upper arm 11 can realize two containers more accurately with the clamping of hole for hoist 6 on container 5 5 interlocking, improve the stability and security of two containers 5 of synchronization of jacking up;Driving source 39 is located at the front end of upper arm 11, The bang path of power between driving source 39 and container 5 is shortened, so as to improve the structural strength of upper arm 11, makes this pair of case same It is more stable and safe to walk handling system.Above-mentioned driving source 4 13 can be screw mandrel and motor combination can also be hydraulic cylinder or Person's cylinder.
As shown in Figure 3 and Figure 5, the jacking arm 23 is provided with the driving source three that jacking arm 23 can be driven to move up and down 9, and driving source 39 is hydraulic cylinder 1, the front end of upper arm 11 has two pieces of installing plates 15, formed between two pieces of installing plates 15 Resigning chamber 16, the hydraulic cylinder 1 is between two pieces of installing plates 15 and is hinged respectively with two pieces of installing plates 15, the company Fishplate bar 14 is connected with the hydraulic cylinder 1, and the upper arm 11, which is provided with, drives the rotation of hydraulic cylinder 1 to the drive in resigning chamber 16 Motivation structure.The rotation of hydraulic cylinder 1 that what resigning chamber 16 and hydraulic cylinder 1 and two pieces of installing plates 15 were hinged be designed to make is to allowing In the chamber 16 of position, avoid container 5 and blocked during frame 1 is moved to from flatcar by hydraulic cylinder 1, make container 5 Handling are more stable and safety;The drive mechanism includes V-type plate 19 and hydraulic cylinder 2 20, one end of the V-type plate 19 with Hydraulic cylinder 1 is hinged and the V-type plate 19 and the pin joint of hydraulic cylinder 1 and the pin joint of hydraulic cylinder 1 and installing plate 15 Overlap, the piston rod of the other end and hydraulic cylinder 2 20 of the V-type plate 19 is hinged, and the front end of the installing plate 15 is provided with limited block 21, the limited block 21 is located at the top of the V-type plate 19, and the lower surface of the limited block 21 is confined planes;V-type plate 19 and liquid What the pin joint and hydraulic cylinder 1 of cylinder pressure 1 overlapped with the pin joint of installing plate 15 is designed to make V-type plate 19 and hydraulic cylinder One 27 synchronous axial systems, then the driving hydraulic cylinder 2 20 of hydraulic cylinder 2 20 by being hinged with V-type plate 19 rotate, and revolve hydraulic cylinder 2 20 Go in resigning chamber 16, so that the more stable safety of transfer of the mobile support 4 to container 5;Above-mentioned confined planes and horizontal plane It is parallel, the design of the limited block 21 can make hydraulic cylinder 2 20 from the internal rotation of resigning chamber 16 come out when be vertical state, make hydraulic pressure Cylinder 2 20 can more be stablized, two containers 5 of jack-up of safety.Alternatively, the driving source 39 can also be Cylinder, it can also be the combination of screw mandrel and motor.
As shown in Figure 1, Figure 2 and Figure 3, chute 2 17, the underarm are offered along the length direction of underarm 12 in the frame 1 12 are slidably connected in the chute 2 17, and the both ends of the chute 2 17 are opening, and the both ends of the underarm 12 extend to At the both ends of chute 2 17, the chute 2 17 has smooth bottom wall and two relative side walls, has strip in the side wall The lug boss of shape, the lug boss extend along the length direction of chute 2 17, offer buckling groove in the side wall of the underarm 12, institute State lug boss to be slidably connected in buckling groove, the lower spigot surface 18 of outer end tool of the connection-peg 10.The front end of arm 23 is jacked in order to allow Connection-peg 10 and container 5 the clamping of hole for hoist 6, underarm 12 must stretch out chute 2 17, but underarm 12 is stretched out after going certainly It is hanging some, and the design ensure that the bearing length of underarm 12 is longer, in the case that a part is hanging still Old preferable supporting role, improve the stability and security of this lifting body;Lug boss in the side wall of chute 2 17 with Buckling groove in the side wall of underarm 12 is engaged, and is avoided underarm 12 and is moved left and right when being slided on chute 2 17 or shake up and down Situations such as dynamic, make the slip of underarm 12 more stable, safe;Simultaneously because the limitation of underarm 12,11, upper arm need to be adjusted up and down Height come with the clamping of the hole for hoist of container 56, therefore in order to strengthen the structural strength of connection-peg 10, the outer end of connection-peg 10 Only be provided with lower spigot surface 18, jacking arm 23 is more stablized, safe jack up container 5.
In this pair of case synchronization handling system, two jacking arms 1 can with the clamping of hole for hoist 6 in the outside of two containers 5, And the then clamping of hole for hoist 6 with two inner sides of container 5 respectively of connection-peg 10 of the front end of arm 23 is jacked, and pass through the two It is parallel to each other and spaced connection-peg 10 interfixes two containers 5, jacking arm 1 and jacking arm 23 is driving Two containers 5 can be jacked up simultaneously under the driving of source 28 and driving source 39 and make the bottom surface of container 5 hanging;Jacking Mobile support 4 is set between arm 1 and jacking arm 23, makes to move support 4 under the driving of driving source 1 from the bottom of container 5 Inserted between flatcar, two containers 5 are individually positioned on corresponding mobile support 4, then withdraw jacking arm 1 and top Arm 23 is risen, while mobile support 4 drives 5 synchronous translation of container under the driving of driving source 1, and container 5 is transported into machine On frame 1, the design of the movement support 4 realizes transfer of the flatcar of container 5 to frame 1, and the transfer process will not be with iron Cable above rail interferes, and transfer process is more stable and safe;It is parallel and spaced two to jack arm 23 front end Individual connection-peg 10 can interfix two containers 5, improve two containers 5 during synchronization of jacking up and transfer Stability.
Specific embodiment described herein is only to spirit explanation for example of the invention.Technology belonging to the present invention is led The technical staff in domain can be made various modifications or supplement to described specific embodiment or be replaced using similar mode Generation, but without departing from the spiritual of the present invention or surmount scope defined in appended claims.

Claims (7)

1. a kind of double case synchronization handling systems of container, double case synchronization handling systems include frame (1), and its feature exists In double case synchronization handling systems also include jacking arm two (3) and two jackings for being arranged on described jacking arm two (3) both sides Arm one (2), two jacking arms one (2) be arranged in parallel with jacking arm two (3) and can stretch out frame (1) the same side, jack arm Mobile support (4) is equipped between two (3) and each jacking arm one (2), the mobile support (4) is slidably connected at frame (1) Above and frame (1) side can be stretched out, two jacking arms one (2) can pass through to translate blocks with the hole for hoist (6) of container (5) Connect, the frame (1) is provided with the driving source one (7) that mobile support (4) can be driven to stretch out frame (1) side, the jacking arm One (2) are provided with the driving source two (8) that jacking arm one (2) can be driven to move up and down, and the jacking arm two (3) includes upper arm (11) it is slidably connected at underarm (12), the underarm (12) in frame (1), the upper arm (11) can be with respect on underarm (12) Lower movement, the front end of the upper arm (11) are also hinged with the driving source three (9) for driving upper arm (11) to move up and down, it is described on The front end of arm (11) is parallel to each other with two and spaced connection-peg (10).
A kind of 2. double case synchronization handling systems of container according to claim 1, it is characterised in that the frame (1) The driving source four (13) for being used for driving the underarm (12) to slide is provided with, the upper arm (11) is stacked above underarm (12), The front end of the upper arm (11) is connected with connecting plate (14), and two connection-pegs (10) are fixed on the connecting plate (14).
A kind of 3. double case synchronization handling systems of container according to claim 2, it is characterised in that the driving source three (9) it is hydraulic cylinder one (27), upper arm (11) front end has two pieces of installing plates (15), is formed and allowed between two pieces of installing plates (15) Position chamber (16), the hydraulic cylinder one (27) is between two pieces of installing plates (15) and is hinged respectively with two pieces of installing plates (15), The connecting plate (14) is connected with the hydraulic cylinder one (27), and the upper arm (11), which is provided with, drives hydraulic cylinder one (27) rotation extremely Drive mechanism in resigning chamber (16).
A kind of 4. double case synchronization handling systems of container according to Claims 2 or 3, it is characterised in that the frame (1) chute two (17) is offered along underarm (12) length direction on, the underarm (12) is slidably connected at the chute two (17) Interior, the both ends of the chute two (17) are opening, and the both ends of the underarm (12) are extended at the both ends of chute two (17), institute Stating chute two (17) has smooth bottom wall and two relative side walls, has the lug boss of strip in the side wall, described convex The portion of rising extends along chute two (17) length direction, and buckling groove is offered in the side wall of the underarm (12), and the lug boss slides It is connected in buckling groove, the lower spigot surface (18) of outer end tool of the connection-peg (10).
A kind of 5. double case synchronization handling systems of container according to claim 3, it is characterised in that the drive mechanism Including V-type plate (19) and hydraulic cylinder two (20), one end of the V-type plate (19) is hinged with hydraulic cylinder one (27) and the V-type plate (19) overlapped with the pin joint and hydraulic cylinder one (27) of hydraulic cylinder one (27) with the pin joint of installing plate (15), the V-type plate (19) piston rod of the other end and hydraulic cylinder two (20) is hinged, and the front end of the installing plate (15) is provided with limited block (21), institute The top that limited block (21) is located at the V-type plate (19) is stated, the lower surface of the limited block (21) is confined planes.
A kind of 6. double case synchronization handling systems of container according to claim 1 or 2 or 3, it is characterised in that the top Rising arm one (2) includes trave lling girder (22) and lifting beam (23), and the trave lling girder (22) is slidably connected in frame (1), described Lifting beam (23) is stacked above trave lling girder (22) and lifting beam (23) can relatively move beam (22) and move up and down, the jacking The outer end and the inner of beam (23) are equipped with jig arm (24), and the jig arm (24) is provided with inserting column and driving jig arm (24) and moved down Dynamic driving source two (8).
A kind of 7. double case synchronization handling systems of container according to claim 1 or 2 or 3, it is characterised in that the shifting Dynamic support (4) includes guide rail bracket (25) and transfer frame (26), and the guide rail bracket (25) is slidably connected in frame (1), the shifting Frame (26) is sent to be slidably connected on guide rail bracket (25), the transfer frame (26) is parallel with the moving direction of guide rail bracket (25).
CN201510471847.2A 2015-08-04 2015-08-04 A kind of double case synchronization handling systems of container Active CN105084220B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510471847.2A CN105084220B (en) 2015-08-04 2015-08-04 A kind of double case synchronization handling systems of container

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510471847.2A CN105084220B (en) 2015-08-04 2015-08-04 A kind of double case synchronization handling systems of container

Publications (2)

Publication Number Publication Date
CN105084220A CN105084220A (en) 2015-11-25
CN105084220B true CN105084220B (en) 2017-11-24

Family

ID=54565686

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510471847.2A Active CN105084220B (en) 2015-08-04 2015-08-04 A kind of double case synchronization handling systems of container

Country Status (1)

Country Link
CN (1) CN105084220B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111532811B (en) * 2020-05-18 2022-03-08 中铁第四勘察设计院集团有限公司 Container alignment synchronous loading and unloading method and system based on prestoring

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SE9402504D0 (en) * 1994-07-18 1994-07-18 Sten Loevgren Method and device for handling loads
AT502634B1 (en) * 2005-11-04 2007-12-15 Hans G Unseld MOBILE ENVELOPER
ITMI20072057A1 (en) * 2007-10-24 2009-04-25 Salmoiraghi S P A SYSTEM AND PROCEDURE FOR UNLOADING AND LOADING OF LOAD UNITS FROM AND TO RAILWAY WAGONS
PL2108605T3 (en) * 2008-04-08 2011-01-31 Bermueller Wolfgang Device for transporting a container
DE102010043916A1 (en) * 2010-11-15 2012-05-16 Siemens Aktiengesellschaft Device for treating transmodal transport units

Also Published As

Publication number Publication date
CN105084220A (en) 2015-11-25

Similar Documents

Publication Publication Date Title
CN103692944B (en) Automatic integral loading-unloading vehicle
JP6105085B2 (en) Transport system and transport method for transported goods
CN205366661U (en) Guide rail system is loaded in protractile of back pullout (BPO) special type container
EP3428093B1 (en) Aerial railway-based multimodal transport interconnecting system
CN108657934B (en) Container vertical rotation lifting appliance and operation method thereof
CN103625344B (en) A kind of swing lift
CN203172498U (en) Transportation vehicle and goods jacking device thereof
CN103835727A (en) Extended type multi-platform railway tunnel operation trolley
CN104594830A (en) Petroleum drill and exploitation equipment and drilling pipe storage and transportation device, drilling pipe storage and transportation system and drilling pipe storage and transportation method thereof
CN105129676A (en) Loading and unloading system for container
CN105084220B (en) A kind of double case synchronization handling systems of container
CN105084253B (en) A kind of transfer device in the handling system of container
CN110877856A (en) Automatic hoisting device suitable for transferring cylindrical thin shell and application method thereof
CN105270844A (en) Elevated long-distance telescopic rotary grain conveyor
CN203845490U (en) Logistic loading and unloading conveyer
CN105540450A (en) Container crane
CN105084243B (en) A kind of lifting body in the handling system of container
CN203127520U (en) Self-dumping type construction device special for container structure folding track
CN102991853B (en) Equipment hatch transportation device
CN103625345A (en) Container loading and unloading vehicle with self-loading and self-unloading function
CN210286531U (en) Steel coil ferry railcar
CN105722724B (en) Vehicle, facility and station for loading and unloading container
CN206692216U (en) A kind of handling apparatus in container
CN206203786U (en) A kind of transporter
CN207141953U (en) A kind of container

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant