CN105066140B - A kind of waste incinerator - Google Patents

A kind of waste incinerator Download PDF

Info

Publication number
CN105066140B
CN105066140B CN201510568337.7A CN201510568337A CN105066140B CN 105066140 B CN105066140 B CN 105066140B CN 201510568337 A CN201510568337 A CN 201510568337A CN 105066140 B CN105066140 B CN 105066140B
Authority
CN
China
Prior art keywords
furnace body
combustion chamber
cylinder
waste incinerator
air inlet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510568337.7A
Other languages
Chinese (zh)
Other versions
CN105066140A (en
Inventor
黄峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Huixin Environmental Protection Technology Co ltd
Original Assignee
Guangxi Xiumei Zhuangxiang Energy Environmental Protection Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Xiumei Zhuangxiang Energy Environmental Protection Co Ltd filed Critical Guangxi Xiumei Zhuangxiang Energy Environmental Protection Co Ltd
Priority to CN201510568337.7A priority Critical patent/CN105066140B/en
Publication of CN105066140A publication Critical patent/CN105066140A/en
Application granted granted Critical
Publication of CN105066140B publication Critical patent/CN105066140B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G5/00Incineration of waste; Incinerator constructions; Details, accessories or control therefor
    • F23G5/08Incineration of waste; Incinerator constructions; Details, accessories or control therefor having supplementary heating
    • F23G5/14Incineration of waste; Incinerator constructions; Details, accessories or control therefor having supplementary heating including secondary combustion
    • F23G5/16Incineration of waste; Incinerator constructions; Details, accessories or control therefor having supplementary heating including secondary combustion in a separate combustion chamber
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G5/00Incineration of waste; Incinerator constructions; Details, accessories or control therefor
    • F23G5/38Multi-hearth arrangements
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23GCREMATION FURNACES; CONSUMING WASTE PRODUCTS BY COMBUSTION
    • F23G5/00Incineration of waste; Incinerator constructions; Details, accessories or control therefor
    • F23G5/44Details; Accessories

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Incineration Of Waste (AREA)

Abstract

The present invention provides a kind of waste incinerator, and the waste incinerator includes the first furnace body, the second furnace body, blower, induced duct and exhaust portion, and is equipped with spout and slag-drip opening.Second furnace body of gas of the present invention by the way that the first furnace body for burning solid rubbish is arranged, for being decomposited when burning solid incineration firing, and it is provided with exhaust portion, induced duct and blower to preheat fresh air and introduce the first furnace body and the second furnace body, improve the first combustion chamber, the intake air temperature of the second combustion chamber and the indoor rubbish of the first burning of drying, improve the temperature of incinerator, the temperature in incinerator is set to reach 950 DEG C~1100 DEG C, the decomposition temperature for having reached dioxin reduces the discharge of dioxin.Meanwhile the imperfect combustion particle in combustion process is clung to fall by vapor and is blocking fiery intake section, is blocked fiery intake section due to described and is tilted down and be affected by gravity, imperfect combustion particle eventually falls into the first combustion chamber and burns again.

Description

A kind of waste incinerator
[technical field]
The invention belongs to a kind of stove, in particular to a kind of waste incinerator.
[background technique]
It is following then be a large amount of house refuse, mesh with the development of society, people's lives quality is become better and better Preceding usually used trash processing way has following two: one is garbage loading embeading technology is used, however, with urban land It gradually decreases, people are also in the scheme for finding substitution garbage loading embeading technology;Another way is exactly burning domestic garbage, life rubbish Rubbish generates a large amount of toxic gas when burning, and house refuse is due to many kinds of, density, the shape of combustible therein Shape, chemical property, burning special efficacy are all different, therefore many combustibles all cannot sufficiently fire in common burning mode It burns, and generates a large amount of black smoke and pernicious gas while imperfect combustion, pollute atmosphere and endanger the health of the mankind. In addition, rubbish, which can generate a large amount of foul smell in open incineration, influences the life of surrounding resident.
In the pernicious gas generated in waste incineration, dioxin system one kind extremely toxic substance, it is ripe that toxicity is equivalent to people 130 times of the extremely toxic substance cyanide known, 900 times of arsenic.The dioxin being discharged into atmospheric environment can be adsorbed on particle On object, it is deposited to water body and soil, human body is then entered by the enrichment of food chain.Its generation is common due to using Temperature when mode carries out waste incineration is lower and dioxin under high temperature environment the duration it is too short caused by.
[summary of the invention]
In view of problem above, it is necessary to a kind of waste incinerator is provided and is used to prevent stink when incineration firing from diffusing, and And the dioxin generated when can be by burning decomposes.
In order to achieve the above objectives, the present invention adopts the following technical scheme: a kind of waste incinerator, the waste incinerator packet The first furnace body, the second furnace body, blower, induced duct and exhaust portion are included, and is equipped with spout and slag-drip opening;First furnace body includes Outer cylinder, inner cylinder, hollow sealing portion and bottom plate;In outer barrel, the bottom plate is arranged in the inner cylinder and institute for the inner cylinder setting State the bottom surface of outer cylinder;The hollow sealing portion offers through-hole, and connects the top of the inner cylinder and the outer cylinder;The inner cylinder Inside is the first combustion chamber, and ventilation space is surrounded by together with the outer cylinder, the hollow sealing portion and the bottom plate;It is described Inner cylinder lower sidewall and top offer the first air inlet, the second air inlet respectively, and the slag-drip opening is arranged in first furnace Body bottom, and with first combustion chamber;Second furnace body includes cylinder and blocks fiery intake section;The inner barrel is Second combustion chamber, and one end is connected to the exhaust portion, and the other end is connected to by the through-hole with the inner cylinder;It is described to block fire Intake section includes hollow round table, cored slab and connection wall, and outer rim is connect with the cylinder, and inside offers exhaust duct;The sky The miner diameter end of heart rotary table is directed toward the first furnace body, and coaxial with the outer cylinder;The connection wall connects the hollow round table miner diameter end And the interior edge of the cored slab, and offer third air inlet;Air duct is offered between the hollow round table and the cored slab; The third air inlet is connected to the air duct and the exhaust duct;Along the direction that the smoke exhaust pipe is directed toward first furnace body, The hollow round table, the cored slab are arranged successively;The exhaust portion includes smoke exhaust pipe and diversion division;It is the diversion division, described Preheating space is surrounded by the top of smoke exhaust pipe and the cylinder;Offered on the diversion division by atmosphere be connected to preheating space into Port;The induced duct is connected to the preheating space, described blocks fiery intake section and the outer cylinder;The blower can will be described pre- Gas in heat space is sent to first combustion chamber, second combustion chamber.
Further, the cored slab offers hole, and perpendicular to the axis of the cylinder;Described in the connection wall connection The diameter of the edge in hole and the hollow round table miner diameter end, the hollow round table miner diameter end is less than or equal to the straight of the hole Diameter.
Further, the cylinder both ends are respectively arranged with necking, lower necking;The lower necking and first furnace body Top is connected and is connected to the first combustion chamber and the second combustion chamber, and the upper necking is connected with the exhaust portion and is connected to described second Combustion chamber and exhaust portion.
Further, the outer cylinder, the inner cylinder, the cylinder, the hollow round table, the hole, the smoke exhaust pipe are same Axis.
Further, on the axis direction of the hollow round table, the first furnace body one of the third air inlet axially bored line direction It rolls oblique;On the plane perpendicular to the hollow round table axis, the third air inlet axially bored line is towards in the connection wall of place The tangential direction of position tilts.
Further, the spout bottom surface towards second furnace body central axis direction diagonally downward so that charging End is high and discharge end is low.
Further, the exhaust portion further includes rain cover, and the rain cover is arranged at the top of the exhaust portion.
Further, the induced duct includes supervisor and manifold, and described supervisor one end is connected to the preheating space, another End is connected to the manifold, and the manifold is connected to the supervisor, the air duct and the ventilation space.
Further, the blower is connected on the supervisor, from the preheating space air inlet, to the manifold exhaust.
Further, the waste incinerator further includes support frame, and support frame as described above is uniformly arranged on the side of the outer cylinder On wall, it is used to support the waste incinerator.
The invention has the following advantages:
The present invention is used for the first furnace body of burning solid rubbish by being arranged, for decompositing when burning solid incineration firing Gas the second furnace body, and be provided with exhaust portion, induced duct and blower by fresh air preheat and introduce the first furnace body And second furnace body, it improves the first combustion chamber, the intake air temperature of the second combustion chamber and drying and is deposited in the indoor rubbish of the first burning Rubbish improves the temperature of waste incinerator, so that the temperature in waste incinerator is reached 950 DEG C~1100 DEG C, has reached dioxin Decomposition temperature, greatly reduce the discharge of dioxin.Meanwhile water can be generated when drying rubbish and when solid refuse burns Steam, the imperfect combustion particle in combustion process is clung by vapor to be fallen on blocking fiery intake section, due to blocking fiery intake section Top surface tilts down and is affected by gravity, and imperfect combustion particle eventually falls into the first combustion chamber and burns again.
[Detailed description of the invention]
Fig. 1 is a kind of structural schematic diagram of waste incinerator of the present invention.
Main element symbol description
Waste incinerator 100 First furnace body 1 Outer cylinder 11
Inner cylinder 12 First air inlet 121 Second air inlet 122
Bottom plate 13 Hollow sealing portion 14 Through-hole 141
Support frame 15 First combustion chamber 16 Ventilation space 17
Cylinder 21 Lower necking 211 Upper necking 212
Block fiery intake section 22 Connection wall 221 Third air inlet 222
Air duct 223 Hollow round table 224 Cored slab 225
Hole 2251 Exhaust portion 3 Smoke exhaust pipe 31
Diversion division 32 Rain cover 33 Preheating space 34
Air inlet 35 Induced duct 4 Supervisor 41
First manifold 42 Second manifold 43 Blower 5
Spout 6 Slag-drip opening 7 Lid 71
The present invention that the following detailed description will be further explained with reference to the above drawings.
[specific embodiment]
Referring to Fig. 1, in a preferred embodiment of the present invention, a waste incinerator 100 include one first furnace body 1, One second furnace body 2, an exhaust portion 3, an induced duct 4 and a blower 5, and it is equipped with a spout 6 and a slag-drip opening 7.
First furnace body 1 includes an outer cylinder 11, an inner cylinder 12, a bottom plate 13, a hollow sealing portion 14 and three support frames 15.The lower part of 12 side wall of inner cylinder offers first air inlet of circle 121, and top offers second air inlet of circle 122.Institute The bottom that the outer cylinder 11, the inner cylinder 12 is arranged in bottom plate 13 is stated, the hollow sealing portion 14 is a plate, offers through-hole 141, and connect the top of the inner cylinder 12 and the outer cylinder 11.It is the first combustion chamber 16 inside the inner cylinder 12;The outer cylinder 11, the inner cylinder 12, the bottom plate 13 and the hollow sealing portion 14 are surrounded by a ventilation space 17 together.The outer cylinder 11 with The inner cylinder 12 is coaxial.The slag-drip opening 7 is arranged on the side wall of 1 bottom of the first furnace body, with first combustion chamber 16 Connection, and it is equipped with lid 71.Three support frame 15 is uniformly arranged on the side wall of the outer cylinder 11, is used to support the rubbish Incinerator 100.
Second furnace body 2 includes that a cylinder 21 and one blocks fiery intake section 22.It is the second combustion chamber inside the cylinder 21 23, both ends are respectively arranged with necking 212, lower necking 211.It is connected and leads at the top of the lower necking 211 and first furnace body 1 It crosses the through-hole 141 and is connected to the first combustion chamber 16 and the second combustion chamber 23.The upper necking 212 is connected simultaneously with the exhaust portion 3 It is connected to second combustion chamber 23 and the exhaust portion 3.Described to block fiery 22 outer rim of intake section and connect with the cylinder 21, inside is opened Equipped with exhaust duct 24, and a circle third air inlet 222 is offered in the connection wall 221 round the exhaust duct 24.It is described to block An air duct 223 is equipped with inside fiery intake section 22;The third air inlet 222 is connected to the air duct 223 and the exhaust duct 24.? In the present embodiment, it is described block fiery intake section 22 include a hollow round table 224, a cored slab 225 and the connection wall 221; 224 miner diameter end of hollow round table is directed toward the first furnace body 1, and coaxial with the outer cylinder 11, the inner cylinder 12;The hollow round table The air duct 223 is offered between 224 and the cored slab 225;The cored slab 225 offers hole 2251, the connection wall The edge and 224 miner diameter end of hollow round table in the 221 connection holes 2251, and offer the third air inlet 222;It is described The diameter of 224 miner diameter end of hollow round table is less than or equal to the diameter in the hole 2251;The third air inlet 222 is connected to described Air duct 223 and the exhaust duct 24;Along the direction that first furnace body 1 is directed toward in the exhaust portion 3, the hollow round table 224, The cored slab 225 is arranged successively;The spout 6 is connect with 2 bottom of the second furnace body, the 6 bottom surface direction of spout The central axis direction of second furnace body diagonally downward so that feed end is high and discharge end is low.Preferably, in the hollow round table On 224 axis direction, 222 axis of third air inlet is tilted towards 1 side of the first furnace body;Perpendicular to the sky In the plane of 224 axis of heart rotary table, tangential side of 222 axis of third air inlet towards the position in place connection wall 221 To inclination.Preferably, the central axis of the cored slab 225 and the cylinder 21.In another embodiment of the present invention, The hollow sealing portion 14 is the extension of the lower necking 211, and lower 211 miner diameter end of necking is connected with the inner cylinder 12, institute Outer cylinder 11 is stated to be connected with the side wall of the lower necking 211 or bigger diameter end.
The exhaust portion 3 includes smoke exhaust pipe 31, diversion division 32 and rain cover 33.The diversion division 32, the smoke exhaust pipe 31 It is surrounded by preheating space 34 with the upper necking 212, the top of the exhaust portion 3 is arranged in the rain cover 33.The water conservancy diversion The air inlet 35 for being connected to atmosphere with the preheating space 34 is offered in portion 32.In the present embodiment, the diversion division 32 For the rotary table that a major diameter is identical as upper 212 major diameter of necking and connect with upper 212 bigger diameter end of necking, and the water conservancy diversion The taper in portion 32 is greater than the taper of the upper necking 212, and the miner diameter end of the diversion division 32 is connect with the smoke exhaust pipe 31.Especially Ground, the outer cylinder 11, the inner cylinder 12, the cylinder 21, the hollow round table 224, the hole, the smoke exhaust pipe 31 are coaxial.
The induced duct 4 includes the 41, first manifold 42 of supervisor and the second manifold 43.41 one end of the supervisor and the preheating Space 34 is connected to, and the other end be connected to first manifold 41, the second manifold 43, first manifold 41 be connected to it is described be responsible for and The air duct, the second manifold connection supervisor 41 and the ventilation space 17.The blower 5 is connected to the supervisor 41 On, from 34 air inlet of preheating space, and to 43 outlet of first manifold 42 and the second manifold.
In use, rubbish is poured into the waste incinerator 100 from spout 6, rubbish falls into institute along the spout 6 The inner cylinder 12 of the first furnace body 1 is stated, blower 5 is then opened and supplies, rubbish is lighted using charcoal and gasoline, with gradually increasing for furnace temperature And the increase of intake air temperature, the moisture in rubbish are gradually evaporated, therefore are not had to add charcoal and gasoline rubbish again and can all be continued Burning.Solid decomposites a large amount of unburnt gas when first combustion chamber 16 is burnt, these imperfect combustion gas Body can be again when second combustion chamber 23 encounters second air inlet 122, the air that the third air inlet 222 sprays Burning.Since the third air inlet 222 is tangentially into second combustion chamber 23, meeting is in second combustion chamber 23 Middle formation vortex, mixes well with air unburnt gas, improves the efficiency of combustion of unburnt gas.Meanwhile Since the temperature of second combustion chamber 23 reaches 950-1100 DEG C, the dioxin generated during incineration firing is described second Combustion chamber 23 is decomposed, and greatly reduces the discharge of dioxin.
Meanwhile the imperfect combustion particle in combustion process is oven-dried the vapor generated when rubbish and solid refuse burning It clings to fall and blocks fiery intake section 22 described, block fiery 22 top surface of intake section due to described and tilt down and be affected by gravity, no Completely burned particle eventually falls into the first combustion chamber 16 and burns again, makes described to block fiery intake section 22 and be not easy to accumulate Charcoal.
Fresh air is preheated in preheating space 34 by smoke exhaust pipe 3 after passing through air inlet 35, and by the blower 5 described in Induced duct 4 introduces the first combustion chamber 16 and the second combustion chamber 23.
Lime-ash after incineration firing falls the bottom in the first furnace body 1, can be taken out by slag-drip opening 7.
The present invention is used for the first furnace body 1 of burning solid rubbish by being arranged, for decomposing when burning solid incineration firing Second furnace body 2 of gas out, and be provided with after exhaust portion 3, induced duct 4 and blower 5 preheat fresh air and introduce first Furnace body 1 and the second furnace body 2 improve the first combustion chamber 16, the intake air temperature of the second combustion chamber 23 and drying and are deposited in the first combustion Burn room 16 in rubbish, improve the temperature of waste incinerator 100, make the temperature in waste incinerator 100 reach 950 DEG C~ 1100 DEG C, reach the decomposition temperature of dioxin, greatly reduces the discharge of dioxin.Meanwhile it is when drying rubbish and solid Vapor can be generated when body incineration firing, the imperfect combustion particle in combustion process, which is clung to fall by vapor, is blocking fiery air inlet In portion 22, tilts down and be affected by gravity due to blocking fiery 22 top surface of intake section, imperfect combustion particle eventually falls into first It burns in combustion chamber 16 and again.
Above description is the detailed description for the present invention preferably possible embodiments, but embodiment is not limited to this hair Bright patent claim, it is all the present invention suggested by technical spirit under completed same changes or modifications change, should all belong to In the covered the scope of the patents of the present invention.

Claims (6)

1. a kind of waste incinerator, it is characterised in that: the waste incinerator includes the first furnace body, the second furnace body, blower, air inducing Pipe and exhaust portion, and it is equipped with spout and slag-drip opening;First furnace body includes outer cylinder, inner cylinder, hollow sealing portion and bottom plate;Institute It states inner cylinder to be arranged in outer barrel, the bottom surface of the inner cylinder and the outer cylinder is arranged in the bottom plate;The hollow sealing portion opens Equipped with through-hole, and connect the top of the inner cylinder and the outer cylinder;Be the first combustion chamber inside the inner cylinder, and with it is described outer Cylinder, the hollow sealing portion and the bottom plate are surrounded by ventilation space together;The inner cylinder lower sidewall and top open up respectively There are the first air inlet, the second air inlet, the slag-drip opening is arranged in first bottom of furnace body, and connects with first combustion chamber It is logical;Second furnace body includes cylinder and blocks fiery intake section;The inner barrel is the second combustion chamber, and one end and the row The connection of cigarette portion, the other end are connected to by the through-hole with the inner cylinder;The cylinder both ends are respectively arranged with necking, lower contracting Mouthful;Be connected at the top of the lower necking and first furnace body and be connected to the first combustion chamber and the second combustion chamber, the upper necking and The exhaust portion is connected and is connected to second combustion chamber and exhaust portion;It is described that block fiery intake section include hollow round table, cored slab And connection wall, outer rim are connect with the cylinder, inside offers exhaust duct;The miner diameter end of the hollow round table is directed toward the first furnace Body, and it is coaxial with the outer cylinder;The connection wall connects the interior edge of the hollow round table miner diameter end and the cored slab, and opens up There is third air inlet;On the axis direction of the hollow round table, the third air inlet axially bored line is rolled towards the first furnace body one Tiltedly, on the plane perpendicular to the hollow round table axis, the third air inlet axially bored line is towards the position in the connection wall of place Tangential direction inclination;Air duct is offered between the hollow round table and the cored slab;The cored slab offers hole, and hangs down Directly in the axis of the cylinder;The connection wall connects the edge and the hollow round table miner diameter end in the hole, the open circles The diameter of platform miner diameter end is less than or equal to the diameter in the hole;The third air inlet is connected to the air duct and the exhaust Road;The exhaust portion includes smoke exhaust pipe and diversion division;It is described hollow along the direction that the smoke exhaust pipe is directed toward first furnace body Rotary table, the cored slab are arranged successively;Preheating space is surrounded by the top of the diversion division, the smoke exhaust pipe and the cylinder;Institute State the air inlet for offering on diversion division and being connected to atmosphere with preheating space;The induced duct is connected to the preheating space, described Block fiery intake section and the outer cylinder;Gas in the preheating space can be sent to first combustion chamber, institute by the blower State the second combustion chamber;The outer cylinder, the inner cylinder, the cylinder, the hollow round table, the hole, the smoke exhaust pipe are coaxial.
2. waste incinerator as described in claim 1, it is characterised in that: the spout bottom surface is towards second furnace body Central axis direction diagonally downward so that feed end is high and discharge end is low.
3. waste incinerator as claimed in claim 2, it is characterised in that: the exhaust portion further includes rain cover, the rain-proof It is provide with and sets at the top of the exhaust portion.
4. such as waste incinerator as claimed in any one of claims 1-3, it is characterised in that: the induced duct includes supervisor and discrimination Pipe, described supervisor one end is connected to the preheating space, and the other end is connected to the manifold, the manifold be connected to it is described be responsible for, The air duct and the ventilation space.
5. waste incinerator as claimed in claim 4, it is characterised in that: the blower is connected on the supervisor, from described Preheating space air inlet, to the manifold exhaust.
6. waste incinerator as claimed in claim 5, it is characterised in that: the waste incinerator further includes support frame, described Support frame is uniformly arranged on the side wall of the outer cylinder, is used to support the waste incinerator.
CN201510568337.7A 2015-09-08 2015-09-08 A kind of waste incinerator Active CN105066140B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510568337.7A CN105066140B (en) 2015-09-08 2015-09-08 A kind of waste incinerator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510568337.7A CN105066140B (en) 2015-09-08 2015-09-08 A kind of waste incinerator

Publications (2)

Publication Number Publication Date
CN105066140A CN105066140A (en) 2015-11-18
CN105066140B true CN105066140B (en) 2018-12-18

Family

ID=54495574

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510568337.7A Active CN105066140B (en) 2015-09-08 2015-09-08 A kind of waste incinerator

Country Status (1)

Country Link
CN (1) CN105066140B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109224793A (en) * 2018-11-26 2019-01-18 佛山科学技术学院 A kind of equipment using fence corona shower discharge treatment volatile organic contaminant
CN110307549A (en) * 2019-07-09 2019-10-08 江苏维尔思环境工程股份有限公司 A kind of minimum discharge can UTILIZATION OF VESIDUAL HEAT IN three industrial wastes furnace

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2655050Y (en) * 2003-09-25 2004-11-10 陈泽鹏 Two-section type refuse pyrolysis gasifying incinerator
CN101033845A (en) * 2007-04-23 2007-09-12 王延德 Self-burning simple harmless life refuse high temperature combustion furnace
CN204329032U (en) * 2014-12-19 2015-05-13 张殿才 A kind ofly can to burn separately or the incinerator of mixed burning
CN205026678U (en) * 2015-09-08 2016-02-10 广西南岜仔科技有限公司 Garbage incinerator

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03274309A (en) * 1990-03-23 1991-12-05 Nippon Puraiburiko Kk Incinerator for polymer material to be incinerated
CN201507930U (en) * 2009-03-20 2010-06-16 白世义 Straight-line destructor

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2655050Y (en) * 2003-09-25 2004-11-10 陈泽鹏 Two-section type refuse pyrolysis gasifying incinerator
CN101033845A (en) * 2007-04-23 2007-09-12 王延德 Self-burning simple harmless life refuse high temperature combustion furnace
CN204329032U (en) * 2014-12-19 2015-05-13 张殿才 A kind ofly can to burn separately or the incinerator of mixed burning
CN205026678U (en) * 2015-09-08 2016-02-10 广西南岜仔科技有限公司 Garbage incinerator

Also Published As

Publication number Publication date
CN105066140A (en) 2015-11-18

Similar Documents

Publication Publication Date Title
CN205026675U (en) Garbage incinerator
CN105066139B (en) A kind of waste incinerator
CN105090968B (en) A kind of waste incinerator
CN105066140B (en) A kind of waste incinerator
CN206600832U (en) One kind is used for solid waste incinerator
CN105090972A (en) Garbage incinerator
CN105135440A (en) Garbage incinerator
CN205037307U (en) Garbage incinerator
CN205037303U (en) Garbage incinerator
CN206817469U (en) A kind of house refuse burning processing device
CN105042597B (en) A kind of waste incinerator
CN205119079U (en) Garbage incinerator
CN105090978B (en) A kind of waste incinerator
CN204987026U (en) Garbage incinerator
CN205026681U (en) Garbage incinerator
CN205037308U (en) Garbage incinerator
CN205048451U (en) Garbage incinerator
CN105090967A (en) Garbage incinerator
CN105090979B (en) A kind of waste incinerator
CN205026676U (en) Garbage incinerator
CN205037306U (en) Garbage incinerator
CN205037311U (en) Incinerator
CN205026678U (en) Garbage incinerator
CN105066141B (en) A kind of waste incinerator
CN205065731U (en) Garbage incinerator

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201210

Address after: 530021 the first floor of the supporting comprehensive building of Haozhuang Yipin Zunfu, No.5, Yinghua Road, Qingxiu District, Nanning City, Guangxi Zhuang Autonomous Region

Patentee after: Guangxi Gehui Construction Engineering Co.,Ltd.

Address before: 533800 318 Xinsheng street, Xinjing Town, Jingxi County, Baise, the Guangxi Zhuang Autonomous Region

Patentee before: GUANGXI XIUMEIZHUANGXIANG ENERGY ENVIRONMENTAL PROTECTION Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210616

Address after: 362005 No.10 Huangshi East Road, Huangshi community, Fuqiao street, Licheng District, Quanzhou City, Fujian Province

Patentee after: FUJIAN HUIXIN ENVIRONMENTAL TECHNOLOGY CO.,LTD.

Address before: 530021 the first floor of the supporting comprehensive building of Haozhuang Yipin Zunfu, No.5, Yinghua Road, Qingxiu District, Nanning City, Guangxi Zhuang Autonomous Region

Patentee before: Guangxi Gehui Construction Engineering Co.,Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: No. 46, Huangshi East Road, Huangshi Community, Fuqiao Street, Licheng District, Quanzhou City, Fujian Province, 362,000

Patentee after: Fujian Huixin Environmental Protection Technology Co.,Ltd.

Address before: 362005 No.10 Huangshi East Road, Huangshi community, Fuqiao street, Licheng District, Quanzhou City, Fujian Province

Patentee before: FUJIAN HUIXIN ENVIRONMENTAL TECHNOLOGY CO.,LTD.