CN105064513A - Concrete outer wall screw rod hole sealing and blocking structure and construction method of concrete outer wall screw rod hole sealing and blocking structure - Google Patents
Concrete outer wall screw rod hole sealing and blocking structure and construction method of concrete outer wall screw rod hole sealing and blocking structure Download PDFInfo
- Publication number
- CN105064513A CN105064513A CN201510491864.2A CN201510491864A CN105064513A CN 105064513 A CN105064513 A CN 105064513A CN 201510491864 A CN201510491864 A CN 201510491864A CN 105064513 A CN105064513 A CN 105064513A
- Authority
- CN
- China
- Prior art keywords
- exterior wall
- screw hole
- screw rod
- rod hole
- concrete exterior
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Road Paving Structures (AREA)
Abstract
The invention discloses a concrete outer wall screw rod hole sealing and blocking structure, which comprises a concrete outer wall and a screw rod hole, wherein the screw rod hole penetrates through the cross section of the concrete outer wall; injection holes are formed in the inner side and the outer side of the screw rod hole; the screw rod hole is filled with foaming agents; waterproof mortar is injected into the injection holes of the screw holes formed at the two sides of the foaming agents and is used for sealing and blocking; three polyurethane waterproof paint layers sequentially coat the outer side surface of the concrete outer wall; and then, a cement mortar protection layer coats the outside of the three polyurethane paint layers for integrally sealing and blocking the screw rod hole. The invention also discloses a concrete outer wall screw rod hole sealing and blocking construction method. Compared with a conventional construction method, the concrete outer wall screw rod hole sealing and blocking construction method has the advantages that the operation process is simple; the implementation is easy; the concrete outer wall screw rod hole water seepage phenomenon is avoided; the anti-seepage effect of the construction method is good; the seepage due to improper screw rod hole sealing and blocking processing of the concrete outer wall surface is avoided; the engineering progress and the quality guarantee are facilitated; the repair cost due to seepage can be greatly reduced by the same concrete outer wall; and the cost is reduced.
Description
Technical field
The present invention relates to a kind of concrete exterior wall screw hole plugging structure.
The invention still further relates to a kind of concrete exterior wall screw hole plugging construction method.Be applicable to the construction of concrete exterior wall screw hole shutoff in civilian construction and industrial construction cast-in-situ concrete.
Background technology
Traditional concrete exterior wall screw hole, for the common quality defect preventing sealing hole imprecision from producing seepage, in screw hole, fill the method such as cement mortar or blowing agent shutoff, but in these two kinds of method application processes, water-proof plug hole effect is general, correspondingly adds the time of reprocessing and expense.
Therefore, need to provide a kind of new technical scheme to solve the problems referred to above.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of concrete exterior wall screw hole plugging structure.
The technical problem that the present invention also will solve is to provide a kind of concrete exterior wall screw hole plugging construction method.
For solving the problems of the technologies described above; a kind of concrete exterior wall screw hole plugging structure of the present invention; comprise concrete exterior wall and screw hole; described screw hole is through concrete exterior wall cross section; injection hole is formed in the inside and outside both sides of screw hole; blowing agent is filled with in described screw hole; waterproofing mortar is injected for shutoff in the screw hole injection hole of blowing agent both sides; the lateral surface of described concrete exterior wall is brushed successively three road polyurethane water-proof paint layers, polyurethane water-proof paint layer outer brushing cement mortar protective course in Zai tri-road carrys out comprehensive shutoff screw hole.
The thickness of described waterproofing mortar is 30 ㎜.
The thickness of described polyurethane water-proof paint layer is 1 ㎜.
The thickness of described cement mortar protective course is 10 ㎜.
A kind of concrete exterior wall screw hole plugging construction method,
(1) pvc pipe is rejected: concrete exterior wall face die plate rejects pvc pipe with chisel after removing, and removes the residual slurry in reserving hole, blows off the grieshoch of the inside outside concrete exterior wall with little hair-dryer;
(2) waterproofing mortar shutoff: inject appropriate water with water jet in screw hole and keep fully moistening, inwardly waterproofing mortar is injected with special tool again after hole is slightly dry, the position of waterproofing mortar shutoff is that in concrete exterior wall, each 30 ㎜ in outside are thick, centre blowing agent tamps, inside outer wall screw hole outwards, compacting is floating for waterproofing mortar;
(3) blowing agent tamps: in concrete exterior wall, the middle blowing agent that adopts of outside waterproofing mortar shutoff tamps, after the waterproofing mortar sclerosis of inner side, blowing agent is squeezed in hole, when waiting blowing agent to solidify 60% soon, with instrument, outstanding blowing agent is compressed into hole, outside waterproofing mortar shutoff;
(4) water-repellent paint construction: after the waterproofing mortar sclerosis outside concrete exterior wall, brush the heterochromatic polyurethane water-proof paint that three road 1 ㎜ are thick in outside;
(5) topping construction: after above-mentioned water-repellent paint drying, at the cement mortar protective course that surface construction 10 ㎜ is thick, cement mortar protective course has been constructed rear reinforcement maintenance.
Beneficial effect of the present invention: compared with traditional construction method, operating process is simple, easy, stop concrete exterior wall screw hole infiltration phenomenon, this construction good seepage-proof property, stop the seepage that concrete exterior wall face is caused because screw hole shutoff process is not good at, be conducive to programming, guarantee quality, same concrete exterior wall can greatly reduce cause because of seepage reprocess expense, cost-saving.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention.
Fig. 2 is the enlarged diagram at A place in Fig. 1.
Wherein: 1, concrete exterior wall, 2, screw hole, 3, injection hole, 4, blowing agent, 5, waterproofing mortar, 6, polyurethane water-proof paint layer, 7, cement mortar protective course.
Detailed description of the invention
In order to deepen the understanding of the present invention, below in conjunction with embodiment and accompanying drawing, the invention will be further described, and this embodiment, only for explaining the present invention, does not form the restriction to protection scope of the present invention.
As illustrated in fig. 1 and 2, a kind of concrete exterior wall screw hole plugging structure of the present invention, comprise concrete exterior wall 1 and screw hole 2, screw hole 2 is through concrete exterior wall 1 cross section, in screw hole 2, outer both sides form injection hole 3, blowing agent 4 is filled with in screw hole 2, waterproofing mortar 5 is injected for shutoff in screw hole 2 injection hole 3 of blowing agent 4 both sides, the thickness of waterproofing mortar 5 is 30 ㎜, the lateral surface of concrete exterior wall 1 is brushed successively three road polyurethane water-proof paint layers 6, the thickness of polyurethane water-proof paint layer 6 is 1 ㎜, the comprehensive shutoff screw hole 2 of the outer brushing cement mortar protective course 7 of Zai tri-road polyurethane water-proof paint layer 6, the thickness of cement mortar protective course 7 is 10 ㎜.
A kind of concrete exterior wall screw hole plugging construction method,
(1) pvc pipe is rejected: concrete exterior wall face die plate rejects pvc pipe with chisel after removing, and removes the residual slurry in reserving hole, blows off the grieshoch of the inside outside concrete exterior wall with little hair-dryer;
(2) waterproofing mortar shutoff: inject appropriate water with water jet in screw hole 2 and keep fully moistening, waterproofing mortar 5 is inwardly injected with special tool again after hole is slightly dry, the position of waterproofing mortar 5 shutoff is that in concrete exterior wall, each 30 ㎜ in outside are thick, centre blowing agent 4 tamps, adopt the waterproofing mortar 5 of DP20 outside inside outer wall screw hole 2, compacting is floating;
(3) blowing agent tamps: in concrete exterior wall, the middle blowing agent 4 that adopts of outside waterproofing mortar 5 shutoff tamps, after waterproofing mortar 5 sclerosis of inner side, blowing agent 4 is squeezed in hole, when solidifying 60% soon Deng blowing agent 4, with instrument, outstanding blowing agent 4 is compressed into hole, outside waterproofing mortar 5 shutoff;
(4) water-repellent paint construction: the waterproofing mortar 5 outside concrete exterior wall 1 brushes the heterochromatic polyurethane water-proof paint layer 6 that three road 1 ㎜ are thick after hardening in outside;
(5) topping construction: after above-mentioned water-repellent paint drying, at the cement mortar protective course 7 that surface construction 10 ㎜ is thick, cement mortar protective course 7 has been constructed rear reinforcement maintenance.
Change traditional construction technology filling cement mortar or blowing agent shutoff in screw hole; carry out comprehensive shutoff with the thick waterproofing mortar of 30 ㎜, blowing agent, waterproofing mortar that 30 ㎜ are thick, polyurethane water-proof paint that three road 1 ㎜ are thick, cement mortar protective course that 10 ㎜ are thick successively at concrete exterior wall from-inner-to-outer, stop concrete exterior wall screw hole infiltration phenomenon.This construction good seepage-proof property, has saved greatly and has reprocessed cost, avoided common quality defect.
Claims (5)
1. a concrete exterior wall screw hole plugging structure; comprise concrete exterior wall and screw hole; described screw hole is through concrete exterior wall cross section; it is characterized in that: form injection hole in the inside and outside both sides of screw hole; blowing agent is filled with in described screw hole; waterproofing mortar is injected for shutoff in the screw hole injection hole of blowing agent both sides; the lateral surface of described concrete exterior wall is brushed successively three road polyurethane water-proof paint layers, polyurethane water-proof paint layer outer brushing cement mortar protective course in Zai tri-road carrys out comprehensive shutoff screw hole.
2. a kind of concrete exterior wall screw hole seal structure according to claim 1, is characterized in that: the thickness of described waterproofing mortar is 30 ㎜.
3. a kind of concrete exterior wall screw hole seal structure according to claim 1, is characterized in that: the thickness of described polyurethane water-proof paint layer is 1 ㎜.
4. a kind of concrete exterior wall screw hole plugging construction method according to claim 1, is characterized in that: the thickness of described cement mortar protective course is 10 ㎜.
5. a kind of concrete exterior wall screw hole plugging construction method according to claim 1, is characterized in that:
(1) pvc pipe is rejected: concrete exterior wall face die plate rejects pvc pipe with chisel after removing, and removes the residual slurry in reserving hole, blows off the grieshoch of the inside outside concrete exterior wall with little hair-dryer;
(2) waterproofing mortar shutoff: inject appropriate water with water jet in screw hole and keep fully moistening, inwardly waterproofing mortar is injected with special tool again after hole is slightly dry, the position of waterproofing mortar shutoff is that in concrete exterior wall, each 30 ㎜ in outside are thick, centre blowing agent tamps, inside outer wall screw hole outwards, compacting is floating for waterproofing mortar;
(3) blowing agent tamps: in concrete exterior wall, the middle blowing agent that adopts of outside waterproofing mortar shutoff tamps, after the waterproofing mortar sclerosis of inner side, blowing agent is squeezed in hole, when waiting blowing agent to solidify 60% soon, with instrument, outstanding blowing agent is compressed into hole, outside waterproofing mortar shutoff;
(4) water-repellent paint construction: after the waterproofing mortar sclerosis outside concrete exterior wall, brush the heterochromatic polyurethane water-proof paint that three road 1 ㎜ are thick in outside;
(5) topping construction: after above-mentioned water-repellent paint drying, at the cement mortar protective course that surface construction 10 ㎜ is thick, cement mortar protective course has been constructed rear reinforcement maintenance.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510491864.2A CN105064513A (en) | 2015-08-12 | 2015-08-12 | Concrete outer wall screw rod hole sealing and blocking structure and construction method of concrete outer wall screw rod hole sealing and blocking structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510491864.2A CN105064513A (en) | 2015-08-12 | 2015-08-12 | Concrete outer wall screw rod hole sealing and blocking structure and construction method of concrete outer wall screw rod hole sealing and blocking structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105064513A true CN105064513A (en) | 2015-11-18 |
Family
ID=54494000
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510491864.2A Pending CN105064513A (en) | 2015-08-12 | 2015-08-12 | Concrete outer wall screw rod hole sealing and blocking structure and construction method of concrete outer wall screw rod hole sealing and blocking structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105064513A (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106088447A (en) * | 2016-06-12 | 2016-11-09 | 中国十七冶集团有限公司 | A kind of exterior wall builder's jack shaped steel eye protective brick device and construction method |
CN106639313A (en) * | 2017-02-21 | 2017-05-10 | 潍坊市宏源防水材料有限公司 | Rubber water stopping plug and construction method for plugging and stopping water of opposite-pull bolt hole of underground outer wall template |
CN109577639A (en) * | 2018-12-28 | 2019-04-05 | 山西五建集团有限公司 | Exterior wall protects mould integrated board and aluminum alloy mould plate combined system construction method |
CN110185260A (en) * | 2019-05-24 | 2019-08-30 | 五冶集团上海有限公司 | A kind of shear wall screw hole antiseep method for blocking through walls |
CN110344506A (en) * | 2019-07-12 | 2019-10-18 | 无锡市亨利富建设发展有限公司 | A kind of exterior wall split bolt hole antiseep blocks treatment process |
CN110863667A (en) * | 2019-10-31 | 2020-03-06 | 上海建工七建集团有限公司 | Anti-seepage plugging structure and method for concrete shear wall screw hole |
CN111058629A (en) * | 2020-02-27 | 2020-04-24 | 中国二十二冶集团有限公司 | Construction method for plugging through-wall bolt hole of concrete outer wall |
CN111350294A (en) * | 2020-03-19 | 2020-06-30 | 中国十七冶集团有限公司 | Shear wall outer wall through-wall screw hole plugging device and construction method thereof |
CN111910944A (en) * | 2020-07-20 | 2020-11-10 | 中铁十六局集团有限公司 | Bolt hole plugging method |
CN112554591A (en) * | 2020-11-16 | 2021-03-26 | 浙江至方建设有限公司 | Construction method for anti-seepage inner and outer walls |
CN113668899A (en) * | 2021-09-27 | 2021-11-19 | 贵州建工集团第一建筑工程有限责任公司 | Construction method for plugging concrete outer wall hole |
CN113775197A (en) * | 2021-05-17 | 2021-12-10 | 天津住宅集团建设工程总承包有限公司 | Construction method for plugging and preventing leakage of concrete outer wall through-wall bolt hole |
CN116815938A (en) * | 2023-07-19 | 2023-09-29 | 北京城建一建设发展有限公司 | Anti-leakage construction method for EVE assembled shear wall structure outer wall |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE19535555A1 (en) * | 1995-09-25 | 1997-03-27 | Gts Ges Fuer Technologie Im St | Device to bridge over holes in vapour barriers for walls, floors and ceilings etc |
CN202559540U (en) * | 2012-05-08 | 2012-11-28 | 中建六局建设发展有限公司 | Waterproof plugging structure for outer wall split bolt hole |
CN203961067U (en) * | 2014-01-28 | 2014-11-26 | 中建四局第五建筑工程有限公司 | The external wall structure in a kind of shutoff screw rod hole |
CN204898902U (en) * | 2015-08-12 | 2015-12-23 | 江苏南通三建集团有限公司 | Concrete outer wall screw rod hole block structure |
-
2015
- 2015-08-12 CN CN201510491864.2A patent/CN105064513A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE19535555A1 (en) * | 1995-09-25 | 1997-03-27 | Gts Ges Fuer Technologie Im St | Device to bridge over holes in vapour barriers for walls, floors and ceilings etc |
CN202559540U (en) * | 2012-05-08 | 2012-11-28 | 中建六局建设发展有限公司 | Waterproof plugging structure for outer wall split bolt hole |
CN203961067U (en) * | 2014-01-28 | 2014-11-26 | 中建四局第五建筑工程有限公司 | The external wall structure in a kind of shutoff screw rod hole |
CN204898902U (en) * | 2015-08-12 | 2015-12-23 | 江苏南通三建集团有限公司 | Concrete outer wall screw rod hole block structure |
Non-Patent Citations (1)
Title |
---|
南通四建集团有限公司等: "外墙螺栓孔封堵方案", 《百度文库》 * |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106088447A (en) * | 2016-06-12 | 2016-11-09 | 中国十七冶集团有限公司 | A kind of exterior wall builder's jack shaped steel eye protective brick device and construction method |
CN106088447B (en) * | 2016-06-12 | 2018-08-17 | 中国十七冶集团有限公司 | A kind of exterior wall builder's jack shaped steel hole eye protection brick device and construction method |
CN106639313A (en) * | 2017-02-21 | 2017-05-10 | 潍坊市宏源防水材料有限公司 | Rubber water stopping plug and construction method for plugging and stopping water of opposite-pull bolt hole of underground outer wall template |
CN106639313B (en) * | 2017-02-21 | 2019-08-27 | 宏源防水科技集团有限公司 | A kind of rubber water-proof plug and underground external wall template split bolt hole block water stop construction method |
CN109577639A (en) * | 2018-12-28 | 2019-04-05 | 山西五建集团有限公司 | Exterior wall protects mould integrated board and aluminum alloy mould plate combined system construction method |
CN110185260A (en) * | 2019-05-24 | 2019-08-30 | 五冶集团上海有限公司 | A kind of shear wall screw hole antiseep method for blocking through walls |
CN110344506A (en) * | 2019-07-12 | 2019-10-18 | 无锡市亨利富建设发展有限公司 | A kind of exterior wall split bolt hole antiseep blocks treatment process |
CN110863667A (en) * | 2019-10-31 | 2020-03-06 | 上海建工七建集团有限公司 | Anti-seepage plugging structure and method for concrete shear wall screw hole |
CN111058629A (en) * | 2020-02-27 | 2020-04-24 | 中国二十二冶集团有限公司 | Construction method for plugging through-wall bolt hole of concrete outer wall |
CN111350294A (en) * | 2020-03-19 | 2020-06-30 | 中国十七冶集团有限公司 | Shear wall outer wall through-wall screw hole plugging device and construction method thereof |
CN111910944A (en) * | 2020-07-20 | 2020-11-10 | 中铁十六局集团有限公司 | Bolt hole plugging method |
CN112554591A (en) * | 2020-11-16 | 2021-03-26 | 浙江至方建设有限公司 | Construction method for anti-seepage inner and outer walls |
CN113775197A (en) * | 2021-05-17 | 2021-12-10 | 天津住宅集团建设工程总承包有限公司 | Construction method for plugging and preventing leakage of concrete outer wall through-wall bolt hole |
CN113668899A (en) * | 2021-09-27 | 2021-11-19 | 贵州建工集团第一建筑工程有限责任公司 | Construction method for plugging concrete outer wall hole |
CN116815938A (en) * | 2023-07-19 | 2023-09-29 | 北京城建一建设发展有限公司 | Anti-leakage construction method for EVE assembled shear wall structure outer wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105064513A (en) | Concrete outer wall screw rod hole sealing and blocking structure and construction method of concrete outer wall screw rod hole sealing and blocking structure | |
CN202730973U (en) | Concrete outer wall bolt hole leakproof structure | |
CN202559540U (en) | Waterproof plugging structure for outer wall split bolt hole | |
CN205591363U (en) | Building outer wall is encorbelmented scaffold frame shaped steel and is reserved hole shutoff structure | |
CN104153400B (en) | Construction method for preventing soft soil foundation cast-in-place pile head from being waterproof | |
CN105239789A (en) | Construction process for plugging and consolidating concrete crack through chemical grouting | |
CN204898902U (en) | Concrete outer wall screw rod hole block structure | |
CN204703312U (en) | A kind of outer shear wall bolt hole plugging structure | |
CN105064579B (en) | A kind of construction method ensureing toilet water stopping thresholds platform pouring molding | |
CN206205164U (en) | A kind of device and the external wall structure of screw hole closure for the closure of outer wall screw hole | |
CN108412222A (en) | A kind of construction leakage internal maintenance waterproof layer structure and construction technology | |
CN109056843A (en) | A kind of FS101, FS102 underground rigid composite water-proof construction method | |
CN103498486A (en) | Method for blocking post-cast strip downcast pipe well through sleeve pipe | |
CN104746479A (en) | Diversion tunnel concrete water seepage leaking stoppage construction method | |
JP2018203582A5 (en) | ||
CN105274967A (en) | Repairing method for hydraulic concrete crack | |
CN104179205A (en) | Anticorrosion reinforcing method of transmission line tower foundation | |
CN111851570A (en) | Reinforced concrete retaining wall mold and mounting method thereof | |
CN105587938A (en) | Toilet pipe root blocking structure and construction process thereof | |
CN105178364B (en) | Underground building light precipitation well point post-cast strip anti-seepage construction method | |
CN106759308B (en) | A kind of precast hollow pile head waterproof construction method | |
CN108867709A (en) | A kind of waterproofing for basement method | |
CN104047268B (en) | Dam reinforcement method | |
CN207079637U (en) | A kind of poured band of outer wall of basement water sealing structure | |
CN204982923U (en) | Foundation ditch stagnant water curtain reinforcement structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information |
Address after: 226100 Jiangsu city of Nantong Province Haimen Shishan Road No. 131 Applicant after: Jiangsu Nantong three construction group Limited by Share Ltd Address before: 226100 Jiangsu city of Nantong Province Haimen Shishan Road No. 131 Applicant before: Jiangsu Nantong No.3 Construction Group Co., Ltd. |
|
CB02 | Change of applicant information | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20151118 |
|
RJ01 | Rejection of invention patent application after publication |