CN105044451A - Power compensation optimizing method used in electric energy meter replacement in live working state based on least square method curve fitting - Google Patents

Power compensation optimizing method used in electric energy meter replacement in live working state based on least square method curve fitting Download PDF

Info

Publication number
CN105044451A
CN105044451A CN201510353832.6A CN201510353832A CN105044451A CN 105044451 A CN105044451 A CN 105044451A CN 201510353832 A CN201510353832 A CN 201510353832A CN 105044451 A CN105044451 A CN 105044451A
Authority
CN
China
Prior art keywords
electric energy
energy meter
power
time
curve fitting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510353832.6A
Other languages
Chinese (zh)
Other versions
CN105044451B (en
Inventor
朱梦梦
李仕林
翟少磊
王洪林
林聪�
朱全聪
于辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute of Yunnan Power System Ltd
Original Assignee
Electric Power Research Institute of Yunnan Power System Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Research Institute of Yunnan Power System Ltd filed Critical Electric Power Research Institute of Yunnan Power System Ltd
Priority to CN201510353832.6A priority Critical patent/CN105044451B/en
Publication of CN105044451A publication Critical patent/CN105044451A/en
Application granted granted Critical
Publication of CN105044451B publication Critical patent/CN105044451B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

Provided is a power compensation optimizing method used in electric energy meter replacement in a live working state based on least square method curve fitting. The method comprises the following steps of: connecting the voltage wire of a three-phase electric energy meter field calibrator with a loop in parallel and connecting the current wire of the three-phase electric energy meter field calibrator with the loop in series before an electric energy meter is replaced; when the electric energy meter is replaced, reliably connecting the secondary current test terminals of the replaced electric energy meter in a short circuit manner and measuring a current value by using a clamp ammeter in order to determine whether reliable short-circuit connection is achieved, starting a stopwatch to record replacing time; acquiring active power discrete points p(tn) within a time segment from t1 to t2 by using the three-phase electric energy meter field calibrator when replacement begins, acquiring a power curve function p(t) by using a least square method curve fitting method according to discrete point sampling values, and computing total active power lost in a meter replacing process by using a relation between power and time. The method improves the accuracy of metering results and guarantees the economic interests of a power seller and a power buyer.

Description

Based on the live replacement of electric energy meter electric quantity compensating optimization method of least square curve fit
Technical field
Patent of the present invention belongs to Electric Energy Metering Technology field, is more specifically the live replacement of electric energy meter electric quantity compensating optimization method based on least square curve fit.
Background technology
It is the work on the spot comparatively frequently that measurement centre electric energy metrical professional is engaged in that gate energy meter is changed, for ensureing that not affecting normal electricity produces and run, Electric Energy Tariff Point Metering Device renovates and adopts the online mode changed to carry out, so just relate to dismounting gate energy meter and can produce electric quantity loss during this period of time, corresponding compensation must be carried out, to ensure the economic interests of run unit by electric quantity loss during swap table.But in real work; usually changing the compensation scheme adopted in table process is before pulling down old gate energy meter, record the instantaneous voltage of gate energy meter, electric current, power and power factor; be shorted to the correct time of recovery from secondary current loop with stopwatch record simultaneously; the electric quantity loss during changing table is estimated as the average power during changing table to change the instantaneous power before table, and when the compensation electricity increased in monthly billing electricity during this part changes table.
But Source of Gateway Meter finds in changing at the scene, and above-mentioned scheme has comparatively big error when load variations is larger, is not optimal electricity compensation way.Owing to cannot accomplish accurate-metering electricity during this period of time at all, can only by manually carrying out measurements and calculations, and there is very large error, so a lot of Electricity customers is not approved the electricity of remedying calculated, thus have impact on electric power enterprise and reasonable, the just electricity consumption transaction of Electricity customers.
Summary of the invention
The object of the invention is to provide a kind of live replacement of electric energy meter electric quantity compensating optimization method based on least square curve fit, to improve the metering accuracy that in transformation, electric quantity loss compensates under Source of Gateway Meter online mode, conscientiously ensure the economic interests purchasing sale of electricity both sides.
For realizing above technical purpose, this invention takes following technical scheme:
Based on the live replacement of electric energy meter electric quantity compensating optimization method of least square curve fit, comprise the following steps: first, before carrying out changing table handling, by three-phase electric energy meter on-site calibrator device voltage link and be connected to loop, electric current wiring serial connection to loop; When carrying out changing table handling, reliable short circuit is changed electric energy meter secondary current testing terminal, and judges whether reliable short circuit by clamp reometer measurement current value size, starts stopwatch record and changes the table time; Changing when table starts utilizes three-phase electric energy meter on-site calibrator to obtain t 1to t 2the active power discrete point of time period is p (t n), then utilize least square curve fitting method to draw function p (t) of powertrace according to its discrete point sampled value, finally utilize power and time relationship to measure to change in table process and lose total active energy.
The present invention utilizes the instantaneous power dis-crete sample values of three-phase electric energy meter on-site calibrator measurement device, and record changes required time in table process, by least square fitting powertrace function, finally calculates to change in table process and loses electricity.
Beneficial effect of the present invention and advantage as follows: under the online substitute mode of gate energy meter, load fluctuation is indefinite, generally present unordered discrete point, therefore least square method is suitable for the matching of powertrace, real power curve can be approached, and then guarantee to change the accuracy of losing electric quantity metering in electric energy meter process.
Accompanying drawing explanation
Fig. 1 is the powertrace schematic diagram utilizing least square fitting.
Embodiment
Below in conjunction with the drawings and specific embodiments, the specific embodiment of the present invention is further described.
As shown in Figure 1, the present invention is a kind of live replacement of electric energy meter electric quantity compensating optimization method based on least square curve fit, comprise the following steps: first, before carrying out changing table handling, by three-phase electric energy meter on-site calibrator device voltage link and be connected to loop, electric current wiring serial connection to loop.When carrying out changing table handling, reliable short circuit is changed electric energy meter secondary current testing terminal, and judges whether reliable short circuit by clamp reometer measurement current value size, starts stopwatch record and changes the table time.Changing when table starts utilizes three-phase electric energy meter on-site calibrator to obtain t 1to t 2the active power discrete point of time period is p (t n), then utilize least square curve fitting method to draw function p (t) of powertrace according to its discrete point sampled value, and then utilize power and time relationship to measure to change in table process and lose total active energy.
The present invention utilizes the instantaneous power dis-crete sample values of three-phase electric energy meter on-site calibrator measurement device, and record changes required time in table process, by least square fitting powertrace function, finally calculates to change in table process and loses electricity.
Respectively each step is described as follows below:
1, in order to further instruction this kind of Optimization Compensation method, table 1 gives one group of discrete power data, wherein lists the power factor (PF) of each time point.
The power data that one group, table 1 is discrete
2, for above-mentioned experimental data, then utilize least square fitting function to go matching instantaneous power data, three-phase electric energy meter tester instantaneous power curve situation can be obtained as shown in Figure 1.
Above-mentioned power matched curve is for changing instantaneous power and time relationship in table process, and electricity is the area that power and time t axle surround, and then can calculate active energy is 11.6318w.And general gate energy meter electric energy is all calculate with kwh, by calculating electricity through being scaled 0.0116kwh.
Be not difficult to find, if it is more to change the number of times recording instantaneous power in table process, powertrace is close to reality, therefore at the scene in record repeatedly instantaneous power as much as possible, if three-phase electric energy meter on-site calibrator has communication function and instantaneous electric quantity writing function, computing machine can be utilized to carry out repeatedly the record of instantaneous value, can computational accuracy be improved.

Claims (2)

1. based on the live replacement of electric energy meter electric quantity compensating optimization method of least square curve fit, it is characterized in that, comprise the following steps: first, before carrying out changing table handling, by three-phase electric energy meter on-site calibrator device voltage link and be connected to loop, electric current wiring serial connection to loop; When carrying out changing table handling, reliable short circuit is changed electric energy meter secondary current testing terminal, and judges whether reliable short circuit by clamp reometer measurement current value size, starts stopwatch record and changes the table time; Changing when table starts utilizes three-phase electric energy meter on-site calibrator to obtain t 1to t 2the active power discrete point of time period is p (t n), then utilize least square curve fitting method to draw function p (t) of powertrace according to its discrete point sampled value, finally utilize power and time relationship to measure to change in table process and lose total active energy.
2. the live replacement of electric energy meter electric quantity compensating optimization method based on least square curve fit according to claim 1, it is characterized in that, utilize the instantaneous power dis-crete sample values of three-phase electric energy meter on-site calibrator measurement device, record changes required time in table process, by least square fitting powertrace function, finally calculate to change in table process and lose electricity.
CN201510353832.6A 2015-06-24 2015-06-24 Live replacement of electric energy meter electric quantity compensating optimization method based on least square curve fit Active CN105044451B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510353832.6A CN105044451B (en) 2015-06-24 2015-06-24 Live replacement of electric energy meter electric quantity compensating optimization method based on least square curve fit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510353832.6A CN105044451B (en) 2015-06-24 2015-06-24 Live replacement of electric energy meter electric quantity compensating optimization method based on least square curve fit

Publications (2)

Publication Number Publication Date
CN105044451A true CN105044451A (en) 2015-11-11
CN105044451B CN105044451B (en) 2017-12-12

Family

ID=54451140

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510353832.6A Active CN105044451B (en) 2015-06-24 2015-06-24 Live replacement of electric energy meter electric quantity compensating optimization method based on least square curve fit

Country Status (1)

Country Link
CN (1) CN105044451B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105610154A (en) * 2016-01-18 2016-05-25 云南电网有限责任公司电力科学研究院 Electric quantity compensation processing method and device for electric energy meter during on-line replacement
CN110542772A (en) * 2019-09-06 2019-12-06 国网黑龙江省电力有限公司鹤岗供电公司 Nondestructive replacement device and method for electric energy meter
CN112133029A (en) * 2020-09-15 2020-12-25 赵敏 Real-time electric quantity charging settlement method for electric energy meter replacement
CN112505613A (en) * 2020-10-29 2021-03-16 国网山东省电力公司济宁供电公司 High-power-supply high-metering full-voltage-loss metering fault loss electric quantity estimation method and system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102393480A (en) * 2011-11-11 2012-03-28 天津市电力公司 Electric quantity compensation method during live replacement of electric energy meter
CN103245809A (en) * 2013-06-03 2013-08-14 国家电网公司 Portable electric quantity remedying device and electric energy meter replacing method for accurate metering
US9318861B2 (en) * 2011-11-02 2016-04-19 ConnectDER LLC Meter collar for plug-in connection of distributed power generation
CN105974195A (en) * 2016-06-29 2016-09-28 杭州华春科技有限公司 Bypass electric quantity metering device and metering method thereof
CN104122526B (en) * 2014-06-24 2017-05-17 武汉国测恒通智能仪器有限公司 High voltage electric energy meter with metering unit capable of being charged to replace

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9318861B2 (en) * 2011-11-02 2016-04-19 ConnectDER LLC Meter collar for plug-in connection of distributed power generation
CN102393480A (en) * 2011-11-11 2012-03-28 天津市电力公司 Electric quantity compensation method during live replacement of electric energy meter
CN103245809A (en) * 2013-06-03 2013-08-14 国家电网公司 Portable electric quantity remedying device and electric energy meter replacing method for accurate metering
CN104122526B (en) * 2014-06-24 2017-05-17 武汉国测恒通智能仪器有限公司 High voltage electric energy meter with metering unit capable of being charged to replace
CN105974195A (en) * 2016-06-29 2016-09-28 杭州华春科技有限公司 Bypass electric quantity metering device and metering method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨世海 等: "一起因二次回路失压造成的上网电量追补问题分析", 《江苏电机工程》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105610154A (en) * 2016-01-18 2016-05-25 云南电网有限责任公司电力科学研究院 Electric quantity compensation processing method and device for electric energy meter during on-line replacement
CN110542772A (en) * 2019-09-06 2019-12-06 国网黑龙江省电力有限公司鹤岗供电公司 Nondestructive replacement device and method for electric energy meter
CN112133029A (en) * 2020-09-15 2020-12-25 赵敏 Real-time electric quantity charging settlement method for electric energy meter replacement
CN112505613A (en) * 2020-10-29 2021-03-16 国网山东省电力公司济宁供电公司 High-power-supply high-metering full-voltage-loss metering fault loss electric quantity estimation method and system

Also Published As

Publication number Publication date
CN105044451B (en) 2017-12-12

Similar Documents

Publication Publication Date Title
CN106569164A (en) Method and system for synchronization testing of electric quantity of double-core electric energy meter
CN105044451A (en) Power compensation optimizing method used in electric energy meter replacement in live working state based on least square method curve fitting
CN202815191U (en) Storage battery internal resistance measuring device
TWI479159B (en) Method for estimating voltage stability
WO2007063180A1 (en) Method and system for the calibration of meters
CN103412168B (en) A kind of high-precision current sampling circuit of intelligent electric meter
CN103149471A (en) Calibration method and calibration device for battery charger and charging pile
CN105116369A (en) Radio frequency radiation disturbance rejection degree test apparatus and system
CN109507630A (en) Wiring judgment method and system
CN105510864B (en) A kind of detection method of electric energy meter error metering
CN105044649B (en) A kind of current transformer error horizontal dynamic detection method and system
CN106569166B (en) A kind of test method in twin-core electric energy meter legality measurement portion
CN103558571A (en) Calibration system of electronic transformer and merging unit
CN108562860A (en) Electric energy meter two-way accessory power supply power consumption Auto-Test System and test method
CN111175689A (en) Quick electric energy meter calibration device and use method
CN105093163A (en) Error debugging method for electronic electric energy meter
CN114518549A (en) Method and system for monitoring wrong wiring mode of three-phase intelligent electric meter in real time
CN106546943B (en) Method and device for measuring error and loss self-test
CN203551762U (en) Electronic instrument transformer and merging unit verification system
CN103312561A (en) Detection method for intelligent concentrator
CN108152782B (en) Method for testing correction coefficient of high-supply high-count electric energy meter
CN114325555B (en) Metering equipment abnormality online monitoring model and error calculation method
CN112986884B (en) User metering multiplying power file checking method and system
CN204882669U (en) Change electric energy meter electric quantity with electricity and remedy optimization metering device
CN202421328U (en) Self-testing electronic electricity meter

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant