CN105040574B - A kind of hull-cable-stayed bridge is quickly crossed a river device and application thereof - Google Patents

A kind of hull-cable-stayed bridge is quickly crossed a river device and application thereof Download PDF

Info

Publication number
CN105040574B
CN105040574B CN201510487916.9A CN201510487916A CN105040574B CN 105040574 B CN105040574 B CN 105040574B CN 201510487916 A CN201510487916 A CN 201510487916A CN 105040574 B CN105040574 B CN 105040574B
Authority
CN
China
Prior art keywords
bridge
bailey beam
river
hull
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510487916.9A
Other languages
Chinese (zh)
Other versions
CN105040574A (en
Inventor
汪振
张文学
寇文琦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hainan Zhongjiao Expressway Investment And Construction Co ltd
China Highway Engineering Consultants Corp
Original Assignee
Beijing University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing University of Technology filed Critical Beijing University of Technology
Priority to CN201510487916.9A priority Critical patent/CN105040574B/en
Publication of CN105040574A publication Critical patent/CN105040574A/en
Application granted granted Critical
Publication of CN105040574B publication Critical patent/CN105040574B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of hull cable-stayed bridge quickly to cross a river device and application thereof, it includes hull and additional member, additional member is to be located at eight or the three separate formula military piers on deck, it is supported in the Bailey beam bridge on deck, military Bailey beam and direction across bridge I-steel and the floorings laid on it collectively constitute Bailey beam bridge, Bailey beam bridge and eight or three formula military piers are connected by drag-line, collectively constitute cable-stayed bridge system.Deck in ship structure, after simple transformation, can arrange runway and pass through vehicle.When setting up in river course, arranging bridge pier at river bank, overhanging Bailey beam bridge is overlapped on bridge pier, can increase the stability of hull.It is an advantage of the current invention that to be installed among boats and ships by cable-stayed bridge system, set up convenient and simple, mobility is good, fast changeable sets up place, and it is applicable to high flow rate and the complicated state of high bold shore, it is only necessary to less personnel participate in controlling, and can also save the human resources of preciousness.

Description

A kind of hull-cable-stayed bridge is quickly crossed a river device and application thereof
Technical field
The present invention relates to hull-cable-stayed bridge quickly cross a river the design of device, it is directed to current tradition and crosses a river that device (such as pontoon bridge) is poor for applicability to river, change sets up the shortcomings such as place is dumb, this design is based on boats and ships existing in river course, such as barge etc., it is installed additional cable-stayed bridge device, tradition technology for cable-stayed bridges is applied in the middle of boats and ships and plays respective advantage and the novel device of quickly crossing a river of one that formed.After original ship deck installs additional cable-stayed bridge device, the strong feature of cable-stayed bridge span ability can be made full use of to meet the temporary traffic demand in river, the combination of device of being crossed a river by varying number, the current demand of different river widths in the Changjiang river can be met.This hull-cable-stayed bridge boats and ships that device can directly utilize in the Changjiang river wartime of quickly crossing a river carry out rapid batch transformation in places such as staiths, its feature that mobility is good in river course then can be played during erection, quickly arrive at erection place, and set bridge pier on riverbank, make overhanging Bailey beam be overlapped in increase stability of hull on bridge pier.It can immediately pass through water route after fleet has passed through and change erection place, and the normal navigation impact on navigable river also can be less.Hull-cable-stayed bridge device of quickly crossing a river may be used for tradition and crosses a river place or the hydrological characteristics that device (such as pontoon bridge) cannot be carried out setting up, and its logistics support is simple, has with stopping with the advantage such as setting up, the suitability is strong.
Background technology
China is for the leap of rivers, such as the Changjiang river, the Yellow River etc., all based on Longspan Bridge, and in wartime, especially 15 Yangtze Bridge of China will strike target as first choosing, the surface-to-air ballistic missile disposed at present is far from meeting its defence demand, and these important bridge are once destroyed, the transport of army at present then relies primarily on the bridge of boats and sets up army's erection pontoon bridge, from the point of view of the data of various disclosures, China can in the km level large span river such as the Changjiang river, the Yellow River fast erecting pontoon bridge, military floating bridge develops through several generations, and current technology is the most ripe.Although but pontoon bridge has many good qualities, but inherent defect therein is the most fairly obvious: first setting up km level pontoon bridge in the Changjiang river, it sets up needs an one-level combat unit, staff training, equipment maintenance workload the hugest, also limit the quantity of its equipment;Secondly pontoon bridge is poor for the suitability of high flow rate, high bold shore; set up place and need that river flow is the highest, two sides are mild; it is prone to the bridge of boats and sets up army's expansion; and when pontoon bridge needs to change and sets up place; need again to disassemble; transport by a land route, extensive controllable velocity necessarily quickly will not the most just limit its motility.Therefore, the problem in the Changjiang river is crossed over temporarily by fleet military for wartime, and the little novel device of crossing a river of high in the urgent need to a kind of flexibility ratio, strong to ambient adaptability, logistics support amount is to make up the deficiency of existing pontoon bridge.
In China the Changjiang river, shipping boats and ships are intensive, and a large amount of ship for civil use can be taken over wartime for use for army temporarily, can consider to transform in the boats and ships of requisition, install the organized equipment such as military Bailey beam, eight or the three military piers of formula additional, it transform hull-cable-stayed bridge as quickly to cross a river device, it passes through hull navigation in river, can accomplish with stopping with erection, be the novel device of crossing a river of a kind of fast and flexible.
Summary of the invention
It is an object of the invention to overcome existing device of crossing a river setting up ground point selection, setting up the various problems existing for the aspect such as flexibility ratio, logistic maintenance, ship manoeuverability can the good advantage the strongest with cable-stayed bridge span ability be combined, it is provided that a kind of can be at the device of crossing a river of confession in wartime military fleet fast passing.
A kind of hull-cable-stayed bridge is quickly crossed a river device, including boats and ships, it is characterised in that:
Also include that eight or three formula military piers 2, military Bailey beam 3 and drag-line 4,83 formula military pier 2 are arranged on the head and the tail both sides of boats and ships 1, separate eight or three formula military pier 2,83 formula military pier 2 bottoms, two, every side with ship deck 6 for just to connect;
Bailey beam bridge 13 is attached by drag-line 4 with eight or three formula military piers 2, drag-line 4 one end is fixed on the column of eight or three formula military piers 2, the other end is then fixed in military Bailey beam 3 by attachment means 10, and the arrangement form that drag-line 4 uses is that double rope faces harp-shaped is arranged;Drag-line on eight or three formula military piers is double rope faces, and the drag-line 4 in a funiculus lateralis face is to be connected with Bailey beam bridge 13, and the drag-line 4 in another funiculus lateralis face is then to be connected with ship deck 6;Fixing the I-steel of direction across bridge in military Bailey beam 3, at I-steel upper berth floorings 7, three collectively constitutes Bailey beam bridge 13.One end of Bailey beam bridge 13 is overlapped on ship deck 6, uses base-supporting structure,
Further, barge selected by boats and ships.
Further, ship deck 6 is divided into two-way two tracks.
Described a kind of hull-cable-stayed bridge is quickly crossed a river the application of device, it is characterised in that:
The first step: eight or three formula military piers 2 are installed on ship deck 6, splicing Bailey beam bridge 13, after Bailey beam bridge 13 has spliced, is fixed on eight or three formula military piers 2 by drag-line 4 one end simultaneously, the other end is fixed on Bailey beam bridge 13, adjusts drag-line 4 stress simultaneously.
Second step: the hull-cable-stayed bridge transformed device of quickly crossing a river rolls away from from harbour, arrives at after regulation sets up place, starts ship turning, and by original downbeam, half-twist is horizontal to carry out hull-cable-stayed bridge in river course and quickly cross a river the docking of device.
3rd step: carry out the mating operation of Bailey beam bridge 13.Setting bridge pier on riverbank, be overlapped on by Bailey beam bridge 13 on the bridge pier of riverbank, hull opposite side Bailey beam bridge 13 then needs Bailey beam bridge 13 phase with adjacent vessels to dock.
Concrete principle explanation: a kind of hull-cable-stayed bridge for the efficient fast passing of military vehicle is quickly crossed a river device, agent structure is for selecting substantial amounts of barge in the Changjiang river, such feature is that itself is not from boat ability, therefore ship deck is smooth, ship deck is transformed the vehicle that just can pass through by these type of boats and ships a little, can be by towboat or push boat during walking in river course.The primary structure installed additional on this basis is eight or three formula military piers 2, military Bailey beam 3, drag-line 4 etc., eight or three formula military piers 2 are arranged on the head and the tail of boats and ships 1, eight or the three formula military piers 2 that every two, side is separate, eight or three formula military piers 2 are a kind of Railway Bridges And Piers repairing standard equipments that China develops voluntarily, it has the advantages such as spelling group is simple, easy to connect, interchangeability is strong, simple and quick splicing can save the plenty of time, and its pier shaft height quickly can adjust according to practical situation.The rod member 12 of eight or three formula military piers 2 makes to be connected with by connecting plate 11.Eight or three formula military pier 2 bottoms just connect with ship deck 6, and ensure that enough bonding strengths bear pulling force.Bailey beam bridge 13 is attached by drag-line 4 with eight or three formula military piers 2, drag-line 4 uses the cable wire employed in tradition cable-stayed bridge, the steel bundle weaved into according to certain rules by steel strand wires is made, drag-line 4 one end is fixed on the column of eight or three formula military piers 2, the other end is then fixed in military Bailey beam 3 by attachment means 10, vehicular load and deadweight that military Bailey beam 3 is born pass to eight or three formula military piers 2 by drag-line 4, the arrangement form that drag-line 4 uses is that double rope faces harp-shaped is arranged, favourable to the stress of eight or three formula military piers 2.
Military Bailey beam 3 is a kind of war preparedness emergency repair goods and materials that China develops voluntarily, and it is formed by connecting by Bailey bracket 8, goes for different spans, and it has portable construction, simple structure, the erection lot of advantages such as rapidly.Military Bailey beam 3 is by fixing the I-steel of direction across bridge thereon, and at I-steel upper berth floorings 7, three collectively constitutes Bailey beam bridge 13 and meets driving demand.
Bailey beam bridge 13 and 83 formula military pier 2 is directly installed on boats and ships at staith, and collectively constitute stress system with drag-line 4, one end of Bailey beam bridge 13 is overlapped on ship deck 6, use base-supporting structure, because floorings 7 are highly relatively low relative to ship deck 6, junction does not interferes with travel safety after adding backing plate.Ship deck 6 is divided into two-way two tracks.After staith is completed, Bailey beam bridge 13 stretches on river outside big portion, is therefore considered as its stability, fixes Bailey beam bridge 13 with ship deck 6 lap-joint.
On being embodied as, Bailey beam bridge 13 length, eight or three formula military pier 2 height, can be adjusted as the case may be, for selecting the kind of boats and ships, being also not limited to barge, other kind is suitable for the ship of transformation and all can use, and runway quantity is modified also dependent on specific ship width.
Accompanying drawing explanation
Fig. 1 is that hull-cable-stayed bridge of the present invention is quickly crossed a river device front view;
Fig. 2 is that hull-cable-stayed bridge of the present invention is quickly crossed a river device side view;
Fig. 3 is that hull-cable-stayed bridge of the present invention is quickly crossed a river device eight or three formula military pier and attachment means detail drawing;
Fig. 4 is that hull-cable-stayed bridge of the present invention is quickly crossed a river the device Bailey beam bridge detail of construction;
Fig. 5 is that hull-cable-stayed bridge of the present invention is quickly crossed a river device river course construction drawing;
Detailed description of the invention
1 to Fig. 5 describes the specific embodiment of the invention in detail below in conjunction with the accompanying drawings.
It is embodied as step as follows:
The first step: the barge of many interim collections stops staith, transforms it.Eight or three formula military piers 2 are installed on ship deck 6, splicing Bailey beam bridge 13 simultaneously, after Bailey beam bridge 13 has spliced, eight or three formula military piers 2 are fixed in drag-line 4 one end, the other end is fixed in military Bailey beam 3, adjusting drag-line 4 stress, the cable-stayed bridge system making three form meets driving requirement simultaneously.Assembly is fixed with ship deck 6 lap-joint at Bailey beam bridge 13 after completing, and makes to keep the stability of Bailey beam bridge 13 during navigation.
Second step: the hull-cable-stayed bridge transformed device of quickly crossing a river rolls away from from harbour, arrives at after regulation sets up place, starts ship turning, and by original downbeam, half-twist is horizontal to carry out hull-cable-stayed bridge in river course and quickly cross a river the docking of device.
3rd step: carry out the mating operation of Bailey beam bridge 13.Bridge pier is set on riverbank, Bailey beam bridge 13 is overlapped on the bridge pier of riverbank, both can reduce the stress of Bailey beam bridge 13, increase stability of hull, can meet again the overlap joint requirement of different riverbanks height, hull opposite side Bailey beam bridge 13 then needs Bailey beam bridge 13 phase with adjacent vessels to dock.The Bailey beam bridge 13 of all hulls docks simultaneously, with time-consuming, after all having docked, and fleet of just can passing through.
In figure, 5 is ship anchor, after device of crossing a river has docked, under anchor of undocking play the effect fixing boats and ships in current, prevent the hull caused because of the disturbance of current unstable.
The above, it it is only presently preferred embodiments of the present invention, not the present invention is done any pro forma restriction, any without departing from technical solution of the present invention content, the technical spirit of the foundation present invention, to any simple modification made for any of the above embodiments, equivalent variations and modification, all still falls within the range of technical solution of the present invention.

Claims (4)

1. hull-cable-stayed bridge is quickly crossed a river a device, including boats and ships, it is characterised in that:
Also including eight or three formula military piers (2), military Bailey beam (3) and drag-line (4), eight or three formulas are military Bridge pier (2) is arranged on the head and the tail both sides of boats and ships, eight or the three formula military piers (2) that two, every side is separate, Eight or three formula military pier (2) bottoms and ship deck (6) are for just to connect;
Bailey beam bridge (13) is attached by drag-line (4) with eight or three formula military piers (2), drag-line (4) one end is fixed on the column of eight or three formula military piers (2), and the other end is then by attachment means (10) Being fixed in military Bailey beam (3), the arrangement form that drag-line (4) uses is arranged for double rope faces harp-shaped; Drag-line on eight or three formula military piers is double rope faces, and the drag-line (4) in a funiculus lateralis face is and Bailey beam bridge (13) Being connected, the drag-line (4) in another funiculus lateralis face is then to be connected with ship deck (6);Military Bailey beam (3) I-steel of upper fixing direction across bridge, on I-steel upper berth floorings (7), three collectively constitutes Bei Lei Beam bridge (13);One end of Bailey beam bridge (13) is overlapped on ship deck (6), uses base-supporting Structure.
A kind of hull-cable-stayed bridge the most according to claim 1 is quickly crossed a river device, it is characterised in that:
Barge selected by boats and ships.
A kind of hull-cable-stayed bridge the most according to claim 1 is quickly crossed a river device, it is characterised in that:
Ship deck (6) is divided into two-way two tracks.
4. according to a kind of hull-cable-stayed bridge described in claim 1-3 any one quickly cross a river device should With, it is characterised in that:
The first step: eight or three formula military piers (2) are installed on ship deck (6), splice simultaneously Bailey beam bridge (13), after Bailey beam bridge (13) has spliced, is fixed on eight by drag-line (4) one end Three formula military piers (2), the other end is fixed on Bailey beam bridge (13), adjusts drag-line (4) stress simultaneously;
Second step: the hull-cable-stayed bridge transformed device of quickly crossing a river rolls away from from harbour, arrives at regulation frame If behind place, starting ship turning, by original downbeam, half-twist is horizontal to be carried out in river course Hull-cable-stayed bridge is quickly crossed a river the docking of device;
3rd step: carry out the mating operation of Bailey beam bridge (13);Bridge pier is set, by shellfish thunder on riverbank Beam bridge (13) is overlapped on the bridge pier of riverbank, the overhanging Bailey beam bridge (13) of hull opposite side then need with The Bailey beam bridge (13) of adjacent vessels docks mutually.
CN201510487916.9A 2015-08-10 2015-08-10 A kind of hull-cable-stayed bridge is quickly crossed a river device and application thereof Active CN105040574B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510487916.9A CN105040574B (en) 2015-08-10 2015-08-10 A kind of hull-cable-stayed bridge is quickly crossed a river device and application thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510487916.9A CN105040574B (en) 2015-08-10 2015-08-10 A kind of hull-cable-stayed bridge is quickly crossed a river device and application thereof

Publications (2)

Publication Number Publication Date
CN105040574A CN105040574A (en) 2015-11-11
CN105040574B true CN105040574B (en) 2016-11-02

Family

ID=54447524

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510487916.9A Active CN105040574B (en) 2015-08-10 2015-08-10 A kind of hull-cable-stayed bridge is quickly crossed a river device and application thereof

Country Status (1)

Country Link
CN (1) CN105040574B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112030757A (en) * 2020-08-21 2020-12-04 中国船舶重工集团应急预警与救援装备股份有限公司 Anchor casting machine for mooring of pontoon bridge

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7200887B1 (en) * 2006-01-27 2007-04-10 Powers James M Bridges assembled from ocean-mobile pontoon bridge modules
CN101230558A (en) * 2008-01-18 2008-07-30 许是勇 Floating type landscape stayd-cable bridge
CN201756677U (en) * 2009-11-26 2011-03-09 周鹏 Multipurpose pontoon bridge
CN201648943U (en) * 2010-04-09 2010-11-24 中铁十一局集团第五工程有限公司 Temporary steel bridge supporting structure
CN202718034U (en) * 2012-06-26 2013-02-06 武汉理工大学 Novel floating combined cross-sea bridge

Also Published As

Publication number Publication date
CN105040574A (en) 2015-11-11

Similar Documents

Publication Publication Date Title
CN101234662A (en) Floating type hotel
Eidem Overview of floating bridge projects in Norway
CN105040574B (en) A kind of hull-cable-stayed bridge is quickly crossed a river device and application thereof
Ellers Advanced offshore oil platforms
LaNier et al. New technologies proven in precast concrete modular floating pier for US Navy
Kusaka et al. Ujina floating ferry pier and kan-on floating breakwater, Japan
Nguyen Solutions for navigated safety of super-tankers operating on Dinh River traffic-lanes and PTSC port
Hakkaart Transport of tunnel elements from Baltimore to Boston, over the Atlantic Ocean
Opgård et al. Chained floating bridge
Koh et al. The floating platform at the Marina Bay, Singapore
Budiman Construction challenge of submerged floating tunnel in indonesia
RU201201U1 (en) ASSEMBLY FALSE FLOATING BERTH
Sørensen 16.01: Bjørnafjorden suspension bridge TLP concept
RU2747690C1 (en) Island-type sea floating base
WO1990015223A1 (en) Submerged bridge tunnel
CN207659913U (en) A kind of novel inclined formula passenger wharf
Hovilainen et al. Next Generation to Break the Ice-The Oblique Icebreaker
Edelson et al. Aasta Hansteen Spar Inshore Pre-Service Operations
Farmer Pier Design vs. Operations: A Navy Perspective
Jakobsen et al. Concept development of a Sognefjord floating bridge crossing
Desai et al. Design Considerations for a New Marine Oil Terminal at Port of Los Angeles, Berths B238–239
Cowderoy et al. Lyttelton cruise berth
Vander Meulen et al. Design and construction of a modern cyclone tug servicing facility in Port Hedland
RU2475585C2 (en) Method to produce ferry site
Redpath et al. Pier collision protection at Tay Road Bridge, Scotland

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20231215

Address after: Room D-1, Building D-1, South Pearl Courtyard Residence, No. 39, Bihai Avenue, Meilan District, Haikou City, Hainan Province, 570100

Patentee after: Hainan Zhongjiao expressway investment and Construction Co.,Ltd.

Patentee after: CHINA HIGHWAY ENGINEERING CONSULTING Corp.

Address before: 100124 No. 100 Chaoyang District Ping Tian Park, Beijing

Patentee before: Beijing University of Technology

TR01 Transfer of patent right