CN104999083A - Preparation method of sloped top of heteromorphic waterway and sloped top - Google Patents

Preparation method of sloped top of heteromorphic waterway and sloped top Download PDF

Info

Publication number
CN104999083A
CN104999083A CN201510351482.XA CN201510351482A CN104999083A CN 104999083 A CN104999083 A CN 104999083A CN 201510351482 A CN201510351482 A CN 201510351482A CN 104999083 A CN104999083 A CN 104999083A
Authority
CN
China
Prior art keywords
oblique top
special
water route
shaped
waterway structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510351482.XA
Other languages
Chinese (zh)
Other versions
CN104999083B (en
Inventor
卢欣红
吴家平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dongguan Mefun Industry Co Ltd
Original Assignee
Dongguan Mefun Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dongguan Mefun Industry Co Ltd filed Critical Dongguan Mefun Industry Co Ltd
Priority to CN201510351482.XA priority Critical patent/CN104999083B/en
Publication of CN104999083A publication Critical patent/CN104999083A/en
Application granted granted Critical
Publication of CN104999083B publication Critical patent/CN104999083B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Moulds For Moulding Plastics Or The Like (AREA)

Abstract

The invention discloses a preparation method of a sloped top of a heteromorphic waterway and the sloped top. The preparation method comprises the following steps: (1) building an injection mold and a three-dimensional modeling model of the sloped top through a CAE auxiliary analysis software, and performing optimization so as to obtain structural three-dimensional files of the sloped top and the heteromorphic waterway; (2) arranging material parameters in CAD three-dimensional modeling software, and outputting the three-dimensional files; (3) processing the three-dimensional files obtained in the step (2) by using layering and slicing software, and performing 3D printing; and (4) arranging a graphene coating at a push-out position, which is in contact with an injection molding plastic component, of the sloped top. The invention further discloses the sloped top carried out by the preparation method. According to the preparation method disclosed by the invention, the heteromorphic waterway with good temperature regulation and the sloped top with the good temperature regulation are manufactured through repeatedly optimized waterway design and a 3D printing technique, so that the cooling efficiency of a mold or the sloped top is improved, the forming period is shortened, the production efficiency of the mold is improved, the thermal residual stress of the injection molding is decreased, and the injection molding quality is improved.

Description

A kind of oblique top preparation method of special-shaped water route and oblique top
Technical field
The present invention relates to technical field prepared by mould, be specifically related to a kind of oblique top preparation method of special-shaped water route, and implement the oblique top of this preparation method.
Background technology
In injection moulding process, cooling procedure plays very important effect for Forming Quality, because it directly can have influence on the production efficiency of injection moulding and the internal performance of injection-molded item and apparent mass.Excellent cooling system significantly can reduce cool time, shortens the injection cycle cycle, reduces goods residual thermal stress and buckling deformation, and strengthens mechanical property and inside, the surface quality etc. of goods.If injection-molded item inhomogeneous cooling is even, can thermal residual strain be produced, thus the shape of injection-molded item, size and serviceability etc. are brought and had a strong impact on.Research test shows, a thermal residual strain order of magnitude at least larger than flowing residual stress of moulding, therefore in injection molding process, mainly should consider the influence factor of thermal residual strain.When viscoelastic polymer melt is cooled to lower than glass transition temperature in mould, uneven variable density and uneven variations in temperature all can form thermal residual strain.In injection moulding process, thermal residual strain easily produces in following 2 stages: one is the cooling stage of injection-molded item in die cavity, and two is injection-molded item stages from calcining temperature cool to room temperature.Therefore, high efficiency production be accomplished, and the injection-molded item of excellent, temperature adjustment must be carried out to mould.
In injection mold, the cooling effect of mould is related to the height of production efficiency and the quality good or not of final injection-molded item, and therefore the design of its cooling system is one of key issue needing in die design process to consider.But, because present stage Making mold means are limited, and lack suitable cooling water channel design theory, under making the Design and manufacture of cooling water channel can only be confined to relatively simple version.However, mold designers are still devoted to improve the cooling effectiveness of cooling system all the time, propose the water route form that spiral, dividing plate point cold type and spiral plug etc. are different, obtain evenly and effectively cooling to enable front and back mould.But, to those complex structures and the high product of quality requirement carries out Design of Dies time, said method is not fully effective.
Summary of the invention
This invention is not enough for current art, a kind of oblique top preparation method of special-shaped water route is provided, by the water route design repeatedly optimized, manufacture temperature by 3D printing technique and regulate excellent special-shaped water route and oblique top, improve the cooling effectiveness of mould or oblique top, shorten molding cycle, improve mould production efficiency, reduce moulding thermal residual strain, improve injection moulding quality.
The present invention also provides a kind of oblique top implementing this preparation method.
The technical scheme that the present invention is adopted for achieving the above object is:
The oblique top preparation method in special-shaped water route, it comprises and is provided with CAD 3D modeling software, CAE assistant analysis software, hierarchy slicing software, the computer of 3D print software and 3D printer, and it is characterized in that, it comprises the following steps:
(1) the three-dimensional modeling model of injection mould and oblique top is set up by CAE assistant analysis software, select rational injection molding parameter, simulation injection moulding production process, and compensate injection moulding by the profound and negative feedbck of CAE assistant analysis software and produce the change of product and the special-shaped waterway structure revised in advance in oblique top, make the cooling effect that the realistic injection moulding of oblique top is produced, thus obtain the three-dimensional archives of oblique top and special-shaped waterway structure, ensure that product reaches requirement;
(2) in CAD 3D modeling software, the oblique top that step (1) obtains is arranged bi-material, be respectively special-shaped waterway structure inwall in oblique top and the copper product of the thick high heat conduction of 0.3 ~ 0.6mm is set, abnormity waterway structure is equivalent to be arranged to a wall thickness be the heat-conducting copper pipe of 0.3 ~ 0.6mm, other positions that oblique top removes special-shaped waterway structure are die steel material, and export the three-dimensional archives of oblique top and special-shaped waterway structure;
(3) the three-dimensional archives hierarchy slicing software of oblique top step (2) obtained and special-shaped waterway structure processes it, obtain the information parameter of each cross sectional shape, the track of two-dimensional scan is carried out as laser beam, the light beam sent by laser is under the control of computer 3D print software, coordinate data according to each layer cross section of geometrical body scans different materials powder bed selectively, together powder sintered on the position of laser irradiation, after one deck has sintered, repave powder and carry out lower one deck scanning sintering, new one deck and front one deck are sintered together naturally, the oblique top that final generation follows three-dimensional archives consistent and special-shaped water route,
(4) the thick high heat conduction hard Graphene coating of 0.05 ~ 0.1mm is set at the position that ejects contacted with injection moulding plastic part of oblique top.
As further improvement, in described step (1), the running of the profound and negative feedbck of described CAE assistant analysis software specifically comprises the following steps:
(11) the three-dimensional modeling model of the injection mould set up and oblique top is imported to CAE assistant analysis software, selection material and injection molding parameter in CAE assistant analysis software, set up initial waterway structure;
(12) simulate injection moulding to produce, produce the product 3D model of simulation, and the distortion of the product 3D model of prognosis modelling,
Compared with original product model by the product 3D model of simulation, the difference of distortion is fed back to CAE assistant analysis software, CAE assistant analysis software regenerates the waterway structure of oblique top according to the difference of distortion, the three-dimensional modeling model of the oblique top be improved;
(13) again simulate injection moulding to produce, again obtain product model, and the distortion of the product 3D model of prognosis modelling, computer repeats above step (12) repeatedly automatically, until simulate the deformation requirements that the product generating out meets setting, the three-dimensional modeling model of the oblique top obtained is for Design of Dies and processing.Thus ensureing that the product that injection moulding is produced once meets product requirement, computer simulation replaces original by CAE assistant analysis technology Chief, passes through die trial, repair a die, advantage economizes on resources, and cuts the waste, the Speeding up development cycle, thus reach high-quality, efficient production requirement.
As further improvement, in described step (3), as follows according to the concrete steps that the coordinate data of each layer cross section of geometrical body scans different materials powder bed selectively:
(31) mould steel powder is laid, together powder sintered on the position of laser irradiation, after last layer has sintered, re-lay powder and carried out lower one deck scanning sintering;
(32) when the information parameter being positioned at this layer cross section shape only has the die steel material of oblique top, it is once powder sintered that this layer only need lay a mould steel;
When the information parameter being positioned at this layer cross section shape comprises the copper product of the die steel material of oblique top and special-shaped waterway structure, first mould steel is laid once powder sintered, subsequently, copper powders is laid after cleaning out mould steel powder, carry out the sintering of special-shaped waterway structure again, the die steel material being positioned at same layer cross section is combined with copper product firmly; So repeatedly repeat, finally obtain the complete oblique top containing special-shaped waterway structure.
As further improvement, oblique top described in step (1) comprises the base connecting portion of integrative-structure, push rod portion, the ejection part contacted with injection moulding plastic part and the Graphene layer structure being arranged on ejection part, and described oblique top also comprises the special-shaped waterway structure be arranged in described oblique top; The water inlet of described special-shaped waterway structure and delivery port are arranged on the bottom in base push rod portion, and are communicated with the vertical cooling water channel in push rod portion, are provided with conformal cooling water route in described ejection part.
Described special-shaped waterway structure comprises two groups of cooling fluids and flows to the contrary cooling water channel arranged, be respectively first group of cooling water channel and second group of cooling water channel, often organize cooling water channel to comprise and be positioned at base connecting portion and push rod portion is provided with main flow water route, and the water route of ejection part being positioned at the contact of injection moulding plastic part is provided with two or more water route, tributary.
The described water route, tributary being positioned at the ejection part of injection moulding plastic part contact connects described main flow water route, and the diameter in water route, described tributary is less than the diameter in main flow water route.
Water route, described tributary is conformal cooling water route, and this casual cooling water channel is arranged along the appearance profile of ejection part.
A kind of oblique top implementing the oblique top preparation method in above-mentioned special-shaped water route, described oblique top comprises the base connecting portion of integrative-structure, push rod portion, the ejection part contacted with injection moulding plastic part and the Graphene layer structure being arranged on ejection part, and described oblique top also comprises the special-shaped waterway structure be arranged in described oblique top;
The water inlet of described special-shaped waterway structure and delivery port are arranged on the bottom in base push rod portion, and are communicated with the vertical cooling water channel in push rod portion, are provided with conformal cooling water route in described ejection part;
Described special-shaped waterway structure is the cooling water channel that wall thickness 0.3 ~ 0.6mm copper product is made, and described oblique top is the solid construction that the die steel material except special-shaped waterway structure is made.
Described special-shaped waterway structure comprises two groups of cooling fluids and flows to the contrary cooling water channel arranged, be respectively first group of cooling water channel and second group of cooling water channel, often organize cooling water channel to comprise and be positioned at base connecting portion and push rod portion is provided with main flow water route, and the water route of ejection part being positioned at the contact of injection moulding plastic part is provided with two or more water route, tributary.
Described two or more the water route, tributary being positioned at ejection part is communicated with described main flow water route, and the diameter in water route, described tributary is less than the diameter in main flow water route.
Beneficial effect of the present invention: the present invention meets the oblique top of injection moulding production by CAE assistant analysis software simulation, then by simulation result feedback to computing system, automatic change product design data, simulated production product is out made more to meet the requirement of original product, in computer CAE system, simulation replaces original die trial to change mold process repeatedly, analyze best cooling effect simultaneously, complete the design in oblique top abnormity water route.
Special-shaped waterway structure of the present invention comprises the vertical cooling water channel in push rod portion and the conformal cooling water route of ejection part, and this conformal cooling water route changes along with the change of oblique top morphology.As everyone knows, in general injection moulding process, need the production status that mould just can be made to reach stable through the regular hour, this is because after the plastics of melting inject mould, heat transmission is there is in injection mold and molten plastic between contact surface, meanwhile, mould carries out thermal pulse conduction by self to cooling water channel.So mold temperature rises, and imports heat into cooling fluid simultaneously.If cooling water channel has longer distance from die surface, continuous print thermal pulse will make the constant temperature of mould raise, until the pulse heat that the pulse heat taken away of cooling system and molten plastic bring mould reaches balance.If cooling water channel is nearer apart from die surface, the heat then accumulated in mould or oblique top will greatly reduce, and heat is limited in the region between cooling water channel and die surface, make also to shorten much from mold cavity surface to the path of cooling water channel heat conduction.Like this, in an injection cycle, mould just can reach stable duty.
The present invention is also by 3D printing technique (namely selectively layering sintering metal powder technology), by computer and 3D printer, employing direct metal is powder sintered, to select and die steel material and copper product powder sinter, the density of burning out can reach 100% substantially, and characteristic (intensity, hardness etc.) follows the metal of same material consistent, precision can reach 20-50 micron, and roughness can reach 5-10 micron.
The position that ejects that the present invention contacts at injection moulding plastic part arranges high heat conduction hard Graphene coating, strengthens heat-conducting effect.
Below in conjunction with accompanying drawing and detailed description of the invention, the present invention is described in more detail.
Accompanying drawing explanation
Fig. 1 is the ramp-roof structure schematic diagram of the present embodiment;
Fig. 2 is B-B cross section result schematic diagram in Fig. 1;
Fig. 3 is C-C cross section result schematic diagram in Fig. 1;
Fig. 4 is the perspective structure schematic diagram of ejection part in Fig. 1.
In figure: 1. oblique top, 11. base connecting portions, 12. push rod portions, 13. ejection parts, 14. special-shaped waterway structures, 141. cooling water channels, 15. Graphene layer structures.
Detailed description of the invention
Embodiment 1, see Fig. 1 ~ 4, the oblique top preparation method in a kind of special-shaped water route that the present embodiment provides, it comprises and is provided with CAD 3D modeling software, CAE assistant analysis software, hierarchy slicing software, the computer of 3D print software and 3D printer, and it comprises the following steps:
(1) the three-dimensional modeling model of injection mould and oblique top is set up by CAE assistant analysis software, select rational injection molding parameter, simulation injection moulding production process, and compensate injection moulding by the profound and negative feedbck of CAE assistant analysis software and produce the change of product and the special-shaped waterway structure revised in advance in oblique top, make the cooling effect that the realistic injection moulding of oblique top is produced, thus obtain the three-dimensional archives of oblique top and special-shaped waterway structure, ensure that product reaches requirement;
(2) in CAD 3D modeling software, the oblique top that step (1) obtains is arranged bi-material, be respectively special-shaped waterway structure inwall in oblique top and the copper product of the thick high heat conduction of 0.3 ~ 0.6mm is set, abnormity waterway structure is equivalent to be arranged to a wall thickness be the heat-conducting copper pipe of 0.3 ~ 0.6mm, other positions that oblique top removes special-shaped waterway structure are die steel material, and export the three-dimensional archives of oblique top and special-shaped waterway structure;
(3) the three-dimensional archives hierarchy slicing software of oblique top step (2) obtained and special-shaped waterway structure processes it, obtain the information parameter of each cross sectional shape, the track of two-dimensional scan is carried out as laser beam, the light beam sent by laser is under the control of computer 3D print software, coordinate data according to each layer cross section of geometrical body scans different materials powder bed selectively, together powder sintered on the position of laser irradiation, after one deck has sintered, repave powder and carry out lower one deck scanning sintering, new one deck and front one deck are sintered together naturally, the oblique top that final generation follows three-dimensional archives consistent and special-shaped water route,
(4) the thick high heat conduction hard Graphene coating of 0.05 ~ 0.1mm is set at the position that ejects contacted with injection moulding plastic part of oblique top.
In described step (1), the running of the profound and negative feedbck of described CAE assistant analysis software specifically comprises the following steps:
(11) the three-dimensional modeling model of the injection mould set up and oblique top is imported to CAE assistant analysis software, selection material and injection molding parameter in CAE assistant analysis software, set up initial waterway structure;
(12) simulate injection moulding to produce, produce the product 3D model of simulation, and the distortion of the product 3D model of prognosis modelling,
Compared with original product model by the product 3D model of simulation, the difference of distortion is fed back to CAE assistant analysis software, CAE assistant analysis software regenerates the waterway structure of oblique top according to the difference of distortion, the three-dimensional modeling model of the oblique top be improved;
(13) again simulate injection moulding to produce, again obtain product model, and the distortion of the product 3D model of prognosis modelling, computer repeats above step (12) repeatedly automatically, until simulate the deformation requirements that the product generating out meets setting, the three-dimensional modeling model of the oblique top obtained is for Design of Dies and processing.Thus ensureing that the product that injection moulding is produced once meets product requirement, computer simulation replaces original by CAE assistant analysis technology Chief, passes through die trial, repair a die, advantage economizes on resources, and cuts the waste, the Speeding up development cycle, thus reach high-quality, efficient production requirement.
In described step (3), as follows according to the concrete steps that the coordinate data of each layer cross section of geometrical body scans different materials powder bed selectively:
(31) mould steel powder is laid, together powder sintered on the position of laser irradiation, after last layer has sintered, re-lay powder and carried out lower one deck scanning sintering;
(32) when the information parameter being positioned at this layer cross section shape only has the die steel material of oblique top, it is once powder sintered that this layer only need lay a mould steel;
When the information parameter being positioned at this layer cross section shape comprises the copper product of the die steel material of oblique top and special-shaped waterway structure, first mould steel is laid once powder sintered, subsequently, copper powders is laid after cleaning out mould steel powder, carry out the sintering of special-shaped waterway structure again, the die steel material being positioned at same layer cross section is combined with copper product firmly; So repeatedly repeat, finally obtain the complete oblique top containing special-shaped waterway structure.
Oblique top 1 described in step (1) comprises the base connecting portion 11 of integrative-structure, push rod portion 12, the ejection part contacted with injection moulding plastic part and the Graphene layer structure 15 being arranged on ejection part 13, and described oblique top 1 also comprises the special-shaped waterway structure be arranged in described oblique top 1; The water inlet of described special-shaped waterway structure and delivery port are arranged on the bottom in base push rod portion 12, and are communicated with the vertical cooling water channel in push rod portion 12, are provided with conformal cooling water route 141 in described ejection part 13.
The present embodiment also provides the oblique top of a kind of oblique top preparation method of special-shaped water route, described oblique top comprises the base connecting portion 11 of integrative-structure, push rod portion 12, the ejection part 13 contacted with injection moulding plastic part and the Graphene layer structure 15 being arranged on ejection part 13, and described oblique top 1 also comprises the special-shaped waterway structure 14 be arranged in described oblique top;
The water inlet of described special-shaped waterway structure 14 and delivery port are arranged on the bottom in base push rod portion 12, and are communicated with the vertical cooling water channel in push rod portion 12, are provided with conformal cooling water route 141 in described ejection part 13.
Described special-shaped waterway structure is the cooling water channel 141 that wall thickness 0.3 ~ 0.6mm copper product is made, and described oblique top is the solid construction that the die steel material except special-shaped waterway structure is made.
The present invention meets the oblique top of injection moulding production by CAE assistant analysis software simulation, then by simulation result feedback to computing system, automatic change product design data, simulated production product is out made more to meet the requirement of original product, in computer CAE system, simulation replaces original die trial to change mold process repeatedly, analyze best cooling effect simultaneously, complete the design in oblique top abnormity water route.
Special-shaped waterway structure of the present invention comprises vertical cooling water channel and conformal cooling water route, and this conformal cooling water route changes along with the change of oblique top morphology.As everyone knows, in general injection moulding process, need the production status that mould just can be made to reach stable through the regular hour, this is because after the plastics of melting inject mould, heat transmission is there is in injection mold and molten plastic between contact surface, meanwhile, mould carries out thermal pulse conduction by self to cooling water channel.So mold temperature rises, and imports heat into cooling fluid simultaneously.If cooling water channel has longer distance from die surface, continuous print thermal pulse will make the constant temperature of mould raise, until the pulse heat that the pulse heat taken away of cooling system and molten plastic bring mould reaches balance.If cooling water channel is nearer apart from die surface, the heat then accumulated in mould or oblique top will greatly reduce, and heat is limited in the region between cooling water channel and die surface, make also to shorten much from mold cavity surface to the path of cooling water channel heat conduction.Like this, in an injection cycle, mould just can reach stable duty.
The present invention is also by 3D printing technique (namely selectively layering sintering metal powder technology), by computer and 3D printer, employing direct metal is powder sintered, to select and die steel material and copper product powder sinter, the density of burning out can reach 100% substantially, and characteristic (intensity, hardness etc.) follows the metal of same material consistent, precision can reach 20-50 micron, and roughness can reach 5-10 micron.
The present invention arranges high heat conduction hard Graphene coating at the ejection part 13 that injection moulding plastic part contacts, and strengthens heat-conducting effect.
Embodiment 2, the present embodiment is basic identical with embodiment 1, its difference is, described special-shaped waterway structure comprises two groups of cooling fluids and flows to the contrary cooling water channel arranged, be respectively first group of cooling water channel and second group of cooling water channel, often organize cooling water channel and comprise and be positioned at base connecting portion and push rod portion is provided with main flow water route, and the water route of ejection part being positioned at the contact of injection moulding plastic part is provided with two or more water route, tributary, the water route, tributary of two groups is arranged in a crossed manner, strengthens heat-conducting effect.
Described two or more the water route, tributary being positioned at ejection part is communicated with described main flow water route, and the diameter in water route, described tributary is less than the diameter in main flow water route.
Water route, described tributary is conformal cooling water route, and this casual cooling water channel is arranged along the appearance profile of ejection part.
The present invention is not limited to above-mentioned embodiment, adopts or approximation method identical with the above embodiment of the present invention or structure, and the oblique top preparation method in other the special-shaped water routes obtained and oblique top, all within protection scope of the present invention.

Claims (10)

1. the oblique top preparation method in special-shaped water route, it comprises and is provided with CAD 3D modeling software, CAE assistant analysis software, hierarchy slicing software, the computer of 3D print software and 3D printer, and it is characterized in that, it comprises the following steps:
(1) the three-dimensional modeling model of injection mould and oblique top is set up by CAE assistant analysis software, select injection molding parameter, simulation injection moulding production process, and compensate injection moulding by the profound and negative feedbck of CAE assistant analysis software and produce the change of product and the special-shaped waterway structure revised in advance in oblique top, make the cooling effect that the realistic injection moulding of oblique top is produced, thus obtain the three-dimensional archives of oblique top and special-shaped waterway structure;
(2) in CAD 3D modeling software, the oblique top that step (1) obtains is arranged bi-material, be respectively special-shaped waterway structure inwall in oblique top and the copper product of the thick high heat conduction of 0.3 ~ 0.6mm is set, other positions that oblique top removes special-shaped waterway structure are die steel material, and export the three-dimensional archives of oblique top and special-shaped waterway structure;
(3) the three-dimensional archives hierarchy slicing software of oblique top step (2) obtained and special-shaped waterway structure processes it, obtain the information parameter of each cross sectional shape, the track of two-dimensional scan is carried out as laser beam, the light beam sent by laser is under the control of computer 3D print software, coordinate data according to each layer cross section of geometrical body scans different materials powder bed selectively, together powder sintered on the position of laser irradiation, after one deck has sintered, repave powder and carry out lower one deck scanning sintering, new one deck and front one deck are sintered together naturally, the oblique top that final generation follows three-dimensional archives consistent and special-shaped water route,
(4) the thick high heat conduction hard Graphene coating of 0.05 ~ 0.1mm is set at the position that ejects contacted with injection moulding plastic part of oblique top.
2. the oblique top preparation method in special-shaped water route according to claim 1, is characterized in that, in described step (1), the running of the profound and negative feedbck of described CAE assistant analysis software specifically comprises the following steps:
(11) the three-dimensional modeling model of the injection mould set up and oblique top is imported to CAE assistant analysis software, selection material and injection molding parameter in CAE assistant analysis software, set up initial waterway structure;
(12) simulate injection moulding to produce, produce the product 3D model of simulation, and the distortion of the product 3D model of prognosis modelling,
Compared with original product model by the product 3D model of simulation, the difference of distortion is fed back to CAE assistant analysis software, CAE assistant analysis software regenerates the waterway structure of oblique top according to the difference of distortion, the three-dimensional modeling model of the oblique top be improved;
(13) again simulate injection moulding to produce, again obtain product model, and the distortion of the product 3D model of prognosis modelling, computer repeats above step (12) repeatedly automatically, until simulate the deformation requirements that the product generating out meets setting, the three-dimensional modeling model of the oblique top obtained is for Design of Dies and processing.
3. the oblique top preparation method in special-shaped water route according to claim 2, is characterized in that, in described step (3), as follows according to the concrete steps that the coordinate data of each layer cross section of geometrical body scans different materials powder bed selectively:
(31) mould steel powder is laid, together powder sintered on the position of laser irradiation, after last layer has sintered, re-lay powder and carried out lower one deck scanning sintering;
(32) when the information parameter being positioned at this layer cross section shape only has the die steel material of oblique top, it is once powder sintered that this layer only need lay a mould steel;
When the information parameter being positioned at this layer cross section shape comprises the copper product of the die steel material of oblique top and special-shaped waterway structure, first mould steel is laid once powder sintered, subsequently, after cleaning out mould steel powder, lay copper powders, then carry out the sintering of special-shaped waterway structure; So repeatedly repeat, finally obtain the complete oblique top containing special-shaped waterway structure.
4. the oblique top preparation method in special-shaped water route according to claim 1, it is characterized in that, oblique top described in step (1) comprises the base connecting portion of integrative-structure, push rod portion, the ejection part contacted with injection moulding plastic part and the Graphene layer structure being arranged on ejection part, and described oblique top also comprises the special-shaped waterway structure be arranged in described oblique top; The water inlet of described special-shaped waterway structure and delivery port are arranged on the bottom in base push rod portion, and are communicated with the vertical cooling water channel in push rod portion, are provided with conformal cooling water route in described ejection part.
5. the oblique top preparation method in special-shaped water route according to claim 4, it is characterized in that, described special-shaped waterway structure comprises two groups of cooling fluids and flows to the contrary cooling water channel arranged, be respectively first group of cooling water channel and second group of cooling water channel, often organize cooling water channel to comprise and be positioned at base connecting portion and push rod portion is provided with main flow water route, and the water route of ejection part being positioned at the contact of injection moulding plastic part is provided with two or more water route, tributary.
6. the oblique top preparation method in special-shaped water route according to claim 5, is characterized in that, described in be positioned at the contact of injection moulding plastic part the water route, tributary of ejection part connect described main flow water route, the diameter in water route, described tributary is less than the diameter in main flow water route.
7. the oblique top preparation method in special-shaped water route according to claim 6, is characterized in that, water route, described tributary is conformal cooling water route, and this casual cooling water channel is arranged along the appearance profile of ejection part.
8. one kind implements the claims the oblique top of the oblique top preparation method in one of 1 to 7 described special-shaped water route, it is characterized in that, described oblique top comprises the base connecting portion of integrative-structure, push rod portion, the ejection part contacted with injection moulding plastic part and the Graphene layer structure being arranged on ejection part, and described oblique top also comprises the special-shaped waterway structure be arranged in described oblique top;
The water inlet of described special-shaped waterway structure and delivery port are arranged on the bottom in base push rod portion, and are communicated with the vertical cooling water channel in push rod portion, are provided with conformal cooling water route in described ejection part;
Described special-shaped waterway structure is the cooling water channel that wall thickness 0.3 ~ 0.6mm copper product is made, and described oblique top is the solid construction that the die steel material except special-shaped waterway structure is made.
9. oblique top according to claim 8, it is characterized in that, described special-shaped waterway structure comprises two groups of cooling fluids and flows to the contrary cooling water channel arranged, be respectively first group of cooling water channel and second group of cooling water channel, often organize cooling water channel to comprise and be positioned at base connecting portion and push rod portion is provided with main flow water route, and the water route of ejection part being positioned at the contact of injection moulding plastic part is provided with two or more water route, tributary.
10. oblique top according to claim 8, is characterized in that, described in be positioned at ejection part two or more water route, tributary be communicated with described main flow water route, the diameter in water route, described tributary is less than the diameter in main flow water route.
CN201510351482.XA 2015-06-19 2015-06-19 A kind of oblique top preparation method in special-shaped water route and oblique top Active CN104999083B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510351482.XA CN104999083B (en) 2015-06-19 2015-06-19 A kind of oblique top preparation method in special-shaped water route and oblique top

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510351482.XA CN104999083B (en) 2015-06-19 2015-06-19 A kind of oblique top preparation method in special-shaped water route and oblique top

Publications (2)

Publication Number Publication Date
CN104999083A true CN104999083A (en) 2015-10-28
CN104999083B CN104999083B (en) 2017-03-15

Family

ID=54372088

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510351482.XA Active CN104999083B (en) 2015-06-19 2015-06-19 A kind of oblique top preparation method in special-shaped water route and oblique top

Country Status (1)

Country Link
CN (1) CN104999083B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108121840A (en) * 2016-11-29 2018-06-05 中车大同电力机车有限公司 The distribution method in water route between a kind of traction current transformation cabinet and train power supply cabinet
CN108819050A (en) * 2018-06-04 2018-11-16 宁波恒富汽车部件发展有限公司 A kind of mold production technology for applying special-shaped water route 3D printing
CN109016272A (en) * 2018-06-26 2018-12-18 珠海格力精密模具有限公司 A kind of production method and 3D printing injection mold of injection mold
CN112223695A (en) * 2020-09-22 2021-01-15 珠海市英诚电子科技有限公司 Method capable of quickly modifying pitched roof mechanism model
CN112570730A (en) * 2020-12-09 2021-03-30 西安航天发动机有限公司 High-precision selective laser melting forming method for cooling body part

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2334573Y (en) * 1998-07-02 1999-08-25 张炎光 Inclined pin slide seat for ingot stripping
JP2001018275A (en) * 1999-07-07 2001-01-23 Canon Inc Resin molding method and mold temperature regulating device
CN202162972U (en) * 2011-07-21 2012-03-14 嘉兴信元精密模具科技有限公司 Inclined ejection mechanism
CN202439195U (en) * 2012-03-01 2012-09-19 陈志烟 Inclined ejector mechanism of injection molding mold
CN202623186U (en) * 2012-05-08 2012-12-26 滁州浩博科技有限责任公司 Pitched roof main body with water route of injection mold composite pitched roof demolding mechanism
CN104325538A (en) * 2014-08-29 2015-02-04 中南大学 Improved direct writing forming method for preparing three-dimensional structure
CN204712395U (en) * 2015-06-19 2015-10-21 东莞市锋铭实业有限公司 A kind of oblique top of special-shaped waterway structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2334573Y (en) * 1998-07-02 1999-08-25 张炎光 Inclined pin slide seat for ingot stripping
JP2001018275A (en) * 1999-07-07 2001-01-23 Canon Inc Resin molding method and mold temperature regulating device
CN202162972U (en) * 2011-07-21 2012-03-14 嘉兴信元精密模具科技有限公司 Inclined ejection mechanism
CN202439195U (en) * 2012-03-01 2012-09-19 陈志烟 Inclined ejector mechanism of injection molding mold
CN202623186U (en) * 2012-05-08 2012-12-26 滁州浩博科技有限责任公司 Pitched roof main body with water route of injection mold composite pitched roof demolding mechanism
CN104325538A (en) * 2014-08-29 2015-02-04 中南大学 Improved direct writing forming method for preparing three-dimensional structure
CN204712395U (en) * 2015-06-19 2015-10-21 东莞市锋铭实业有限公司 A kind of oblique top of special-shaped waterway structure

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108121840A (en) * 2016-11-29 2018-06-05 中车大同电力机车有限公司 The distribution method in water route between a kind of traction current transformation cabinet and train power supply cabinet
CN108819050A (en) * 2018-06-04 2018-11-16 宁波恒富汽车部件发展有限公司 A kind of mold production technology for applying special-shaped water route 3D printing
CN109016272A (en) * 2018-06-26 2018-12-18 珠海格力精密模具有限公司 A kind of production method and 3D printing injection mold of injection mold
CN112223695A (en) * 2020-09-22 2021-01-15 珠海市英诚电子科技有限公司 Method capable of quickly modifying pitched roof mechanism model
CN112223695B (en) * 2020-09-22 2022-04-29 珠海市英诚电子科技有限公司 Method capable of quickly modifying pitched roof mechanism model
CN112570730A (en) * 2020-12-09 2021-03-30 西安航天发动机有限公司 High-precision selective laser melting forming method for cooling body part

Also Published As

Publication number Publication date
CN104999083B (en) 2017-03-15

Similar Documents

Publication Publication Date Title
Feng et al. Design and fabrication of conformal cooling channels in molds: Review and progress updates
King et al. Alternative materials for rapid tooling
Venkatesh et al. Comparison of straight line to conformal cooling channel in injection molding
Park et al. Development of a smart plastic injection mold with conformal cooling channels
CN104999083A (en) Preparation method of sloped top of heteromorphic waterway and sloped top
Rännar et al. Efficient cooling with tool inserts manufactured by electron beam melting
Altaf et al. Prototype production and experimental analysis for circular and profiled conformal cooling channels in aluminium filled epoxy injection mould tools
Equbal et al. Rapid tooling: A major shift in tooling practice
CN103434137B (en) A kind of toy manufacture method based on rapid shaping technique
CN103009633B (en) A kind of entity manufacture method based on superthin layer wood plastic composite
CN105855819A (en) Manufacturing method for conformal cooling channels in steel injection mold
CN113591350B (en) Material extrusion forming 3D printing forming quality improvement method
Arman et al. A comprehensive review of injection mold cooling by using conformal cooling channels and thermally enhanced molds
Kuo et al. Effects of different cooling channels on the cooling efficiency in the wax injection molding process
CN204712395U (en) A kind of oblique top of special-shaped waterway structure
Saifullah et al. New cooling channel design for injection moulding
Deepika et al. Plastic injection molded door handle cooling time reduction investigation using conformal cooling channels
CN105537588A (en) Three-dimensional printing and preparing method for plastic injection mold core and plastic injection mold core
Dimla Design considerations of conformal cooling channels in injection moulding tools design: an overview
Shinde et al. Effect of Different Shapes of Conformal Cooling Channel on the Parameters of Injection Molding.
Rahmati et al. Design and manufacture of a wax injection tool for investment casting using rapid tooling
CN109986724B (en) Structural function integrated design method for additive manufacturing mould conformal cooling water channel
Kuo et al. A cost-effective approach for rapid fabricating cooling channels with smooth surface
KR100848707B1 (en) mold for injection molding
CN112476878A (en) Injection mold manufacturing method based on CAE application

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant