CN104992007B - A kind of automatic reviewing method of power supply plan design drawing - Google Patents

A kind of automatic reviewing method of power supply plan design drawing Download PDF

Info

Publication number
CN104992007B
CN104992007B CN201510352572.0A CN201510352572A CN104992007B CN 104992007 B CN104992007 B CN 104992007B CN 201510352572 A CN201510352572 A CN 201510352572A CN 104992007 B CN104992007 B CN 104992007B
Authority
CN
China
Prior art keywords
power supply
supply plan
cad design
design
rule
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510352572.0A
Other languages
Chinese (zh)
Other versions
CN104992007A (en
Inventor
白朝果
聂萌
王鑫萌
孔令稷
尹全磊
单长鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Heze Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Heze Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Heze Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510352572.0A priority Critical patent/CN104992007B/en
Publication of CN104992007A publication Critical patent/CN104992007A/en
Application granted granted Critical
Publication of CN104992007B publication Critical patent/CN104992007B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of automatic reviewing method of power supply plan design drawing, belong to automatic Evaluation technology field.Segment title and coordinate information in power supply plan CAD design figure is converted to specific element and space layout by the present invention, and the interconnection situation and layout of element are extracted according to space geometry theory;Then each element anode is traveled through, rule corresponding with the element of this in database is matched, find out in power supply plan CAD design figure element use or connection procedure in the problem of and mistake, and the mistake in power supply plan CAD design map file is marked according to different errorlevels, ultimately produce a power supply plan CAD design figure audit report.The inventive method is simple to the review process of power supply plan CAD design figure, and principle of operation is reliable, and wrong identification correctness is high, and review efficiency is high, simplifies the examination of power supply plan CAD design figure.

Description

A kind of automatic reviewing method of power supply plan design drawing
Technical field
The present invention relates to automatic Evaluation technology field, more particularly to a kind of automatic reviewing method of power supply plan design drawing, It is automatic that particularly a kind of algorithm of use automatic identification CAD design figure drawing component placement carries out machine to power supply plan design drawing The method of evaluation.
Background technology
At present, CAD drawing is applied in increasing field, in power supply engineering, and power supply plan design drawing is real The foundation of border engineering, power supply plan design drawing draw correctness be whole electric power system can normally run guarantee, be the later stage The accurate reference of construction, underproof power supply plan design drawing is easily caused power supply engineering and produces fund waste, work progress chance There is a series of problems, such as recessive operation hidden danger, later maintenance inconvenience after to obstacle, Practical Completion.Therefore, power supply plan is set The examination & verification of meter figure seems important, and existing technology is all to carry out manual examination and verification using check of drawings personnel, due to the subjective thinking of personnel It is inconsistent, cause the result that different check of drawings personnel audit also not near identical, meanwhile, the energy of the work of people be it is limited, Prolonged check of drawings can cause the fatigue of vision, it is easy to produce a series of mistakes for being difficult gap, traditional artificial check of drawings is not But inefficiency, takes time and effort, and very easily produce mistake.
The content of the invention
It is not enough in order to make up the above, it is power network the invention provides a kind of automatic reviewing method of power supply plan design drawing Examination & verification and the construction of power supply engineering provide accurate review data, improve the reliability and specification of the evaluation of power supply plan design drawing Property, using the image information in power supply plan CAD design map file, and based on geometric theory, element in identification CAD drawing and Component placement, progress analysis evaluation, the problem of drawing power supply plan design drawing and mistake are compared with existing rule base, and it is accurate to produce Review data.
The technical scheme is that:
A kind of automatic reviewing method of power supply plan design drawing, by the segment title and seat in power supply plan CAD design figure Mark information is converted to specific element and space layout, and the interconnection situation and cloth of element are extracted according to space geometry theory Office;Then each element anode is traveled through, rule corresponding with the element of this in database is matched, and finds out power supply plan CAD In design drawing element use or connection procedure in the problem of and mistake, and according to different errorlevels mark power supply plan CAD set The mistake in map file is counted, a power supply plan CAD design figure audit report is ultimately produced.
Preferably, the automatic reviewing method of the power supply plan design drawing is concretely comprised the following steps:
1)Corresponding element data discrimination storehouse is set up according to the element of power supply plan CAD design figure composition and makees rule map number According to storehouse;
2)Input information will be used as by the power supply plan CAD design figure of the element construction in the element data discrimination storehouse;
3)According in segment title in power supply plan CAD design figure and coordinate information identification power supply plan CAD design figure Component kind and space layout, and stored;
4)All element anodes in power supply plan CAD design figure are traveled through, finds out in the mapping rule database and owns The Rule Information related to current each element;
5)According to the rule related to element of annexation before and after element, the conflict or superfluous between automatic lookup element is front and rear It is remaining, and matched;
6)According to matching result, the matching of mistake is found out, one or more error message related to element is automatically generated;
7)Judge whether that traversal is completed, if not traveling through completion repeats 4)-6)Operating process, ultimately generate a complete Audit report, realizes the automatic evaluation of power supply plan CAD design figure.
It is preferred that, judge whether two elements are connected, it is only necessary to judge whether the geometric figure for constituting two elements has friendship Point.
Further, judge whether geometric figure has the rule of intersection point to include circle and intersect judgment rule, circle and line with round The intersecting judgment rule of section, the intersecting judgment principle for intersecting judgment principle, line segment and other figures of line segment and line segment.
Preferably, when the interconnection situation of judgment component and layout, if in power supply plan CAD design figure in element What information was stored is relative position, relative rotation angle, relative scaling size, it is necessary to which the information in element is transformed into absolute position Put, its conversion formula is:
Abstract image coordinate is converted to tool by the present invention using the image coordinate information in power supply plan CAD design figure The element of body, the interconnection situation and layout of element are extracted according to space geometry theory;Then each element section is traveled through Point, rule corresponding with the element of this in database is matched, and is found out element in power supply plan CAD design figure and is used or connected The problem of in journey and mistake, and the mistake in power supply plan CAD design map file is marked according to different errorlevels, ultimately produce A power supply plan CAD design figure audit report, its specific steps is at one equipped with conventional CAD design software and pipe-line system Computer in realize:
Certainly, different types of CAD diagram, component library is also different from the selection of rule base.
Beneficial effects of the present invention are:
Compared with prior art, its review process to power supply plan CAD design figure is simple, and principle of operation can by the present invention Lean on, wrong identification correctness is high, review efficiency is high, simplifies the examination of power supply plan CAD design figure.
Brief description of the drawings
Interfacial structure schematic diagram when Fig. 1 imports for file in the automatic reviewing method of power supply plan design drawing of the present invention;
Fig. 2 is related to component kind and space cloth for analysis design drawing in the automatic reviewing method of power supply plan design drawing of the present invention Office and interfacial structure schematic diagram when being stored;
Fig. 3 is that interfacial structure when drawing auditing result in power supply plan design drawing automatic reviewing method of the present invention is illustrated Figure.
Embodiment
Embodiment 1
The present embodiment is to a power supply plan CAD design figure by CAD design, 1 mistake of manual setting, by check of drawings personnel And the inventive method(Computer)Evaluated respectively.
Reviewing method of the present invention is concretely comprised the following steps:
1)Corresponding element data discrimination storehouse is set up according to the element of power supply plan CAD design figure composition and makees rule map number According to storehouse;
2)Using the power supply plan CAD design figure constructed by the element in the element data discrimination storehouse as input information, As shown in Figure 1;
3)All information in power supply plan CAD design figure are read, wherein segment is as element, and non-segment connects as circuit Line, and the title of segment is recognized, the information for extracting counter element from element Identification Data storehouse is stored, as shown in Figure 2;
4)According in power supply plan CAD design figure main wiring diagram reserve initial start points as identification starting point, by Start finds the element or line being connected with start as the root node of element tree, if line then continues matching directly To terminating or find element;Using the element being connected with start as start child node, while the element is used as new element The root node of subtree proceeds matching connection, finally gives element threaded tree, that is, obtains all elements of the electric hookup The order of connection and structure, then begin stepping through the element threaded tree from root node, and it is corresponding to obtain each element from rule database Strictly all rules;
5)According to the rule related to element of annexation before and after element, the conflict or superfluous between automatic lookup element is front and rear It is remaining, and matched;That is, the rule of correspondence entry inquired according to rule database, search element before and after element, see whether There is situation about conflicting with rule entries.
6)According to matching result, the matching of mistake is found out, one or more error message related to element is automatically generated And be added in error listing;
7)It is observed that judging, system is traveled through to the power supply plan CAD design figure of the present embodiment and completed, and completes evaluation.
Review result is:
Mistake 1.
Mistake is found when detecting voltage transformer:Arrester and voltage transformer on bus are connected on, one group is preferably shared Disconnecting switch.
The auditing result of check of drawings personnel is:
Arrester and voltage transformer on bus are connected on, one group of disconnecting switch is preferably shared.
It can thus be seen that check of drawings personnel are consistent with the result that machine is evaluated automatically.
The present embodiment is judged in connection procedure, because element is made up of the fundamental figure such as line segment and circle, therefore judges two Whether individual element is connected, it is only necessary to judge whether the line segment in two elements, circle have intersection point;Wherein justify the judgement intersected with circle to advise It is then:Intersect if 1 and the radius of circle 2 and the distance more than circle 1 with justifying 2 centers of circle is justified;Circle intersects judgment rule with line segment For:If the distance of line segment and circle is less than round radius and the distance of line segment two-end-point to circle at least has one and is more than radius of circle Distance, then intersect;To travel through that institute in element is wired, circle between element and element, and judge whether intersection point, if two Line has parallel, judges whether to overlap;If intersecting, judge in the whether online segment limit of intersection point;When judging connection, in cad file Segment in information stores is relative position, relative rotation angle, relative scaling size, it is necessary to which segment i.e. element is transformed into Absolute position, its conversion formula is:

Claims (3)

1. a kind of automatic reviewing method of power supply plan design drawing, it is characterised in that:By the segment in power supply plan CAD design figure Title and coordinate information are converted to specific element and space layout, and the interconnection of element is extracted according to space geometry theory Situation and layout;Then each element anode is traveled through, rule corresponding with the element of this in database is matched, and finds out power supply In scheme CAD design figure element use or connection procedure in the problem of and mistake, and according to different errorlevels mark supplier of electricity Mistake in case CAD design map file, ultimately produces a power supply plan CAD design figure audit report;
Concretely comprise the following steps:
1)Corresponding element data discrimination storehouse and mapping regular data are set up according to the element of power supply plan CAD design figure composition Storehouse;
2)Input information will be used as by the power supply plan CAD design figure of the element construction in the element data discrimination storehouse;
3)According to the element in segment title in power supply plan CAD design figure and coordinate information identification power supply plan CAD design figure Species and space layout, and stored;
4)All element anodes in power supply plan CAD design figure are traveled through, are found out all with working as in the mapping rule database The related Rule Information of preceding each element;
5)According to the rule related to element of annexation before and after element, conflict or redundancy between automatic lookup element is front and rear, And matched;
6)According to matching result, the matching of mistake is found out, one or more error message related to element is automatically generated;
7)Judge whether that traversal is completed, if not traveling through completion repeats 4)-6)Operating process, ultimately generate a complete examination & verification Report, realizes the automatic evaluation of power supply plan CAD design figure;
When the interconnection situation of judgment component and layout, if in power supply plan CAD design figure in element information store be Relative position, relative rotation angle, relative scaling size by the information in element, it is necessary to be transformed into absolute position, and it changes public Formula is:
2. the automatic reviewing method of power supply plan design drawing as claimed in claim 1, it is characterised in that:Whether judge two elements It is connected, it is only necessary to judge whether the geometric figure for constituting two elements has intersection point.
3. the automatic reviewing method of power supply plan design drawing as claimed in claim 2, it is characterised in that:Judging geometric figure is The no rule for having intersection point includes the phase of circle and the intersecting judgment rule, line segment and the line segment that intersect judgment rule, circle and line segment of circle Judgment principle, line segment is handed over to intersect judgment principle with other figures.
CN201510352572.0A 2015-06-24 2015-06-24 A kind of automatic reviewing method of power supply plan design drawing Expired - Fee Related CN104992007B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510352572.0A CN104992007B (en) 2015-06-24 2015-06-24 A kind of automatic reviewing method of power supply plan design drawing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510352572.0A CN104992007B (en) 2015-06-24 2015-06-24 A kind of automatic reviewing method of power supply plan design drawing

Publications (2)

Publication Number Publication Date
CN104992007A CN104992007A (en) 2015-10-21
CN104992007B true CN104992007B (en) 2017-08-11

Family

ID=54303821

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510352572.0A Expired - Fee Related CN104992007B (en) 2015-06-24 2015-06-24 A kind of automatic reviewing method of power supply plan design drawing

Country Status (1)

Country Link
CN (1) CN104992007B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105975802A (en) * 2016-07-05 2016-09-28 北京数码大方科技股份有限公司 Grading method and device for CAD drawing
CN107067228A (en) * 2017-03-31 2017-08-18 南京钧元网络科技有限公司 A kind of hand-held authentication intelligent checks system and its checking method
CN108875599A (en) * 2018-05-30 2018-11-23 成都小智审图科技有限公司 A kind of identification check of drawings method of building trade ENGINEERING CAD drawing
CN108846398B (en) * 2018-06-26 2021-09-07 北京天工矩阵信息技术有限公司 CAD graph recognition method and device
CN110795809B (en) * 2019-11-07 2023-08-29 国网河北省电力有限公司电力科学研究院 Method, system and medium for automatically picking up connection relation of electric secondary circuit of transformer substation based on CAD (computer aided design) drawing
CN112037086A (en) * 2020-09-14 2020-12-04 国网重庆市电力公司营销服务中心 Power supply scheme examination method and device and readable storage medium
CN115062369A (en) * 2022-05-09 2022-09-16 云南省设计院集团有限公司 Automatic construction drawing standard name checking system based on CAD
CN115659434B (en) * 2022-12-09 2023-03-21 中交第四航务工程勘察设计院有限公司 CAD drawing quality scoring method and system based on style

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101477548A (en) * 2009-01-20 2009-07-08 中国测绘科学研究院 Regulation based universal space data quality checking technique
CN101882225A (en) * 2009-12-29 2010-11-10 北京中科辅龙计算机技术股份有限公司 Engineering drawing material information extraction method based on template
CN104281756A (en) * 2014-10-28 2015-01-14 国家电网公司 Analytic method of CAD wiring diagram

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1889115A (en) * 2006-07-27 2007-01-03 华为技术有限公司 Computer-assisted designing products on-line estimating and examining system and method
CN104504221A (en) * 2015-01-13 2015-04-08 北京恒华伟业科技股份有限公司 Evaluation data processing method and system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101477548A (en) * 2009-01-20 2009-07-08 中国测绘科学研究院 Regulation based universal space data quality checking technique
CN101882225A (en) * 2009-12-29 2010-11-10 北京中科辅龙计算机技术股份有限公司 Engineering drawing material information extraction method based on template
CN104281756A (en) * 2014-10-28 2015-01-14 国家电网公司 Analytic method of CAD wiring diagram

Also Published As

Publication number Publication date
CN104992007A (en) 2015-10-21

Similar Documents

Publication Publication Date Title
CN104992007B (en) A kind of automatic reviewing method of power supply plan design drawing
WO2016000341A1 (en) Method and system for searching cross-regional power supply range based on cim model
CN107545085B (en) Automatic generation method for process level network connection diagram of intelligent substation
US11580272B2 (en) 3D model creation support system and 3D model creation support method
CN104050605B (en) Power equipment matching process and system
CN102411764A (en) Data management system of electrical network equipment and management method thereof
CN103269279B (en) A kind of boss stands associating topology Identification method
CN106203641A (en) Power station based on HTML5 topological diagram on-line monitoring system and method
CN109214314B (en) Automatic fusion matching algorithm for lane lines
CN110909935A (en) Grid rack diagnosis analysis and intelligent auxiliary system based on power grid planning data
CN105389666B (en) Distribution network model topology connectivity method of calibration
CN106910140B (en) SVG format-based power system wiring diagram network topology analysis method
CN103853737A (en) Hypertext markup language (HTML) content visualization compiling method and system
CN114778936A (en) Monitoring method, monitor, system and electronic equipment for electric energy metering abnormity
CN104765910A (en) Multiple-loop branch line selection, ranking interaction, scene modeling system and method
CN115422628A (en) Electromechanical drawing method and system based on contribution drawing
CN104123588A (en) Comprehensive evaluation system and method of smart distribution grid
CN110415362B (en) Overlapping point cloud fusion method
Hamzah et al. The importance of design process in housing quality
CN107146165B (en) Distribution network planning data management method and system
CN102403715A (en) Data matching method for electric power system
CN105389302B (en) A kind of electrical reticulation design appraised index structural information recognition methods
Gao et al. Complementing onboard sensors with satellite maps: a new perspective for HD map construction
CN112308736B (en) Information processing method and device for complex environments of areas
CN110427527A (en) A kind of distribution terminal data structure optimization method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170811