CN104988888A - Water obtaining structure for water works of debris flow activity regions - Google Patents
Water obtaining structure for water works of debris flow activity regions Download PDFInfo
- Publication number
- CN104988888A CN104988888A CN201510392610.5A CN201510392610A CN104988888A CN 104988888 A CN104988888 A CN 104988888A CN 201510392610 A CN201510392610 A CN 201510392610A CN 104988888 A CN104988888 A CN 104988888A
- Authority
- CN
- China
- Prior art keywords
- water intaking
- bar
- debris flow
- aperture
- drain grating
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Abstract
The invention discloses a water obtaining structure, particularly discloses a water obtaining structure for water works of the debris flow activity regions, and belongs to the technical field of design and construction of buildings of water conservancy and hydropower engineering. The water obtaining structure for the water works of the debris flow activity regions is simple and can be used for conveniently overhauling and managing water obtaining galleries even during the flood season or even if debris flow happens. The water obtaining structure comprises water obtaining holes formed in a bottom grille dam of a water obtaining gallery and sewage blocking grid bars distributed on the water obtaining holes. The water obtaining structure further comprises fixing devices used for fixing the sewage blocking grid bars, and the sewage blocking grid bars are detachably mounted on the water obtaining holes through the fixing devices.
Description
Technical field
The present invention relates to a kind of water intaking structure, especially relate to a kind of water intaking structure for the debris flow activity region hydraulic engineering, belong to Hydraulic and Hydro-Power Engineering Building Design building technology field.
Background technology
On mountain stream river course, channel gradient is comparatively steep, carries a large amount of cobbles, gravel, sand, withered tree even megalith in current, for preventing a large amount of silt from entering channel, grit chamber or intake tunnel, and normal employing bottom sieve frame grid fence structure.But when flood season or generation mud-rock flow, barrier gap easily blocks by the material carried in current, and barrier grizzly bar easily destroys by withered tree, megalith etc., and the maintenance condition of gallery of just fetching water becomes poor, and management also becomes very inconvenient.
Summary of the invention
Technical problem to be solved by this invention is: provide a kind of structure simply, both to make because flood season or mud-rock flow occur also very easily to the water intaking structure for the debris flow activity region hydraulic engineering that water intaking gallery overhauls and manages.
For solving the problems of the technologies described above adopted technical scheme be: a kind of water intaking structure for the debris flow activity region hydraulic engineering, the drain grating bar comprising the water intaking aperture on water intaking gallery grille bottom dam and be arranged on this water intaking aperture, described water intaking structure also comprises the fastening devices for fixing described drain grating bar, and described drain grating bar is arranged on described water intaking aperture by described fastening devices is dismountable.
The invention has the beneficial effects as follows: by arranging a fastening devices, described drain grating bar is arranged on described water intaking aperture by described fastening devices is dismountable.Like this, both made, in the flood season in channel gradient steeper mountain stream river course, mud-rock flow occurs, there is the material blocking barrier gap of carrying in current, also can very easily described drain grating bar be pulled down from described water intaking aperture, overhaul to water intaking gallery and manage, unlike in the prior art, owing to being non-removable mounting structure, thus maintenance and management is made to become very inconvenient.
Further, described water intaking structure also comprises grizzly bar and installs strengthening frame, and the described drain grating bar be fixed on described grizzly bar installation strengthening frame is arranged on described water intaking aperture by described fastening devices is dismountable.
The preferred embodiment of such scheme is, described grizzly bar is installed strengthening frame and is made up of longitudinal bracing rail and the horizontal reinforcing rail be packed on described longitudinal bracing rail, described drain grating bar is arranged on described grizzly bar by described horizontal reinforcing rail and installs on strengthening frame, and described grizzly bar is installed strengthening frame and is fixedly connected with described fastening devices by described longitudinal bracing rail.
Be further, described fastening devices comprises pre-buried frame and dismountable link be arranged on described pre-buried frame, described pre-buried frame is packed in the concrete foundation of described water intaking aperture periphery, and the two ends of described drain grating bar and the two ends of described longitudinal bracing rail are fixed on described link respectively.
The preferred embodiment of such scheme is, described fastening devices also comprises dowel, and described pre-buried frame is packed in the concrete foundation of described water intaking aperture periphery by described dowel.
Be further, described drain grating bar is made up of two pieces of bar battens and a spacer bars, bar batten described in two pieces is arranged to up big and down small chevron shaped structure on its cross section, described spacer bars is arranged in the openend of described chevron shaped structure along its length, and is closed this openend.
Be further, the arranged in form of described water intaking aperture on the whole in inclined downstream is on described water intaking gallery grille bottom dam, and what described drain grating bar was adapted by described fastening devices and angle of inclination, described water intaking aperture is arranged on described water intaking aperture.
Accompanying drawing explanation
Fig. 1 is the layout schematic diagram of the present invention for the water intaking structure of the debris flow activity region hydraulic engineering;
Fig. 2 is the A-A sectional view of Fig. 1;
Fig. 3 is the B-B sectional view of Fig. 1.
Be labeled as in figure: water intaking gallery grille bottom dam 1, water intaking aperture 2, drain grating bar 3, fastening devices 4, grizzly bar install strengthening frame 5, longitudinal bracing rail 6, horizontal reinforcing rail 7, pre-buried frame 8, link 9, dowel 10, bar batten 11, spacer bars 12.
Detailed description of the invention
As shown in Figure 1, Figure 2 and be that a kind of structure provided by the invention simply, had both made because flood season or mud-rock flow occur also very easily to the water intaking structure for the debris flow activity region hydraulic engineering that water intaking gallery overhauls and manages shown in Fig. 3.The drain grating bar 3 that described water intaking structure comprises the water intaking aperture 2 on water intaking gallery grille bottom dam 1 and is arranged on this water intaking aperture 2, it is characterized in that: described water intaking structure also comprises the fastening devices 4 for fixing described drain grating bar 3, and described drain grating bar 3 is arranged on described water intaking aperture 2 by described fastening devices 4 is dismountable.Above by arranging a fastening devices 4, described drain grating bar 3 is arranged on described water intaking aperture 2 by described fastening devices 4 is dismountable.Like this, both made, in the flood season in channel gradient steeper mountain stream river course, mud-rock flow occurs, there is the material blocking barrier gap of carrying in current, also can very easily described drain grating bar 3 be pulled down from described water intaking aperture 4, water intaking gallery is overhauled and managed, unlike in the prior art, owing to being non-removable mounting structure, thus maintenance and management is made to become very inconvenient.
In above-mentioned embodiment, in order to strengthen the intensity of described drain grating bar 3, in order to resist carry in current when flood season in river course or mud-rock flow occur withered tree, megalith in flow at high speed to the destruction that described drain grating bar 3 causes, and then improve maintenance and the management condition in later stage, water intaking structure described in the application also comprises grizzly bar and installs strengthening frame 5, and the described drain grating bar 3 be fixed on described grizzly bar installation strengthening frame 5 is arranged on described water intaking aperture 2 by described fastening devices 4 is dismountable.Now, the preferred structure that described grizzly bar installs strengthening frame 5 is be made up of longitudinal bracing rail 6 and the horizontal reinforcing rail 7 be packed on described longitudinal bracing rail 6, described drain grating bar 3 is arranged on described grizzly bar by described horizontal reinforcing rail 7 and installs on strengthening frame 5, and described grizzly bar is installed strengthening frame 5 and is fixedly connected with described fastening devices 4 by described longitudinal bracing rail 6.The structure of grizzly bar installation strengthening frame 5 is suitable therewith, now described fastening devices 4 can adopt the structure comprising pre-buried frame 8 and dismountable link 9 be arranged on described pre-buried frame 8, described pre-buried frame 8 is packed in the concrete foundation of described water intaking aperture 2 periphery, and the two ends of described drain grating bar 3 and the two ends of described longitudinal bracing rail 6 are fixed on described link 9 respectively.Like this, the strength and stiffness of drain grating bar 3 can be strengthened to greatest extent, decrease the probability that drain grating bar is destroyed, be convenient to later stage maintenance and management.Further, in order to increase the reliability that described pre-buried frame 8 is fixedly mounted with in the concrete foundation of described water intaking aperture 2 periphery, described fastening devices 4 also comprises dowel 10, and described pre-buried frame 8 is packed in the concrete foundation of described water intaking aperture 2 periphery by described dowel 10.
And in order to avoid cobble, gravel, sand, withered tree and the megalith drain grating bar 3 especially described in cobble, gravel and husky blocking carried in current to greatest extent, described drain grating bar 3 is arranged to the structure be made up of two pieces of bar battens 11 and a spacer bars 12 by the application, and the bar batten 11 described in two pieces is arranged to up big and down small chevron shaped structure on its cross section, described spacer bars 12 is arranged in the openend of described chevron shaped structure along its length, and is closed this openend.Like this, along in water (flow) direction, the water gap excessively of described drain grating bar 3 just can form up-small and down-big flared structure, as long as the upper surface of the drain grating bar 3 that the cobble carried in current, gravel, sand, withered tree and megalith pass, just directly can enter in water intaking gallery and drain grating bar 3 can not be blocked, especially be beneficial to passing through of silt, maximum limit avoid the blocking of delivering dirty grizzly bar 3 for sale.Simultaneously, in order to avoid being hindered the diameter that connects larger cobble, gravel by drain grating bar 3, especially megalith puts the accumulation of staying and drain grating bar 3 causing silt and the less cobble of diameter, gravel, described water intaking aperture 2 is arranged the structure of arranged in form on described water intaking gallery grille bottom dam 1 in inclined downstream by the application on the whole, and what described drain grating bar 3 was adapted with angle of inclination, described water intaking aperture 2 by described fastening devices 4 is arranged on described water intaking aperture 2.Like this, carry in current not by drain grating bar 3 cobble, gravel and megalith just can fast speed move out described drain grating bar 3, avoid drain grating bar 3 to greatest extent blocked.
Claims (7)
1. the water intaking structure for the debris flow activity region hydraulic engineering, the drain grating bar (3) comprising the water intaking aperture (2) in water intaking gallery grille bottom dam (1) and be arranged on this water intaking aperture (2), it is characterized in that: described water intaking structure also comprises the fastening devices (4) for fixing described drain grating bar (3), and described drain grating bar (3) is arranged on described water intaking aperture (2) by described fastening devices (4) is dismountable.
2. the water intaking structure for the debris flow activity region hydraulic engineering according to claim 1, it is characterized in that: described water intaking structure also comprises grizzly bar and installs strengthening frame (5), the described drain grating bar (3) be fixed on described grizzly bar installation strengthening frame (5) is arranged on described water intaking aperture (2) by described fastening devices (4) is dismountable.
3. the water intaking structure for the debris flow activity region hydraulic engineering according to claim 2, it is characterized in that: described grizzly bar is installed strengthening frame (5) and is made up of longitudinal bracing rail (6) and the horizontal reinforcing rail (7) be packed on described longitudinal bracing rail (6), described drain grating bar (3) is arranged on described grizzly bar by described horizontal reinforcing rail (7) and installs on strengthening frame (5), described grizzly bar is installed strengthening frame (5) and is fixedly connected with described fastening devices (4) by described longitudinal bracing rail (6).
4. the water intaking structure for the debris flow activity region hydraulic engineering according to claim 3, it is characterized in that: described fastening devices (4) comprises pre-buried frame (8) and dismountable link (9) be arranged on described pre-buried frame (8), described pre-buried frame (8) is packed in the concrete foundation of described water intaking aperture (2) periphery, and the two ends of described drain grating bar (3) and the two ends of described longitudinal bracing rail (6) are fixed on described link (9) respectively.
5. the water intaking structure for the debris flow activity region hydraulic engineering according to claim 4, it is characterized in that: described fastening devices (4) also comprises dowel (10), described pre-buried frame (8) is packed in the concrete foundation of described water intaking aperture (2) periphery by described dowel (10).
6. the water intaking structure for the debris flow activity region hydraulic engineering according to claim 1,2,3,4 or 5, it is characterized in that: described drain grating bar (3) is made up of two pieces of bar battens (11) and a spacer bars (12), bar batten (11) described in two pieces is arranged to up big and down small chevron shaped structure on its cross section, described spacer bars (12) is arranged in the openend of described chevron shaped structure along its length, and is closed this openend.
7. the water intaking structure for the debris flow activity region hydraulic engineering according to claim 6, it is characterized in that: the arranged in form of described water intaking aperture (2) on the whole in inclined downstream is on described water intaking gallery grille bottom dam (1), and what described drain grating bar (3) was adapted by described fastening devices (4) and described water intaking aperture (2) angle of inclination is arranged on described water intaking aperture (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510392610.5A CN104988888B (en) | 2015-07-06 | 2015-07-06 | Water obtaining structure for water works of debris flow activity regions |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510392610.5A CN104988888B (en) | 2015-07-06 | 2015-07-06 | Water obtaining structure for water works of debris flow activity regions |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104988888A true CN104988888A (en) | 2015-10-21 |
CN104988888B CN104988888B (en) | 2017-02-22 |
Family
ID=54300770
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510392610.5A Active CN104988888B (en) | 2015-07-06 | 2015-07-06 | Water obtaining structure for water works of debris flow activity regions |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104988888B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113494068A (en) * | 2021-07-26 | 2021-10-12 | 四川大学工程设计研究院有限公司 | Device for eliminating blockage of water intake of bottom grid dam |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1065305A (en) * | 1991-03-25 | 1992-10-14 | 黄国宏 | The partition method of silt dirt in water conservancy, the hydroelectric project |
CN201010882Y (en) * | 2007-03-29 | 2008-01-23 | 昆明琢石机电有限责任公司 | Water surface cleaning device |
CN101260662A (en) * | 2007-03-06 | 2008-09-10 | 上海市南洋模范中学 | Detachable type sewage-barrier and method of use thereof |
JP2009068292A (en) * | 2007-09-14 | 2009-04-02 | Mitsuo Yamamoto | Zigzag-arranged bar screen for river intake works |
CN204753540U (en) * | 2015-07-06 | 2015-11-11 | 中国电建集团成都勘测设计研究院有限公司 | Multiple regional water conservancy project engineering of mud -rock flow is with water intaking structure |
-
2015
- 2015-07-06 CN CN201510392610.5A patent/CN104988888B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1065305A (en) * | 1991-03-25 | 1992-10-14 | 黄国宏 | The partition method of silt dirt in water conservancy, the hydroelectric project |
CN101260662A (en) * | 2007-03-06 | 2008-09-10 | 上海市南洋模范中学 | Detachable type sewage-barrier and method of use thereof |
CN201010882Y (en) * | 2007-03-29 | 2008-01-23 | 昆明琢石机电有限责任公司 | Water surface cleaning device |
JP2009068292A (en) * | 2007-09-14 | 2009-04-02 | Mitsuo Yamamoto | Zigzag-arranged bar screen for river intake works |
CN204753540U (en) * | 2015-07-06 | 2015-11-11 | 中国电建集团成都勘测设计研究院有限公司 | Multiple regional water conservancy project engineering of mud -rock flow is with water intaking structure |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113494068A (en) * | 2021-07-26 | 2021-10-12 | 四川大学工程设计研究院有限公司 | Device for eliminating blockage of water intake of bottom grid dam |
Also Published As
Publication number | Publication date |
---|---|
CN104988888B (en) | 2017-02-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105283604B (en) | River Chip entrapment structure | |
KR100794922B1 (en) | The beam creen rhombic dam which h-steel and screen are combined | |
CN215168679U (en) | Sand barrier for preventing sand from overflowing | |
WO2018036317A1 (en) | Water collecting and draining system, and construction method thereof | |
CN207904879U (en) | A kind of Debris Flow on Slope Surface improvement integration engineering structure | |
CN204753540U (en) | Multiple regional water conservancy project engineering of mud -rock flow is with water intaking structure | |
CN204551491U (en) | A kind of side slope protection greening structure | |
CN203270470U (en) | Comprehensive prevention and control facility structure suitable for wind and sand of railway of plateau river wide-valley section | |
CN104988888A (en) | Water obtaining structure for water works of debris flow activity regions | |
CN205954559U (en) | A ditch water treatment structure that is used for large -scale sediment field of blocking | |
CN206428785U (en) | It is a kind of to remove the Multifunctional rain management and control facility become silted up | |
CN108376203A (en) | A kind of design method of slit dam opening width for non-sticky mud-rock flow | |
CN208183765U (en) | A kind of ecotype slope protection system | |
KR101313868B1 (en) | A debris barrier with plural empty structure | |
KR101170789B1 (en) | Complex debris barrier of eco-friendly | |
CN103790223B (en) | A kind of karst depression drainage system | |
CN215630021U (en) | Highway bridge construction foundation ditch protector | |
CN104963379A (en) | Water taking structure for mountainous area river course | |
CN105545356B (en) | Bored tunnel bottom plate drainage sunk well | |
CN205399343U (en) | Reinforcement type waterproof and anti -seepage bank protection | |
KR102351049B1 (en) | Debris barrier with integrated side wall | |
CN208167639U (en) | A kind of hydraulic engineering ecological supporting structure | |
JP4663403B2 (en) | Transmission type sabo dam | |
CN203878546U (en) | Culvert with energy dissipation function | |
KR100879973B1 (en) | Beamcreen rhombic dam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |