CN104981976A - 对本地电网事件和分布式电网事件的响应 - Google Patents
对本地电网事件和分布式电网事件的响应 Download PDFInfo
- Publication number
- CN104981976A CN104981976A CN201380070420.0A CN201380070420A CN104981976A CN 104981976 A CN104981976 A CN 104981976A CN 201380070420 A CN201380070420 A CN 201380070420A CN 104981976 A CN104981976 A CN 104981976A
- Authority
- CN
- China
- Prior art keywords
- event
- grid
- distributed
- local
- grid event
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/28—Arrangements for balancing of the load in a network by storage of energy
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/001—Methods to deal with contingencies, e.g. abnormalities, faults or failures
- H02J3/0012—Contingency detection
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2310/00—The network for supplying or distributing electric power characterised by its spatial reach or by the load
- H02J2310/10—The network having a local or delimited stationary reach
- H02J2310/12—The local stationary network supplying a household or a building
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/04—Circuit arrangements for ac mains or ac distribution networks for connecting networks of the same frequency but supplied from different sources
- H02J3/06—Controlling transfer of power between connected networks; Controlling sharing of load between connected networks
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B70/00—Technologies for an efficient end-user side electric power management and consumption
- Y02B70/30—Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
- Y02B70/3225—Demand response systems, e.g. load shedding, peak shaving
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S20/20—End-user application control systems
- Y04S20/222—Demand response systems, e.g. load shedding, peak shaving
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Supply And Distribution Of Alternating Current (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
- Inverter Devices (AREA)
Abstract
一种用于能量储存设备的控制系统联接到电网上的传感器。该控制系统被配置成从传感器中的每个传感器接收测量结果。该控制系统基于所接收的测量结果确定电网事件是本地事件还是分布式事件。该控制系统选择基于确定该电网事件是本地事件还是分布式事件来控制该能量储存设备的响应模式。
Description
技术领域
本公开总体涉及对功率流进行管理,并且更具体地涉及响应于不同类型的事件而对电网中的能量输送进行管理。
背景技术
现代电力系统必须高效且可靠地输送能量。这是因为人们严重依赖电力。电力为许多设备提供动力,这些设备如计算机、手机、灯、家用电器和机器等,所有这些是许多市民生活的组成部分。随着社会对能量需求的增加,电力系统基础设施需要改进,以便以高效且可靠的方式提供日益重要的电力资源。
大的发电厂通常生成电力并且将在电力达到目标负载之前通过电网分配系统发送电力。然而,电力系统可能经历有问题的事件,如发电机的波动的功率输出、负载显著变化或分配基础设施受到物理损坏等。为了提高电力输送系统的可靠性,电力输送系统应该能够调节和适应此类事件。
发明内容
一种用于一个或多个能量储存设备的控制系统联接到电网上的传感器。该控制系统被配置成从这些传感器中的每个传感器接收测量结果。该控制系统基于所接收的测量结果确定电网事件是本地事件还是分布式事件。该控制系统选择基于确定电网事件是本地事件还是分布式事件来控制该能量储存设备或这些能量储存设备的响应模式。
通常,本说明书中所描述的主题的一个方面能够体现在多种方法中,这些方法包括以下动作:从联接到电网的多个传感器中的每个传感器接收测量结果,该电网包括在不同地理位置处的多个计量节点,每个传感器联接到一个计量节点;基于所接收的测量结果确定电网事件是本地事件还是分布式事件;并且选择基于确定该电网事件是本地事件还是分布式事件来控制能量储存设备的响应模式。本方面的其他实施例包括对应的、其被配置成执行这些方法的动作、编码在计算机存储设备上的系统、装置和计算机程序。一个或多个计算机的系统能够被配置成借助于将软件、固件、硬件或它们的组合安装在该系统上来执行具体的动作,该软件、固件、硬件或它们的组合在操作时引起该系统执行这些动作。一个或多个计算机程序能够被配置成借助于包括多个指令来执行具体动作,这些指令当被数据处理装置执行时引起该装置这些动作。
这些和其他实施例每个能够任选地包括以下特征中的一个或多个。这些动作包括确定第一电网事件是本地事件,并且作为响应,引起该能量储存设备以第一速率注入或吸收有功功率或无功功率以补偿该第一电网事件;并且确定第二电网事件是分布式事件,并且作为响应,引起该能量储存设备以大于该第一速率的第二速率注入或吸收有功功率或无功功率以补偿该第二电网事件。确定该电网事件是本地事件还是分布式事件包括对报告该电网事件的传感器数量进行计数,并且如果该传感器数量大于阈值传感器数量,则确定该电网事件是分布式事件。该电网包括第一级电网部件和第二级电网部件,并且多个第一传感器位于该第一级电网部件中,并且多个第二传感器位于该第二级电网部件中,并且其中,确定该电网事件是本地事件还是分布式事件包括对在该第一级中的报告该电网事件的第一传感器数量和对在该第二级中的报告该电网事件的第二传感器数量进行计数并且基于该第一传感器数量和该第二传感器数量来确定该电网事件是本地事件还是分布式事件。基于该第一传感器数量和该第二传感器数量确定该电网事件是本地事件还是分布式事件包括:确定该第一传感器数量与该第二传感器数量之间的差值;并且如果该差值大于阈值差值,则确定该电网事件是本地事件,并且如果该差值小于或等于该阈值差值,则确定该电网事件是分布式事件。确定该电网事件是本地事件还是分布式事件包括:从这些传感器中的每个传感器接收位置信息;并且基于该位置信息确定该电网事件是本地事件还是分布式事件。基于该位置信息确定该电网事件是本地事件还是分布式事件包括:对处于第一位置的报告该电网事件的第一传感器数量进行计数;对处于第二位置的报告该电网事件的第二传感器数量进行计数;确定该第一传感器数量与该第二传感器数量之间的差值;并且如果该差值小于或等于阈值差值,则确定该电网事件是本地事件,并且如果该差值大于该阈值差值,则确定该电网事件是分布式事件。这些动作包括通过确定至少第一传感器已经报告了该电网的所测量的电参数的减小来确定该电网事件已经发生。这些动作包括确定至少第一传感器已经报告了所测量的电参数的减小包括确定在至少阈值时间段内该第一传感器已经报告了所测量的电参数的减小。
该控制系统的具体实现方式能够提供以下优点中的一个或多个优点:该控制系统能够更强有力地响应于分布式电网事件,并且由此为电网上的用户提供更好的服务;该控制系统能够不那么强有力地响应于本地电网事件,并且由此减小对电网的意外影响;并且该控制系统能够使用从传感器接收到的不同数据确定电网事件是本地的还是分布式的,由此更可靠地确定电网事件是本地的还是分布式的。
所公开的一个或多个实现方式的细节在这些附图和以下具体实施方式中阐述。其他特征、方面和优点根据本描述、附图以及权利要求将变得明显。
附图说明
图1是示例电网的框图。
图2是联接到分配网络的示例功率管理系统(PMS)的框图。
图3是一个或多个功率管理系统的示例控制系统的框图。
图4是用于响应于电网事件而控制一个或多个能量储存设备的示例过程的流程图。
具体实施方式
图1是示例电网100的框图。该电网被组织成多级层次,包括主级102、次级104和本地级106。功率管理系统108a-d联接到电网并且被配置成从传感器110a-f接收信号并且从能量储存设备注入或吸收实际功率和无功功率以补偿电网事件。
电网的主级包括主发电机112a-b。主发电机能够是例如燃煤电厂、核电厂、风力发电厂、太阳能电池阵列和水力发电厂。电网的主级联接到电网的次级。一个或多个变压器能够在主级与次级之间逐步减低电压。
第二级包括次级发电机114,并且在某些实现方式中是负载。次级发电机能够是例如产生比主发电机更少电力的燃煤发电厂。该负载能够是例如用户负载。
第二级联接到本地级。一个或多个变压器能够在次级与本地级之间逐步减低电压。该本地级能够包括本地电网118a-b,这些本地电网包括本地用户120a-b和本地发电机122a-b。本地用户能够是例如居民用户、商业用户和工业用户。
这些传感器的每个在地理上分布的各自计量节点处联接到电网。这些传感器能够定位在电网的不同级中,并且这些传感器能够定位在本地电网的不同分支中。这些传感器中的某些传感器能够定位在具体负载附近以监控那些负载。这些传感器中的某些传感器能够定位在具体发电机附近或在具体发电机处以监控那些发电机。
这些传感器能够测量例如在计量节点处的电流、电压、频率、相位、电阻和温度中的一项或多项。每个传感器被配置成例如定期或响应于询问而向功率管理系统中的一个或多个功率管理系统报告一个或多个测量结果。这些传感器能够通过数据网络(例如,通过电力线)或通过经由互联网上的蜂窝塔的通信或通过现有智能电网基础设施向功率管理系统报告。这些功率管理系统被配置成接收测量结果并且确定用于对电网事件进行响应的响应模式。
电网事件能够包括例如电流、电压、相位角、谐波和频率的变化。例如当电网上的电力频率在一定时间段内下降一定量或功率系统上的分散的位置处存在显著的相位角差时,功率管理系统能够确定发生了电网事件。功率管理系统的响应模式能够确定,例如功率管理系统是否从一个或多个能量储存设备注入或吸收有功功率或无功功率和它从该能量储存设备或这些能量储存设备注入或吸收功率所在的速率。
功率管理系统能够基于电网事件是本地事件还是分布式事件来确定它从一个或多个能量储存设备注入或吸收功率所在的速率。在某些实现方式中,该功率管理系统响应于本地事件以第一速率从该能量储存设备或这些能量储存设备注入或吸收功率并且响应于分布式事件以大于该第一速率的第二速率从该这些能量储存设备注入或吸收功率。
图2是联接到分配网络250的示例功率管理系统(PMS)200的框图。该功率管理系统包括能量储存装置阵列211、221和231。这些能量储存装置阵列中每个能量储存装置联接到对应的功率变换系统212、222和232,并且这些功率变换系统中每个联接到对应的变压器215、225和235。这些功率变换系统能够例如是双向逆变器。在某些实现方式中,这些能量储存装置阵列包括串联、并联或以串-并联配置联接的蓄电池。在其他实现方式中,这些能量储存装置阵列可以包括例如电容器、飞轮、超导磁性元件或其组合。
变压器联接到变电站254,该变电站联接到间歇性电源260和电网270(例如,图1的电网100)。该间歇性电源能够是,例如风力发电厂或太阳能电力发电机。在操作时,该功率管理系统向间歇性电源提供一项或多项支持服务或向电网提供一项或多项辅助服务。
该功率管理系统包括通过通信接口操作性地链接到每个逆变器的控制系统140。控制系统通过通信接口为逆变器提供控制信号和/或数据,包括例如目标有功功率设置和无功功率设置、分配网络状态信息和激活/待机控制命令。分配网络状态信息包括例如来源于例如联接到电网的一个或多个传感器的电压、电流、有功功率、无功功率和频率信息。基于这个信息,控制系统能够控制每个功率变换系统的操作,使得功率管理系统像是分配网络作为单个高容量系统。
控制系统基于系统性能要求向每个逆变器发出目标有功功率设置(“P命令”)和目标无功功率设置(“Q命令”)。例如,在频率调节模式下,控制系统响应于检测到分配网络上的频率下降可以发出增加从能量储存装置阵列向分配网络传输的有功功率量的P命令。
该控制系统发出目标频率谐波设置以生成用于抵消不期望的频率的异相谐波。例如,电网的基本频率可以是50或60Hz。如果该控制系统确定电网上存在不令人期望的10Hz振荡,则该控制系统能够引起能量储存系统生成异相信号来抵消不期望的频率。
进一步地,在电压调节模式下,控制系统能够响应于检测到电压降发出增加在能量储存装置阵列与分配网络之间传输的无功功率量的Q命令。而且,在VAR调节模式下,控制系统能够响应于越限状况发出调节在能量储存装置阵列与分配网络之间传输的无功功率量的Q命令。
控制系统能够根据需要发出P和Q命令,以便对在间歇性电源与电网之间的互连点(POI)265处传输的功率进行管理。例如,控制系统能够发出吸收间歇性电源所生成的功率的P命令,以避免在间歇性电源的功率输出的突然增加期间违背正的爬坡率限制。类似地,控制系统能够在间歇性电源的功率输出突然下降时发出向分配网络150提供功率的P命令,以避免违背负的爬坡率限制。
图3是一个或多个功率管理系统的示例控制系统302的框图。例如,该控制系统能够是图2的控制系统240。该控制系统至少接收传感器数据(例如,来自图1的传感器110a-f的数据)并且将命令(例如,P和Q命令)发送至如上参考图2所述的功率变换系统。控制系统能够被实现例如在执行一个或多个可执行的指令模块的一个或多个计算机上。
该控制系统包括事件检测模块304、响应选择模块306和能量储存控制模块308。该事件检测模块对传感器数据进行分析,以确定电网事件是否已经发生。在某些实现方式中,当所测量的电网参数在一定时间段内变化一定量时,该事件检测模块确定电网事件已经发生。例如,当电网上的所测量的频率在一定时间段内下降到低于阈值频率时,事件检测模块能够确定电网事件已经发生。
响应于确定电网事件已经发生,响应选择模块选择用于控制一个或多个能量储存设备的响应模式。该响应选择模块确定电网事件是本地事件还是分布式事件。
在某些实现方式中,本地事件是由阈值数量的传感器或更少的传感器报告的事件,并且分布式事件是大于阈值数量的传感器报告的电网事件。例如,假设传感器的阈值数量是二。如果一个或两个传感器测量电网上的相位角的变化,则响应选择模块将确定电网事件是本地事件。如果多于两个传感器测量电网上的相位角的变化,则响应选择模块将确定电网事件是分布式事件,该响应选择模块将确定电网事件是本地事件。
在某些实现方式中,该响应选择模块使用位置信息来确定事件是本地的还是分布式的。例如,响应选择模块可以访问所存储的指示传感器的位置的信息,或传感器可以报告位置信息。然后,响应选择模块能够确定本地事件是某一区域(例如,以上关于图1所描述的电网级之一)的传感器所报告的电网事件,并且响应选择模块能够确定分布式事件是多于一个区域或多于阈值数量区域内的传感器所报告的电网事件。
在某些实现方式中,该响应选择模块使用时间同步传感器数据和地理数据以及电网架构数据来生成本地和分布式控制响应。例如,响应选择模块能够对移动的时间窗口内的时间坐标电压、频率和相位进行分析,并且确定是否需要时间同步分布式响应。
在某些实现方式中,该响应选择模块使用除了地理位置信息以外的层次信息(如位置信息)。例如,考虑图1中所图示的示例电网。传感器110a和110b位于电网的主级中。该响应选择模块能够确定由传感器110a和110b之一或两者所报告的电网事件是分布式事件。传感器110e和110f位于电网的本地级中。该响应选择模块能够确定由传感器110a和110b之一所报告的电网事件是本地事件。
在确定了电网事件是本地事件还是分布式事件之后,响应选择模块选择用于控制一个或多个能量储存设备的响应模式。例如,该响应模式能够指定以一定速率从能量储存设备注入或吸收功率,或者使用电网上的频率变化率在反馈环路中从能量储存设备注入或吸收功率。如以下参考图4进一步描述的,该响应模式能够指定用于从能量储存设备注入或吸收功率的不同参数。
能量储存控制模块对从一个或多个能量储存设备注入或吸收功率进行控制。该能量储存模块可以应用一个或多个控制算法来控制能量储存设备,并且这些控制算法可以使用不同因素中的一个或多个因素,例如,间歇性电源的所测量的功率输出、间歇性电源的变化率或功率输出和能量储存设备的荷电状态。响应于检测到电网事件,能量储存控制模块使用响应选择模块所选择的响应模式来控制从能量储存设备注入或吸收功率。
图4是用于响应于电网事件而控制一个或多个能量储存设备的示例过程400的流程图。该过程能够例如由图1的功率管理系统之一或者由图2的控制系统240来执行。出于说明的目的,将关于执行该过程的系统来描述该过程。
该系统从联接到电网的多个传感器中的每个传感器接收测量结果(402)。测量结果能够是时间同步的。在某些实现方式中,测量结果包括电压和电流幅值、相位角和频率或者它们的组合。该电网包括不同地理位置处的计量节点,并且这些传感器中的至少一些传感器联接到计量节点。
该系统基于测量结果确定电网事件是否已经发生(404)。例如,该系统能够确定在至少一段阈值时间段内至少第一传感器已经报告了所测量的电参数的减小。
该系统确定电网事件是本地事件还是分布式事件(406)。例如,该系统能够通过对报告该电网事件的传感器数量进行计数来确定该电网事件是本地事件还是分布式事件,并且如果该传感器数量大于阈值传感器数量,则确定该电网事件是分布式事件。
在某些实现方式中,确定电网事件是本地事件还是分布式事件包括计算在第一传感器处的第一相位角与在第二传感器处的第二相位角之间的差值,并且如果该差值超过阈值,则确定该电网事件是分布式事件。在某些实现方式中,确定电网事件是本地事件还是分布式事件包括计算历史区域间的功率流,并且如果超过了阈值振荡或阈值变化率,则确定电网事件是分布式事件。
例如,该系统能够确定从第一传感器到第二传感器的第一功率流并且将该第一功率流与从该第一传感器到该第二传感器的所记录的功率流进行比较。如果该第一功率流振荡与所记录的功率流振荡相差大于阈值振荡量或者该功率流相对于所记录的功率流的变化率超过阈值变化率,则该系统能够确定电网事件是分布式事件。
在某些实现方式中,电网包括第一级电网部件和第二级电网部件。该系统通过对在该第一级中的报告该电网事件的第一传感器数量和对在该第二级中的报告该电网事件的第二传感器数量进行计数,并且基于该第一传感器数量和该第二传感器数量来确定电网事件是本地事件还是分布式事件,从而确定电网事件是本地事件还是分布式事件。例如,该系统能够确定第一传感器数量与第二传感器数量之间的差值,并且如果该差值大于阈值差值,则确定电网事件是本地事件,并且如果该差值小于或等于该阈值差值,则确定电网事件是分布式事件。
在某些实现方式中,该系统从这些传感器中的每个传感器接收位置信息,并且基于该位置信息确定电网事件是本地事件还是分布式事件。例如,该系统能够对处于第一位置中的报告电网事件的第一传感器数量和对处于第二位置中的报告电网事件的第二传感器数量进行计数。然后,该系统能够确定该第一传感器数量与该第二传感器数量之间的差值。如果该差值小于或等于阈值差值,则该系统确定电网事件是本地事件,并且如果该差值大于该阈值差值,则该系统确定电网事件是分布式事件。
如果电网事件是本地事件,则该系统选择本地响应模式(408)。如果电网事件是分布式事件,则该系统选择分布式响应模式(410)。例如,该系统能够引起能量储存设备在本地响应模式下以第一速率注入或吸收功率并在分布式响应模式下以大于第一速率的第二速率注入或吸收功率。
在某些实现方式,当电网事件是频率下降并且该系统确定电网事件是分布式事件时,该系统引起能量储存设备以高增益输出频率响应,试图按以下方程所控制的那样最小化频率偏差的绝对值:
方程1:
其中R=传统下降系数(Hz/MW)
Td=超前幅值系数
Tg=超前时间常系数
TMRlead=相对于频率事件开始的时间值
频率偏差=所测量的频率与标称频率之间的差异。
替代地,该系统能够根据其他不同的常规控制算法引起能量储存设备输出频率响应。
本说明书中所描述的主题和操作的实施例能够在数字电路中实现,或以计算机软件、固件或硬件(包括本说明书中所公开的结构及其结构等效物中)实现,或在它们中的一个或多个的组合中实现。本说明书中所描述的主题的实施例能够被实现为一个或多个计算机程序,例如,编码在计算机存介储质上的计算机程序指令的一个或多个模块,以便由数据处理装置执行或控制其操作。替代地或此外,这些程序指令能够编码在人工生成的传播的信号(例如,机器生成的电信号、光信号或电磁信号)上,该信号被生成用于对信息进行编码以便传送到合适的接收器装置,以供数据处理装置执行。计算机存储介质能够是或者被包括在机器可读存储设备、机器可读存储基板、随机或串行存取存储器阵列或设备或它们中的一个或多个的组合。而且,虽然计算机存储介质不是传播的信号,但计算机存储介质能够是编码在人工生成的传播的信号中的计算机程序指令的来源或目的地。计算机存储介质还能够是例如或包括在一个或多个单独的物理部件或介质(例如,多个CD、盘或其他存储设备)中。
本说明书中所描述的操作能够被实现为由数据处理装置对存储在一个或多个计算机可读存储设备上的或从其他来源接收的数据执行的操作。
术语“数据处理装置”包括所有种类的用于数据处理的装置、设备和机器,举例来讲,包括可编程处理器、计算机、片上系统、或前述的多个或组合。该装置能够包括专用逻辑电路,例如,FPGA(现场可编程门阵列)或ASIC(专用集成电路)。除了硬件以外,该装置还能够包括,为正在讨论的计算机程序创建执行环境的代码,例如,构成处理器固件、协议栈、数据库管理系统、操作系统、跨平台运行时环境、或它们中的一个或多个的组合的代码。
本说明书中所描述的过程和逻辑流能够由执行一个或多个计算机程序(还被称为程序、软件、软件应用程序、脚本或代码)的一个或多个可编程处理器执行,以便执行对输入数据进行操作并且生成输出的动作。这些过程和逻辑流还能够由装置执行,并且装置还能够被实现为专用逻辑电路,例如,FPGA(现场可编程门阵列)或ASIC(专用集成电路)。
虽然本说明书包含许多特定实现方式细节,但这些不应被构造成为对任何发明或可能要求保护的发明的范围的限制,而是被构造成为专门对于具体发明的具体实施例的特征的描述。在单独的实施例的背景下在本说明书中所描述的某些特征还能够按组合形式实现在单一实施例中。相反,在单一实施例的背景下描述的不同特征也能够被单独的或以任何合适的子组合的方式实现在多个实施例中。而且,尽管特征在以上可以被描述为以某些组合起作用并且甚至如最初被要求保护的那样起作用,但来自所要求保护的组合的一个或多个特征在某些情况下可以与组合离体,并且所要求保护的组合可以涉及子组合或子组合的变体。
类似地,虽然附图中以具体顺序描绘了操作,但这不应被理解成要求以所示的具体顺序或以有序顺序执行这种操作,或者所有图示的操作可以被执行,以达到令人期望的效果。在某些情况下,多重任务处理和并行处理可能是有利的。而且,上述实施例中的不同系统部件的分离不应被理解成在所有实施例中都要求这种分离,并且应理解的是,所描述的程序部件和系统通常能够一起整合在单个软件产品中或封装进多个软件产品中。
因此,已经描述了本主题的具体实施例。其他实施例在以下权利要求书的范围内。在某些情况下,权利要求书中所引用的动作能够以按不同的顺序执行并且仍然达到令人期望的效果。此外,附图中所描绘的过程不一定需要所示的具体顺序或有序顺序来达到令人期望的效果。在某些实现方式中,多重任务处理和并行处理可能是有利的。
Claims (20)
1.一种系统,其包括:
联接到电网的能量储存设备;
联接到该电网的多个传感器,该电网包括在不同地理位置处的多个计量节点,每个传感器联接到一个计量节点;
联接到该能量储存设备和该传感器的控制系统,其中,该控制系统被配置成:
从该传感器中的每个传感器接收测量结果;
基于所接收的测量结果确定电网事件是本地事件还是分布式事件;并且
选择基于确定该电网事件是本地事件还是分布式事件来控制该能量储存设备的响应模式。
2.如权利要求1所述的系统,其中,该控制系统被进一步被配置成:
确定第一电网事件是本地事件,并且作为响应,引起该能量储存设备以第一速率注入或吸收有功功率以补偿该第一电网事件;并且
确定第二电网事件是分布式事件,并且作为响应,引起该能量储存设备以大于该第一速率的第二速率注入或吸收有功功率以补偿该第二电网事件。
3.如权利要求1所述的系统,其中,确定该电网事件是本地事件还是分布式事件包括计算在第一传感器处的第一相位角与在第二传感器处的第二相位角之间的差值,并且如果该差值超过阈值,则确定该电网事件是分布式事件。
4.如权利要求1所述的系统,其中,确定该电网事件是本地事件还是分布式事件包括:
确定从第一传感器到第二传感器的第一功率流;
将该第一功率流与从该第一传感器到该第二传感器的记录的功率流进行比较,并且如果该第一功率流振荡与所记录的功率流振荡相差大于阈值振荡量或者该功率流相对于所记录的功率流的变化率超过阈值变化率,则确定该电网事件是分布式事件。
5.如权利要求1所述的系统,其中,确定该电网事件是本地事件还是分布式事件包括对报告该电网事件的传感器数量进行计数,并且如果该传感器数量大于个阈值传感器数量,则确定该电网事件是分布式事件。
6.如权利要求1所述的系统,其中,该电网包括第一级电网部件和第二级电网部件,并且多个第一传感器位于该第一级电网部件中,并且多个第二传感器位于该第二级电网部件中,并且其中,确定该电网事件是本地事件还是分布式事件包括对在该第一级中的报告该电网事件的第一传感器数量和对在该第二级中的报告该电网事件的第二传感器数量进行计数并且基于该第一传感器数量和该第二传感器数量来确定该电网事件是本地事件还是分布式事件。
7.如权利要求6所述的系统,其中,基于该第一传感器数量和该第二传感器数量确定该电网事件是本地事件还是分布式事件包括:
确定该第一传感器数量与该第二传感器数量之间的差值;并且
如果该差值大于阈值差值,则确定该电网事件是本地事件,并且如果该差值小于或等于该阈值差值,则确定该电网事件是分布式事件。
8.如权利要求1所述的系统,其中,确定该电网事件是本地事件还是分布式事件包括:
从该传感器中的每个传感器接收位置信息;并且
基于该位置信息确定该电网事件是本地事件还是分布式事件。
9.如权利要求8所述的系统,其中,基于该位置信息确定该电网事件是本地事件还是分布式事件包括:
对处于第一位置的报告该电网事件的第一传感器数量进行计数;
对处于第二位置的报告该电网事件的第二传感器数量进行计数;
确定该第一传感器数量与该第二传感器数量之间的差值;并且
如果该差值小于或等于阈值差值,则确定该电网事件是本地事件,并且如果该差值大于该阈值差值,则确定该电网事件是分布式事件。
10.如权利要求1所述的系统,其中,该系统被配置成通过确定至少第一传感器已经报告了该电网的所测量的电参数的减小来确定该电网事件已经发生。
11.如权利要求10所述的系统,其中,确定至少第一传感器已经报告了所测量的电参数的减小包括确定在至少阈值时间段内该第一传感器已经报告了所测量的电参数的减小。
12.一种方法,其包括:
从联接到电网的多个传感器中的每个传感器接收测量结果,该电网包括在不同地理位置处的多个计量节点,每个传感器联接到一个计量节点;
基于所接收的测量结果确定电网事件是本地事件还是分布式事件;并且
选择基于确定该电网事件是本地事件还是分布式事件来控制能量储存设备的响应模式。
13.如权利要求12所述的方法,包括:
确定第一电网事件是本地事件,并且作为响应,引起该能量储存设备以第一速率注入或吸收有功功率或无功功率以补偿该第一电网事件;并且
确定第二电网事件是分布式事件,并且作为响应,引起该能量储存设备以大于该第一速率的第二速率注入或吸收有功功率或无功功率以补偿该第二电网事件。
14.如权利要求12所述的方法,其中,确定该电网事件是本地事件还是分布式事件包括对报告该电网事件的传感器数量进行计数,并且如果该传感器数量大于阈值传感器数量,则确定该电网事件是分布式事件。
15.如权利要求12所述的方法,其中,该电网包括第一级电网部件和第二级电网部件,并且多个第一传感器位于该第一级电网部件中,并且多个第二传感器位于该第二级电网部件中,并且其中,确定该电网事件是本地事件还是分布式事件包括对在该第一级中的报告该电网事件的第一传感器数量和对在该第二级中的报告该电网事件的第二传感器数量进行计数并且基于该第一传感器数量和该第二传感器数量来确定该电网事件是本地事件还是分布式事件。
16.如权利要求15所述的方法,其中,基于该第一传感器数量和该第二传感器数量确定该电网事件是本地事件还是分布式事件包括:
确定该第一传感器数量与该第二传感器数量之间的差值;并且
如果该差值大于阈值差值,则确定该电网事件是本地事件,并且如果该差值小于或等于该阈值差值,则确定该电网事件是分布式事件。
17.如权利要求10所述的方法,其中,确定该电网事件是本地事件还是分布式事件包括:
从该传感器中的每个传感器接收位置信息;并且
基于该位置信息确定该电网事件是本地事件还是分布式事件。
18.如权利要求15所述的方法,其中,基于该位置信息确定该电网事件是本地事件还是分布式事件包括:
对处于第一位置的报告该电网事件的第一传感器数量进行计数;
对处于第二位置的报告该电网事件的第二传感器数量进行计数;
确定该第一传感器数量与该第二传感器数量之间的差值;并且
如果该差值小于或等于阈值差值,则确定该电网事件是本地事件,并且如果该差值大于该阈值差值,则确定该电网事件是分布式事件。
19.如权利要求12所述的方法,包括通过确定至少第一传感器已经报告了该电网的所测量的电参数的减小来确定该电网事件已经发生。
20.如权利要求19所述的方法,其中,确定至少第一传感器已经报告了所测量的电参数的减小包括确定在至少阈值时间段内该第一传感器已经报告了所测量的电参数的减小。
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US13/729,801 US9368968B2 (en) | 2012-12-28 | 2012-12-28 | Responding to local grid events and distributed grid events |
US13/729,801 | 2012-12-28 | ||
PCT/US2013/078069 WO2014106095A1 (en) | 2012-12-28 | 2013-12-27 | Responding to local grid events and distributed grid events |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104981976A true CN104981976A (zh) | 2015-10-14 |
Family
ID=51016348
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201380070420.0A Pending CN104981976A (zh) | 2012-12-28 | 2013-12-27 | 对本地电网事件和分布式电网事件的响应 |
Country Status (9)
Country | Link |
---|---|
US (1) | US9368968B2 (zh) |
EP (1) | EP2939342A4 (zh) |
JP (1) | JP2016504008A (zh) |
KR (1) | KR20150107761A (zh) |
CN (1) | CN104981976A (zh) |
AU (1) | AU2013370280A1 (zh) |
CA (1) | CA2901748A1 (zh) |
SG (1) | SG11201505125RA (zh) |
WO (1) | WO2014106095A1 (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106896710A (zh) * | 2017-04-07 | 2017-06-27 | 成都府河电力自动化成套设备有限责任公司 | 现场可配置的时间同步测试系统及实现方法 |
Families Citing this family (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102011055231A1 (de) * | 2011-11-10 | 2013-05-16 | Evonik Industries Ag | Verfahren zur Bereitstellung von Regelleistung |
JP6156493B2 (ja) * | 2013-05-30 | 2017-07-05 | 東芝三菱電機産業システム株式会社 | 電力管理装置 |
US20150142197A1 (en) * | 2013-11-19 | 2015-05-21 | Intelligent Power & Energy Research Corporation (Iperc) | Automated identification of components connected in a power grid |
KR101398400B1 (ko) * | 2014-03-06 | 2014-05-27 | 전북대학교산학협력단 | 시변 드룹 기반 풍력발전기의 관성 제어 방법 |
US9843189B2 (en) * | 2014-05-19 | 2017-12-12 | The University Of North Carolina At Charlotte | Grid tied system controller including logic coupled to a photovoltaic station and an energy storage system |
US10879695B2 (en) | 2014-07-04 | 2020-12-29 | Apparent Labs, LLC | Grid network gateway aggregation |
US20160087441A1 (en) | 2014-07-04 | 2016-03-24 | Stefan Matan | Virtual power grid |
US11063431B2 (en) | 2014-07-04 | 2021-07-13 | Apparent Labs Llc | Hierarchical and distributed power grid control |
US9941700B2 (en) * | 2014-12-30 | 2018-04-10 | Eaton Intelligent Power Limited | Utility scale renewable energy system controls for ramp-rate, voltage, and frequency management |
US10516270B2 (en) | 2016-01-06 | 2019-12-24 | Enphase Energy, Inc. | Method and apparatus for coordination of generators in droop controlled microgrids using hysteresis |
DE102017202209A1 (de) | 2017-02-13 | 2018-08-16 | Siemens Aktiengesellschaft | Verfahren und Vorrichtung zur Stabilisierung einer Frequenz in einem Wechselspannungsnetz |
CA3147955A1 (en) * | 2017-02-15 | 2018-08-23 | Systemex Energies Inc. | Power control device |
WO2019199806A1 (en) * | 2018-04-14 | 2019-10-17 | Merit Si, Llc | Method and system for controlling a renewable energy plant |
CN108964059B (zh) * | 2018-06-29 | 2021-10-29 | 中国电力科学研究院有限公司 | 一种互联电网有功备用共享容量的计算方法及系统 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20060195229A1 (en) * | 2002-04-01 | 2006-08-31 | Programmable Control Services, Inc. | Electrical power distribution control systems and processes |
US20080167756A1 (en) * | 2007-01-03 | 2008-07-10 | Gridpoint, Inc. | Utility console for controlling energy resources |
WO2011022390A2 (en) * | 2009-08-17 | 2011-02-24 | Premium Power Corporation | Energy storage systems and associated methods |
US20110074215A1 (en) * | 2009-09-28 | 2011-03-31 | A123 Systems, Inc. | Energy storage based countermeasure for a delayed voltage recovery |
Family Cites Families (70)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5274571A (en) | 1991-05-20 | 1993-12-28 | The Fleming Group | Energy storage scheduling system |
US5369353A (en) | 1992-12-08 | 1994-11-29 | Kenetech Windpower, Inc. | Controlled electrical energy storage apparatus for utility grids |
WO1995020836A1 (en) | 1994-01-26 | 1995-08-03 | Onan Corporation | Generator power system and method |
US5633573A (en) | 1994-11-10 | 1997-05-27 | Duracell, Inc. | Battery pack having a processor controlled battery operating system |
JP3352662B2 (ja) | 2000-02-03 | 2002-12-03 | 関西電力株式会社 | 二次電池システムを用いた電力系統安定化装置および電力系統安定化方法 |
JP2001327083A (ja) | 2000-05-18 | 2001-11-22 | Ngk Insulators Ltd | 高温二次電池による電力貯蔵及び補償システム |
US6522031B2 (en) | 2000-10-10 | 2003-02-18 | American Electric Power Company, Inc. | Power load-leveling system and packet electrical storage |
US6580977B2 (en) | 2001-01-16 | 2003-06-17 | Ford Global Technologies, Llc | High efficiency fuel cell and battery for a hybrid powertrain |
JP4019734B2 (ja) | 2001-03-28 | 2007-12-12 | 株式会社ジーエス・ユアサコーポレーション | 二次電池の運用方法及び二次電池装置 |
US6858953B2 (en) | 2002-12-20 | 2005-02-22 | Hawaiian Electric Company, Inc. | Power control interface between a wind farm and a power transmission system |
US20040207266A1 (en) | 2003-04-16 | 2004-10-21 | Abel Stephen G. | Standby electrical power generation and storage system and method |
US7353083B2 (en) | 2004-01-15 | 2008-04-01 | Vrb Power Systems Inc. | Vanadium redox battery energy storage and power generation system incorporating and optimizing diesel engine generators |
US8277964B2 (en) | 2004-01-15 | 2012-10-02 | Jd Holding Inc. | System and method for optimizing efficiency and power output from a vanadium redox battery energy storage system |
US7265456B2 (en) | 2004-01-15 | 2007-09-04 | Vrb Bower Systems Inc. | Power generation system incorporating a vanadium redox battery and a direct current wind turbine generator |
US7298059B2 (en) | 2004-12-17 | 2007-11-20 | General Electric Company | System and method for operating a wind farm under high wind speed conditions |
US7679215B2 (en) | 2004-12-17 | 2010-03-16 | General Electric Company | Wind farm power ramp rate control system and method |
US7227275B2 (en) | 2005-02-01 | 2007-06-05 | Vrb Power Systems Inc. | Method for retrofitting wind turbine farms |
US7613548B2 (en) | 2006-01-26 | 2009-11-03 | General Electric Company | Systems and methods for controlling a ramp rate of a wind farm |
US7184903B1 (en) | 2006-03-16 | 2007-02-27 | Vrb Power Systems Inc. | System and method for a self-healing grid using demand side management techniques and energy storage |
WO2008009025A2 (en) | 2006-07-14 | 2008-01-17 | The Board Of Trustees Of The University Of Illinois | Methods and apparatus for providing an extremely fast response in swithcing power converters |
US7609158B2 (en) | 2006-10-26 | 2009-10-27 | Cooper Technologies Company | Electrical power system control communications network |
US8067932B2 (en) * | 2006-11-06 | 2011-11-29 | Gamesa Innovation & Technology, S.L. | Advanced real-time grid monitoring system and method |
JP5132158B2 (ja) | 2007-01-29 | 2013-01-30 | パナソニック株式会社 | 電源システム、電源システムの電力供給制御方法及びその電力供給制御プログラム |
JP4804375B2 (ja) | 2007-01-30 | 2011-11-02 | 三洋電機株式会社 | 系統連系装置及び系統連系システム |
JP4949902B2 (ja) | 2007-03-16 | 2012-06-13 | 日本碍子株式会社 | 二次電池の電力制御方法 |
KR20100049064A (ko) * | 2007-07-12 | 2010-05-11 | 엠엘에스 일렉트로시스템 엘엘씨 | 풍력 터빈 피치 컨트롤 시스템용 전력망 손실 라이드 스루를 하는 방법 및 장치 |
US7826908B2 (en) | 2007-11-02 | 2010-11-02 | Emerson Process Management Power & Water Solutions, Inc. | Variable rate feedforward control based on set point rate of change |
US7965195B2 (en) | 2008-01-20 | 2011-06-21 | Current Technologies, Llc | System, device and method for providing power outage and restoration notification |
US8237301B2 (en) | 2008-01-31 | 2012-08-07 | General Electric Company | Power generation stabilization control systems and methods |
US8373312B2 (en) | 2008-01-31 | 2013-02-12 | General Electric Company | Solar power generation stabilization system and method |
US7941246B2 (en) | 2008-02-29 | 2011-05-10 | General Electric Company | Automatic generation control augmentation for wind plant integration |
US8116915B2 (en) | 2008-03-03 | 2012-02-14 | University Of Delaware | Methods and apparatus using hierarchical priority and control algorithms for grid-integrated vehicles |
US7952232B2 (en) | 2008-03-13 | 2011-05-31 | General Electric Company | Wind turbine energy storage and frequency control |
BRPI0911954B1 (pt) | 2008-05-09 | 2023-12-19 | Accenture Global Services Gmbh | Estrutura de integração, método para comunicação de dados operacionais e de evento, sistema e método de gerenciamento de dados para uma rede de energia e subestação em rede de energia |
US8901411B2 (en) | 2008-08-27 | 2014-12-02 | General Electric Company | System and method for controlling ramp rate of solar photovoltaic system |
US7839027B2 (en) * | 2008-10-09 | 2010-11-23 | The Aes Corporation | Frequency responsive charge sustaining control of electricity storage systems for ancillary services on an electrical power grid |
US20120059527A1 (en) | 2008-11-05 | 2012-03-08 | GreenSmith Energy Management Systems, L.L.C. | Distributed Energy Storage System, and Applications Thereof |
US8008808B2 (en) | 2009-01-16 | 2011-08-30 | Zbb Energy Corporation | Method and apparatus for controlling a hybrid power system |
US8222765B2 (en) | 2009-02-13 | 2012-07-17 | First Solar, Inc. | Photovoltaic power plant output |
US8301311B2 (en) | 2009-07-06 | 2012-10-30 | Siemens Aktiengesellschaft | Frequency-responsive wind turbine output control |
EP2293406B1 (en) | 2009-09-07 | 2015-08-05 | ABB Research Ltd. | Energy storage systems |
US20110082598A1 (en) | 2009-10-02 | 2011-04-07 | Tod Boretto | Electrical Power Time Shifting |
US7908036B2 (en) | 2009-10-20 | 2011-03-15 | General Electric Company | Power production control system and method |
US7890217B2 (en) | 2009-10-26 | 2011-02-15 | General Electric Company | Integrated real-time power and solar farm control system |
US9466984B2 (en) | 2009-10-26 | 2016-10-11 | General Electric Company | Power ramp rate control for renewable variable power generation systems |
US8471406B2 (en) | 2009-11-02 | 2013-06-25 | General Electric Company | Controllable energy utilization system and associated method |
ES2613869T3 (es) * | 2010-01-26 | 2017-05-26 | Vestas Wind Systems A/S | Método para la emulación de una máquina síncrona |
US8338987B2 (en) | 2010-02-26 | 2012-12-25 | General Electric Company | Power generation frequency control |
US8914158B2 (en) | 2010-03-11 | 2014-12-16 | Aes Corporation, The | Regulation of contribution of secondary energy sources to power grid |
US8471520B2 (en) | 2010-05-04 | 2013-06-25 | Xtreme Power Inc. | Managing renewable power generation |
US8359125B2 (en) * | 2010-06-17 | 2013-01-22 | Sharp Laboratories Of America, Inc. | Energy management system to reduce the loss of excess energy generation |
US8504214B2 (en) * | 2010-06-18 | 2013-08-06 | General Electric Company | Self-healing power grid and method thereof |
US20120056588A1 (en) | 2010-09-06 | 2012-03-08 | Eric James Cai | Use of Battery Energy for Power Grid Optimization and Electric Vehicle Charging |
CA2730658A1 (en) | 2010-10-29 | 2012-04-29 | Mitsubishi Heavy Industries, Ltd. | Wind-turbine-generator control system, wind, farm, and wind-turbine-generator control method |
US8532834B2 (en) | 2010-10-29 | 2013-09-10 | Hatch Ltd. | Method for integrating controls for captive power generation facilities with controls for metallurgical facilities |
US8400112B2 (en) | 2010-11-10 | 2013-03-19 | Ford Global Technologies, Llc | Method for managing power limits for a battery |
GB201019061D0 (en) | 2010-11-11 | 2010-12-29 | The Technology Partnership Plc | System and method for controlling an electricity supply |
US20120123604A1 (en) | 2010-11-12 | 2012-05-17 | Nathan Bowman Littrell | Systems, methods, and apparatus for demand response of battery-powered devices |
US8335547B2 (en) | 2010-12-16 | 2012-12-18 | General Motors Llc | System and method for providing discharge authorization to a battery-powered vehicle via a telematics system |
US8344550B2 (en) | 2010-12-21 | 2013-01-01 | General Electric Company | Power conversion control with energy storage |
US8635036B2 (en) * | 2011-01-04 | 2014-01-21 | General Electric Company | Systems, methods, and apparatus for providing energy management utilizing a power meter |
US8452461B2 (en) | 2011-05-10 | 2013-05-28 | First Solar, Inc | Control system for photovoltaic power plant |
US20120316688A1 (en) * | 2011-06-08 | 2012-12-13 | Alstom Grid | Coordinating energy management systems and intelligent electrical distribution grid control systems |
US20130064178A1 (en) * | 2011-09-13 | 2013-03-14 | Adishesha CS | System For Monitoring Electrical Power Distribution Lines In A Power Grid Using A Wireless Sensor Network |
ES2448794T3 (es) | 2011-09-20 | 2014-03-17 | Siemens Aktiengesellschaft | Método para hacer funcionar una granja eólica, controlador de granja eólica y granja eólica |
EP2591944A1 (en) | 2011-11-10 | 2013-05-15 | Alcatel Lucent | A method, a system, a computer program for discharging an energy storage of a vehicle in particular and electrical battery of an electric vehicle, having a predetermined discharge limit threshold, in particular below a maximum capacity of said energy storage |
CN102412594B (zh) * | 2011-11-25 | 2013-11-27 | 北京金风科创风电设备有限公司 | 微网系统的控制方法 |
JP5563008B2 (ja) | 2012-03-29 | 2014-07-30 | 株式会社東芝 | 充放電制御装置、充放電監視装置、充放電制御システム及び充放電制御プログラム |
US10756543B2 (en) * | 2012-09-13 | 2020-08-25 | Stem, Inc. | Method and apparatus for stabalizing power on an electrical grid using networked distributed energy storage systems |
US9634508B2 (en) * | 2012-09-13 | 2017-04-25 | Stem, Inc. | Method for balancing frequency instability on an electric grid using networked distributed energy storage systems |
-
2012
- 2012-12-28 US US13/729,801 patent/US9368968B2/en not_active Expired - Fee Related
-
2013
- 2013-12-27 CN CN201380070420.0A patent/CN104981976A/zh active Pending
- 2013-12-27 AU AU2013370280A patent/AU2013370280A1/en not_active Abandoned
- 2013-12-27 WO PCT/US2013/078069 patent/WO2014106095A1/en active Application Filing
- 2013-12-27 KR KR1020157020126A patent/KR20150107761A/ko not_active Application Discontinuation
- 2013-12-27 CA CA2901748A patent/CA2901748A1/en not_active Abandoned
- 2013-12-27 EP EP13868190.3A patent/EP2939342A4/en not_active Withdrawn
- 2013-12-27 SG SG11201505125RA patent/SG11201505125RA/en unknown
- 2013-12-27 JP JP2015550814A patent/JP2016504008A/ja active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20060195229A1 (en) * | 2002-04-01 | 2006-08-31 | Programmable Control Services, Inc. | Electrical power distribution control systems and processes |
US20080167756A1 (en) * | 2007-01-03 | 2008-07-10 | Gridpoint, Inc. | Utility console for controlling energy resources |
WO2011022390A2 (en) * | 2009-08-17 | 2011-02-24 | Premium Power Corporation | Energy storage systems and associated methods |
US20110074215A1 (en) * | 2009-09-28 | 2011-03-31 | A123 Systems, Inc. | Energy storage based countermeasure for a delayed voltage recovery |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106896710A (zh) * | 2017-04-07 | 2017-06-27 | 成都府河电力自动化成套设备有限责任公司 | 现场可配置的时间同步测试系统及实现方法 |
Also Published As
Publication number | Publication date |
---|---|
EP2939342A1 (en) | 2015-11-04 |
AU2013370280A1 (en) | 2015-07-16 |
SG11201505125RA (en) | 2015-07-30 |
EP2939342A4 (en) | 2016-06-08 |
WO2014106095A1 (en) | 2014-07-03 |
CA2901748A1 (en) | 2014-07-03 |
JP2016504008A (ja) | 2016-02-08 |
KR20150107761A (ko) | 2015-09-23 |
US20140183961A1 (en) | 2014-07-03 |
US9368968B2 (en) | 2016-06-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104981976A (zh) | 对本地电网事件和分布式电网事件的响应 | |
Sahoo et al. | Cyber security in control of grid-tied power electronic converters—Challenges and vulnerabilities | |
Cheng et al. | To centralize or to distribute: That is the question: A comparison of advanced microgrid management systems | |
Macana et al. | A survey on cyber physical energy systems and their applications on smart grids | |
Wu et al. | Applications of wireless sensor networks for area coverage in microgrids | |
CN105024397A (zh) | 海上风电经vsc-mtdc输电并网系统的动态模拟系统 | |
JP5962770B2 (ja) | 電力系統制御システム及び電力系統制御方法 | |
Xiang et al. | IoT and edge computing based direct load control for fast adaptive frequency regulation | |
US9461473B2 (en) | Method and apparatus for damping oscillations in a power system | |
CN111628986A (zh) | 交互数据处理方法、系统、装置、计算机设备和存储介质 | |
CN110011298B (zh) | 一种构建自治型可重构微网群系统的运行控制策略 | |
CN104158489A (zh) | 光伏电站的监测方法和电站监测系统 | |
Muzafarov et al. | Model for building wireless sensor networks | |
US9507364B2 (en) | Methods for reducing solar inverter output volatility, and related nodes and solar inverters | |
CN113517701A (zh) | 计及信息设备故障的分布式电压控制系统风险评估方法 | |
Selseleh Jonban et al. | Intelligent fault tolerant energy management system with layered architecture for a photovoltaic power plant | |
Arboleya et al. | Distributed resources coordination inside nearly-zero energy buildings providing grid voltage support from a symmetrical component perspective | |
CN103178519B (zh) | 基于scada数据实时定位电力系统功率振荡扰动源的方法 | |
Arunagirinathan et al. | Wide-area situational awareness based power system stabilizer tuning with utility scale pv integration | |
CN105449697A (zh) | 一种基于转速信号的发电机阻尼控制方法 | |
Li et al. | Supply and demand oriented energy management in the internet of things | |
Hossain et al. | A distributed-mpc framework for voltage control under discrete time-wise variable generation/load | |
CN105470999A (zh) | 一种基于分布式有限时间控制器的微电网功率分配方法 | |
CN111401577A (zh) | 设备管理方法、装置、设备及存储介质 | |
CN117175656B (zh) | 一种构网型储能提升新型电力系统支撑能力评估方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20151014 |