CN104976435A - 一种变电楼外墙穿墙套管板的节点防水结构 - Google Patents

一种变电楼外墙穿墙套管板的节点防水结构 Download PDF

Info

Publication number
CN104976435A
CN104976435A CN201510331689.0A CN201510331689A CN104976435A CN 104976435 A CN104976435 A CN 104976435A CN 201510331689 A CN201510331689 A CN 201510331689A CN 104976435 A CN104976435 A CN 104976435A
Authority
CN
China
Prior art keywords
wall
angle steel
outside
waterproof structure
outdoor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510331689.0A
Other languages
English (en)
Inventor
郑志荣
严佳
龚建备
王春芸
钱志平
毛晓梦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Quzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Quzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Quzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510331689.0A priority Critical patent/CN104976435A/zh
Publication of CN104976435A publication Critical patent/CN104976435A/zh
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L5/00Devices for use where pipes, cables or protective tubing pass through walls or partitions
    • F16L5/02Sealing
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls

Abstract

一种变电楼外墙穿墙套管板的节点防水结构,它包括在墙上开设有用于穿墙套管穿过并固定的墙洞,在墙洞内周边预埋有角钢并形成角钢框,所述的角钢框四周现浇有朝向室外侧的混凝土L型防水止口,另在该室外侧洞口外侧墙面上设置有60mm的外凸挑沿、并在挑沿与外侧墙面之间形成有使外墙面的水流向两侧的集水槽;所述的预埋角钢在L型防水止口处,角钢与锚筋焊接后直接现浇于四周钢筋混凝土框内;所述墙洞位于室内侧在粉刷时形成的向外坡度;它具有结构简单,使用安装方便,杜绝雨水侵入内墙,避免给电网运行带来安全隐患,减少后续维修成本等特点。

Description

一种变电楼外墙穿墙套管板的节点防水结构
技术领域
本发明涉及的是一种变电楼外墙穿墙套管板的节点防水结构,属于变电所的设计技术领域。
背景技术
现有技术中,如图1所示,穿墙套管的布置是:在变电楼的外墙11上开设有用于套管穿入的墙洞口12,在洞口12内周边预埋有扁铁13和与粉刷面平锚筋14,另在洞口12的内周边用角钢15与所述扁铁13焊接,而穿墙套管在穿过墙洞口12并固定在洞口中,一侧端外露于墙的室外侧16,另一侧端外露于墙的室内侧17;上述穿墙套管的布置,使得变电楼的穿墙套管板与外墙连接处普遍存在渗水现象,这已是目前电力工程中的一个质量通病,给电网运行带来安全隐患,增加后续的维修成本。
发明内容
本发明的目的在于克服现有技术存在的不足,而提供一种结构简单,使用安装方便,杜绝雨水侵入内墙,避免给电网运行带来安全隐患,减少后续维修成本的变电楼外墙穿墙套管板的节点防水结构。
本发明的目的是通过如下技术方案来完成的,一种变电楼外墙穿墙套管板的节点防水结构,它包括在墙上开设有用于穿墙套管穿过并固定的墙洞,在墙洞内周边预埋有角钢并形成角钢框,所述的角钢框四周现浇有朝向室外侧的混凝土L型防水止口,另在该室外侧洞口外侧墙面上设置有外凸的挑沿、并在挑沿与外侧墙面之间形成有使外墙面的水流向两侧的集水槽。
所述的预埋角钢在L型防水止口处,角钢与锚筋焊接后直接现浇于四周钢筋混凝土框内;所述墙洞的位于室内侧有在粉刷时形成的向外坡度。
所述的该室外侧洞口外侧墙面上设置有外凸的挑沿、并在挑沿与外侧墙面之间形成有使外墙面的水流向两侧的集水槽。
本发明属于对现有技术的一种改良,它具有结构简单,使用安装方便,杜绝雨水侵入内墙,避免给电网运行带来安全隐患,减少后续维修成本等特点。
附图说明
图1是现有技术的穿墙套管示意图。
图2是本发明所述穿墙套管防水布置结构示意图。
具体实施方式
下面将结合附图对本发明作详细的介绍:图2所示,本发明所述的一种变电楼外墙穿墙套管板的节点防水结构,它包括在墙21上开设有用于穿墙套管穿过并固定的墙洞22,在墙洞22内周边预埋有角钢23并形成角钢框,所述的角钢框四周现浇有朝向室外侧的混凝土L型防水止口24,另在该室外侧25洞口外侧墙面上设置有外凸的挑沿26、并在挑沿26与外侧墙面25之间形成有使外墙面的水流向两侧的集水槽29,它能够较好地杜绝雨水侵入内墙,达到防水的目的。
图中所示,所述的预埋角钢23在L型防水止口24处,角钢23与锚筋30焊接后直接现浇于带L型止水口的钢筋混凝土框31内,所述墙洞22的位于室外侧在粉刷时形成的向外坡度32,并在挑沿处设置滴水线槽28。
本发明主要通过对现有技术的分析,发现了防水的薄弱环节,加以改进,不增加相关投资费用。

Claims (3)

1.一种变电楼外墙穿墙套管板的节点防水结构,它包括在墙上开设有用于穿墙套管穿过并固定的墙洞,在墙洞内周边预埋有角钢并形成角钢框,其特征在于所述的角钢框四周现浇有朝向室外侧的混凝土L型防水止口;另在该室外侧洞口外侧墙面上设置有外凸的挑沿、并在挑沿与外侧墙面之间形成有使外墙面的水流向两侧的集水槽。
2.根据权利要求1所述的变电楼外墙穿墙套管板的节点防水结构,其特征在于所述的预埋角钢在L型防水止口处,角钢与锚筋焊接后直接现浇于四周钢筋混凝土框内;所述墙洞室外侧有在粉刷时形成的向外坡度。
3.根据权利要求1或2所述的变电楼外墙穿墙套管板的节点防水结构,该室外侧洞口外侧墙面上设置有外凸的挑沿、并在挑沿与外侧墙面之间形成有使外墙面的水流向两侧的集水槽。
CN201510331689.0A 2015-06-16 2015-06-16 一种变电楼外墙穿墙套管板的节点防水结构 Pending CN104976435A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510331689.0A CN104976435A (zh) 2015-06-16 2015-06-16 一种变电楼外墙穿墙套管板的节点防水结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510331689.0A CN104976435A (zh) 2015-06-16 2015-06-16 一种变电楼外墙穿墙套管板的节点防水结构

Publications (1)

Publication Number Publication Date
CN104976435A true CN104976435A (zh) 2015-10-14

Family

ID=54273225

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510331689.0A Pending CN104976435A (zh) 2015-06-16 2015-06-16 一种变电楼外墙穿墙套管板的节点防水结构

Country Status (1)

Country Link
CN (1) CN104976435A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109654304A (zh) * 2017-10-10 2019-04-19 沈阳铝镁设计研究院有限公司 一种活动管道穿防火墙洞口封堵构造
CN109736460A (zh) * 2018-12-18 2019-05-10 浙江绿筑集成科技有限公司 一种预制外墙外保温构造

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11315961A (ja) * 1998-05-07 1999-11-16 Aron Kasei Co Ltd ケーブル用管路及びその構築法
CN202302338U (zh) * 2011-09-29 2012-07-04 沈阳铝镁设计研究院有限公司 电解车间金属管道穿墙防水构造
CN203099102U (zh) * 2013-03-08 2013-07-31 夏克升 固定式穿墙管防水构造
CN103604002A (zh) * 2013-11-29 2014-02-26 天津住宅集团建设工程总承包有限公司 一种穿墙管道施工结构
CN204357270U (zh) * 2014-12-18 2015-05-27 上海建工二建集团有限公司 防渗漏窗台板
CN204986036U (zh) * 2015-06-16 2016-01-20 国家电网公司 变电楼外墙穿墙套管板的节点防水结构

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11315961A (ja) * 1998-05-07 1999-11-16 Aron Kasei Co Ltd ケーブル用管路及びその構築法
CN202302338U (zh) * 2011-09-29 2012-07-04 沈阳铝镁设计研究院有限公司 电解车间金属管道穿墙防水构造
CN203099102U (zh) * 2013-03-08 2013-07-31 夏克升 固定式穿墙管防水构造
CN103604002A (zh) * 2013-11-29 2014-02-26 天津住宅集团建设工程总承包有限公司 一种穿墙管道施工结构
CN204357270U (zh) * 2014-12-18 2015-05-27 上海建工二建集团有限公司 防渗漏窗台板
CN204986036U (zh) * 2015-06-16 2016-01-20 国家电网公司 变电楼外墙穿墙套管板的节点防水结构

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109654304A (zh) * 2017-10-10 2019-04-19 沈阳铝镁设计研究院有限公司 一种活动管道穿防火墙洞口封堵构造
CN109736460A (zh) * 2018-12-18 2019-05-10 浙江绿筑集成科技有限公司 一种预制外墙外保温构造

Similar Documents

Publication Publication Date Title
CN203161245U (zh) 一种隧道防水管片连接结构
CN103147764B (zh) 一种隧道拱墙二衬定型端头模板
CN203769401U (zh) 法兰机构
CN104976435A (zh) 一种变电楼外墙穿墙套管板的节点防水结构
CN208472734U (zh) 一种用于基坑工程的钢支撑留撑接头结构
CN204059610U (zh) 矩形钢管混凝土柱与钢梁单边螺栓连接节点
CN204986036U (zh) 变电楼外墙穿墙套管板的节点防水结构
CN204844469U (zh) 预制剪力墙安装用预埋钢管孔定位装置
CN203983518U (zh) 变电站设备用接地结构
CN203795936U (zh) 一种加固后的输电线路角钢塔主材结构
CN202359665U (zh) 拉索、钢梁和钢管柱混合节点
CN207844941U (zh) 一种内套式万能塔机调节拉杆
CN204356915U (zh) 钢管柱与地下室混凝土外墙相交的自防水结构
CN204627014U (zh) 拆卸式防风棚
CN103953277B (zh) Eps门及安装方法
CN202181614U (zh) 工字钢的钢管固定装置
CN204947419U (zh) 一种新型设备接地固定抱箍
CN205956562U (zh) 带有套管的穿墙管
CN206608185U (zh) 一种具有排水功能的隧道衬砌裂损修补组合结构
CN202165696U (zh) 工字钢的电缆桥架固定架夹紧装置
CN206289987U (zh) 可重复使用的钢管柱安装装置
CN206267199U (zh) 混凝土剪力墙止水钢板连接装置
CN205907828U (zh) 一种止水钢板连接件
CN105220771B (zh) 一种预制清水柱湿接缝连接方法
CN211774968U (zh) 线管精准定位固定模具

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20151014