CN104937508B - Programable display - Google Patents

Programable display Download PDF

Info

Publication number
CN104937508B
CN104937508B CN201380069680.6A CN201380069680A CN104937508B CN 104937508 B CN104937508 B CN 104937508B CN 201380069680 A CN201380069680 A CN 201380069680A CN 104937508 B CN104937508 B CN 104937508B
Authority
CN
China
Prior art keywords
access
mentioned
data
access target
processing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201380069680.6A
Other languages
Chinese (zh)
Other versions
CN104937508A (en
Inventor
古山欣史
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hakko Electronics Co Ltd
Original Assignee
Hakko Electronics Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hakko Electronics Co Ltd filed Critical Hakko Electronics Co Ltd
Publication of CN104937508A publication Critical patent/CN104937508A/en
Application granted granted Critical
Publication of CN104937508B publication Critical patent/CN104937508B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F3/00Input arrangements for transferring data to be processed into a form capable of being handled by the computer; Output arrangements for transferring data from processing unit to output unit, e.g. interface arrangements
    • G06F3/14Digital output to display device ; Cooperation and interconnection of the display device with other functional units
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/04Programme control other than numerical control, i.e. in sequence controllers or logic controllers
    • G05B19/05Programmable logic controllers, e.g. simulating logic interconnections of signals according to ladder diagrams or function charts
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/10File systems; File servers
    • G06F16/11File system administration, e.g. details of archiving or snapshots
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/23Updating
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F3/00Input arrangements for transferring data to be processed into a form capable of being handled by the computer; Output arrangements for transferring data from processing unit to output unit, e.g. interface arrangements
    • G06F3/01Input arrangements or combined input and output arrangements for interaction between user and computer
    • G06F3/048Interaction techniques based on graphical user interfaces [GUI]
    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09GARRANGEMENTS OR CIRCUITS FOR CONTROL OF INDICATING DEVICES USING STATIC MEANS TO PRESENT VARIABLE INFORMATION
    • G09G5/00Control arrangements or circuits for visual indicators common to cathode-ray tube indicators and other visual indicators
    • G09G5/36Control arrangements or circuits for visual indicators common to cathode-ray tube indicators and other visual indicators characterised by the display of a graphic pattern, e.g. using an all-points-addressable [APA] memory
    • GPHYSICS
    • G09EDUCATION; CRYPTOGRAPHY; DISPLAY; ADVERTISING; SEALS
    • G09GARRANGEMENTS OR CIRCUITS FOR CONTROL OF INDICATING DEVICES USING STATIC MEANS TO PRESENT VARIABLE INFORMATION
    • G09G2360/00Aspects of the architecture of display systems
    • G09G2360/12Frame memory handling
    • G09G2360/125Frame memory handling using unified memory architecture [UMA]

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Human Computer Interaction (AREA)
  • Data Mining & Analysis (AREA)
  • Databases & Information Systems (AREA)
  • Automation & Control Theory (AREA)
  • Computer Hardware Design (AREA)
  • Programmable Controllers (AREA)
  • Information Transfer Between Computers (AREA)

Abstract

The programable display of the present invention is characterised by, in common storage (55), the project of save project processing unit (62) etc. shows associated access target of the logical process of associated access target etc. and logical process portion (64) etc. etc..Classification judges that processing unit (70) be stored in the upgrading judgement of the associated each access target of in common storage (55), logical process.Optimum instruction generating unit (69) does not show associated access target merely with project, also using the access target after upgrading, generates optimal access list (54).

Description

Programable display
Technical field
The present invention relates to programable display.
Background technology
Programable display is typically connected with the various connection equipment such as PLC main bodys, temperature regulating device, and display carries out these connections The numerical value of the status display of equipment show and lamp etc. project, or show switch for sending any instruction for user etc. The image of project.In addition, project is also referred to as screen component etc..(also referred to as operate in the picture of programable display and show picture Face) in, generally show the image of multiple screen components (project).
Data for showing such operating display frame (screen) etc. (being referred to as picture data etc.) are not schemed in advance Arbitrarily generated by developer etc. in the servicing unit shown, programable display is downloaded to from servicing unit.
In above-mentioned picture data, included for above-mentioned each project:Image (image of switch or the figure of lamp of the project Picture;Or the identification id of image etc.), display location coordinate, the address (distribution of the predetermined region of external storage also described later Holder address) etc. data.Also there is the situation for also including certain program etc..
Above-mentioned projects for example correspond to the shape for being formed arbitrarily key element, carrying out this composition key element of arbitrary connection equipment respectively State is shown, or receives the instruction being turned on and off of this composition key element.For example, showing the temperature measuring value of temperature regulating device in numerical value Project in the case of, current temperature is shown with numerical value at any time.
The associated display control of above-mentioned various projects passes through for example fixed for above-mentioned projects in programable display Handle to realize as defined in performing to phase.Defined processing refers to for example, the storage facilities read in connection equipment (is assumed to be outer Portion's holder) the above-mentioned predetermined region region of address (distribution holder) storage data, the storage data based on the reading (" acquisition data ") determine simultaneously display items purpose display content etc..In addition, connection equipment updates said external holder at any time The storage data (for example updating said temperature measured value at any time in above-mentioned temperature regulating device) of predetermined region.
In addition, the data read from said external holder to be temporarily stored within to the storage facilities in programable display The predetermined region of (being assumed to be interior magazine), is determined and display items purpose display content based on the storage data.
In the case of the example, read the storage data of external storage and be stored in the processing of interior magazine, by can The defined function part (it is assumed here that being communication unit (not shown)) of programming display is for example regularly performed.Above-mentioned communication unit example Such as communicated with above-mentioned PLC main bodys, the various connection equipment of temperature regulating device, obtain the said external holder in connection equipment Defined storage area storage data, the data cover is stored in the predetermined region of above-mentioned interior magazine.Also, can The function part (being assumed to be described project processing unit) of the associated display control of above-mentioned various projects is carried out in programming display By regular visit interior magazine come item controlled display content.
Store the image of various projects in advance in above-mentioned servicing unit.This be for such as every kind of project (switch, lamp, Instrument panel lamp) previously generate the item image of various designs and be stored in the storage unit of servicing unit.
Above-mentioned item image for example for above-mentioned switch, previously generate and log in it is a variety of switch images (for example open with and Close and use;Switch opens image and switch closes image).Similarly, for lamp similarly, previously generate and log in multiple lamp Image (is for example opened to use and close and used;The closing image for opening image and lamp of lamp).
The above-mentioned item image that arbitrary project is associated is arranged on the desired position on picture by developer etc., The selection and setting of project are carried out with this.In addition, not only carrying out the setting of project, projects to setting also carry out setting above-mentioned Distribute the operation of holder address.
Figure 21, Figure 22 are the functional block diagram (1/2) of conventional programable display, (2/2).In addition, not making below especially Distinguish, labeled as " Figure 21 etc. ".
Conventional programable display 200 has CPU211, RAM213, graphics controller 215, display 219 etc., enters one Step ground has non-volatile memory device (not shown) (flash memory etc.).Stored picture data 222 and regulation in the storage device Application program etc..
CPU211 for example by perform it is above-mentioned as defined in application program, realized in Figure 21 in dotted line shown in it is each Plant processing function portion.I.e., it is illustrated that project generating unit 261, project processing unit 262, communication processing section 263 (263-1,263-2 Deng), logical process portion 264, project processing plan portion 265, common storage generation processing unit 266, logical process planning department 267th, the processing function in the various processing function portions such as logical order generating unit 268, optimum instruction generating unit 269 is implemented.
Project generating unit 261 is based on above-mentioned picture data 222 etc., generates bulleted list 251.This is, such as with duplication A part for Form generation picture data 222.
Corresponding to the bulleted list 251 that common storage generation processing unit 266 will be generated as above-mentioned project generating unit 261 Data storage is in common storage 255.In other words, the storage data to common storage 255 are updated.
Projects are corresponding above-mentioned " acquisition data " in save project list 251 in common storage 255." it should obtain The storage content of data " is updated by communication processing section 263.
Each communication processing section 263 is communicated via communication line 6 with each connection equipment 4, obtains the external storage The storage data of predetermined region (distribution storage area).Also, " acquisition data " covering will be somebody's turn to do and be stored in common storage 255 On corresponding region.
Communication processing section 263 is based on optimum instruction list 254 (254-1,254-2), carries out obtaining above-mentioned distribution storage area The processing of the storage data in domain.
Optimum instruction list 254 is that optimum instruction generating unit 269 is generated based on common storage 255.This is to store Access mesh is generated in the way of merging access in the access target (distribution storage area) of each project of common storage 255 Mark.
Project processing unit 262 for example regularly (cyclically) is transferred out using project processing plan portion 265, based on above-mentioned common With the storage data of holder 255, the processing being associated to renewal of each its display content of the project implementation etc..
More than, mainly show determination and renewal processing (refresh process) phase of the display content of projects of operation screen The existing processing function portion of association and data etc..
Here, in programable display, the refresh process of only not above-mentioned circulation is also arbitrarily generated using user Logical program (such as utilizing certain program if~then~else language) implement logical process situation.In the logic In processing, producing needs irregularly (sudden) the arbitrary access target of acquisition (the arbitrary outside in arbitrary connection equipment The arbitrary storage area of holder) storage data situation.
The associated processing function portion of above-mentioned logical process is above-mentioned logical process portion 264, logical process planning department 267 and logical order generating unit 268 etc..
The generation logical order of logical order generating unit 268 list 252.Above-mentioned is for example stored in logical order list 252 Processing corresponding to the storage data of the access target of meaning and the access target performs condition (branch condition etc.).
Logical process portion 264 carries out logical order list based on the planning management using logical process planning department 267 252 corresponding data acquisition process etc..For example, the above-mentioned access target for being stored in logical order list 252 is stored in shared Holder 255, and the instruction comprising the access target etc. is stored in instruction list (FIFO) 253 (253-1,253-2).
Here, in most cases, logical process portion 264 keeps holding state until data acquisition.For example, obtaining If In the case of the associated data of sentence, do not know if data are not obtained and perform which in then and else.
In the case where instruction list 253 stores more than one instruction, communication processing section 263 for example extracts beginning Instruction, the above-mentioned access target included to the instruction also conducts interviews processing.Also, by the acquisition data from access target Common storage 255 is stored in, and notifies data acquisition to complete to logical process portion 264.
The logical process portion 264 for receiving the notice obtains the storage data of common storage 255, restarts above-mentioned standby The logical process of state.
In addition, for example, the prior art described in patent document 1,2 is known.
The invention of patent document 1 has following each operations.
Holder digital independent process, the holder digital independent process periodically reads the number of the holder of external equipment According to;
Data length adjustment process is read, the data of above-mentioned holder are being read using the holder digital independent process When, the reading data length adjusts process to instructing the holder data length read to be adjusted using above-mentioned reading, so that Instruction, which is read, using one terminates the processing of holder digital independent within the preassigned time;
In addition, the invention of patent document 2 is related to the communication instruction optimization method in electronic equipment, it is to read external connection During the storage data of equipment, storage facilities, the holder of an above-mentioned data storage of storage are only set respectively in instruction is read The size of address and the storage data read from the holder address performs reading.
Also, there is identical data component class process, the very first time to calculate process, the second time for the invention of patent document 2 Calculate process, call duration time and compare process and storage digital independent process.
Identical data component class process is classified for each external connection apparatus and each storage facilities to storage data, It is classified in the holder data group of same category.
The very first time calculates process to the above-mentioned holder data group for the above-mentioned same category being classified, and links the holder Desired multiple storage data of data group, the link data of situation about being read out to performing once above-mentioned reading instruction Reading call duration time calculated.This is the communication speed according to the said external connection equipment with the holder data group Degree, the reception time for sending time and the corresponding above-mentioned desired storage data of reading instruction of above-mentioned reading instruction Come what is calculated.
Second time calculated process to the above-mentioned holder data group for the above-mentioned same category being classified, and the storage is not linked Desired multiple storage data of device data group, the non-link of situation about being read out to performing repeatedly above-mentioned reading instruction The reading call duration time of data is calculated.This is the communication that equipment is connected according to the said external with the holder data group Speed, during the reception for sending time and the corresponding above-mentioned desired storage data of reading instruction of above-mentioned reading instruction Between calculate.
When call duration time compares process to above-mentioned link digital independent call duration time and the communication of above-mentioned non-link digital independent Between be compared.
Holder digital independent process is in the comparison of the call duration time, in above-mentioned link digital independent call duration time than upper When stating non-link digital independent call duration time faster, link above-mentioned desired storage data, perform once above-mentioned reading instruction It is read out.In addition, above-mentioned non-link digital independent call duration time than above-mentioned link digital independent call duration time faster when, do not connect Tie and state desired storage data and perform repeatedly above-mentioned reading instruction and be read out.
In above-mentioned patent document 1,2, disclose for example due to having the address of two access targets therefore needing to lead to twice Letter, by linking two addresses with the completion that once communicates.For example in Fig. 6 of patent document 2, disclose by linking address ' X0000 ' and address ' X0010 ', the data of address ' X0000~X0010 ' are obtained once to communicate in the lump.In addition, disclosing this Data between two addresses, are the data being rejected after being read in the lump.
Patent document 1:Japanese Patent Laid-Open 2009-54055 publications
Patent document 2:Japanese Patent Laid-Open 2009-54056 publications
The content of the invention
As described above, such as logical process portion 264 is needing to perform from any with arbitrary logical process in the past Access target (the arbitrary storage area of the arbitrary external storage in arbitrary connection equipment 4) obtain the situation of data Under, as described below.
It will be stored in for the instruction that data are obtained from above-mentioned access target after instruction list 253, until data acquisition Holding state is kept before.
Thus, according to circumstances stand-by time is elongated, treatment effeciency reduction.
In addition, communication processing section 263 in order to carry out from said external holder obtain data processing, it is necessary to via communication Circuit 6 is communicated with being connected equipment 4, generally, compared with internal processing, like this along with the processing with PERCOM peripheral communication compared with The cost time.Also, 263 pairs of communication processing section is like this with the external storage access process of communication, not only with above-mentioned Refresh process carries out cyclic access processing, the processing and adjoint above-mentioned logical process conducts interviews.Particularly, with above-mentioned logic The access process of reason is irregularly (sudden) to be occurred, and performs access process during action every time.
Therefore, (such as logical process in the case that the frequency of the external storage access process of adjoint logical process is higher In the situation of the frequent movement of portion 264 or setting), the processing load increase of communication processing section 263 becomes to expend the shape of processing time State.As a result, there is the obvious slack-off situation (bottleneck) of (refresh process and logical process) action of both sides.
It is such as above-mentioned above, it is particularly in the higher state of the frequency of the external storage access performed with logical process, There is the problem of slack-off situation of the action of refresh process or/and logical process is such.
The problem of the present invention is to provide a kind of programable display, and its program etc., to carrying out the item in display picture The external storage that the refresh process that mesh is shown is associated is accessed, and performs progress external storage access with logical process Programable display, even in logical process perform external storage access frequency be higher state, also can Make action slack-off.
The programable display of the present invention is the programable display with being arbitrarily connected equipment connection, such as with as follows Each unit.
Project information storage element, the project information storage element is to representing that the access information of each access target is stored up Deposit, projects that each access target is corresponded respectively in display picture;
First data capture unit, first data capture unit is regularly based on the access information, from the connection Data are obtained at each access target in equipment, are stored the data in interior magazine;
Logical process execution unit, while arbitrary logical process is performed, is generated along with the logical process In the case of being the access process of irregular access target for access target, the logical process execution unit judges that this is irregular Whether access target has been integrated into the access information, and the access information has been integrated into the irregular access target In the case of, obtain data corresponding with the irregular access target from the interior magazine;
Stage unit, the stage unit at intervals of set time, by access frequency be it is more than defined first threshold described in Irregular access target is adjusted to upgrade status access target;And
Irregular access target as the upgrade status access target is integrated into institute by integral unit, the integral unit State access information.
Brief description of the drawings
Fig. 1 is the brief configuration figure of the system entirety of the programable display 1 comprising this example.
Fig. 2 is the configuration example of the programable display of this example.
Fig. 3 is the figure for the software configuration for representing the system.
Fig. 4 is the processing function figure (1/2) of the programable display 1 of this example.
Fig. 5 is the processing function figure (2/2) of the programable display 1 of this example.
Fig. 6 is the flow chart (1/2) of the external storage access process of communication processing section.
Fig. 7 is the flow chart (2/2) of the external storage access process of communication processing section.
Fig. 8 is the process chart of project processing unit.
Fig. 9 is the process chart that common storage generates processing unit.
Figure 10 is the process chart (1/2) in logical process portion.
Figure 11 is the process chart (2/2) in logical process portion.
Figure 12 is the process chart (1/2) of the associated external storage access process in logical process portion.
Figure 13 is the process chart (2/2) of the associated external storage access process in logical process portion.
Figure 14 is the process chart (1/2) that classification judges processing unit.
Figure 15 is the process chart (2/2) that classification judges processing unit.
Figure 16 (a) is the data structure example of common storage, and (b) is the concrete example of cyclic access holder list.
Figure 17 (a) is one of holder information, and (b) is the data structure diagram of bulleted list.
Figure 18 is the concrete example of logical order list.
Figure 19 is the data structure example of instruction.
Figure 20 is other processing function figures of the programable display of this example.
Figure 21 is the functional block diagram (1/2) of conventional programable display.
Figure 22 is the functional block diagram (2/2) of conventional programable display.
Embodiment
Below, embodiments of the present invention are illustrated referring to the drawings.
Fig. 1 is the brief configuration figure of the system entirety of the programable display 1 comprising this example.
Programable controller system shown in Fig. 1 has various connection equipment 4 and connects various via communication line 6 Connect the programable display 1 of equipment 4.In addition, programable display 1 can also be via the connection mapping editor's dress of communication line 3 Put 5 (servicing units) and constitute.Include multiple communication interfaces 2 (COM1) in programable display 1, by connecting each communication The communication line 6 of communication line 3/ of interface 2 is connected with various connection equipment 4, mapping editing device 5.
But, mapping editing device 5 is not required to be connected with programable display and (simply show one).For example, also may be used In 1 installation screen data of programable display, mapping editing device 5 is connected to programable display 1.Thus, in mapping Picture data that editing device 5 is generated etc., programable display 1 is downloaded to from mapping editing device 5 via communication line 3.When So, it is not limited to the example.
In addition, above-mentioned picture data etc. can be also transmitted to can via mobile storage medium (not shown) (memory card etc.) Display 1 is programmed, instead of the download via above-mentioned communication line 3.In any case, it will substantially be given birth in mapping editing device 5 Into or update picture data be stored in programable display 1.Also, in programable display 1, based on the picture data Deng display aforesaid operations display picture.
Or, programable display 1 has the situation for performing above-mentioned arbitrary logical process (logical program).This method is basic On like this also execution logic processing programable display 1 in, realize the raising for the treatment of effeciency, above-mentioned ask solved with this Inscribe point (problem).
In addition, in the following description, there is the situation that editing device 5 of mapping is labeled as to servicing unit 5.
Fig. 2 is the hardware configuration example of the programable display 1 of this example.
The programable display 1 of diagram has display operating control device 10, touch panel 18, display 19 and above-mentioned Communication interface 2 etc..
Show operating control device 10 by CPU11, ROM12 (flash memory etc.), RAM13, communication controler 14, graphics controller 15th, touch panel controller 16 etc. is constituted, and these are connected with bus 17.
CPU11 is that control shows the overall central processing unit (arithmetic processor) of operating control device 10.CPU11 passes through The program (such as main body program 21 described below) for having previously been stored in ROM12 is performed, defined computing action (place is carried out Reason).Defined processing refers to, the processing for being for example cyclically updated the display content of each project of aforesaid operations display picture (above-mentioned refresh process).Therefore, the processing that conducted interviews to the corresponding said external holder of projects (obtains the distribution of projects The processing of the storage data of storage area).Also, carry out picture display control based on " acquisition data " are somebody's turn to do.In addition, these are handled As described above, it is prior art.
Further, here, suppose that the program also arbitrarily generated comprising user etc. in main body program 21 (is also referred to as logic Program).The processing (logical process) carried out by the logical program has various, has comprising the place for accessing said external holder The situation of reason.As described above, the logical process is also the content existed in the past in itself.Also, as described above, logical process Influenceed, produced such as refresh process and the problem of the side of logical process two all consuming time by above-mentioned refresh process.
In addition, operation result performed with main body program 21 etc. is for example stored in RAM13 and ROM12.
In addition, storing the picture data (picture data 22 described later) illustrated in above-mentioned background technology in ROM12.Such as It is described above, in the projects of picture data 22 such as in above-mentioned switch, lamp, with its display location coordinate and size etc. The associated data of display and above-mentioned distribution holder address (distribution storage area) etc. the associated number of storage access According to etc..In addition, in picture data 22 image (or the identification id of item image etc.) comprising projects.
In processing using the CPU11 of the grade of aforementioned body program 21, such " the distribution of each project storage is obtained comprising above-mentioned Deposit the storage data in region " processing etc..It is somebody's turn to do " acquisition data " and is for example temporarily stored within common storage 55.In addition, sharing storage Storage 55 can for above-mentioned RAM13 and ROM12 storage area a part, or other holders (not shown).
In addition, using above-mentioned CPU11 processing, the display pair such as based on above-mentioned picture data and above-mentioned acquisition data Image data deploys (description) for example on RAM13 (or video-ram (not shown)).Based on the description, graphics controller 15 exists Above-mentioned operating display frame etc. is shown on display 19.
In addition, in the past, in picture data 22, for each project comprising for example open with and closing two kinds of project figures Picture.Also, in the side of programable display 1, such as lamp extinguishes image and turns into above-mentioned display object if above-mentioned acquisition data are ' 0 ' Data, lamp is lighted image and (for example retouched as above-mentioned display object data on video-ram if above-mentioned acquisition data are ' 1 ' Paint).
Display 19 sets touch surface in an overlapping manner such as being constituted by LCDs on the LCDs Plate 18.In the past, show on the display 19 and the respective item image of multiple projects is substantially arranged on structure on assigned position Into operating display frame.
In addition, communication controler 14 is via communication interface 2, the connection with PLC main bodys (not shown) etc. or temperature regulating device etc. Equipment 4 and mapping editing device 5 are communicated (data transmit-receive etc.).
Waited by operator and the testing result of pressing operation (touch) position is carried out on touch panel 18 via touch panel Controller 16 is obtained and parsed by CPU11 etc..Enter such as above-mentioned display location coordinate or the data of size based on projects Row parsing.For example, after operator etc. touches to the display location of the image of above-mentioned switch, CPU11 etc., which is resolved to, to be opened this Put into and gone operation.
Fig. 3 represents the software architecture diagram of above-mentioned the system.
In programable display 1, the various programs of main body program 21, picture data 22, signal procedure 23 etc., data are for example It is stored in above-mentioned ROM12 (flash memory etc.).By these programs or data etc. are read out by CPU11, implemented or with reference to etc., enter Display control of above-mentioned each operating display frame of row programable display etc. etc..
The operating display frame samely, is shown, the image of the various projects of lamp, switch etc. by above-mentioned numerical value Display is constituted, and the display content of projects image is for example updated at any time in the form of reflecting above-mentioned " acquisition data ".
Substantially CPU11 is based on main body program 21 and picture data 22 is handled, and shows aforesaid operations display picture.And And, the display content of each screen component on the operating display frame (numerical value of temperature etc. is shown and lamp is lighted or extinguished) It is updated at any time based on the result of communication (above-mentioned " acquisition data " etc.) using signal procedure 23 and each connection equipment 4.Enter one Step ground, includes above-mentioned logical program in main body program 21, and CPU11 is generated also by the logical program is performed to perform user Arbitrary processing.
In above-mentioned picture data 22, the picture data file 32 for example arbitrarily generated in mapping editing device 5 side in advance Some or all are downloaded and are stored in programable display 1.In addition, not distinguishing picture data file 32 especially and drawing Face data 22, the situation for also having referred to as picture data 22.
In addition, above-mentioned signal procedure 23 also will for example have previously been stored in the signal procedure file 33 of mapping editing device 5 side A part download and be stored in programable display 1.
As described above, substantially CPU11 based on main body program 21 and picture data 22 " obtaining from said external holder Access evidence " etc., carries out the display control of aforesaid operations display picture.For example, showing the project with lamp etc. for numerical value, regularly Data are read from the distribution storage area of the project, the display content of the project is updated based on the reading data.Or, Such as the project switch, user (is beaten after being touched to the desired switch on the operating display frame Open or close after closed operation), then progress switch opening image shows or switched closing image and shows.
In addition, CPU11 also carries out the control of the connection equipment 4 corresponding to the switching manipulation.For example, corresponding point will be switched Storage data (representing mark opened or closed of switch etc.) with storage area, are updated according to switching manipulation.Thus, Connect controller (not shown) of the side of equipment 4 etc. and perform the corresponding action of the mark.
In addition, such as narration in the past, said external holder is the storage facilities for possessing connection equipment 4, it is to carry out The storage facilities of the storage distribution of projects.As described above, storage of the display content of projects based on the distribution storage area Deposit data is determined and updated.
Also, such as narration in the past, the reading data from the distribution storage area are temporarily stored within programmable It is the configuration example based on this progress project display control in above-mentioned interior magazine in display 1.
In this example, periodically carried out such as using each communication processing section 63 described later from the storage facilities in connection equipment 4 Data are read in the defined storage area of (external storage), and the reading data (above-mentioned " acquisition data ") are stored in into internal storage The processing of storage (hereafter above-mentioned common storage 55).Also, for example using project processing unit 62 described later, based on above-mentioned interior Storage data of portion's holder etc., carry out the display control of aforesaid operations display picture.Thus, in the display of operating display frame Hold and (the shape of current control object is reflected to the content of the current storage data of the corresponding distribution storage area of projects The corresponding display content such as state).
In addition, the Graph editor 31 of making of servicing unit 5 has to for the desired picture data file of the generation such as developer 32 functions of being aided in.In addition, servicing unit 5 also has following function:That is, lead to from the various signal procedure groups stored in advance Believe program file 33, the signal procedure more than any one is downloaded to programable display 1, stored up as above-mentioned signal procedure 23 Deposit.But, the function of these servicing units 5 is functional, is not described further here.
In addition, mapping editing device 5 is, for example, computer etc., with the computer that need not especially illustrate but typically commonly use Structure (CPU, storage unit (hard disk, holder etc.), communication unit, operating portion (mouse etc.), display).It is pre- by being performed by CPU The application program of storage unit is first stored in, is realized above-mentioned functional.
Fig. 4, Fig. 5 are the processing function figure (1/2) of the programable display 1 of this example, (2/2).In addition, not making below especially Distinguish, labeled as " Fig. 4 etc. ".
In stored picture data 22 of programable display 1 etc..
CPU11 is for example stored in above-mentioned ROM12 regulated procedure (such as aforementioned body program 21, communication by performing Program 23 etc.), the various processing function portions represented in realizing such as Fig. 4 in dotted line.I.e., it is illustrated that project generating unit 61, item Mesh processing unit 62, communication processing section 63 (63-1,63-2 etc.), logical process portion 64, project processing plan portion 65, common storage Generate processing unit 66, logical process planning department 67, logical order generating unit 68, optimum instruction generating unit 69, classification judgement processing The processing function in the various processing function portions such as portion 70 is implemented.
In addition, in these various processing function portions 61~70, processing function portion 61~63,65~69 can substantially be seen Make to carry out and in the past almost identical processing.But, also there are cyclic access counter 85 described later, Burst frequency access counter 86th, the situation that any one associated processing in upgrading judge mark 87 is performed.It is cyclic access counter 85 described later, prominent Send out the substantially conventional non-existent information of frequency access counter 86, upgrading judge mark 87.Therefore, substantially, these are counted The processing associated with mark of number device, can be regarded as the new processing in this method.
In addition, logical process portion 64 is also basic processing function, can be counted as with it is in the past almost identical.But, patrol A part for the function of volume processing unit 64 be burst holder visiting portion 64a described later from it is conventional different.
Classification judges that processing unit 70 is conventional non-existent processing function portion.
In addition, communication processing section 63 is realized by main body program 21 and signal procedure 23.Processing beyond communication processing section 63 Function part is substantially realized by main body program 21, but is not limited to the example.
Project generating unit 61 is based on above-mentioned picture data 22 etc., generates bulleted list 51.This is for example to replicate frame numbers According to (further add processing described later and complete mark 118) of the Form generation of 22 part.
The number corresponding to bulleted list 51 that common storage generation processing unit 66 will be generated as above-mentioned project generating unit 61 Common storage 55 is stored according to (access target etc.).In other words, to each storage data (each access target of common storage 55 Deng) be updated.
In addition, the operation that the storage data of above-mentioned bulleted list 51 and common storage 55 for example become showing is shown The corresponding content of projects on picture (screen).Thus, when carrying out screens switch every time, generated again.In addition, sharing In holder 55, the data with the access target of logical process etc. are further also stored.Detailed following article is above-mentioned.
Projects corresponding above-mentioned " acquisition data " on the above-mentioned operating display frame (screen) shown pass through Communication processing section 63 is stored and (is cyclically updated) in common storage 55.
Communication processing section 63 is provided in communication processing section 63-1,63-1 in each connection equipment 4 (4-1,4-2).That is, The communication processing section 63-1 of diagram use with the connection corresponding COM1 WAY1 of equipment 4-1, via communication line 6, carry out with Equipment 4-1 communication is connected, the storage data of the predetermined region (distribution storage area) of its external storage are obtained.Also, will " acquisition data " covering is somebody's turn to do to be stored on the region of common storage 55.
Similarly, it is illustrated that communication processing section 63-2 use with the connection corresponding COM1 WAY2 of equipment 4-2, via logical Believe circuit 6, carry out the communication with being connected equipment 4-2, obtain the storage of the predetermined region (distribution storage area) of its external storage Deposit data.Also, " acquisition data " covering will be somebody's turn to do to be stored on the corresponding region of common storage 55.
The acquisition of the data from said external holder of above-mentioned each communication processing section 63 handles and is somebody's turn to do " acquisition data " Common storage 55 storage data renewal processing, by periodically (cyclically) perform.
Here, the communication processing section 63 of this example is based on optimum instruction list 54 (54-1,54-2), carries out obtaining above-mentioned distribution The processing of the storage data of storage area.Optimum instruction list 54 is that optimum instruction generating unit 69 is based on the correspondence of common storage 55 What each connection equipment 4 was generated.The optimum instruction list 54-1 of diagram with connection equipment 4-1 it is corresponding, optimum instruction list 54-2 and Connect equipment 4-2 correspondences.
Optimum instruction generating unit 69 has progress (Japanese Patent Laid-Open 2009-54056 such as above-mentioned patent document 1,2 Publication, Japanese Patent Laid-Open 2009-54055 publications) disclosed in existing processing function part, therefore do not carry out especially here Explanation.
But, it is by the access target (distribution for each project for being stored in common storage 55 if simply illustrating Storage area) access target is generated in the way of merging access.For example, having project A, B, C, have respectively No. D101, No. D105, In the case of No. D108 distribution storage area, stored the region merging technique untill No. D101~No. D108 as an access target In optimum instruction list 54.
Certainly, due in the processing, also obtaining unwanted data, therefore only by data (No. D101, the D105 of needs Number, each data of No. D108) be stored in the corresponding region of common storage 55.Also, give up should not data.
Generally, the processing via communication line 6 with being connected the communication of equipment 4 more expends the time, thus, even if the number obtained According to amount slightly increase and additional Screening Treatment, processing time can also shorten.
But, it is above-mentioned that address is merged into one like that, number of communications is reduced, is not that one will surely shorten processing time, Therefore the generation of optimum instruction list 54 is not essential.However, in the case of not generating optimum instruction list 54, this method In, also there is the external storage access for being associated hereafter above-mentioned logical process to include to project and show associated circulation The situation that external storage is accessed.
In addition, such as above-mentioned above, each connection equipment 4 of correspondence sets communication processing section 63 and optimum instruction list 54 (to enter one Step has hereafter above-mentioned instruction list 53 etc.).Thus, connection equipment 4 have it is multiple in the case of, communication processing section 63 and optimal Instruction list 54 etc. is also provided with multiple.However, in this explanation, it is not right for communication processing section 63 and optimum instruction list 54 etc. Each connection equipment 4 (4-1,4-2) illustrates, but uniformly illustrates.
In addition, optimum instruction generating unit 69 is entered substantially when for example along with screens switch renewal item list 51 One step with this along with update common storage 55 when, generate corresponding to the storage content of the new common storage 55 most Excellent instruction list 54.In other words, substantially this moment beyond the content of optimum instruction list 54 do not change.But, we In method, have and judge the situation that processing unit 70 makes the content of optimum instruction list 54 change using classification.For example have on hereafter The access target for the grade of logical process portion 64 stated adds the situation into optimum instruction list 54.In addition, at this moment, it is preferable that utilize Optimum instruction generating unit 69 carries out the optimization processing (link of address above mentioned for also including access target of the grade of logical process portion 64 Deng;Address is merged into one etc.), optimum instruction list 54 is generated again.Detailed following article is above-mentioned.
The storage data (" acquisition data ") of project processing unit 62 based on above-mentioned common storage 55 etc., hold to each project The processing being associated the renewal (being switched such as opening image or closing with image) of the row display content.That is, project is handled Portion 62 is such as based on the nearest acquisition data from above-mentioned distribution storage area, it is determined that or the above-mentioned display operation screen of renewal Display content.
The processing of above-mentioned project processing unit 62 is also periodically carried out, and the planning management is carried out by project processing plan portion 65.That is, Project processing plan portion 65 is carried out the planning management of the display renewal processing of projects etc. by project processing unit 62.That is, at project Reason planning department 65 for example regularly recalls project processing unit 62, performs for example that hereafter above-mentioned Fig. 8 processing (in other words, is circulated Perform Fig. 8 processing).
More than, mainly to the decision or renewal processing (refresh process) of the display content for showing projects on operation screen (still, classification judge processing unit 70 except) is illustrated in associated processing function portion or data etc..
On the other hand, such as above-mentioned above, CPU11 also carries out above-mentioned logical process.The logical process performs associated place Logical process portion 64, logical process planning department 67, logical order generating unit 68, logic that function part, data etc. are diagrams is managed to refer to Make list 52 and instruction list 53 (53-1,53-2) etc..
Above-mentioned logical process perform associated processing function portion, data etc. substantially with beyond logical process portion 64 with Past is almost identical, therefore simply illustrates below.
Logical order generating unit 68, will be based on arbitrary access target (any connection equipment 4 for arbitrary logical program Any external storage device arbitrary address) data processing (such as branch process;If~then~else etc.) it is related The information of connection is stored to logical order list 52.Show that concrete example is illustrated after for logical order list 52.
Logical process portion 64 carries out logical order list 52 based on the planning management using logical process planning department 67 Corresponding data acquisition process etc..For example, the above-mentioned access target for being stored in logical order list 52 is stored in into shared storage Device 55, and the instruction generated based on the access target is stored in instruction list (FIFO) 53.
In addition, " access process " in following explanation is substantially represented " processing for accessing external storage ".Likewise, " access target " is substantially represented " arbitrary address of any external storage device of any connection equipment 4 ".
Here, the communication processing section 63 of this example not only performs the access process based on above-mentioned optimum instruction list 54, also holds Access process of the row based on instruction list 53.That is, any one instruction (such as hereafter above-mentioned instruction is stored in instruction list 53 130 etc.) in the case of, the instruction is extracted, is conducted interviews processing based on the instruction.Also, by access process result (from access " the acquisition data " of target) store to the corresponding region of common storage 55.
Logical process portion 64, which is waited, is stored above-mentioned " acquisition data " to above-mentioned common storage 55 by communication processing section 62 Corresponding region in, after storage, above-mentioned processing (such as branch process) is performed based on the acquisition data.Particularly branch process In the case of, which in then and else is performed if not knowing if mustn't go to above-mentioned acquisition data, therefore is waited.Cause This, there is the situation that stand-by time is elongated.If in addition, frequently carrying out irregular (sudden) visit along with logical process like this Processing is asked, then the access process that above-mentioned refresh process is associated is impacted, has display content to update time-consuming situation.
Thus, in this method, in the access target with irregular (sudden) access process of logical process, there is frequency The access target of processing that conducts interviews numerously in the case of, the access target is set to include to optimum instruction list 54.Accordingly, for The access target, occurs, progress above-mentioned circulation visit unrelated with irregular (sudden) access process of logical process with whetheing there is Ask, obtain data storage in the corresponding region of common storage 55.
And in the case of access target irregularly the processing generation of (sudden) access, logical process portion 64 is obtained altogether With the storage data of the corresponding region of holder 55.Thus above-mentioned stand-by time, and the also above-mentioned brush of without prejudice to are hardly consumed The associated access process of new processing.Thus, the renewal processing of project display content will not be slack-off.
In addition, also including hereafter above-mentioned burst holder visiting portion 64a (not shown) processing in logical process portion 64 Function.Thus, logical process portion 64 not only carries out hereafter above-mentioned Figure 10, Figure 11 processing, also carry out hereafter above-mentioned Figure 12, Figure 13 processing.Detailed following article is above-mentioned.
Below, above-mentioned various processing function portions and various data are further described.
First, to communication processing section 63, and its detailed processing example is illustrated.
Fig. 6, Fig. 7 are that each communication processing section 63 (63-1,63-2) for example regularly (cyclically) performs external storage respectively The flow chart (1/2) of device access process, (2/2).In addition, not making especially differentiation below, labeled as " Fig. 6 etc. ".
In processing example above-mentioned Fig. 6 etc., the communication process of the associated circulation of above-mentioned refresh process is essentially performed, but Associated irregular (sudden) communication process of above-mentioned logical process is carries out the communication process in the case of necessary.In addition, Irregularly (sudden) communication process is that necessary situation refers to, for example, (instruction from somewhere is represented into the finger of access target Order;Such as hereafter above-mentioned instruction 130) when be stored in above-mentioned instruction list 53.
In addition, the processing of the communication processing section 63 shown in Fig. 6 etc. can be prior art in itself.In addition, the processing is related , should in the various data of connection (optimum instruction list 54, common storage 55, instruction 130 hereafter exemplified by above-mentioned Figure 19) Data structure can also be prior art in itself.But, also there is the situation of the content of data unlike the prior art.That is, most Excellent instruction list 54 has the not only associated access target of the communication process comprising above-mentioned circulation, also comprising above-mentioned bursty communication The situation of the associated access target of processing.Detailed following article is above-mentioned.
For the communication process of above-mentioned circulation, arbitrary holder access instruction is obtained from optimum instruction list 54 first (step S11).This is for example correspondingly to refer to the execution index (not shown) in optimum instruction list 54 to extract as keyword Order.
Here, Figure 19 represents the data structure example of above-mentioned instruction.In addition, optimum instruction list 54 and instruction list 53 are for example It is by the content of the list of instruction 130 as shown in Figure 19.
Instruction 130 exemplified by Figure 19 is by instruction type 131, storage module number 132, (the N number of storage of each storage module 133 Storing module 133) etc. constitute.
Instruction type 131 is such as being " module reading ", " multimode reading " as one.Because these are also existing skill Art, therefore be not described in detail especially, but simple illustration following article is above-mentioned.
Module is read;The instruction specified to arbitrary beginning address and data amount check.Address acquisition data from the outset The data in the region of individual quantity.Storage module number 132 is fixed as ' 1 '.
Multimode is read;It is the instruction that the module expanded is read, multiple access targets can be specified.That is, storage module Number 132 is more than ' 2 '.
Storage module number 132 is the number of storage module 133.
In each such as example illustrated of storage module 133, by port 141, equipment 142, address 143 and data amount check Each data items such as 144 are constituted.Port 141, equipment 142 and address 143 represent access target (such as above-mentioned distribution storage area Beginning address).That is, port 141 is identiflication number of the corresponding port of connection equipment 4 of access target etc..Equipment 142 is to visit Ask identification information of storage facilities of access target in the connection equipment 4 of target etc..Address 143 is access in the storage facilities Beginning address of the storage area of target etc..
Also, the storage area of the region representation access target of the amount of the data amount check 144 from the beginning address, the storage The storage data for depositing region are read.
That is, in Fig. 7 etc. processing, by the way that the instruction obtained in above-mentioned steps S11 processing 130 is sent to access mesh Target connection equipment 4 (step S12), the storage of the above-mentioned access target represented in the connection side of equipment 4 from above-mentioned each storage module 133 Region is deposited, storage data is read and replys.If receiving the reply (step S13), " acquisition data " that the reply is included (from The data that the storage area of above-mentioned access target is read) store into the corresponding region of common storage 55.The processing in itself may be used With as in the past, but in the case of this example, in above-mentioned " acquisition data ", have and not only include following of being used for that above-mentioned project to show The associated data of the communication process of ring, also comprising the associated data of above-mentioned bursty communication processing.
Finally, the execution index (not shown) in above-mentioned optimum instruction list 54 is for example made to advance to next instruction (step Rapid S15).That is, the instruction 130 of next process object is specified.
Then, from (the step of instruction 130 for the 130 groups of acquisition beginnings of more than one instruction for being stored in instruction list 53 S16).But, in the case of 130 no ones are instructed in instruction list 53 (step S17 is no), present treatment terminates.
Obtain in the case of any one instruction 130 from instruction list 53 (step S17 is yes), to the processing pair The instruction 130 of elephant also carries out step S12, S13, S14's associated with the instruction 130 obtained from above-mentioned optimum instruction list 54 The almost identical processing (step S18, S19, S20) of processing.
That is, it will be sent in the above-mentioned steps S16 instructions 130 obtained to the connection equipment 4 (step S18) of access target, by This reads storage data from the storage area of access target in the connection side of equipment 4 and replied.If receiving the reply (step S19), " the acquisition data " that then reply is included are stored into the corresponding region of common storage 55 (step S20).
Also, it is last, the request source (such as logical process portion 64) of the instruction 130 of above-mentioned process object is notified to complete (step S21).Logical process portion 64 of the completion notice etc. is received, is stored from the reading above-mentioned steps of common storage 55 S20 Data etc..
Here, Figure 16 (a) represents the data structure example of common storage 55.
In the example shown in Figure 16 (a), the storage data of common storage 55 are by port 81, data name 82, address 83rd, each data item such as data 84, cyclic access counter 85, Burst frequency access counter 86 and upgrading judge mark 87 Mesh is constituted.
Among these, port 81, device name 82, address 83 and data 84 can be identical with conventional, simply enter below Row explanation.
Port 71 is identification information of above-mentioned COM1 etc., and substantially the connection equipment 4 to communication counterpart is identified Information.Equipment 72 is the identification information of the storage facilities (external storage) in the connection equipment 4 of communication counterpart.Address 73 is Equipment 72 is represented in the address of storage area specified in external storage, the data storage from storage area acquisition is in data In 74.In addition, port 71, device name 72 and address 73 are also seen as above-mentioned " the distribution holder equivalent to projects Location ".
Beyond above-mentioned conventional data items, above-mentioned cyclic access counter 85, Burst frequency are also set up in this example and is accessed Counter 86 and upgrading judge mark 87.These are illustrated after, makees brief description here.
First, the associated access target of above-mentioned refresh process is stored and from the access target in common storage 55 Data etc. are obtained, the associated access target of above-mentioned burst access processing and the acquisition data from the access target are also stored Deng.Also, for the record that above-mentioned refresh process is associated, value (+1 as defined in storage is forced in cyclic access counter 85 Deng), and without using Burst frequency access counter 86 and upgrading judge mark 87.On the other hand, for above-mentioned burst access The associated record of processing, forces storage ' 0 ' etc., and use Burst frequency access counter in cyclic access counter 85 86 and upgrading judge mark 87.
Here, if the application method to these counters 86 and mark 87 is simply illustrated, it assumes that performing every time During arbitrary above-mentioned sudden access process, the Burst frequency access counter 86 of corresponding record is set to be counted upwards.And And, in the case that the value of counter 86 exceedes defined threshold value, upgrading judge mark 87 is opened for mark.Also, make above-mentioned The process object of communication cycle processing is not only comprising the record that cyclic access counter 85 is setting (+1 etc.), also comprising upgrading The record that judge mark 87 is opened for mark.
In addition, above-mentioned Burst frequency access counter 86 is periodically reset.Thus, in the value of specified time limit inside counting device 86 Access, that is, in the case of frequently executing access, make in above-mentioned burst access processing, the also visit comprising circulation more than above-mentioned threshold value Ask processing.Also, samely, in this method, the access process to circulation is optimized.Thus, burst is contained to visit Ask that the overall access efficiency of the external storage access process of processing is improved.It is however not limited to the example.Also can be without excellent Change, and above-mentioned burst access processing is merely included in cyclic access processing.
Then, reference picture 8, the processing to project processing unit 62 is illustrated.
Fig. 8 is the process chart of project processing unit 62.
Project processing unit 62 is periodically recalled using project processing plan portion 65 as described above, performs Fig. 8 processing.
In the processing example of diagram, first, the processing of whole records of bulleted list 51 is completed into mark 119 and initialized (mark is closed) (step S31).
Here, Figure 17 (b) represents the data structure diagram of bulleted list 51.
The bulleted list 51 of example illustrated is by item types 111, coordinate 112, size 113, port 114, device name 115th, address 116, the data 117 of each item types and processing complete each data items composition such as mark 118.Project is arranged Each record of table 51 is corresponding with projects of operating display frame.In addition, example illustrated is not limited to, it is further or every Purpose identiflication number etc..
Stored in item types 111 and represent that the project kind of the project kind (switch, lamp, numerical value are shown) recognizes letter Breath.
In addition, port 114, device name 115 and address 116 are the associated storage distribution information of projects, equivalent to Above-mentioned distribution holder address.That is, in the external storage that the device name 115 in the corresponding connection equipment 4 in port 114 is represented The storage area that address 116 is represented is the region (above-mentioned distribution storage area) that the project is distributed.The distribution storage area Storage data represent the current state of the associated control of the project or supervision object.If such as item types 111 are lamp, Flag data lighted or extinguished of indication lamp etc. is above-mentioned storage data.
The data 117 of every kind of item types are image (such as the lamp opening image and lamp closing image of such as project Deng).Coordinate 62 and size 63 represent display location and the size of the item image.
It is back to Fig. 8 explanation.
Then above-mentioned steps S31 processing, by the arbitrary untreated project from bulleted list 51, (processing is completed Mark 119 records associated project for what is closed) as process object (step S32).Also, obtained in common storage 55 The grade of data 84 of the corresponding record of above-mentioned process object project is used as holder information 71 (step S33).
In addition, for example, the port 114 of the port 81, device name 82 and address 84 and above-mentioned process object, setting Standby title 115 and the identical of address 116 are recorded, and are above-mentioned corresponding records.
Here, one of the above-mentioned holder information 71 of Figure 17 (a) expressions.
The holder information 71 of example illustrated is by data 101, cyclic access counter 102, Burst frequency access count Device 103 and upgrading judge mark 104 etc. are constituted.This is for example by the data 84 of above-mentioned corresponding record, cyclic access counter 85th, the content that Burst frequency access counter 86 and upgrading judge mark 87 are replicated.
It is however not limited to which above-mentioned example, such as holder information 71 also can be only above-mentioned data 101.
Also, using the holder information 71 of above-mentioned acquisition, carry out the associated display (step of above-mentioned process object project S34).Certainly, at this moment, data (coordinate 112, size 113 or the item of above-mentioned process object project in bulleted list 51 are also utilized Mesh image etc.) carry out display processing.
Finally, it is used as in bulleted list 51 the processing completion mark 118 of the record of above-mentioned process object project to have handled Into (mark is opened) (step S35).Also, in the case of the remaining untreated record of bulleted list 51 (step S36 is yes), Return to step S32.Above-mentioned steps S32~S35 processing (step is performed to whole records (whole projects) of bulleted list 51 S36 is no), then present treatment terminates.
Then, common storage generation processing unit 66 is illustrated.
Fig. 9 is the process chart that common storage generates processing unit 66.
Common storage generates processing unit 66 for example when being transferred out every time from project generating unit 61, performs Fig. 9 processing. Project generating unit 61 for example every time based on picture data 22 when bulleted list 51 generates new list (new record), is recalled altogether Processing unit 66 is generated with holder.At this moment, project generating unit 61 will represent that the information of the new list (new record) of above-mentioned generation (refers to Pin) it is sent to common storage generation processing unit 66.
Thus, common storage generates new list (the new note with reference to above-mentioned generation in bulleted list 51 of processing unit 66 Record), obtain (step S51) such as the port 114, device name 115, addresses 116.
Also, based on the acquisition data, (step is judged to whether the record completes to log in common storage 55 Rapid S52).For example, in common storage 55, exist the port 81, device name 82, the port 114 of address 83 and above-mentioned acquisition, In the case of device name 115, the identical of address 116 record, it is judged as logging in completion (step S52 is yes).In this case, not Step S53 processing is carried out, step S54 processing is transferred to.
On the other hand, do not complete in the case of logging in (step S52 is no), the above-mentioned data supplementing is logged on into shared storage Storage 55 (step S53).That is, new record is added in common storage 55, is stored up in the port 81, device name 82, address 83 Deposit each data of the port 114 obtained in above-mentioned steps S51, device name 115, address 116.Also, shifted to step S54.
The record completed in step S54, common storage 55 to above-mentioned login or the record added in above-mentioned steps S53 (it is not to update that can also regard as to middle renewal (+1 etc.) above-mentioned cyclic access counter 85, but regards pressure as so that it becomes setting (being here ' 1 ')).Thus, such as hereafter above-mentioned step S72 is judged as NO.Also, terminate present treatment.
Then, the processing to logical process portion 64 is illustrated.
Figure 10, Figure 11 are the process chart (1/2) in logical process portion 64, (2/2).In addition, do not make especially differentiation below, Labeled as " Figure 10 etc. ".
In addition, such as above-mentioned above here, logical process portion 64 also carries out hereafter above-mentioned Figure 12, Figure 13 processing.
In processing example shown in Figure 10 etc., first, the processing of whole records of logical order list 52 is completed into mark 137 Initialized (mark is closed) (step S41).
Here, logical order 52 is illustrated.
Figure 18 is the concrete example of logical order list 52.
The logical order list 52 of illustrated example has execution condition 121, port 122, device name 123, address 124, life Make line number 125, respectively order 126, processing complete mark 127, the data items such as sub-value 128 on instruction memory.
Port 122, project name 123 and address 124 represent access target.That is, the corresponding connection equipment 4 in port 122 The storage area that address 124 is represented in the external storage device that interior device name 123 is represented is access target.This is accompanied by The access target that the arbitrary logical process accessed to external storage is associated (also has the feelings of referred to as instruction memory below Condition).Also, the associated order of the arbitrary logical process is stored in each order 126 line by line.Also, of the order 126 Number (line number) is stored in order line number 125.
Also, store the condition for performing above-mentioned each order 126 in execution condition 121.This be substantially based on it is above-mentioned The condition of the storage data of access target.For example, in the case that the storage data of above-mentioned access target are the mark of 1, for example Switching from from mark off-mode to mark open mode becomes execution condition 121.In the example, for example logical process portion 63 exists The marker for judgment of above-mentioned access target is in the case of switching from closing to opening, to perform above-mentioned each order 126.
In the judgement that above-mentioned execution condition 121 is associated, for example with sub-value on instruction memory 128.That is, following article Above-mentioned, logical process portion 64 is stored up when newly obtaining the storage data of above-mentioned access target every time based on the acquisition data and instruction Sub-value 128 carries out above-mentioned judgement on storage.It is that mark is opened and sub-value 128 is mark on instruction memory for example to obtain data In the case of closing, it is judged as switching to the state of opening from closing.In addition, it is unrelated with judged result, newly obtain every time above-mentioned During the storage data of access target, stored the acquisition data as sub-value 128 on new instruction memory.
In addition, respectively record (is particularly the execution condition 121, port 122, device name in above-mentioned logical order list 52 123rd, address 124, order line number 125, each order 126 etc.) generated by logical order generating unit 68.This is for example based on arbitrary Logical program generation.The generation processing is existing processing in itself, is not especially illustrated or is illustrated here.Also, logic Processing unit 64 performs Figure 10 etc. processing using the grade of logical order list 52 of above-mentioned generation.It is back to Figure 10 etc. explanation.
Above-mentioned steps S41 processing is performed, then using each record of above-mentioned logical order list 52 as dealing with objects successively Repeat the processing between the step S42- steps S46 of diagram.
That is, with reference to the untreated record (logical order) (step S42) from above-mentioned logical order list 52, for example, know The access target (instruction memory), the data i.e. data for obtaining or storing from the access target are not obtained from common storage 55 84 (step S43).That is, the port 81 in common storage 55, device name 82, address 83 and above-mentioned process object are for example obtained Port 122, device name 123, the identical of address 124 record in data 84.
Also, sub-value 128 etc., the data of decision instruction holder in data 84 and above-mentioned instruction memory based on acquisition Whether change (step S44).Such as above-mentioned one like that from mark close change turn to mark open (or vice versa, from mark beat Open change turn to mark close) etc. in the case of, whether the data of decision instruction holder change (step S44 is yes).The feelings Under condition, further, based on above-mentioned execution condition 121 etc., judge whether to perform triggering (step S47).
In above-mentioned one, close change from mark and turn in the case that mark opens, being judged as performing triggering, (step S47 is It is), step S48 processing is performed, step S49 processing is performed afterwards.On the other hand, in above-mentioned one, open and become from mark In the case of turning to mark closing, it is judged as being not carried out triggering (step S47 is no), step S48 processing is not performed, directly Perform step S49 processing.
Step S48 processing be perform successively in the logical order of above-mentioned process object above-mentioned each order 126 processing (according to Secondary execution the first row~Nth row).Also, with the execution successively of each order 126, accessed in each arbitrary external storage During generation, such as, using the burst holder visiting portion 64a (not shown) with logical process portion 64, perform hereafter above-mentioned figure The processing of 12 grades.To each logical order, step S48 processing, therefore Figure 12 etc. processing are only carried out when step S47 is to be Middle external storage, which is accessed, becomes irregular (sudden) external storage access process.In addition, representing the information of access target For example comprising extremely order 126.
In addition, step S49 processing is by sub-value on above-mentioned instruction memory in the logical order of above-mentioned process object 128 processing being updated using the above-mentioned steps S43 data 84 obtained.
Also, it is last above-mentioned processing is completed the processing completion (mark of mark 127 in the logical order of above-mentioned process object Open) (step S45).
Also, (step S46 is in the case of the remaining untreated record (logical order) of above-mentioned logical order list 52 It is), return to step S42.If the state (step S46 is no) without untreated record (logical order), terminates present treatment.
The external storage access process that Figure 12, Figure 13 are accompanied by logical process is (i.e. above-mentioned irregular (sudden ) access process) process chart (1/2) in logical process portion 64 when occurring, (2/2).In addition, not making special area below Point, labeled as " Figure 12 etc. ".
In addition, such as above-mentioned above, Figure 12 etc. processing can also be regarded as with the (not shown) sudden of logical process portion 64 The content that holder visiting portion 64a is performed.But, in the present invention, do not carried especially for sudden holder visiting portion 64a And, the situation for being denoted as the content of the execution of logical process portion 64 is more.
In processing above-mentioned Figure 12 etc., logical process portion 64 recognizes irregular (sudden) access process of above-mentioned generation Access target, the data of the access target be stored in as above-mentioned data 84 in shared data 55 in the case of (in other words, comprising In the case of the access process of circulation), obtain the data 84.This is for example, first, it is determined that whether above-mentioned access target logs in In common storage 55 (step S61).This is for example, the port 81, device name 82, address 83 and above-mentioned access target (should Port, device name, address) identical record be present in common storage 55 in the case of, be judged as having logged in (step S61 is yes).
Also, if above-mentioned access target is not logged in holder 55 (step S61 is no), then by the access target Xindeng Record is in common storage 55 (step S62).This is for example to add new record in common storage 55, (should by above-mentioned access target Port, device name, address) store in the port 81 of the new record, device name 82, address 83.In addition, the new record is followed Ring access counter 85, Burst frequency access counter 86, upgrading judge mark 87 are set as predetermined original state. That is, such as cyclic access counter 85 and Burst frequency access counter 85 are set to initial value ' 0 '.Upgrading judge mark 87 is set Closed for mark.
Then, from common storage 55 obtain the record (the associated login of above-mentioned access target complete record or on State new record) data 84, cyclic access counter 85, Burst frequency access counter 86, upgrading judge mark 87 as storage Storage information 71.These sentence as above-mentioned data 101, cyclic access counter 102, Burst frequency access counter 102, upgrading Disconnected mark 104 and obtain (step S63).
Also, based on above-mentioned holder information 71, determine whether cyclic access object (step S64).This is in step Cyclic access counter 102 is that more than ' 1 ' situation or upgrading judge mark 104 are mark in the holder information 71 that S63 is obtained In the case that note is opened, it is judged as cyclic access object (step S64 is yes).
In addition, in the case that above-mentioned this is recorded as new record, certainly, step S64 is judged as NO.
Even in addition, the content crossed for the access target that logical process is associated by hereafter above-mentioned " upgrading ", step Rapid S64 is judged as YES.That is, included for such a access target to above-mentioned cyclic access object.Thus, should be with above-mentioned item Mesh shows that associated cyclic access processing is together accessed.Detailed following article is above-mentioned.
In the case of having cyclic access object, the data 84 (data 101 in holder information 71) obtained in step S63 It is the data that should be obtained in this access process.That is, handled and obtained from the storage area of above-mentioned access target using cyclic access Newest (recently) data taken should be stored as data 84.Thus, in this case, being performed using the data 84 obtained Defined logical process.Also, the login that above-mentioned access target in common storage 55 is associated is completed to the burst frequency of record Rate access counter 86 is updated (+1 is incremented by) (step S68), terminates present treatment.
On the other hand, it is not in the case of cyclic access object (step S64 is no), to perform existing access process.That is, Generation includes the above-mentioned instruction 130 of above-mentioned access target (port, device name, address), is added and is stored in instruction list 53 (step S65).Also, the instruction 130 of 63 pairs of communication processing section performs above-mentioned Fig. 6 etc. processing, wait above-mentioned steps S21's Access the progress that completion event is notified.Also, once receive and access completion event and notify, at this moment should the above-mentioned record number According to newest (nearest) data that above-mentioned access target is stored in 84.Thus, the data 84 (step S67) are obtained, using obtaining The data 84 taken perform above-mentioned defined logical process.Also, to the note that above-mentioned access target in common storage 55 is associated The Burst frequency access counter 86 of record is updated (+1 is incremented by) (step S68), terminates present treatment.
In the associated existing access process of above-mentioned sudden access, the stand-by period for having above-mentioned steps S66 becomes non- Situation about often growing.This is for example, forcing the situation of the 130 wait orders of other instructions stored in instruction list 53.With This is relative, in the case of being judged as YES of above-mentioned steps S64, the data 84 from the acquisition of common storage 55 can be utilized to be immediately performed Logical process.That is, processing time can be shortened.The mailing address that the instruction 130 of instruction list 53 is associated is stored in addition, can mitigate The processing load in reason portion 63.Also, the access process for hindering above-mentioned refresh process associated is reduced using sudden access process.
Even in addition, the access target associated on logical process relation becomes also as described below by " upgrading " The object of the optimization of above-mentioned optimum instruction generating unit 69, therefore can efficiently obtain the data of access target.Detailed following article institute State.
Above-mentioned " upgrading " etc. judges that processing unit 66 is carried out by classification.
Figure 14, Figure 15 are process chart (1/2), (2/2) that classification judges processing unit 66.In addition, not making below especially Distinguish, labeled as " Figure 14 etc. ".
Classification judges that processing unit 66 is periodically executed the processing shown in Figure 14 etc..
First, each record of common storage 55 is repeated into step S71 as dealing with objects successively to process object ~S78 processing.
I.e., first, the data 84 for dealing with objects record, cyclic access counter 85, Burst frequency access counter are obtained 86th, upgrading judge mark 87 is used as holder information 71 (step S71).But, in the following description, without using holder information 71 above-mentioned ' 101 ', ' 102 ' etc. symbol, but directly use above-mentioned ' 84 ', ' 85 ' etc. symbol.
Using above-mentioned holder information 71, it is first determined whether being classification object (step S72).At above-mentioned logic What the sudden access of reason was associated is recorded as being classified object.Thus, the cyclic access counter 85 of above-mentioned process object record In the case of more than ' 1 ', process object record is the associated record of above-mentioned refresh process, therefore is judged as it not being classification pair As (step S72 is no).
On the other hand, in the case of the deficiency of cyclic access counter 85 ' 1 ' (being ' 0 ' in this example), process object record is sentenced Break to be classified object (step S72 is yes), next, it is determined that whether process object record is upgrading object (step S73).This is example Such as, in the case that the value of the Burst frequency access counter 86 of process object record is more than first threshold set in advance, sentence Break as upgrading object (step S73 is yes).Also, in this case (step S73 is yes), pass through the upgrading by record is dealt with objects The mark of judge mark 87 is opened, and is made its " upgrading " (step S74).Also, shifted to step S77.
In addition, " upgrading " here refers to, the sudden access process for making process object record associated is included in above-mentioned In the associated cyclic access processing of refresh process.
In addition, process object record is judged as it not being in the case of upgrading object (step S73 is no), to judge process object It is degradation object (step S75) when record.This is for example, dealing with objects the value of the Burst frequency access counter 86 of record not In the case of foot Second Threshold set in advance, it is judged as degradation object (step S75 is yes).Also, in this case (step S75 is yes), by the way that the upgrading judge mark 87 for dealing with objects record is marked into closing, make its " degradation " (step S76).Also, Shifted to step S77.
That is, in this example, the associated sudden access process of process object record becomes to be included in cyclic access processing State after, be not limited to maintain the state all the time, also have from cyclic access processing and remove the situation of (carry out " degradation ") Situation.In addition, therefore as described above, even in step S64 in the case of being, also execution step S68 processing is (to burst Frequency access counter 86 is updated the processing of (+1)).
In addition, above-mentioned first threshold and the value of Second Threshold can arbitrarily be set, it is preferable to set into satisfaction " first threshold The condition of≤Second Threshold ".
In addition, in the case that step S75 is judged as NO, being directly transferred to step S77 processing.In addition, classification judges mark In the case that note 87 is closed for mark, also forcibly step S75 can be judged as NO.
Figure 14 etc. processing is regularly performed (every specified time limit) as described above, at this moment, by aftermentioned step S77 Processing, make process object record Burst frequency access counter 86 be back to original state (' 0 ').Thus, Figure 14 etc. The value of Burst frequency access counter 86 during processing represents the number of times for producing sudden access within above-mentioned specified time limit (to every The number of processing for Figure 12 that individual access target is produced along with logical process).
Here, suppose that having arbitrary specified time limit A and the specified time limit B after it.And, it is assumed that due to specified time limit A In the associated sudden access of arbitrary access target occurrence frequency it is higher, therefore Figure 14 when specified time limit, A passed through Deng processing in perform step S74 upgrading processing.Accordingly, for the access target, the figure in specified time limit after which In the processing of 12 grades, step S64 is yes, but in this case also performs step S58 processing as described above.Here, suppose that by , can also be in rule in the case that the occurrence frequency of the associated sudden access of above-mentioned access target is relatively low in specified time limit B Step S76 degradation processing is performed in Figure 14 when B passes through between periodically etc. processing.
No matter also, above-mentioned step S72, S73, S75 judged result, the Burst frequency for recording process object Access counter 86 is original state (removing ' 0 ') (step S77).Also, there is remaining untreated note in common storage 55 (step S78 is yes), return to step S71 in the case of record.
Each record of common storage 55 is recorded as above-mentioned process object successively, above-mentioned processing is performed, to whole (step S78 is no) is transferred to step S79 after record processing is performed.
The processing of step S79, S80 is the common storage 55 after the processing based on above-mentioned steps S71~S78, then secondary Into optimum instruction list 54.
I.e., first, the common storage 55 after processing based on above-mentioned steps S71~S78, generates cyclic access holder List 72 (step S79).This is in each record of common storage 55, to extract all records for meeting rated condition, be based on The record generation cyclic access holder list 72 of the extraction.Condition as defined in above-mentioned is that cyclic access counter 85 is more than 1, Or upgrading judge mark 87 is opened and (meets a wherein side).
In addition, the processing of step S79, S80 is that each port (connection equipment 4) is performed into processing as dealing with objects successively. Thus, strictly speaking, further comprising port of the port 81 for process object in above-mentioned rated condition.
Here, Figure 16 (b) represents the concrete example of cyclic access holder list 72.
In example shown in Figure 16 (b), cyclic access holder list 72 is made up of device name 91, address 92.The example In son, the device name 82 of each record of said extracted, address 83 are stored in device name 91, address 92.
Also, send the cyclic access holder list 72 of generation to optimum instruction generating unit 69 etc., utilize optimal refer to Generating unit 69 is made to generate new optimum instruction list 54 (step S80).In addition, utilizing the optimum instruction of optimum instruction generating unit 69 The generation processing of list 54 is prior art disclosed in above-mentioned patent document 1,2 etc., therefore is not illustrated especially herein.
Finally, in the case of having untreated port (step S81 is yes), return to step S79, for next processing pair The port of elephant also carries out the processing of above-mentioned steps S79, S80.Also, if processing (step S81 is no) is performed to full record, tie Beam present treatment.
Here, Figure 20 represents the processing function figure of the programable display 1 of this example.
In addition, though processing function portion is shown in Fig. 4 etc., but Figure 20 is indicated from other viewpoints.
In processing function figure shown in Figure 20, programable display 1 has logic control portion 151, external storage reference Receiving portion 152, data buffer storage reading part 153, reference frequency update section 154, classification judging part 155, integration portion 156, circulation are read Take the respectively processing function part such as portion 157 and communication processing section 158.In addition, these various processing function portions are for example, by above-mentioned CPU11 is performed and is had previously been stored in above-mentioned ROM12 etc. application program to realize.
Logic control portion 151 performs arbitrary logical process, and is produced with the logical process to arbitrary access target In the case of raw aperiodically (sudden) access process, access target is obtained with reference to receiving portion 152 via external storage Data.This be for example, to external storage with reference to receiving portion 152 send represent access target external storage identifier 162, Commission obtains data from access target.External storage identifier 162 is, for example, any external storage in any connection equipment 4 Arbitrary address of device etc..
External storage, according to the commission, is obtained with reference to receiving portion 152 via data buffer storage reading part 153 from database 160 The data (external storage data 161) of above-mentioned access target are taken, are sent to logic control portion 151.Further, according to reference Frequency update section 154, is updated to what the above-mentioned access target for being stored in database 160 was associated with reference to frequency data.
In addition, database 160 for example can also be regarded as equivalent to above-mentioned common storage 55.Also, in database 160 for example The various data of storage access target, data buffer storage (data obtained from access target), reference frequency, classification status etc..
In addition, the access target in above-mentioned commission is not logged in the case of database 160, external storage is with reference to receiving The access target etc. is logged on to database 160 by portion 152.
In addition, communication processing section 158 is substantially according to a certain data acquisition request (access process), via order wire Road carries out the processing function portion of communication process with being connected equipment 4.Also, the data obtained using the communication process are sent to please Source is asked, or is stored to database 160.
Here, external storage is obtained at corresponding data with reference to receiving portion 152 according to above-mentioned commission from database 160 Reason, has situation about being carried out immediately after commission is received, and be stored in from the connection acquisition data of equipment 4 according to communication processing section 158 Situation about being carried out after database 160.In addition, the latter can also regard the data capture method of prior art as.In addition, carry out this two The situation of any one in the method for kind all carries out the above-mentioned renewal with reference to frequency data.
The access target that above-mentioned logic control portion 151 is entrusted is integrated into cyclic access described later by integration portion 156 described later In the case of target group, external storage obtains corresponding data from database 160 immediately with reference to receiving portion 152.On the other hand, not In the case of integration, the access target of above-mentioned commission is sent to communication processing section 158, acquisition request data.In addition, above-mentioned be The judgement of no integration is for example carried out based on above-mentioned classification status.For example, above-mentioned classification status is the feelings of upgrade status as be described hereinafter Under condition, it is judged as being integrated.
Receive the communication processing section 158 of above-mentioned data acquisition request and carry out communication process with being connected equipment 4, obtain above-mentioned visit The data of target are asked, by the acquisition data storage in database 160, and number are notified with reference to receiving portion 152 to external storage Completed according to obtaining.
The external storage of the notice is received with reference to receiving portion 152, above-mentioned acquisition data are read from database 160, by it Sent as said external holder data 161 to logic control portion 151.
In addition, circulation reading part 157 keeps cyclic access target group (not shown), for example cyclically, visited from correspondence circulation Ask that each access target of target group carries out data acquisition via above-mentioned communication processing section 158.Cyclic access target group (not shown) The access target of the associated each project of e.g. above-mentioned refresh process.
In addition, above-mentioned cyclic access target group (not shown) is equivalent to the access mesh that refresh process as escribed above is associated Mark group.That is, the access target group being associated equivalent to projects in above-mentioned display picture is (particularly equivalent to above-mentioned optimal finger List 54 is made, but is not limited to the example).
Here, classification judging part 155 for example regularly, to above-mentioned database 160 log in each access target, based on pair That answers is above-mentioned with reference to frequency data, carries out classification judgement, will determine that result is stored as above-mentioned classification status.Classification status There are normal state and upgrade status.Classification judged result has upgrading, degradation and keeps present situation etc..It is judged as rising in normal state In the case of level, upgrade status is transferred to.In the case of being judged as degradation in upgrade status, normal state is transferred to.
If being more than defined first threshold, to be judged as upgrading for example with reference to frequency.If with reference to as defined in frequency deficiency Second Threshold, then be judged as degrading.In addition, the value of threshold value can arbitrarily be set, but be preferably set to meet " the first threshold value≤ The condition of Second Threshold ".
External storage with reference to receiving portion 152 the access target of commission classification status be upgrade status in the case of, Carry out above-mentioned " processing for obtaining corresponding data from database 160 immediately ".On the other hand, in the case of for normal state, such as It is described above, data acquisition is carried out by communication processing section 158.
Also, integration portion 156 for example regularly judges that above-mentioned classification status is at database 160 (every specified time limit) The access target of above-mentioned " upgrade status ".Also, the access target for judging this rises this as upgrade status access target Level conditional access targeted integration is to above-mentioned cyclic access target group.Thus, even the access target of adjoint above-mentioned logical process, Also being conducted interviews with the circulation with above-mentioned refresh process etc. to the external storage for being connected equipment 4, together merging is carried out for processing Regularly access process.Also, reading part 157 is circulated, the data cover obtained in cyclic access processing is stored in number According to the corresponding region in storehouse 160.
In addition, integration portion 156 also can be judged as degrade access target, carry out from above-mentioned cyclic access target group remove Processing.
In addition, cyclic access target group, also can be equivalent to above-mentioned optimum instruction list 54 as one.Also, the example In the case of, integration portion 156 can also have the processing function equivalent to above-mentioned optimum instruction generating unit 69.In addition, the example In the case of, classification judging part 155 and integration portion 156 can also regard as and judge processing unit 70 equivalent to above-mentioned classification.
But, above-mentioned cyclic access target group also can not be optimised.That is, cyclic access target group also can be merely to be above-mentioned The set of the associated each access target of refresh process.
As described above, the refresh process that the programable display 1 of this example is substantially shown with the project in display picture Associated external storage is accessed, and is performed (irregularly along with logical process;It is sudden) carry out external storage access Programable display premised on.Also, even in the high shape of the frequency of the external storage access performed with logical process Under state, action is also set not become slow.
That is, in the programable display 1 of this example, such as during the external storage performed along with logical process is accessed The high access target of access frequency, is integrated into the associated access target group of refresh process.Thus, it can suppress at along with logic The external storage that reason is performed accesses the situation for the larger obstruction of external storage access process being associated to refresh process.
Particularly, the high access target of access frequency is included during the external storage performed along with logical process is accessed Optimized after the access target group being associated to refresh process, generate above-mentioned optimum instruction list 54.Thus, external storage Associated overall treatment effeciency is accessed to improve.
Further, when the sudden external storage that generation is performed along with logical process every time is accessed, it is not necessary to by One carries out external storage access, improves the associated treatment effeciency of logical process.
In addition, the programable display 1 of this example can for example be regarded as with following processing function portions (not shown).
Project information storage unit, the project information storage unit is stored to the access information of each access target of expression, on Each access target is stated corresponding to projects in display picture;
First data capture unit, first data capture unit is regularly based on above-mentioned access information, from above-mentioned connection Data are obtained at each access target in equipment, are stored in interior magazine;
Logical process enforcement division, the logical process enforcement division performs arbitrary logical process, and to along with the logic The access target of processing is in the case that irregular access target produces access process, to judge whether the irregular access target is whole It is bonded to above-mentioned access information.And in the case of being judged as that the irregular access target is integrated into above-mentioned access information, from above-mentioned Interior magazine obtains the corresponding data of the irregular access target;
Access frequency, every specified time limit, is more than defined first threshold above-mentioned indefinite by classification portion, the classification portion Phase access target is adjusted to upgrade status access target;
Irregular access target as above-mentioned upgrade status access target is integrated into above-mentioned visit by integration portion, the integration portion Ask information;And
Second data acquiring section, is being judged as that irregular access target is not integrated into access by above-mentioned logical process enforcement division In the case of information, second data acquiring section obtains data from the irregular access target in connection equipment;
In addition, being for example integrated into the situation of above-mentioned access information in arbitrary more than one above-mentioned irregular access target Under, above-mentioned first data acquiring section also obtains data from each irregular access target and is stored in above-mentioned interior magazine.
In addition, whether for example above-mentioned logical process enforcement division is integrated into above-mentioned access information with above-mentioned irregular access target It is unrelated, it is associated to the irregular access target when producing access process to arbitrary above-mentioned irregular access target every time Access frequency be updated.
In addition, for example in the above-mentioned visit relevant with the above-mentioned irregular access target as above-mentioned upgrade status access target Frequency is asked as defined in being not up in the case of Second Threshold, above-mentioned classification portion is degraded, from without by above-mentioned irregular access Targeted integration enters above-mentioned access information.
Optimization portion is accessed in addition, for example preferably also having, the access optimization portion is based in above-mentioned display picture Above-mentioned access information after each access target corresponding to projects, generation optimization.
In the case of the example, such as, by performing above-mentioned optimization processing by above-mentioned Optimization Dept., above-mentioned integration portion is secondary again Access information into after above-mentioned optimization, wherein, above-mentioned optimization processing is based on each corresponding to projects in above-mentioned display picture Access target and above-mentioned upgrade status access target.
In addition, in the case of the example, visit of above-mentioned first data acquiring section based on the above-mentioned optimization generated again Information is asked, data acquisition is performed from above-mentioned each access target, and storage processing is performed to above-mentioned interior magazine.Preferably also With project display control unit, the project display control unit is obtained using above-mentioned first data acquiring section, above-mentioned projects pair The data for each access target answered, the display content to projects in above-mentioned display picture is controlled.
Above-mentioned project information storage unit for example can also be regarded as equivalent to bulleted list 51.
Above-mentioned first data capture unit for example can also be regarded as equivalent to above-mentioned circulation reading part 157, can also regard as quite In optimum instruction list 54 and communication processing section 63.
Above-mentioned logical process enforcement division can regard as such as can also regard as equivalent to above-mentioned logical process portion 64, also equivalent to Above-mentioned logic control portion 151 and external storage are with reference to receiving portion 152.
Above-mentioned classification portion for example can also regard as equivalent to above-mentioned classification judging part 155.
Above-mentioned integration portion for example can also regard as equivalent to above-mentioned integration portion 156.
Or, above-mentioned classification portion and above-mentioned integration portion can also regard as judges processing unit 70 equivalent to above-mentioned classification.
Above-mentioned second data acquiring section for example can also be regarded as equivalent to said external holder reference receiving portion 152 and lead to Believe processing unit 158.Or, above-mentioned second data acquiring section can also regard above-mentioned instruction list 53 and communication processing section 63 as.
Above-mentioned access optimization portion for example can also regard as equivalent to above-mentioned optimum instruction generating unit 69.
Associated access target is for example shown as project, there is No. D102 and No. D105.In this case, above-mentioned optimal finger Make in the optimum instruction list 54 that generating unit 69 is generated, access target is " No. D102~No. D105 ".Thus, in once communicating From the unified storage data for obtaining " No. D102~No. D105 " of connection equipment 4.This is prior art as described above in itself.
Here, the irregular access target being for example associated as logical process, for example, No. D108.The situation of the example Under, in the past, regularly unify to obtain the storage data of " No. D102~No. D105 ".Also, along with logical process, aperiodically (sudden) the storage data for obtaining No. D108.Thus, in the past, if to No. D108 processing that frequently conducts interviews, to " No. D102 ~No. D105 " access process impact, there is the slack-off situation of the action of refresh process and the side of logical process two.
In this regard, in this method, in the case of above-mentioned irregular access target upgrading, in above-mentioned optimum instruction generating unit 69 In the optimum instruction list 54 of generation, access target is " No. D102~No. D108 ".Thus, from connection equipment in once communicating The 4 unified storage data for obtaining " No. D102~No. D108 ".Thus, the problem of eliminating above-mentioned conventional.
In addition, in the past, it is necessary to by one by one for example in access list 53 when every time to above-mentioned No. D108 generation access process Storage instructs 130 to entrust access process, is carried out before data are obtained standby.In this regard, in this method, due to along with above-mentioned fixed The refresh process of phase reads the data for being stored in common storage 55, therefore improves the associated processing effect of logical process Rate.

Claims (8)

1. a kind of programable display,
It is with being connected the programable display that equipment is connected, it is characterised in that including:
Project information storage element, the project information storage element is to representing that the access information of each access target is stored, institute State projects that each access target is corresponded respectively in display picture;
First data acquisition unit, first data acquisition unit is regularly based on the access information, from the connection equipment Data are obtained at interior each access target, are stored the data in interior magazine;
Logical process execution unit, while execution logic is handled, is generated for accessing mesh along with the logical process In the case that mark is the access process of irregular access target, the logical process execution unit judges that the irregular access target is It is no to be integrated into the access information, in the case where the irregular access target has been integrated into the access information, from The interior magazine obtains data corresponding with the irregular access target;
Access frequency is more than defined first threshold described indefinite at intervals of set time by stage unit, the stage unit Phase access target is adjusted to upgrade status access target;And
Irregular access target as the upgrade status access target is integrated into the visit by integral unit, the integral unit Ask information.
2. programable display as claimed in claim 1, it is characterised in that
Also there is the second data acquisition unit, second data acquisition unit is judged as described in the logical process execution unit In the case that irregular access target is not integrated into the access information, the irregular access mesh out of described connection equipment Data are obtained at mark.
3. programable display as claimed in claim 1, it is characterised in that
In the case where the arbitrary more than one irregular access target has been integrated into the access information, described the One data acquisition unit obtains data also at these irregular access targets, stores the data to the interior magazine.
4. programable display as claimed in claim 1, it is characterised in that
No matter whether the irregular access target has been integrated into the access information, the logical process execution unit exists It is all pair associated with the irregular access target when producing the access process for the arbitrary irregular access target every time The access frequency be updated.
5. programable display as claimed in claim 1, it is characterised in that
It is not up in the access frequency relevant with the irregular access target as the upgrade status access target In the case of defined Second Threshold, the stage unit is degraded, from without the irregular access target is integrated into Access information.
6. programable display as claimed in claim 1, it is characterised in that
Also there is Access Optimization unit, the Access Optimization unit is based on corresponding with projects difference in the display picture each Access target, the access information after generation optimization,
By performing optimization processing by the Access Optimization unit, the integral unit generates the letter of the access after the optimization again Breath, wherein, the optimization processing based on the corresponding each access target of projects difference and the liter in the display picture Level conditional access target is carried out,
Access information after the optimization that first data acquisition unit is generated based on this again, obtains the data and simultaneously will The data storage is in the interior magazine.
7. programable display as claimed in claim 1, it is characterised in that
Also there is project display control unit, the project display control unit is utilized to be obtained simultaneously by first data acquisition unit And the data of each access target corresponding with described projects difference, the display content to projects in the display picture enters Row control.
8. programable display as claimed in claim 1, it is characterised in that
Each access target is the arbitrary address in any storage device in any connection equipment.
CN201380069680.6A 2013-03-15 2013-03-15 Programable display Active CN104937508B (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2013/057507 WO2014141476A1 (en) 2013-03-15 2013-03-15 Programmable display unit and program for same

Publications (2)

Publication Number Publication Date
CN104937508A CN104937508A (en) 2015-09-23
CN104937508B true CN104937508B (en) 2017-10-13

Family

ID=51536170

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201380069680.6A Active CN104937508B (en) 2013-03-15 2013-03-15 Programable display

Country Status (3)

Country Link
JP (1) JP5931276B2 (en)
CN (1) CN104937508B (en)
WO (1) WO2014141476A1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6627571B2 (en) 2016-02-26 2020-01-08 オムロン株式会社 Programmable controller, programmable controller control method, and programmable controller control program
CN113661456B (en) * 2019-04-11 2022-12-09 三菱电机株式会社 Data creation device, data transfer method, and computer-readable recording medium

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009054056A (en) * 2007-08-28 2009-03-12 Hakko Denki Kk Method for optimizing communication command, program, and programmable display unit
JP2010128612A (en) * 2008-11-25 2010-06-10 Panasonic Electric Works Co Ltd Sequence control system
JP2012128719A (en) * 2010-12-16 2012-07-05 Digital Electronics Corp Programmable display and data display program
CN102713774A (en) * 2010-01-20 2012-10-03 三菱电机株式会社 Programmable controller system and development system

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002099498A (en) * 2000-09-25 2002-04-05 Mitsubishi Electric Corp Program performance device and program development support device
JP2009054055A (en) * 2007-08-28 2009-03-12 Hakko Denki Kk Method for adjusting length of data to be read and programmable indicator

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009054056A (en) * 2007-08-28 2009-03-12 Hakko Denki Kk Method for optimizing communication command, program, and programmable display unit
JP2010128612A (en) * 2008-11-25 2010-06-10 Panasonic Electric Works Co Ltd Sequence control system
CN102713774A (en) * 2010-01-20 2012-10-03 三菱电机株式会社 Programmable controller system and development system
JP2012128719A (en) * 2010-12-16 2012-07-05 Digital Electronics Corp Programmable display and data display program

Also Published As

Publication number Publication date
WO2014141476A1 (en) 2014-09-18
CN104937508A (en) 2015-09-23
JPWO2014141476A1 (en) 2017-02-16
JP5931276B2 (en) 2016-06-08

Similar Documents

Publication Publication Date Title
CN101398686B (en) Adaptive industrial systems via embedded historian data
US8059092B2 (en) User interface designing apparatus
CN101241354B (en) Event triggered data capture via embedded historians
KR101675409B1 (en) Methods, systems and devices for performing incremental updates of partial databases
CN100498800C (en) Layout-driven, area-constrained design optimization
CN109800531A (en) A kind of twin model consistency keeping method of dynamoelectric equipment number
CN110009171A (en) Customer behavior modeling method, apparatus, equipment and computer readable storage medium
CN109840206A (en) Data test method, apparatus, terminal and storage medium
CN105260696A (en) Self-learning method and device of fingerprint template
CN101641678B (en) Source program review program, source program review method and source program review device
KR101650686B1 (en) Common parameter interface-generating program and parameter readout program
US20120271435A1 (en) Library synchronization between definitions and instances
JPH0658678B2 (en) Process and apparatus for synthesizing circuit designs
CN104932875B (en) Image processing apparatus, management system and management method
CN104937508B (en) Programable display
CN106708912A (en) Useless file identification method and device, useless file management method and device and terminal
Bülbül et al. Exact and heuristic approaches for joint maintenance and spare parts planning
CN109800887B (en) Generation method and device of prediction process model, storage medium and electronic equipment
CN110990256B (en) Open source code detection method, device and computer readable storage medium
CN112348403B (en) Wind control model construction method and device and electronic equipment
US20120277885A1 (en) Human machine interface device and interface integration method thereof
CN114357337A (en) Cache management method, device, equipment and storage medium
CN107179924A (en) Application program update method and more new system
US20070168921A1 (en) Method for automatic recovery of uml model requirements and updating thereof
CN112817525A (en) Method and device for predicting reliability grade of flash memory chip and storage medium

Legal Events

Date Code Title Description
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant