CN104930683B CN201510323588.9A CN201510323588A CN104930683B CN 104930683 B CN104930683 B CN 104930683B CN 201510323588 A CN201510323588 A CN 201510323588A CN 104930683 B CN104930683 B CN 104930683B
Authority
CN
China
Prior art keywords
conditioning
guiding device
air
leak guiding
drainpipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510323588.9A
Other languages
Chinese (zh)
Other versions
CN104930683A (en
Inventor
许瑞珩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Shanghai Electric Power Co Ltd
Original Assignee
State Grid Shanghai Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Shanghai Electric Power Co Ltd filed Critical State Grid Shanghai Electric Power Co Ltd
Priority to CN201510323588.9A priority Critical patent/CN104930683B/en
Publication of CN104930683A publication Critical patent/CN104930683A/en
Application granted granted Critical
Publication of CN104930683B publication Critical patent/CN104930683B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24FAIR-CONDITIONING; AIR-HUMIDIFICATION; VENTILATION; USE OF AIR CURRENTS FOR SCREENING
    • F24F13/00Details common to, or for air-conditioning, air-humidification, ventilation or use of air currents for screening
    • F24F13/22Means for preventing condensation or evacuating condensate
    • F24F13/222Means for preventing condensation or evacuating condensate for evacuating condensate

Abstract

The present invention relates to a kind of universal leak guiding device for substation's air-conditioning, the leak guiding device is installed on the lower section of air-conditioning, for opening box-structure, including diversion trench and the drainpipe with being communicated inside diversion trench, one end of the drainpipe is connected with diversion trench, the other end leads to outdoor collection water spot, the diversion trench is the drain groove for being opened in opening box structure case bottom, using the drainpipe as line of demarcation, the diversion trench is divided into the first drainage channel and the second drainage channel, the groove bottom of first drainage channel and the second drainage channel is gradually to the inclined slope surface of drainpipe, water in first drainage channel and the second drainage channel enters drainpipe along different directions, the opening up face air-conditioning of leak guiding device is set.It can avoid because leaking air-conditioning causes equipment security risk occur, lifting O&M is horizontal, improves power grid power supply reliability and security, solves the problems, such as because leaking air-conditioning ponding causes power grid power supply reliability poor.

Description

A kind of universal leak guiding device for substation's air-conditioning
Technical field
The present invention relates to substation's technical field, particular for the treatment technology of the water leakage situation of substation's air-conditioning, specifically It is a kind of universal leak guiding device for substation's air-conditioning.
Background technology
Electric company where applicant is responsible for 110 kilovolts of transformer and distribution power stations 15 altogether, and 35 kilovolts of transformer and distribution power stations 35 are all kinds of K stands 271.So far, newly put into operation statistics 2,012 110 kilovolts of transformer and distribution power stations about 2 every year, and 35 kilovolts of transformer and distribution power stations about 3 are all kinds of K stands about 36.In future, since 35 kv substations will not include planning, replaced by 110 kv substations, so 110 kilovolts of changes The annual increment of power distribution station will increase, it is contemplated that and applicant electric company location is currently under high-speed development period, and 35,000 The annual increment of volt transformer and distribution power station may maintain an equal level or slightly increase, and the annual increment at all kinds of K stations will increase.
There are a large amount of air-conditioning equipment long-time high loaded processes in the annual administrative station of high temperature period, in fact it could happen that leaking air-conditioning thing Part occurs, and causes interior excess surface water of standing, and under serious situation, can cause stand interior ground or wall leakage, influences equipment safety fortune OK, security risk is caused.Central station will arrange substantial amounts of manpower to check the air-conditioning equipment of administrative substation every year, in advance Prevent and handle the ponding as caused by air-conditioning and leak event.
Transformer and distribution power station air-conditioning equipment water leakage situation is investigated and analysed at present:, center in 2013 in 2012 in 2011 are chosen respectively Stand administration substation and power distribution station make an inspection tour record, to transformer and distribution power station leaking air-conditioning situation carry out statistical analysis.
1 transformer and distribution power station leaking air-conditioning situation statistical form of table
Analyzed from above table:By analyzing inspection situation of the transformation center station over the years to administrative substation's air-conditioning, find Leaking air-conditioning proportion accounts for 7% or so of sum.For this phenomenon, central station consumes a large amount of human and material resources, financial resources to air-conditioning Hidden danger caused by leak and its energy is investigated and repaired, but leak ratio is still high, and effect is preferable not to the utmost.
The content of the invention
The object of the present invention is to provide a kind of universal leak guiding device for substation's air-conditioning, of the invention is general Type leaking air-conditioning guiding device, can avoid because leaking air-conditioning causes equipment security risk occur, lifting O&M is horizontal, improves electricity Net power supply reliability and security, to solve, because leaking air-conditioning causes the security risk of equipment, failure and electricity to be set so as to trigger The problem of net failure.
To achieve the above object, the solution of the present invention is:A kind of universal leak guiding device for substation's air-conditioning, The leak guiding device is installed on the lower section of air-conditioning, for opening box-structure, leak guiding device include diversion trench With the drainpipe with being communicated inside the diversion trench, one end of the drainpipe is connected with diversion trench, and the other end leads to outdoor collection Water spot, the diversion trench are the drain groove for being opened in opening box inside configuration bottom periphery, using the drainpipe as Line of demarcation, is divided into the first drainage channel and the second drainage channel, first drainage channel and second row by the diversion trench The groove bottom of aquaporin is gradually to inclined slope surface at drainpipe, in first drainage channel and the second drainage channel Water enter drainpipe along different directions, the opening up face air-conditioning of leak guiding device of the opening box-structure is set.
Universal leak guiding device according to the present invention for substation's air-conditioning, it is described to hanging air conditioner Leak guiding device is fixed on wall by iron chains, the bottom interval setpoint distance peace of leak guiding device and hanging air conditioner Dress.
Universal leak guiding device according to the present invention for substation's air-conditioning, vertical air-conditioning are described Leak guiding device is placed on the ground, and vertical air conditioner is placed in leak guiding device.
Universal leak guiding device according to the present invention for substation's air-conditioning, the leak guiding device Using stainless steel material.
Universal leak guiding device according to the present invention for substation's air-conditioning, the drainpipe pass through wall Water in diversion trench, is discharged to the collection water spot of outdoor by the through hole opened up on body.
Universal leak guiding device according to the present invention for substation's air-conditioning, the drain groove it is transversal Face is isosceles trapezoid.
Universal leak guiding device according to the present invention for substation's air-conditioning, the top of the drain groove Width is 90mm~100mm, and bottom width is 40~50mm, and groove depth is 40mm~80mm.
Universal leak guiding device according to the present invention for substation's air-conditioning, the gradient of the slope surface For 15 °~20 °.
Universal leak guiding device according to the present invention for substation's air-conditioning, vertical air-conditioning are described The endurance of leak guiding device is 500KG weight.
The beneficial effect that the present invention reaches:The present invention, can be effective by setting universal leak guiding device to air-conditioning Leaking air-conditioning is all discharged, avoid reducing the peace of power grid power supply because leaking air-conditioning causes the generation of equipment and electric network fault Full hidden danger, improves O&M level, improves the reliability of power grid power supply.It is cheap meanwhile structure of the invention is simple, It is easy to use.
Brief description of the drawings
Fig. 1 is the sectional view of leak guiding device of the present invention;
Fig. 2 is the top view of one leak guiding device of the embodiment of the present invention;
Fig. 3 is the front view of one leak guiding device of the embodiment of the present invention;
Fig. 4 is the side view of one leak guiding device of the embodiment of the present invention;
Fig. 5 is the top view of two leak guiding device of the embodiment of the present invention;
Fig. 6 is the front view of two leak guiding device of the embodiment of the present invention;
Fig. 7 is the side view of two leak guiding device of the embodiment of the present invention.
Embodiment
The invention will now be described in further detail with reference to the accompanying drawings.
As shown in Figure 1, leak guiding device of the present invention is installed on the lower section of air-conditioning, for opening box-structure, institute Leak guiding device include diversion trench and the drainpipe 2 with being communicated inside the diversion trench, one end of the drainpipe is with leading Chute connects, and the other end leads to outdoor collection water spot, and the diversion trench is by being opened in the 4 of opening box leak guiding device bottom Section drain groove 1-1,1-2,1-3 and 1-4 composition, is line of demarcation with the drainpipe 2, the diversion trench is divided into first row The groove bottom of aquaporin and the second drainage channel, first drainage channel and the second drainage channel is gradually to drainpipe Locate inclined slope surface, the water in first drainage channel and the second drainage channel enters drainpipe 2 along different directions, described The opening up face air-conditioning of leak guiding device of opening box-structure is set, the upper shed sectional area of the leak guiding device Accumulated more than air-conditioning bottom section.
In Fig. 1, the left side composition first row aquaporin of 1-4,1-1 and 1-2, the right side composition second row of 1-4,1-3 and 1-2 Aquaporin, when leaking air-conditioning enters in diversion trench, water is by the first drainage channel and the second drainage channel of diversion trench, along up time Pin counterclockwise flows, and into diversion pipe, is discharged the leak of air-conditioning by diversion pipe.
Embodiment one:
As shown in figs. 2 to 4, for hanging air conditioner, leak guiding device is arranged on the underface of air-conditioning, and is consolidated by iron chains It is scheduled on wall, the bottom interval setpoint distance installation of leak guiding device and hanging air conditioner.
To avoid rust corrosion, the diversion trench of the present embodiment uses stainless steel material, and in guiding device position Through hole is opened up on wall, drainpipe is passed through to the through hole opened up on wall, the water in diversion trench is discharged to room by drainpipe Outer collection water spot.
The cross section of drain groove described in the present embodiment is isosceles trapezoid.The top width of the drain groove is 90mm ~100mm, bottom width are 40~50mm, and groove depth is 40mm~80mm.It is 15 °~20 ° that the slope surface, which tilts,.
Embodiment two:
The present embodiment two and embodiment one difference lies in:As shown in Fig. 5~7, for vertical air conditioner, leak guiding device It is positioned on ground, vertical air conditioner is placed in leak guiding device, and the endurance of leak guiding device is 500KG weight, can Meet the long-term weight for placing vertical air conditioner,
After leak guiding device using the present invention, in the air-conditioning high loaded process phase of applicant unit one belongs to, choose 86 air-conditionings observe and record emphatically leak and the ponding situation of sample air-conditioning during daily tour, pass through as observation sample After crossing detailed record, obtain a result such as table 2 below:
2 air-conditioning sample statistics situation of table
Timing statistics Air-conditioning sample (platform) Leak number (platform) Cause ponding (secondary)
July 86 3 0
August 86 2 0
As can be seen from Table 2, in observation interval, due to hot weather, air-conditioning high loaded process, shares 5 air-conditionings There occurs water leakage situation.With without guiding device before compared with, during tour, do not find that ponding caused by leaking air-conditioning oozes again Water phenomenon, has reached target, positive effect, so as to improve equipment operational reliability, reduces the possibility of security risk Property.
The present invention effectively can all be discharged leaking air-conditioning by setting universal leak guiding device to air-conditioning, Avoid, because leaking air-conditioning causes the generation of equipment and electric network fault, reducing the security risk of power grid power supply, improve O&M level, Improve the reliability of power grid power supply.It is cheap meanwhile structure of the invention is simple, it is easy to use.

Claims (8)

  1. A kind of 1. universal leak guiding device for substation's air-conditioning, it is characterised in that the leak guiding device peace Mounted in the lower section of air-conditioning, for opening box-structure, the leak guiding device include diversion trench and with inside the diversion trench The drainpipe communicated, one end of the drainpipe are connected with diversion trench, and the other end leads to outdoor collection water spot;The diversion trench is The drain groove on opening box inside configuration bottom periphery is opened in, the top width of the drain groove is 90mm~100mm, Bottom width is 40~50mm, and groove depth is 40mm~80mm;
    Using the drainpipe as line of demarcation, the diversion trench is divided into the first drainage channel and the second drainage channel, it is described The groove bottom of first drainage channel and the second drainage channel is gradually to lead to the inclined slope surface of drainpipe, first draining Water in road and the second drainage channel enters drainpipe, the leak guiding device opening of the opening box-structure along different directions Face air-conditioning is set upward.
  2. 2. the universal leak guiding device according to claim 1 for substation's air-conditioning, it is characterised in that to hanging Air-conditioning, the leak guiding device are fixed on wall by iron chains, the bottom interval of leak guiding device and hanging air conditioner Setpoint distance is installed.
  3. 3. the universal leak guiding device according to claim 1 for substation's air-conditioning, it is characterised in that vertical Air-conditioning, the leak guiding device are placed on the ground, and vertical air conditioner is placed in leak guiding device.
  4. 4. the universal leak guiding device according to claim 1 for substation's air-conditioning, it is characterised in that described Leak guiding device uses stainless steel material.
  5. 5. the universal leak guiding device according to claim 1 for substation's air-conditioning, it is characterised in that described Drainpipe passes through the through hole opened up on wall, and the water in diversion trench is discharged to the collection water spot of outdoor.
  6. 6. the universal leak guiding device according to claim 1 for substation's air-conditioning, it is characterised in that the row The cross section of water groove is isosceles trapezoid.
  7. 7. the universal leak guiding device according to claim 1 for substation's air-conditioning, it is characterised in that described The inclination of slope surface is 15 °~20 °.
  8. 8. the universal leak guiding device according to claim 3 for substation's air-conditioning, it is characterised in that vertical Air-conditioning, the endurance of the leak guiding device is 500KG weight.
CN201510323588.9A 2015-06-12 2015-06-12 A kind of universal leak guiding device for substation's air-conditioning Active CN104930683B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510323588.9A CN104930683B (en) 2015-06-12 2015-06-12 A kind of universal leak guiding device for substation's air-conditioning

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510323588.9A CN104930683B (en) 2015-06-12 2015-06-12 A kind of universal leak guiding device for substation's air-conditioning

Publications (2)

Publication Number Publication Date
CN104930683A CN104930683A (en) 2015-09-23
CN104930683B true CN104930683B (en) 2018-05-08

Family

ID=54117964

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510323588.9A Active CN104930683B (en) 2015-06-12 2015-06-12 A kind of universal leak guiding device for substation's air-conditioning

Country Status (1)

Country Link
CN (1) CN104930683B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111724572A (en) * 2020-05-20 2020-09-29 青岛海尔智能技术研发有限公司 Water seepage early warning management method, equipment, device, computer equipment and storage medium

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0278835A (en) * 1988-09-16 1990-03-19 Hitachi Ltd Air conditioner
JPH02161235A (en) * 1988-12-14 1990-06-21 Mitsubishi Electric Corp Base frame for air conditioner
CN201909418U (en) * 2010-12-13 2011-07-27 海信(山东)空调有限公司 Water receiving plate and air-conditioner adopting same
CN201973852U (en) * 2011-02-25 2011-09-14 山东欧锴空调科技有限公司 Fan coil with integral large water-containing tray
CN202166131U (en) * 2011-07-29 2012-03-14 珠海格力电器股份有限公司 Air-conditioning device
CN203454297U (en) * 2013-08-29 2014-02-26 深圳麦克维尔空调有限公司 Drainage assembly for outdoor unit of air conditioner

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0278835A (en) * 1988-09-16 1990-03-19 Hitachi Ltd Air conditioner
JPH02161235A (en) * 1988-12-14 1990-06-21 Mitsubishi Electric Corp Base frame for air conditioner
CN201909418U (en) * 2010-12-13 2011-07-27 海信(山东)空调有限公司 Water receiving plate and air-conditioner adopting same
CN201973852U (en) * 2011-02-25 2011-09-14 山东欧锴空调科技有限公司 Fan coil with integral large water-containing tray
CN202166131U (en) * 2011-07-29 2012-03-14 珠海格力电器股份有限公司 Air-conditioning device
CN203454297U (en) * 2013-08-29 2014-02-26 深圳麦克维尔空调有限公司 Drainage assembly for outdoor unit of air conditioner

Also Published As

Publication number Publication date
CN104930683A (en) 2015-09-23

Similar Documents

Publication Publication Date Title
CN104930683B (en) A kind of universal leak guiding device for substation's air-conditioning
CN109064057A (en) A kind of methods of risk assessment of distribution line lightning parameter relative value
CN201883446U (en) Stone pit foundation structure for main transformer
CN103219727A (en) Divisional power grid structure dynamic adjustment method based on actual measurement of power management unit (PMU)
CN202793063U (en) Novel energy-saving and efficient cooling tower
CN104763178A (en) Main power building of thermal power plant
DE202018102630U1 (en) Water supply system for extinguishing work
CN210004133U (en) hydrophobic recovery device for low-pressure heat supply steam pipeline of power plant
CN204808407U (en) Gas storage storehouse surface equipment's risk assessment system
He et al. The Energy efficiency diagnosis research of regional power grid loss reduction
CN209851227U (en) Cement constant temperature and humidity curing box
CN207036642U (en) Digging-free formula grounding net of transformer substation extent of corrosion monitoring device based on humidity change
CN205653881U (en) Sphere pressed sheet stainless steel water tank pump house integration pump station
CN209344729U (en) A kind of steady type down conductor buries an anticorrosive casing pipe
CN202747460U (en) Manifold
CN202930155U (en) Oil discharge device for oil-immersed type distribution transformers
CN207144002U (en) A kind of inspection shaft of heat distribution pipe network
CN206575071U (en) A kind of tree-like door frame outlet structure of 330kV open airs GIS power distribution equipments
CN206211351U (en) A kind of ventilated bin switching station
CN207196067U (en) One kind is applied to the hydrophobic collection device of reheaing steam pipe
CN204112791U (en) The optimum organization structure of thermal power plant's steam turbine building, cooling tower and power distribution equipment
CN205320502U (en) Use system of checking winds and fixing drifting sand of junked tire structure
CN210145371U (en) Valve well structure for foam spray system
CN204769519U (en) Oil storage hole stone sieving mechanism
CN205002667U (en) Circulating water supply system of high -order cooling tower

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant