CN104878866A - Ceiling hanging method and ceiling hanging system for project steel structure - Google Patents

Ceiling hanging method and ceiling hanging system for project steel structure Download PDF

Info

Publication number
CN104878866A
CN104878866A CN201510155491.1A CN201510155491A CN104878866A CN 104878866 A CN104878866 A CN 104878866A CN 201510155491 A CN201510155491 A CN 201510155491A CN 104878866 A CN104878866 A CN 104878866A
Authority
CN
China
Prior art keywords
ceiling
mounting seat
installation
keel structure
steel work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510155491.1A
Other languages
Chinese (zh)
Inventor
王新武
李凤霞
布欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Luoyang Institute of Science and Technology
Original Assignee
Luoyang Institute of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Luoyang Institute of Science and Technology filed Critical Luoyang Institute of Science and Technology
Priority to CN201510155491.1A priority Critical patent/CN104878866A/en
Publication of CN104878866A publication Critical patent/CN104878866A/en
Pending legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses a ceiling hanging method for a project steel structure. The ceiling hanging method includes the steps of S1, setting out to position; S2, mounting an adjustable mounting base on a net-structure lower chord ball joint; S3, mounting a hanging rod; S4, mounting a three-dimensional adjustable hanging disk; S5, mounting a main keel structure and an auxiliary keel; S6, mounting a face plate. A ceiling hanging system for the project steel structure has the advantages of simplicity in mounting, light weight, no welding, high durability, good economy and the like, thereby being great in innovativeness and high in popularization value and market competitiveness.

Description

A kind of ceiling method for engineering steel work and system
Technical field
The present invention relates to large public building spatial steel structure roof suspended ceiling technical field, particularly a kind of ceiling method for engineering steel work and system.
Background technology
In the recent decade, along with the quickening of China's expanding economy and urbanization process, space structures application fast development, has been widely used in the communal facilitys such as the Large-sized Communication of China, culture, physical culture, exhibitions at present.
Spatial complex roof structure, generally for manifesting the beautiful and cost saving of self structure, in the past all lessly carries out furred ceiling.But along with the expansion of economy and cultural construction demand, there is space curved surface rack roofing structure furred ceiling in domestic beginning in recent years.
Spatial steel structure roof suspended ceiling needs to solve ceiling system and adapts to the complex-curved spatial variations of roofing, adapts to rack stressed (wind load, snow load, Forces etc.) distortion and digestion Construction of The Grids error problem, needs to solve the difficult problems such as ceiling system construction and installation, measurement, control errors.
Because also there are not system research in large space elastic construction furred ceiling and Its Relevant Technology Standards in China, ceiling structure mostly or transform on the ceiling system basis of flat concrete structured base layer.In prior art, ceiling structure all will connect with lower edge ball bonding, there is potential safety hazard, do not meet green construction requirement, existing ceiling system complex structure, making, installation, maintenance inconvenience, keel and aluminum deck system can not be docked with the smallpox standard series of existing market maturation, and need special manufacture, cost is high.
In view of this, need to provide a kind of and there is the ceiling system that structure is reliable, install simple, lightweight, welding, good endurance and economic dispatch advantage.
Summary of the invention
In view of above-mentioned the deficiencies in the prior art part, the object of the present invention is to provide a kind of ceiling method for engineering steel work and system, all to connect with the ball bonding of rack lower edge to solve ceiling structure of the prior art, do not meet green construction requirement, system architecture is complicated, making, installation, maintenance inconvenience; Keel structure and aluminum deck system can not be docked with the smallpox standard series of existing market maturation, need special manufacture, high in cost of production problem.
In order to achieve the above object, this invention takes following technical scheme:
For a ceiling system for engineering steel work, comprise the rack chop be connected with large space curved surface steel structure roofing, also comprise:
Installation of ceiling plate, it is arranged on below rack chop;
Adjustable mounting seat, it comprises symmetrical two buckles, the first gripper shoe be arranged in parallel and the second gripper shoe, two fixtures further; Described fixture withstands installation of ceiling plate through the first gripper shoe, and described buckle is fastened on the two ends of installation of ceiling plate;
Connect the three-dimensional adjustable lifting sabot of adjustable mounting seat and channel, adjustable for the level realizing channel;
Channel, it comprises the first syndeton, main keel structure and the rider keel structure that connect successively further;
Panel, it is arranged on the below of described channel.
The described ceiling system for engineering steel work, wherein, described three-dimensional adjustable lifting sabot comprises further: the suspension rod connected successively, upper press cover, roating sphere and the connection bluff piece with some connection pawls; Described suspension rod is connected with adjustable mounting seat, and described connection bluff piece is connected with channel.
The described ceiling system for engineering steel work, wherein, described suspension rod is screw thread suspension rod, and it also comprises installation spring washer under the nut for being connected with adjustable mounting seat by nut.
The described ceiling system for engineering steel work, wherein, the number of described connection bluff piece is 4, and in the same plane, and adjacent two angles connected between bluff piece are 90 degree.
The described ceiling system for engineering steel work, wherein, described main keel structure is 100C type keel, and it is arranged in the first syndeton by securing member; Described rider keel structure is 40C type keel, and it is arranged on main keel structure by hanging piece, and fastening with securing member.
The described ceiling system for engineering steel work, wherein, described connection bluff piece is provided with bolt hole that can be hinged with the first syndeton.
The described ceiling system for engineering steel work, wherein, described connection bluff piece is provided with the bolt hole that Liftable Flange joint parts are hinged.
The described ceiling system for engineering steel work, wherein, described panel is aluminium alloy panel.
The described ceiling system for engineering steel work, wherein, also comprises the lower chord of a connection space rack and channel, when it receives position, limit for being in when ceiling system, plays fixed ceilings keel.
For a ceiling method for engineering steel work, comprise the following steps:
S1, unwrapping wire is located;
S2, rack lower edge ball node installs adjustable mounting seat;
S3, installs suspension rod;
S4, installs three-dimensional adjustable lifting sabot;
S5, installs main keel structure and rider keel structure;
S6, installation panel.
Ceiling method for engineering steel work provided by the invention and system, described ceiling system comprises installation of ceiling plate, adjustable mounting seat, three-dimensional adjustable lifting sabot, channel and panel.Wherein, described adjustable mounting seat is connected installation of ceiling plate by buckle with fixture, without the need to welding, thus change traditional ceiling method connect with the ball bonding of rack lower edge, avoid the potential safety hazard that overhead welding brings, realize green construction, also there is the effect of the construction error of three-dimensional adjustable digestion rack lower edge ball.Meanwhile, three-dimensional adjustable lifting sabot can be rotated by any direction, and main keel structure level is adjustable, can adapt to the change of spatial steel structure roofing curved surface and absorption mesh shelf structure in the distortion of quiet, Dynamic Loading generation and structure installment error.Ceiling system of the present invention, have structure reliable, simple, lightweight, welding, good endurance and economic dispatch advantage are installed, there is larger novelty and very strong promotional value and the market competitiveness.
Accompanying drawing explanation
Fig. 1 is the flow chart of the ceiling system method for engineering steel work of the present invention.
Fig. 2 is the schematic diagram of the ceiling system for engineering steel work of the embodiment of the present invention.
Fig. 3 is the structural representation of the adjustable mounting seat of the embodiment of the present invention.
Fig. 4 is the cross-sectional schematic of the adjustable mounting seat side of the embodiment of the present invention.
Fig. 5 is the decomposing schematic representation of the three-dimensional adjustable lifting sabot of present pre-ferred embodiments.
Fig. 6 is the lateral view of the three-dimensional adjustable lifting sabot of present pre-ferred embodiments.
Fig. 7 is the top view of the three-dimensional adjustable lifting sabot of present pre-ferred embodiments.
Fig. 8 is the schematic diagram of the suspension rod of present pre-ferred embodiments.
Detailed description of the invention
The invention provides a kind of ceiling method for engineering steel work and system.For making object of the present invention, technical scheme and effect clearly, clearly, referring to accompanying drawing examples, the present invention is described in more detail.Should be appreciated that specific embodiment described herein only in order to explain the present invention, be not intended to limit the present invention.
Refer to Fig. 2, Fig. 2 is the schematic diagram of the ceiling system for engineering steel work of the embodiment of the present invention.As shown in the figure, the described ceiling system for engineering steel work comprises sphere structure 100, steel ball column 200, adjustable mounting seat 300, three-dimensional adjustable lifting sabot 400, channel 500 and panel 600.Described sphere structure 100, steel ball column 200 are also referred to as rack chop, and it is connected with large space curved surface steel structure roofing, and its design and construction should make it keep enough rigidity, under meeting normal service condition, there will not be permanent deformation.Described steel ball column 200 connects the soffit of (generally taking welding manner) sphere structure 100, and it has been horizontally disposed with an installation of ceiling plate 210 bottom.Described adjustable mounting seat 300 connects steel ball column 200 and three-dimensional adjustable lifting sabot 400, described three-dimensional adjustable lifting sabot 400 is adjustable for the level realizing main keel structure, can adapt to the change of spatial steel structure roofing curved surface and absorption mesh shelf structure in the distortion of quiet, Dynamic Loading generation and structure installment error, described channel 500 is connected with three-dimensional adjustable lifting sabot 400 and panel 600.
Particularly, described adjustable mounting seat 300 is crucial part of the present invention, refers to Fig. 3, and Fig. 3 is the structural representation of the adjustable mounting seat of the embodiment of the present invention.As shown in the figure, described adjustable mounting seat comprises symmetrical two buckles 310, the first gripper shoe 320 be arranged in parallel and the second gripper shoe 330, two fixtures 340 further; Described fixture 340 props up installation of ceiling plate 210 through the first gripper shoe 330, and described buckle 310 is fastened on the two ends of installation of ceiling plate 210.So, by the acting in conjunction of fixture 340 and buckle 310, adjustable mounting seat is firmly fixed on below installation of ceiling plate, without the need to welding, thus change traditional ceiling method connect with the ball bonding of rack lower edge, avoid the potential safety hazard that overhead welding brings, realize green construction.In embodiments of the present invention, described fixture 340 is screw, and it withstands on installation of ceiling plate 210 times through the first gripper shoe 330.Thus ensure that adjustable mounting seat can not be rocked, serve fixation.
Conveniently understanding, is the cross-sectional schematic of the adjustable mounting seat side of the embodiment of the present invention please continue to refer to Fig. 4, Fig. 4.As shown in the figure, the fixture 340 of described adjustable mounting seat withstands on installation of ceiling plate 210 through the first gripper shoe 330, to the power F1 in the individual direction vertically upward of one; In addition, described buckle 310 is fastened on above installation of ceiling plate 210, also an one reaction force is given) to the individual power F2(installation of ceiling plate vertically downward of one, by coefficient like this effect, adjustable mounting seat is combined with installation of ceiling plate 210 firmly, can not produce and rock.
See also Fig. 5, Fig. 6 and Fig. 7, be respectively the decomposing schematic representation of the three-dimensional adjustable lifting sabot of the embodiment of the present invention, lateral view and top view.As shown in Figure 5, described three-dimensional adjustable lifting sabot comprises suspension rod 40, upper press cover 410, roating sphere 420, comprise several connects pawl 431(in embodiments of the present invention, and the number of described link 431 is 4) connection bluff piece 430.Roating sphere 420 is fixed on connection bluff piece 430 by fixture by described upper press cover, as shown in Figure 5.In embodiments of the present invention, by suspension rod 40(, it is upward through the below that whole three-dimensional adjustable lifting sabot body is fixed on adjustable mounting seat by the second gripper shoe) successively through upper press cover 410, roating sphere 420 and connection bluff piece 430, and form whole three-dimensional adjustable lifting sabot body via spinning in the restriction connecting the stop nut 50 on bluff piece 430, make the ball node that described three-dimensional adjustable lifting sabot body can be regulated by " joint " the formula three-dimensional be made up of upper press cover 410 and roating sphere 420, realize its three-dimensional adjustable lifting sabot formed (also comprising the channel that it connects) and can regulate change accordingly along the change of the rack curve form on roof, under making it can be installed on rack easily.As shown in Figure 6 and Figure 7, described connection pawl 431 number and concrete shape structure can make corresponding structure according to actual needs.In embodiments of the present invention, described connection pawl 431 is rectangular shape, number is 4, adjacent two angles connected between pawl are 90 degree, in addition, in order to " joint " that make connection pawl 431 can regulate as one, connection pawl is provided with bolt hole 432, make can there be larger adjustment space during assembling, meet needs and punctual the do not caused construction error of elimination rack amoeboid movement and ball node position effectively of practical application.In embodiments of the present invention, described bolt hole 432 is arcuate socket, connection pawl and main keel structure can be linked together by bolt by it, simultaneously, utilize the characteristic of arcuate socket, realization connects pawl and main keel structure can move horizontally, and to adapt to the needs of different roof structure, greatly facilitates I&M.
Further, please continue to refer to Fig. 8, Fig. 8 be the schematic diagram of suspension rod of present pre-ferred embodiments.As shown in the figure, described suspension rod 40 is screw thread suspension rod, the height of three-dimensional adjustable lifting sabot can be regulated by it, to adapt to the needs of different roof structure, also comprise an elastic washer, described screw thread suspension rod 40 can be connected with adjustable mounting seat by nut, and described elastic washer is positioned over below nut, plays anti-loose effect.Described connection pawl 431 is also provided with the bolt hole that can be hinged with the first syndeton of channel above, and its operating principle is the same with bolt hole 432.
Please again consult Fig. 2, described channel 500 comprises the first syndeton, main keel structure and the rider keel structure (not marking in figure) that connect successively further, in embodiments of the present invention, described main keel structure adopts 100C type keel, it is arranged in the first syndeton by securing member (such as bolt etc.), form the frame construction of whole channel, described rider keel structure adopts 40C type keel, adjacent two rider keel structure connectors connect, adjacent two row's interface positions stagger, and the level that is adjusted to after installation is straight.Described rider keel structure is arranged on main keel structure by hanging piece, and fastening with securing member, to prevent the slip of bevel direction.Internals in channel all carries out spray treatment, and color can be determined according to designing requirement.The corresponding fabrication hole of Surface Machining of rider keel structure, does not need welding, also without the need to carrying out secondary antirust treatment.Described panel 500 is arranged on the below of channel, panel can be set according to the space layout of reality, in embodiments of the present invention, described panel is aluminium alloy panel, it is connected on channel: first determine to install axis, install according to corresponding order from axis again, accomplish overall level and smooth, straight, nothing sinking sense.
Further, after panel 500 and channel 400 are installed, panel 500 should be able to bear the static load of designing requirement, and its maximum flexibility deflection must not be greater than 10mm, and amount of plastic deformation must not be greater than 2mm.Its channel 400 and panel 500 can select market-ripe standard series furred ceiling product, avoid specialized designs to make, and save cost.
, when the described ceiling system being applicable to large space curved surface steel structure roofing is in receipts position, limit, need installation one lower chord, its connection space rack and channel with should be noted that.When ceiling system is in receipts position, limit, described lower chord plays fixed ceilings keel.
The construction process of the ceiling system of the large-spatial structures of the embodiment of the present invention is as follows:
1, unwrapping wire location:
By the arrangement requirement of drawing ball node, ball node is numbered one by one.Measure the actual coordinate of each lower edge ball point one by one, and check with theoretical ball node coordinate, according to the actual height of furred ceiling finished surface, calculate the length of suspension rod, the usage quantity of changeover panel and triangular support bracket and position; Recycling total powerstation, according to rack present situation, first a fixed reference line on frame ball node, then makes the position of suspension rod by reference line, and furred ceiling finished surface distance rack lower edge ball's dead center distance is 750mm.Measuring process can adopt the modes such as bracing wire to adjust fixed point.The base position that each unit is made marks by red pigment on rack.
2, lower edge ball node installs adjustable mounting seat:
According to field measurement, lower edge ball node locates adjustable mounting seat.For receipts position, limit, as pillar, outer curtain wall place, then adopt special adjustable mounting seat on request, be arranged on lower chord.The required accurate positioning of adjustable mounting seat, installation are firmly.
3, hanger erection and upper limit nut install (in the present embodiment, described suspension rod is screw rod):
Be that the bolt hanging axis of 20mm inserts in the screw hole of adjustable mounting seat by diameter, then make upper limit nut location according to unwrapping wire, then upper limit nut is contained on bolt hanging axis.
4, three-dimensional adjustable lifting sabot is installed:
Three-dimensional adjustable lifting sabot is loaded bolt hanging axis, and lower position nut of screwing on, is namely fixed on main roofing Elements of Space Grid Truss by bolt hanging axis.
5,100 C type main joists are installed:
C type main joist is arranged on and is rotationally connected on pawl, and use bolton.Level is adjusted to straight after installation.
6,40 C type rider keels are installed:
The special hanging piece of C type rider keel is mounted on main joist, and uses bolton.Adjacent two keel connectors connect, and adjacent two row's keel interface positions stagger, and the level that is adjusted to after installation is straight.
7, installation panel suspension member:
Arrangement distance installation panel suspension member by drawing, uses M6X20 bolton.
8, perforated aluminum alloy panel is installed:
Determine that smallpox installs axis, and install according to corresponding order from axis, ethylene-propylene-diene monomer film is socketed on the flanging of plate face.And be stuck in the draw-in groove of panel suspension member.At holding screw.Different units needs the gap adjusting plate face, accomplishes level and smooth, straight.
Further, when mounting fastener, main keel structure, rider keel structure and panel, also the securing member of other models, main keel structure, rider keel structure and panel can be adopted, and to be not limited in the present invention be model in embodiment, as long as installation requirement can be met, realize the features such as whole system welding, good endurance.
Generally speaking, as shown in Figure 1, it comprises the method flow of the described ceiling system for engineering steel work:
S1, unwrapping wire is located;
S2, rack lower edge ball node installs adjustable mounting seat;
S3, installs suspension rod;
S4, installs three-dimensional adjustable lifting sabot;
S5, installs main keel structure and rider keel structure;
S6, installation panel.
For whole construction, should accomplish: the leveling of range estimation keel large area puts in place, connects smooth-going, without sense of sinking; Suspension centre is arranged rationally, and hanging piece is complete, hangs phenomenon without leaking; Dock, be connected firmly, without virtual connection phenomenon.In addition, be with should be noted that: (1) strictly should control the planeness of smallpox: the horizontal control lines in smallpox face should draw logical line, the furred ceiling that span is larger, absolute altitude control point should be added in centre position; (2) levelness of strict elevation control line: must ensure that the relief of furred ceiling is accurate and size is accurate, meet designing requirement, method will meet regulation and stipulation; (3) smallpox seam is controlled well: smallpox lines refer to seam, aluminium alloy joist bar between panel and panel, and its line strip decoration.The quality of seam directly affects decorative effect, strengthens the process of butt joint, most important to the performance of decorative effect.
Be understandable that, for those of ordinary skills, can be equal to according to technical scheme of the present invention and inventive concept thereof and replace or change, and all these change or replace the protection domain that all should belong to the claim appended by the present invention.

Claims (6)

1. for a ceiling method for engineering steel work, it is characterized in that, comprise the following steps:
S1, unwrapping wire is located;
S2, rack lower edge ball node installs adjustable mounting seat;
S3, installs suspension rod;
S4, installs three-dimensional adjustable lifting sabot;
S5, installs main keel structure and rider keel structure;
S6, installation panel.
2., for a ceiling system for engineering steel work, comprise the rack chop be connected with large space curved surface steel structure roofing, it is characterized in that, also comprise:
Installation of ceiling plate, it is arranged on below rack chop;
Adjustable mounting seat, it comprises symmetrical two buckles, the first gripper shoe be arranged in parallel and the second gripper shoe, two fixtures further; Described fixture withstands installation of ceiling plate through the first gripper shoe, and described buckle is fastened on the two ends of installation of ceiling plate;
Connect the three-dimensional adjustable lifting sabot of adjustable mounting seat and channel, adjustable for the level realizing main keel structure;
Channel, it comprises the first syndeton, main keel structure and the rider keel structure that connect successively further;
Panel, it is arranged on the below of described channel.
3. the ceiling system for engineering steel work according to claim 2, is characterized in that, described three-dimensional adjustable lifting sabot comprises further: the suspension rod connected successively, upper press cover, roating sphere and the connection bluff piece with some connection pawls; Described suspension rod is connected with adjustable mounting seat, and described connection bluff piece is connected with channel.
4. the ceiling system for engineering steel work according to claim 3, is characterized in that, described suspension rod is screw thread suspension rod, and it also comprises installation spring washer under the nut for being connected with adjustable mounting seat by nut.
5. the ceiling system for engineering steel work according to claim 2, is characterized in that, described main keel structure is 100C type keel, and it is arranged in the first syndeton by securing member; Described rider keel structure is 40C type keel, and it is arranged on main keel structure by hanging piece, and fastening with securing member.
6. the ceiling system for engineering steel work according to claim 2, is characterized in that, also comprises the lower chord of a connection space rack and channel, when it receives position, limit for being in when ceiling system, plays fixed ceilings keel.
CN201510155491.1A 2015-04-03 2015-04-03 Ceiling hanging method and ceiling hanging system for project steel structure Pending CN104878866A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510155491.1A CN104878866A (en) 2015-04-03 2015-04-03 Ceiling hanging method and ceiling hanging system for project steel structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510155491.1A CN104878866A (en) 2015-04-03 2015-04-03 Ceiling hanging method and ceiling hanging system for project steel structure

Publications (1)

Publication Number Publication Date
CN104878866A true CN104878866A (en) 2015-09-02

Family

ID=53946526

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510155491.1A Pending CN104878866A (en) 2015-04-03 2015-04-03 Ceiling hanging method and ceiling hanging system for project steel structure

Country Status (1)

Country Link
CN (1) CN104878866A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105421644A (en) * 2015-12-14 2016-03-23 苏州金螳螂建筑装饰股份有限公司 Suspending device of suspended ceiling
CN108412184A (en) * 2018-01-25 2018-08-17 广州珠江工程建设监理有限公司 A kind of installation method based on big roof ceiling furred ceiling operating platform

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101575892A (en) * 2009-03-26 2009-11-11 北京市建筑工程装饰有限公司 Large-area lower edge nested aluminum plate curved hung ceiling with high punching rate and construction method thereof
CN201433492Y (en) * 2009-05-26 2010-03-31 亨特道格拉斯工业(中国)有限公司 Buckle assembly structure for metal decorative board
CN201574507U (en) * 2009-05-19 2010-09-08 湖南望新建设集团股份有限公司 Soft film ceiling mounting structure
CN102220795A (en) * 2011-04-14 2011-10-19 广东省建筑装饰工程有限公司 Ceiling system applicable to large-span space steel structure and construction method thereof
CN203569765U (en) * 2013-10-21 2014-04-30 欧华玛新型建材(上海)有限公司 Double-inner-hook hanging type ceiling structure
CN103806586A (en) * 2014-01-22 2014-05-21 昆山协多利金属有限公司 Keel for lamp
CN104060745A (en) * 2014-07-10 2014-09-24 苏州金螳螂建筑装饰股份有限公司 Three-dimensional adjustable clamping piece of steel-structure conversion layer

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101575892A (en) * 2009-03-26 2009-11-11 北京市建筑工程装饰有限公司 Large-area lower edge nested aluminum plate curved hung ceiling with high punching rate and construction method thereof
CN201574507U (en) * 2009-05-19 2010-09-08 湖南望新建设集团股份有限公司 Soft film ceiling mounting structure
CN201433492Y (en) * 2009-05-26 2010-03-31 亨特道格拉斯工业(中国)有限公司 Buckle assembly structure for metal decorative board
CN102220795A (en) * 2011-04-14 2011-10-19 广东省建筑装饰工程有限公司 Ceiling system applicable to large-span space steel structure and construction method thereof
CN203569765U (en) * 2013-10-21 2014-04-30 欧华玛新型建材(上海)有限公司 Double-inner-hook hanging type ceiling structure
CN103806586A (en) * 2014-01-22 2014-05-21 昆山协多利金属有限公司 Keel for lamp
CN104060745A (en) * 2014-07-10 2014-09-24 苏州金螳螂建筑装饰股份有限公司 Three-dimensional adjustable clamping piece of steel-structure conversion layer

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105421644A (en) * 2015-12-14 2016-03-23 苏州金螳螂建筑装饰股份有限公司 Suspending device of suspended ceiling
CN108412184A (en) * 2018-01-25 2018-08-17 广州珠江工程建设监理有限公司 A kind of installation method based on big roof ceiling furred ceiling operating platform

Similar Documents

Publication Publication Date Title
CN102220795A (en) Ceiling system applicable to large-span space steel structure and construction method thereof
CN102979312B (en) Indoor aluminum honeycomb board suspended ceiling reverse installation technology
CN200992763Y (en) Ceiling unit structure hanging aluminium slat under hyperboloid grid third quavter
CN101255722B (en) Double-trough curved surface unit type panel wall
CN112443070A (en) Finished product ceiling stepped mounting structure and mounting method
CN202139744U (en) Space hyperbolic quadrangular unit type suspended ceiling adapter claw piece
CN104878866A (en) Ceiling hanging method and ceiling hanging system for project steel structure
CN205171782U (en) Frame curtain system between stone material edge list
CN206722301U (en) A kind of raised flooring system
CN111549961B (en) Energy-saving ceiling for airport terminal building and construction method thereof
CN105133774A (en) Combined assembly type suspended ceiling reverse support system structure and designing and installing integrated method
CN205531317U (en) Assembled concrete shear wall structure adjustable tripod support system
CN218668112U (en) Super high-rise building jumbo size deformed steel structure decorates roof
CN107035035B (en) Light external vertical curtain wall
CN202466902U (en) Transverse decorative molding curtain wall system connected through sleeve core
CN205890889U (en) A decorate mounting structure in automobile body for track engineering vehicle
CN103243888B (en) Stone-like aluminum alloy light grid component and construction method of decorative outer wall made of stone-like aluminum alloy light grid components
CN102535691A (en) Overhanging type transparent sandwich panel curtain wall
CN211396127U (en) Novel bank wall bearing structure
CN203569833U (en) Novel dry hanging system for building outer decoration and insulation integrated boards
CN209494101U (en) A kind of open type aluminium plate curtain wall adapting to different angle
CN102493582A (en) Three-dimension adjustable connection assembly for curtain walls
CN209585374U (en) A kind of suspension type glass curtain wall construction
CN203654575U (en) Ceiling installation structure
CN2755216Y (en) Movable network floor with high support strength

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150902