CN104868484B - Powerless control method is coordinated up and down by 220/110kV transformer stations - Google Patents
Powerless control method is coordinated up and down by 220/110kV transformer stations Download PDFInfo
- Publication number
- CN104868484B CN104868484B CN201510272565.XA CN201510272565A CN104868484B CN 104868484 B CN104868484 B CN 104868484B CN 201510272565 A CN201510272565 A CN 201510272565A CN 104868484 B CN104868484 B CN 104868484B
- Authority
- CN
- China
- Prior art keywords
- cord
- transformer
- transformer stations
- station
- max
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E40/00—Technologies for an efficient electrical power generation, transmission or distribution
- Y02E40/30—Reactive power compensation
Abstract
The present invention provides 220/110 kV transformer stations and coordinates powerless control method up and down, comprises the following steps:(1)Obtain the electrical network parameter of area power grid;(2)Limit value is coordinated in calculating up and down;(3)Upper and lower correlated state is determined according to hysteretic characteristic;(4)Corresponding coordination control strategy up and down is selected by upper and lower correlated state.The present invention proposes a kind of 220 kV/110 kV power networks and coordinates powerless control method up and down, can be used for idle support of the 110 kV transformer stations to 220 kV transformer stations in area power grid, remaining reactive-load compensation equipment in area power grid can be effectively utilized, the critical point reactive power of the kV transformer stations of area power grid 220 is better adapted to the requirement of upper strata power network.
Description
Technical field
The present invention relates to the idle operation method of power system, more particularly to a kind of 110kV power transformations based on hysteretic characteristic
Stand and coordinate the powerless control method of 220kV transformer stations.
Background technology
In AC network, reactive power plays very crucial effect to the security and economy of power network.Idle work(
Flowing of the rate in power network, can cause voltage landing and active power loss.In order to ensure operation voltage level and reduce active
Power attenuation, idle control is a vital task of grid company.
Provincial power network traffic department can typically manage for the idle control effect of provincial power network to regional power grid scheduling department
220kV transformer stations in the range of linchpin propose the requirement of critical point Reactive Power Control, that is, provide the critical point reactive power of 220kV transformer stations
Allowed band.
At present, area power grid is typically become using the method for controlling on the spot, the i.e. reactive requirement of 220kV transformer stations by 220kV
The reactive-load compensation equipment in power station itself meets.This method for controlling on the spot is although simple and easy to apply, but when 220kV transformer stations
When reactive-load compensation equipment is used up, it is impossible to effectively utilize the remaining reactive-load compensation equipment of 110kV transformer stations.Have now
AVC systems start to introduce the strategy coordinated, but these strategies often independently of the another set of strategy for controlling on the spot, therefore easily
Clashed with existing control strategy on the spot, cause the problem of reactive-load compensation equipment switching repeatedly.
In sum, existing coordination powerless control method also needs to further improvement.
The content of the invention
It is an object of the invention to solve the problems, such as that existing power-less optimized controlling method cannot be mutually coordinated, it is desirable to provide one
That plants practicality coordinates powerless control method up and down in real time.
The present invention proposes that powerless control method is coordinated up and down by a kind of 220/110kV transformer stations, comprises the following steps:
(1) area power grid parameter is obtained;110kV of the area power grid comprising a 220kV transformer station and its institute's band becomes
Power station;The area power grid parameter includes:Reactive-load compensation equipment single group capacity in each power transformation station name, each transformer station and
The critical point reactive power allowed band of transformer gear upper and lower bound, each transformer station in quantity, each transformer station and low
Pressure busbar voltage allowed band;Array CORD is created, the 110kV power transformations of idle coordination are carried out to 220kV transformer stations for depositing
Name of station, the initial value of CORD is empty array;
(2) calculate and coordinate limit value Q up and downcord.max1、Qcord.max2、Qcord.min1And Qcord.min2:
(3) the reactive power/voltage control situation of area power grid is obtained;The reactive power/voltage control situation includes:110kV power transformations
Stand and the critical point reactive power of 220kV transformer stations, low-voltage bus bar voltage, transformer current gear and reactive-load compensation equipment input group
The critical point reactive power Q of number, wherein 220kV transformer stations220Represent;
(4) Q is judged220With Qcord.max1、Qcord.max2、Qcord.min1And Qcord.min2Magnitude relationship, it is true according to hysteretic characteristic
Fixed upper and lower correlated state;Upper and lower correlated state is the condition for selecting upper and lower coordination control strategy, comprising starting, be failure to actuate,
Release three kinds of states;If upper and lower correlated state is to start, into step (5);If upper and lower correlated state enters step to release
Suddenly (6);If upper and lower correlated state is to be failure to actuate, into step (7);
(5) if Q220>Qcord.max1, then all 110kV transformer stations for getting step (1) remove and have been stored in CORD
The corresponding 110kV transformer stations of name of station, selected from remaining 110kV transformer stations critical point reactive power it is qualified and station in do not cut off
Reactor and the maximum transformer station of the capacitor total capacity that does not put into, the critical point reactive power of the 110kV transformer stations is allowed
Upper and lower bound in scope all reduces Q110.com.max, 110kV transformer stations input capacitor or excision reactor are ordered about to mend
Repay a part of reactive power of 220kV transformer stations, Q110.com.maxRepresent area power grid in 110kV Substation Reactive-power Compensations equipment most
Big single group capacity, and the 110kV transformer stations name of station is increased into the last of CORD, into step (7);If Q220<Qcord.min1, then
All 110kV transformer stations that step (1) is got remove the corresponding 110kV transformer stations of name of station being stored in CORD, from
Select that critical point reactive power is qualified in remaining 110kV transformer stations and the capacitor not cut off and the reactor that does not put into are total in station
The maximum transformer station of capacity, Q is all increased by the upper and lower bound in the critical point reactive power allowed band at the station110.com.max, drive
The 110kV transformer stations are made to put into reactor or excision capacitor to compensate a part of reactive power of 220kV transformer stations, and should
110kV transformer stations name of station increases to the last of CORD, into step (7);
(6) if CORD is empty array, into step (7);If CORD is not empty array, last unit of inquiry CORD
Element, the critical point reactive power allowed band of the 110kV transformer stations that the element is represented is set to being somebody's turn to do for the middle acquisition of step (1)
The critical point reactive power allowed band of 110kV transformer stations, and delete last element of CORD;
(7) the nine-zone diagram strategy commonly used according to current AVC is controlled to 110kV transformer stations, 220kV transformer stations;
(8) terminate this cycle and coordinate idle control up and down;Wait setting time, return to step (3).
Above-mentioned 220/110kV transformer stations are coordinated in powerless control method up and down, described to coordinate control up and down, refer to utilize
The reactive-load compensation equipment of 110kV transformer stations, coordinates a kind of control of the reactive requirement of compensation 220kV transformer stations.
Above-mentioned 220/110kV transformer stations are coordinated in powerless control method up and down, the critical point refer to regional grid it
Between power equipment assets and management scope boundary, typically using at transformer station's high-voltage side bus as critical point.
Above-mentioned 220/110kV transformer stations are coordinated in powerless control method up and down, described to coordinate limit value up and down, refer to for
Judge the condition of upper and lower correlated state, limit value Q is coordinated up and downcord.max1、Qcord.max2、Qcord.min1And Qcord.min2Obtained by formula (1)
:
Qcord.max1=Q220.max+Q110.com.max
Qcord.max2=Q220.max-Q110.com.max (1)
Qcord.min1=Q220.min-Q110.com.max
Qcord.min2=Q220.min+Q110.com.max
Formula (1) comprising variable:220kV transformer stations critical points reactive power allowed band upper limit Q220.maxWith lower limit Q220.min;Ground
110kV Substation Reactive-power Compensations equipment maximum single group capacity Q in area's power network110.com.max。
Above-mentioned 220/110kV transformer stations are coordinated in powerless control method up and down, and the hysteretic characteristic refers to 220kV power transformations
The relation that critical point reactive power of standing is formed with upper and lower correlated state, 220kV transformer stations critical point reactive power and upper and lower correlated state
Relation it is specific as follows:
(1) Q is worked as220>Qcord.max1, and do not have in 220kV transformer stations the reactor not cut off and do not put into capacitor when,
Upper and lower correlated state is set on;
(2) Q is worked as220<Qcord.min1, and do not have in 220kV transformer stations the capacitor not cut off and do not put into reactor when,
Upper and lower correlated state is set on;
(3) Q is worked ascord.min2<Q220<Qcord.max2When, upper and lower correlated state is set to release;
(4) when not meeting the condition of (1)~(3), upper and lower correlated state is set to be failure to actuate.
Above-mentioned 220/110kV transformer stations are coordinated in powerless control method up and down, the nine-zone diagram strategy, are a kind of conventional
Utilization real-time monitoring transformer station's low-voltage bus bar voltage and critical point reactive power transformer station's gear and reactive-load compensation equipment are entered
The strategy of row control, its basis for estimation is 9 controls that the bound based on low-voltage bus bar voltage and critical point reactive power is constituted
Area processed, when low-voltage bus bar voltage exceeds allowed band [Umin,Umax] or critical point reactive power exceed allowed band [Qmin,Qmax]
When, control system is adjusted according to predetermined instruction, and each area's action scheme is as follows:
1st area:Low-voltage bus bar voltage is more than Umax, critical point reactive power is less than Qmin, capacitor or input reactor are cut off, when
After capacitor complete resection and reactor whole input, low-voltage bus bar voltage is still greater than UmaxWhen, reduce transformer tap first gear
Position;
2nd area:Low-voltage bus bar voltage is more than Umax, critical point reactive power is qualified, reduces load tap changer gear, works as tap
After first gear position has been adjusted to deep low gear, low-voltage bus bar voltage is still greater than UmaxWhen, cut off capacitor or input reactor;
3rd area:Low-voltage bus bar voltage is more than Umax, critical point reactive power is more than Qmax, reduce load tap changer gear, when point
After joint gear has been adjusted to deep low gear, low-voltage bus bar voltage is still greater than UmaxWhen, cut off capacitor or input reactor;
4th area:Low-voltage bus bar voltage is qualified, and critical point reactive power is less than Qmin, capacitor or input reactor are cut off, work as electricity
After container complete resection and reactor whole input, operating point Reng Gai areas then maintain the operating point;
5th area:Low-voltage bus bar voltage is qualified, and critical point reactive power is qualified, maintains the operating point;
6th area:Low-voltage bus bar voltage is qualified, and critical point reactive power is more than Qmax, capacitor or excision reactor are put into, work as electricity
Container all puts into and after reactor complete resection, operating point Reng Gai areas then maintain the operating point;
7th area:Low-voltage bus bar voltage is less than Umin, critical point reactive power is less than Qmin, raise load tap changer gear, when point
After joint gear has been adjusted to highest shelves, low-voltage bus bar voltage is still less than UminWhen, put into capacitor or excision reactor;
8th area:Low-voltage bus bar voltage is less than Umin, it is idle qualified, raise load tap changer gear, when tap gear
Be adjusted to it is most high-grade after, input capacitor or excision reactor;
9th area:Low-voltage bus bar voltage is less than Umin, critical point reactive power is more than Qmax, capacitor or excision reactor are put into, when
Capacitor all puts into and after reactor complete resection, low-voltage bus bar voltage is still less than UminWhen, raise transformer tap first gear
Position.
Compared with prior art, the beneficial effects of the present invention are:
(1) reactive-load compensation equipment of 110kV transformer stations is transferred, coordinates the reactive requirement of compensation 220kV transformer stations, Ke Yiyou
Remaining reactive-load compensation equipment in effect land productivity area power grid;
(2) coordination control strategy is simply clear and definite, is improved on the basis of control strategy on the spot, does not result in tactful punching
The prominent problem so as to cause equipment switching repeatedly.
Brief description of the drawings
Fig. 1 is that powerless control method is coordinated up and down by the 220kV/110kV transformer stations based on hysteretic characteristic that the present invention is provided
Schematic flow sheet.
Fig. 2 is the hysteretic characteristic curve of upper and lower correlated state-upper and lower harmony value.
Fig. 3 is somewhere power network schematic diagram.
Specific embodiment
Specific implementation of the invention is described further below in conjunction with accompanying drawing and example.
Fig. 1 reflects the specific stream that powerless control method is coordinated up and down by the 220kV/110kV transformer stations based on hysteretic characteristic
Journey.Specifically include:
(1) area power grid parameter is obtained;110kV of the area power grid comprising a 220kV transformer station and its institute's band becomes
Power station;The area power grid parameter includes:Reactive-load compensation equipment single group capacity in the title of each transformer station, each transformer station
With the transformer gear upper and lower bound in quantity, each transformer station, the critical point reactive power allowed band of each transformer station and
Low-voltage bus bar voltage allowed band;Array CORD is created, the 110kV for carrying out idle coordination to 220kV transformer stations for depositing becomes
Power station name of station, the initial value of CORD is empty array;
(2) calculate and coordinate limit value Q up and downcord.max1、Qcord.max2、Qcord.min1And Qcord.min2;
Qcord.max1、Qcord.max2、Qcord.min1And Qcord.min2Obtained by formula (1):
Qcord.max1=Q220.max+Q110.com.max
Qcord.max2=Q220.max-Q110.com.max (1)
Qcord.min1=Q220.min-Q110.com.max
Qcord.min2=Q220.min+Q110.com.max
Formula (1) comprising variable:220kV transformer stations critical points reactive power allowed band upper limit Q220.maxWith lower limit Q220.min;Ground
110kV Substation Reactive-power Compensations equipment maximum single group capacity Q in area's power network110.com.max;
(3) the reactive power/voltage control situation of area power grid is obtained;The reactive power/voltage control situation includes:110kV power transformations
Stand and the critical point reactive power of 220kV transformer stations, low-voltage bus bar voltage, transformer current gear and reactive-load compensation equipment input group
The critical point reactive power Q of number, wherein 220kV transformer stations220Represent;
(4) Q is judged220With Qcord.max1、Qcord.max2、Qcord.min1And Qcord.min2Magnitude relationship, it is true according to hysteretic characteristic
Fixed upper and lower correlated state;Upper and lower correlated state is the condition for selecting upper and lower coordination control strategy, comprising starting, be failure to actuate,
Release three kinds of states;If upper and lower correlated state is to start, into step (5);If upper and lower correlated state enters step to release
Suddenly (6);If upper and lower correlated state is to be failure to actuate, into step (7);
The determination method of upper and lower correlated state is as follows:
A. Q is worked as220>Qcord.max1, and do not have in 220kV transformer stations the reactor not cut off and do not put into capacitor when,
Upper and lower correlated state is set on;
B. Q is worked as220<Qcord.min1, and do not have in 220kV transformer stations the capacitor not cut off and do not put into reactor when,
Upper and lower correlated state is set on;
C. Q is worked ascord.min2<Q220<Qcord.max2When, upper and lower correlated state is set to release;
When d. not meeting the condition of a, b, c, upper and lower correlated state is set to be failure to actuate;
Upper and lower correlated state forms a kind of relation of hysteretic characteristic with upper and lower harmony value, and Fig. 2 gives and coordinates shape up and down
The hysteretic characteristic curve of state-upper and lower harmony value;
(5) if Q220>Qcord.max1, then all 110kV transformer stations for getting step (1) remove and have been stored in CORD
The corresponding 110kV transformer stations of name of station, from remaining 110kV transformer stations, select critical point reactive power it is qualified and station in do not cut
The reactor for removing and the maximum transformer station of the capacitor total capacity not put into, the critical point reactive power of the 110kV transformer stations is permitted
Perhaps the upper and lower bound in scope all reduces Q110.com.max, Q110.com.maxRepresent 110kV Substation Reactive-power Compensations in area power grid
Equipment maximum single group capacity, and the 110kV transformer stations name of station is increased into the last of CORD, into step (7);If Q220<
Qcord.min1, then the corresponding 110kV of name of station that all 110kV transformer stations removing for getting step (1) has been stored in CORD
Transformer station, from remaining 110kV transformer stations, selects that critical point reactive power is qualified and the capacitor that does not cut off and is not put into station
The maximum transformer station of reactor total capacity, the upper and lower bound in the critical point reactive power allowed band at the station is all increased
Q110.com.max, and the 110kV transformer stations name of station is increased into the last of CORD, into step (7);
(6) if CORD is empty array, into step (7);If CORD is not empty array, last unit of inquiry CORD
Element, the critical point reactive power allowed band of the 110kV transformer stations that the element is represented is set to being somebody's turn to do for the middle acquisition of step (1)
The critical point reactive power allowed band of 110kV transformer stations, and delete last element of CORD;
(7) the nine-zone diagram strategy commonly used according to current AVC is controlled to 110kV transformer stations, 220kV transformer stations;
(8) terminate this cycle and coordinate idle control up and down;Wait next controlling cycle (such as 15 minutes), return to step (3).
The following is an example of the inventive method, emulated by taking the power network of somewhere as an example, Fig. 3 shows the power network
Topological structure, A represents 220kV power transformation station names in figure, and B1, B2, B3, B4, B5 represent the title of 110kV transformer stations respectively.
(1) known by Fig. 3, this area's power network has 1 220kV transformer stations A, transformer station A to carry 5 110kV transformer stations, title
Respectively B1, B2, B3, B4, B5;This area's power network is configured without reactor, single group capacity and the quantity such as institute of table 1 of capacitor
Show;
The single group capacity and quantity of the capacitor of table 1
Transformer gear upper and lower bound in each transformer station is as shown in table 2;
The transformer gear upper and lower bound of table 2
Transformer station | The gear upper limit | Gear lower limit | Transformer station | The gear upper limit | Gear lower limit |
A | 5 | 1 | B3 | 17 | 1 |
B1 | 17 | 1 | B4 | 17 | 1 |
B2 | 17 | 1 | B5 | 17 | 1 |
The critical point reactive power allowed band and low-voltage bus bar voltage allowed band of each transformer station are as shown in table 3;
The critical point reactive power allowed band of table 3 and low-voltage bus bar voltage allowed band
Set up an empty array CORD;
(2) calculate and coordinate limit value Q up and downcord.max1、Qcord.max2、Qcord.min1And Qcord.min2;
Qcord.max1=Q220.max+Q110.com.max=8+4Mvar=12Mvar
Qcord.max2=Q220.max-Q110.com.max=8-4Mvar=4Mvar
Qcord.min1=Q220.min-Q110.com.max=-8-4Mvar=-12Mvar
Qcord.min2=Q220.min+Q110.com.max=-8+4Mvar=-4Mvar
In above formula, Q220.max、Q220.minRespectively the 220kV transformer stations critical point reactive power allowed band upper limit, lower limit;
Q110.com.maxIt is 110kV Substation Reactive-power Compensations equipment maximum single group capacity in area power grid.
(3) in a certain controlling cycle, critical point reactive power, the low-voltage bus bar of 110kV transformer stations and 220kV transformer stations are obtained
Voltage, transformer current gear and reactive-load compensation equipment input group number are as shown in table 4;In this embodiment, reactive-load compensation equipment
Refer to capacitor;
The reactive power/voltage control situation of table 4
Q is known by table220=12.38Mvar;
(4) Q is judged to obtain220>Qcord.max1, and (this area's power network does not have not to have the capacitor that does not put into 220kV transformer stations
Configuration reactor), therefore upper and lower correlated state is set to start;
(5) Q is judged to obtain220>Qcord.max1, and now CORD is sky, and transformer station B2 is selected to obtain in all 110kV transformer stations
Critical point reactive power it is qualified and do not put into capacitor total capacity maximum (this area's power network is configured without reactor), remain 3 groups
The capacitor of 4Mvar is not put into, therefore the critical point reactive power allowed band upper and lower bound of transformer station B2 is all reduced
Q110.com.max(reducing 4Mvar), and transformer station's B5 names of station are increased into CORD;
After the completion of this step, the critical point reactive power allowed band of transformer station B2 is [- 8,0] Mvar, CORD={ B2 };
The nine-zone diagram strategy commonly used according to current AVC is controlled to 110kV transformer stations, 220kV transformer stations, control result
To put into a group capacitor 110kV transformer stations B2, other transformer stations are failure to actuate more.
The idle control of coordination up and down of other controlling cycles can be carried out according to the proposed method, no longer be gone to live in the household of one's in-laws on getting married herein
State.
After by coordinating idle control up and down, compared to the control idle on the spot do not coordinated up and down, 110kV power transformations
Standing one group of capacitor of 4Mvar of put into B2 more, table 5 give the critical point of 220kV transformer stations A under two kinds of powerless control methods without
Work(power contrast.
The critical point reactive power contrast of 220kV transformer stations A under 5 two kinds of powerless control methods of table
Idle control on the spot | Coordinate idle control up and down | |
Critical point reactive power | 12.38Mvar | 8.22Mvar |
When as shown in Table 5, using independent powerless control method, the reactive-load compensation equipment of 110kV transformer stations cannot be to 220kV
Transformer station is supported, and the critical point reactive power of 220kV transformer stations deviates allowed band farther out;And when using of the invention upper and lower
When coordinating powerless control method, the reactive-load compensation equipment of 110kV transformer stations can be supported 220kV transformer stations, compensation
The reactive power sent under 220kV substation sections, makes the critical point reactive power of 220kV transformer stations closer to allowed band.And,
Can also be seen that in powerless control method is coordinated up and down 110kV transformer stations are carried out to 220kV transformer stations from the data in table
After support, the critical point reactive power of 220kV transformer stations makes upper and lower correlated state be in the interval being failure to actuate, anti-so as to avoid
The situation of multiple control.
Above-described embodiment is the present invention preferably implementation method, but embodiments of the present invention are not by above-described embodiment
Limitation, other it is any without departing from the modification made under Spirit Essence of the invention and principle, modification, replacement, combination, simplification,
Equivalent substitute mode is should be, should be all included within protection scope of the present invention.
Claims (1)
- Powerless control method is coordinated up and down by 1.220/110kV transformer stations, it is characterised in that comprise the following steps:(1) area power grid parameter is obtained;110kV transformer station of the area power grid comprising a 220kV transformer station and its institute's band; The area power grid parameter includes:Reactive-load compensation equipment single group capacity sum in the title of each transformer station, each transformer station Transformer gear upper and lower bound, the critical point reactive power allowed band and low pressure of each transformer station in amount, each transformer station Busbar voltage allowed band;Array CORD is created, the 110kV transformer stations of idle coordination are carried out to 220kV transformer stations for depositing Name of station, the initial value of CORD is empty array;(2) calculate and coordinate limit value Q up and downcord.max1、Qcord.max2、Qcord.min1And Qcord.min2;It is described to coordinate limit value up and down, refer to For judging the condition of upper and lower correlated state, limit value Q is coordinated up and downcord.max1、Qcord.max2、Qcord.min1And Qcord.min2By formula (1) obtain:Formula (1) comprising variable:220kV transformer stations critical points reactive power allowed band upper limit Q220.maxWith lower limit Q220.min;Regional electricity 110kV Substation Reactive-power Compensations equipment maximum single group capacity Q in net110.com.max;(3) the reactive power/voltage control situation of area power grid is obtained;The reactive power/voltage control situation includes:110kV transformer stations and The critical point reactive power of 220kV transformer stations, low-voltage bus bar voltage, transformer current gear and reactive-load compensation equipment input group number, The wherein critical point reactive power Q of 220kV transformer stations220Represent;(4) Q is judged220With Qcord.max1、Qcord.max2、Qcord.min1And Qcord.min2Magnitude relationship, according to hysteretic characteristic determine on Lower correlated state;Upper and lower correlated state is the condition for selecting upper and lower coordination control strategy, comprising starting, be failure to actuate, release Three kinds of states;If upper and lower correlated state is to start, into step (5);If upper and lower correlated state is to release, into step (6);If upper and lower correlated state is to be failure to actuate, into step (7);The hysteretic characteristic refers to that 220kV transformer stations critical point is idle The relation that power is formed with upper and lower correlated state, 220kV transformer stations critical point reactive power is specific with the relation of upper and lower correlated state It is as follows:(3.1) Q is worked as220>Qcord.max1, and do not have in 220kV transformer stations the reactor not cut off and do not put into capacitor when, will Upper and lower correlated state is set on;(3.2) Q is worked as220<Qcord.min1, and do not have in 220kV transformer stations the capacitor not cut off and do not put into reactor when, will Upper and lower correlated state is set on;(3.3) Q is worked ascord.min2<Q220<Qcord.max2When, upper and lower correlated state is set to release;(3.4) when not meeting the condition of (3.1)~(3.3), upper and lower correlated state is set to be failure to actuate;(5) if Q220>Qcord.max1, then the station that all 110kV transformer stations removing for getting step (1) has been stored in CORD The corresponding 110kV transformer stations of name, the electricity selected that critical point reactive power is qualified from remaining 110kV transformer stations and do not cut off in station Anti- device and the maximum transformer station of the capacitor total capacity not put into, by the critical point reactive power allowed band of the 110kV transformer stations In upper and lower bound all reduce Q110.com.max, Q110.com.maxRepresent area power grid in 110kV Substation Reactive-power Compensations equipment most Big single group capacity, and the 110kV transformer stations name of station is increased into the last of CORD, into step (7);If Q220<Qcord.min1, then All 110kV transformer stations that step (1) is got remove the corresponding 110kV transformer stations of name of station being stored in CORD, from Select that critical point reactive power is qualified in remaining 110kV transformer stations and the capacitor not cut off and the reactor that does not put into are total in station The maximum transformer station of capacity, Q is all increased by the upper and lower bound in the critical point reactive power allowed band at the station110.com.max, and The 110kV transformer stations name of station is increased into the last of CORD, into step (7);(6) if CORD is empty array, into step (7);If CORD is not empty array, last element of CORD is inquired about, will The critical point reactive power allowed band of the 110kV transformer stations that the element is represented is set to the 110kV power transformations obtained in step (1) The critical point reactive power allowed band stood, and delete last element of CORD;(7) the nine-zone diagram strategy commonly used according to current automatism voltage control is controlled to 110kV transformer stations, 220kV transformer stations; The nine-zone diagram strategy is transformer station's low-voltage bus bar voltage and critical point reactive power of a kind of utilization real-time monitoring to transformer station's shelves The strategy that position and reactive-load compensation equipment are controlled;(8) terminate this cycle and coordinate idle control up and down;Wait setting time, return to step (3).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510272565.XA CN104868484B (en) | 2015-05-26 | 2015-05-26 | Powerless control method is coordinated up and down by 220/110kV transformer stations |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510272565.XA CN104868484B (en) | 2015-05-26 | 2015-05-26 | Powerless control method is coordinated up and down by 220/110kV transformer stations |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104868484A CN104868484A (en) | 2015-08-26 |
CN104868484B true CN104868484B (en) | 2017-06-20 |
Family
ID=53914117
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510272565.XA Active CN104868484B (en) | 2015-05-26 | 2015-05-26 | Powerless control method is coordinated up and down by 220/110kV transformer stations |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104868484B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106532729B (en) * | 2016-12-14 | 2018-09-18 | 云南电网有限责任公司电力科学研究院 | It saves ground and coordinates the method that control 220kV collects substation's high voltage bus voltage |
CN108667032A (en) * | 2018-04-18 | 2018-10-16 | 华南理工大学 | D-STATCOM reactive voltage control methods for distributed generation resource |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101800428A (en) * | 2009-12-31 | 2010-08-11 | 清华大学 | Method for acquiring coordinated constraint upper and lower limits of provincial-regional coordinated busbar voltage |
CN102354995A (en) * | 2011-09-28 | 2012-02-15 | 广东省电力调度中心 | Control method and control system for VQC (voltage quality control) of transformer substation |
CN102709918A (en) * | 2012-05-21 | 2012-10-03 | 广东省电力调度中心 | Reactive power control method of grid gateway based on automatic volume control (AVC) system |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2793327B2 (en) * | 1990-05-30 | 1998-09-03 | 株式会社東芝 | Reactive power compensator |
-
2015
- 2015-05-26 CN CN201510272565.XA patent/CN104868484B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101800428A (en) * | 2009-12-31 | 2010-08-11 | 清华大学 | Method for acquiring coordinated constraint upper and lower limits of provincial-regional coordinated busbar voltage |
CN102354995A (en) * | 2011-09-28 | 2012-02-15 | 广东省电力调度中心 | Control method and control system for VQC (voltage quality control) of transformer substation |
CN102709918A (en) * | 2012-05-21 | 2012-10-03 | 广东省电力调度中心 | Reactive power control method of grid gateway based on automatic volume control (AVC) system |
Non-Patent Citations (1)
Title |
---|
地区电网电压无功分层综合协调控制的研究;高冬那;《CNKI优秀硕士学位论文全文数据库》;20131231;全文 * |
Also Published As
Publication number | Publication date |
---|---|
CN104868484A (en) | 2015-08-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101635458B (en) | Coordinating voltage control method of provincial power network and regional power network based on two-way coordination constraint | |
CN104201693B (en) | Distribution line power-less optimized controlling method based on power factor interval dynamic tuning | |
CN108493950B (en) | Ultra-high voltage direct current near-region multi-stage power grid coordinated automatic voltage control method and system | |
CN102820661B (en) | Overall voltage quality coordinated control method for distribution network being oriented to multi-level objects | |
CN103474985B (en) | Realization method for function of adaptive load type distribution transformer | |
CN101764404B (en) | Method for judging coordination running state between provincial and local regions in coordination voltage control between provincial and local regions | |
CN105490312B (en) | A kind of power system multi-source power-less optimized controlling method | |
WO2008049556A1 (en) | Method for operating a low-voltage electrical system | |
CN103248056A (en) | Reactive voltage emergency control method in concentrated grid connecting area of wind power plant | |
WO2009019306A1 (en) | Method for controlling electrical loads in a low-voltage network | |
CN107017660A (en) | The grid-connected protection system in photovoltaic power station region and grid-connected control method | |
CN104917188B (en) | Powerless control method is coordinated in a kind of 220kV transformer stations packet | |
CN104682561B (en) | Method for optimizing transformer area by using intelligent cloud service system | |
CN103812112B (en) | A kind of area power grid AVC control method | |
CN104810840A (en) | Full-network voltage and reactive power optimization control system and control method thereof | |
CN105226665A (en) | The method of busbar voltage daily fluctuation rate is reduced by automatic plant stand cooperation control | |
CN103166217A (en) | Transmission grid phase shifter optimal configuration method | |
CN103093391A (en) | City power distribution network arranging method | |
CN104868484B (en) | Powerless control method is coordinated up and down by 220/110kV transformer stations | |
Wanik et al. | Intelligent management of distributed generators reactive power for loss minimization and voltage control | |
CN109888775B (en) | Low-load operation day power transmission network structure optimization method considering wind power access | |
CN104009482B (en) | Method for dynamically setting gateway reactive power control range under single-line and single-variable wiring mode | |
CN102664400A (en) | Monitoring method for electric energy quality | |
CN105262104A (en) | Reactive power sectional balance control method for 10 kV distribution line containing distributed power supplies | |
CN109936142B (en) | Automatic control method and device for voltage of transmission and distribution integrated power grid |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |